Professional Documents
Culture Documents
1:1.5:3
(d) Reinforced brick work.
G-144
Unit III B. Tech. EXAMINATION, May 2018
5. What are the benefits of doing Rate analysis (Seventh Semester)
in a construction project ? Explain the process
of doing Rate analysis of Highway works. 15 (B. Scheme) (Re-appear Only)
7. What are the functions of Public Works Before answering the question-paper candidates
Department ? Classify Public Works should ensure that they have been supplied to correct
Department. Explain the process of and complete question-paper. No complaint, in this
administrative sanction for a project. 15 regard, will be entertained after the examination.
8. Why is it necessary to prepare DPR of a Note : Attempt Five questions in all, selecting at
Project ? What data is required to prepare a least one question from each Unit. Assume
DPR for a project ? 15 any data if necessary.