Yanmar GHP Pre-testrun Check sheet

Project Name

Address: Date:
Installation Co: Report by:
Outdoor model: Outdoor Qty:
Indoor Type: D type / H type Indoor Qty:
centralized control: Yes / No RESS: Yes / No

GENERAL NOTES
(1)Prepare piping and installation plan (diagram) Yes No
(2)Confirm centralized remote adress setting *option Yes No
OUTDOOR UNIT
(1)Check place of installation GL Roof flor
(2)Check maintenance space OK NG
GAS PIPING
(1)Check installation of Gas piping OK NG
(2)Confirm Pressure is between 1.0~2.5kpa Yes No Standard pressure 2.0KPa( Natural gas)

(3)Confirm fuel gas is used available Yes No


WIRING
(1)Check wiring installation data and electric wire OK NG
(2)Confirm transformer have been installed *option Yes No
(3)Confirm electric voltage 220V Yes No v
(4)Confirm electricalcity is used available for GHP sytem Yes No
(5) To turn on the power of Outddor units before 6hrs Yes No
of the testrun
INDOOR UNIT
(1)Cofirm install panel of cassette type indoor units Yes No
(2)Check instalation of drainage pipe OK NG
(2)Check instalation of remote OK NG
REFRIGERANT PIPING
(1)Check heat insulation OK NG
(2)Confirm Press Test (4.0MPa) Yes No hrs Mpa
(3)Confirm Vacuum (200Microns) Yes No hrs
(4)Don't open stop valves of outdoor units Yes No
(5)Confirm additonal refrigerant amount Yes No kg
(6)Prepare additional charging refrigeratnt Yes No
REMOTE MONITORING SYSTEM (RESS) *option
(1)Check installation of RESS adptor OK NG
(3)Confirm DC24V transformer have been installed Yes No Adptor power source is DC24V 10watt

(3)Check data wiring from outdoor units OK NG


(4)Confirm internet connection with RESS adptor Yes No
I certify that I have checked the Yanmar GHP pre testrun point described above and belive it to be testrun
( )
Date dd.mm.yy Name/Signature of Responsible Person