You are on page 1of 25

An American National Standard

Designation: F 1484 – 04

Standard Test Methods for


Performance of Steam Cookers1
This standard is issued under the fixed designation F 1484; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.

1. Scope 2. Referenced Documents


1.1 This test method evaluates the energy consumption and 2.1 ASTM Standards: 2
cooking performance of steam cookers. The food service A 36/A 36M Specification for Structural Steel
operator can use this evaluation to select a steam cooker and D 3588 Practice for Calculating Heat Value, Compressibil-
understand its energy consumption. ity Factor, and Relative Density (Specific Gravity) of
1.2 This test method is applicable to the following steam Gaseous Fuels
cookers: high-pressure, low-pressure, and pressureless steam F 1217 Specification for Cooker, Steam
cookers (Specification F 1217 Grades A, B, and C); convection 2.2 ASHRAE Documents:3
and non-convection steam cookers; steam cookers with self- ASHRAE Handbook of Fundamentals, “Thermal and Re-
contained gas-fired, electric, or steam coil steam generators, lated Properties of Food and Food Materials,” Chapter 30,
and those connected directly to an external potable steam Table 1, 1989.
source (Specification F 1217 Styles i, ii, iii, and iv). The steam ASHRAE Handbook of Fundamentals, “Thermodynamic
cookers will be tested for the following (where applicable): Properties of Water at Saturation,” Chapter 6, Table 2,
1.2.1 Maximum energy input rate (see 10.2). 1989.
1.2.2 Preheat energy consumption and duration (see 10.3). 2.3 Other Document:4
1.2.3 Idle energy rate (see 10.4). Development and Application of a Uniform Testing Proce-
1.2.4 Pilot energy rate (see 10.5). dure for Steam Cookers
1.2.5 Frozen green pea load cooking energy efficiency (see
10.7). 3. Terminology
1.2.6 Frozen green pea load production capacity (see 10.7). 3.1 Definitions:
1.2.7 Whole potato load cooking energy efficiency (see 3.1.1 boiler, n—self-contained vessel, separate from the
10.9). cooking cavity, wherein water is boiled to produce steam for
1.2.8 Whole potato load production capacity (see 10.9). the steam cooker. Also called a steam generator.
1.2.9 Water consumption (see 10.7 and 10.9). 3.1.2 condensate, n—a mixture of condensed steam and
1.2.10 Condensate temperature (see 10.7 and 10.9). cooling water, exiting the steam cooker and directed to the
1.2.11 Cooking uniformity (see 10.10). floor drain.
1.3 The values stated in inch-pound units are to be regarded 3.1.3 cooking energy effıciency, n—quantity of energy im-
as standard. The SI units given in parentheses are for informa- parted to the specified food product expressed as a percentage
tion only. of energy consumed by the steam cooker during the cooking
1.4 This standard may involve hazardous materials, opera- event.
tions, and equipment. It does not address all of the safety 3.1.4 cooking energy rate, n—average rate of energy con-
concerns, if any, associated with its use. It is the responsibility sumption (kBtu/h or kW) during the cooking energy efficiency
of the user of this standard to establish appropriate safety and test. Refers to any loading scenario in the green pea or potato
health practices and determine the applicability of regulatory load tests.
limitations prior to use.
2
For referenced ASTM standards, visit the ASTM website, www.astm.org, or
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
Standards volume information, refer to the standard’s Document Summary page on
1
This test method is under the jurisdiction of ASTM Committee F26 on Food the ASTM website.
3
Service Equipment and is the direct responsibility of Subcommittee F26.06 on Available from American Society of Heating, Refrigerating and Air Condition-
Productivity and Energy Protocol. ing Engineers, Inc., 1791 Tullie Circle, NE, Atlanta, GA 30329.
4
Current edition approved April 1, 2004. Published April 2004. Originally Available from the Food Service Technology Center, 12949 Alcosta Blvd.,
approved in 1993. Last previous edition approved in 1999 as F 1484 – 99. #101, San Ramon, CA 94583.

Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.

1
F 1484 – 04
3.1.5 electric energy rate, n—refers to rate of electric testing ceases and the manufacturer is contacted. The manu-
energy consumption (kW) by steam cookers whose primary facturer may make appropriate changes or adjustments to the
fuel source is not electricity (for example, gas). Electric energy steam cooker.
is measured and reported separately from the primary fuel 4.2 The energy and time required to preheat the steamer to
energy so that the respective fuel prices can be applied to an operating condition are determined.
estimate energy costs. 4.3 Idle energy rate is determined for the steamer while it is
3.1.6 green pea load, n—12 by 20 by 21⁄2 in. (300 by 500 by maintaining operating pressure or temperature when no cook-
65 mm) perforated hotel pan filled with 8.0 6 0.2 lb (3.6 6 ing is taking place.
0.1kg) of fresh-frozen, grade A, green peas. 4.4 Pilot energy rate is determined when applicable to a gas
3.1.7 high-pressure steam cooker, n—steam cooker wherein fired steam cooker under test.
cooking compartment operates between 10 and 15 psig (Speci- 4.5 Green pea load cooking energy efficiency is determined
fication F 1217 Classification Grade C). by cooking a capacity number of frozen green pea loads from
3.1.8 idle energy rate, n—rate of energy consumed by the 0 to 180°F (–18 to 82°C).
steam cooker while maintaining the boiler or reservoir at a 4.6 Whole potato load cooking energy efficiency is deter-
manufacturer-defined operating pressure or temperature with mined by cooking a capacity number of fresh whole potatoes to
no cooking taking place. a specified doneness.
3.1.9 low-pressure steam cooker, n—steam cooker wherein 4.7 Green pea load and whole potato load production
cooking compartment operates between 3 and 9.9 psig (Speci- capacities (lbpea/h or lbpotato/h (kgpea/h or kg potato/h)) are
fication F 1217 Classification Grade B). determined by the respective cooking energy efficiency tests.
3.1.10 maximum energy input rate, n—peak rate at which an 4.8 Water consumption (gal/h (L/h)) is monitored during
appliance consumes energy, typically reflected during preheat. both cooking energy efficiency tests to determine the rate of
3.1.11 pilot energy rate, n—rate of energy consumption water usage.
(kBtu/h) by a gas steam cooker’s standing pilot (if applicable). 4.9 Condensate temperature is monitored during both cook-
3.1.12 potato load, n—one 12 by 20 by 21⁄2 in. (300 by 500 ing energy efficiency tests.
by 65 mm) perforated hotel pan filled with 50 6 2 fresh, whole, 4.10 The uniformity of heating within the steamer’s com-
US No. 1, size B, red potatoes, weighing 8.0 6 0.2 lb (3.6 6 partment is determined and reported based on the average
0.1 kg). temperature on each pan during ice load cooking tests (pans of
3.1.13 preheat, n—process of bringing the steamer (boiler) ice simulating pans of frozen food).
water from city supply temperature to operating temperature
(pressure). 5. Significance and Use
3.1.14 preheat duration, n—total time required for preheat,
from preheat initiation at controls to when the steam cooker is 5.1 The maximum energy input rate test is used to confirm
ready to cook. that the steam cooker is operating at the manufacturer’s rated
3.1.15 preheat energy, n—amount of energy consumed by input. This test would also indicate any problems with the
the steam cooker during a preheat. electric power supply, gas service pressure, or steam supply
3.1.16 pressureless steam cooker, n—steam cooker wherein flow or pressure.
cooking compartment operates between 0 and 2.9 psig (Speci- 5.2 Preheat energy and duration can be useful to food
fication F 1217 Classification Grade A). service operators for managing power demands and knowing
3.1.17 production capacity, n—maximum rate (lb (kg)/h) at how quickly the steam cooker can be ready for operation.
which steam cooker can bring the specified food product to a 5.3 Idle energy rate and pilot energy rate can be used to
specified “cooked” condition. estimate energy consumption.
3.1.18 production rate, n—rate (lb (kg)/h) at which steam 5.4 Green pea load cooking energy efficiency is an indicator
cooker brings the specified food product to a specified of steam cooker energy performance when cooking frozen
“cooked” condition. Does not necessarily refer to maximum products under various loading conditions. This allows the
rate. The production rate varies with the loading scenario and food service operator to consider energy costs when selecting
the amount of product being cooked. a steam cooker.
3.1.19 steam cooker, n—cooking appliance wherein heat is 5.5 Potato load cooking energy efficiency is an indicator of
imparted to food in a closed compartment by direct contact steam cooker energy performance when cooking foods that
with steam. The compartment can be at or above atmospheric require long cook times (for example, potatoes, beans, rice,
pressure. The steam can be static or circulated. lasagna or casserole rethermalization). The test demonstrates
3.1.20 water consumption, n—water consumed by the the difference in energy efficiency between pressure and
steam cooker. Includes both water used in the production of pressureless steam cookers for this type of cooking event. The
steam and cooling water (if applicable) for condensing/cooling information may help a food service operator to evaluate what
unused steam. type of steamer to select (pressure versus pressureless versus
dual pressure mode) from an energy performance perspective.
4. Summary of Test Method 5.6 Green pea load production capacity and potato load
4.1 The maximum energy input rate is determined to check production capacity can be used by food service operators to
whether the steam cooker is operating properly. If the mea- choose a steam cooker to match their particular food output
sured input rate is not within 5 % of the rated input, all further requirements.

2
F 1484 – 04
5.7 Water consumption characterization is useful for esti- to standard conditions, having a resolution of 0.2 in. Hg (670
mating water and sewerage costs associated with appliance Pa) and an uncertainty of 0.2 in. Hg (670 Pa).
operation. 6.10 Flow Meter, for measuring total water consumption of
5.8 Condensate temperature measurement is useful to verify the appliance. The meter shall have a resolution of 0.01 gal (40
that the temperature does not exceed regional building code ml), and an uncertainty of 0.01 gal (40 ml), at flow rate as low
limits. as 0.2 gpm (13 ml/s).
5.9 Cooking uniformity provides information regarding the 6.11 Stopwatch, with a 1-s resolution.
steamer’s ability to cook food at the same rate throughout the 6.12 Analytical Balance Sale, for measuring weight of food
steamer’s compartment. for cooking test loads and for weighing hotel pans. It shall have
a resolution of 0.01 lb (5 g) and an uncertainty of 0.01 lb (5 g).
6. Apparatus 6.13 Calibrated Exposed Junction Thermocouple Probes,
6.1 Watt-Hour Meter, for measuring the electrical energy with a range from –20 to 400°F (–30 to 200°C), with a
consumption of a steam cooker, shall have a resolution of at resolution of 0.2°F (0.1°C) and an uncertainty of 0.5°F (0.3
least 10 Wh and a maximum uncertainty no greater than 1.5 % °C), for measuring temperature of frozen green peas, potatoes,
of the measured value for any demand greater than 100 W. For calorimeter water, water entering the boiler, and condensate.
any demand less than 100 W, the meter shall have a resolution Calibrated Type T thermocouples (24 GA wire) are a good
of at least 10 Wh and a maximum uncertainty no greater than choice.
10 %. 6.14 Hotel Pans, for frozen green pea and potato loads,
perforated 12 by 20 by 21⁄2 in. (300 by 500 by 65 mm) stainless
6.2 Gas Meter, for measuring the gas consumption of a
steel weighing 2.8 6 0.2 lb (1.3 6 0.1 kg).
steam cooker, shall be a positive displacement type with a
6.15 Water-Bath Calorimeter, for temperature determina-
resolution of at least 0.01 ft3 (0.0003 m3) and a maximum
tion of the cooked green pea load. The calorimeter is comprised
uncertainty no greater than 1 % of the measured value for any
of five components and are shown in Fig. 1: inner container—
demand greater than 2.2 ft3/h (0.06 m3/h). If the meter is used
cylindrical, 0.087-in. (2.2-mm) thick walled, plastic drum
for measuring the gas consumed by the pilot lights, it shall
(PG&E found that a 15-gal container is adequate for most
have a resolution of at least 0.01 ft3 (0.0003 m3) and have a
applications); drum insulation—R-25 fiberglass insulation;
maximum uncertainty no greater than 2 % of the measured
drum lid—plastic lid double reinforced with 2-in. (50 mm)
value.
thick polystyrene board; stirrer—3-ft long, 1⁄4-in. diameter,
6.3 Steam Flow Meter, for measuring the flow of steam to a
steel rod with propeller welded to one end; thermocouple
steam cooker that uses either a direct external potable steam
tree—1⁄4-in. diameter pipe with five temperature sensors at-
source or a steam coil steam generator. Shall have a resolution
tached laterally equidistant from one another. The sensors must
of 0.01 ft3 (0.0003 m3) and a maximum uncertainty of 1 % of
be adjusted so that they are fully submerged for each loading
the measured value.
scenario. A convenient way to construct the water-bath calo-
6.4 Pressure Gage, for measuring pressure of steam to a rimeter is to place the inner container on a 2-in. (50 mm) thick
steam cooker that uses either a direct external potable steam polystyrene board. Wrap the outside of the drum with 1 ft thick
source or a steam coil steam generator. Shall have a resolution R-25 fiberglass insulation so no drum wall is exposed. Cover
of 0.5 psig (3.4 kPa) and a maximum uncertainty of 1 % of the the fiberglass insulation with plastic liner to waterproof the
measured value. interior. Construct the thermocouple tree by affixing five type T
6.5 Canopy Exhaust Hood, 4 ft (1.2 m) in depth, wall- thermocouple probes 3 in. apart along the copper pipe. Fix the
mounted with the lower edge of the hood 6 ft, 6 in. (2.0 m) thermocouple tree vertically along the drum wall as to avoid
from the floor and with the capacity to operate at a nominal contact with the stirrer. Drill a 1⁄2-in. hole in the center of the
exhaust ventilation rate of 150 cfm per linear foot (230 L/s per plastic/polystyrene lid. Place the propeller end of the stirrer in
linear meter) of active hood length. This hood shall extend a the drum and close the lid, allowing the opposite end of the
minimum of 6 in. (150 mm) past both sides and the front of the stirrer to pass through the center of the lid. The calorimeter can
cooking appliance and shall not incorporate side curtains or be placed on castors for ease in mobility, and the content can
partitions. Makeup air shall be delivered through face registers be stirred manually or with the aid of a portable, handheld drill
or from the space, or both. during a test.
6.6 Pressure Gage, for monitoring boiler pressure. The gage
shall have a resolution of 0.5 psig (3.4 kPa) and a maximum
uncertainty of 1 % of the measured value.
6.7 Pressure Gage, for monitoring natural gas pressure. The
gage shall have a range of 0 to 15 in. H2O (0 to 3.7 kPa), a
resolution of 0.5 in. H2O (125 Pa), and a maximum uncertainty
of 1 % of the measured value.
6.8 Temperature Sensor, for measuring gas temperature in
the range of 50 to 100°F (10 to 40 °C), with a resolution of
0.1°F (0.05 °C) and an uncertainty of 60.5°F (0.3°C).
6.9 Barometer, for measuring absolute atmospheric pres-
sure, to be used for adjustment of measured natural gas volume FIG. 1 Water-Bath Calorimeter

3
F 1484 – 04
6.16 Hypodermic-Style Thermocouple Probe for measuring 7.3 Potatoes shall be fresh, whole, US No. 1, Size B, red
potato temperatures. Minimum diameter makes for easier potatoes. The average weight of the potatoes shall be 0.16 6
insertion and faster response. Resolution and uncertainty shall 0.02 lb (73 6 9 g).
be the same as in 6.13. NOTE 1—Red potatoes are sold in three sizes: A, B, and C. This test
6.17 Surface Temperature Thermocouple Probe, for measur- uses Size B.
ing boiler surface temperature. Resolution and uncertainty
shall be the same as in 6.13. This sensor will not be needed if 7.4 Water used for the cooking uniformity test shall have a
the city water supply temperature is 70 6 5°F (21 6 3°C). maximum hardness of three grains per gallon. Distilled water
6.18 Platform Balance Scale, or appropriate load cells, used may be used.
to measure the weight of the water-bath calorimeter and
8. Sampling
content during the frozen green pea load test. Shall have the
capacity to accommodate the total weight of calorimeter plus 8.1 Steam Cooker— A representative production model
the cooked food product and water. The resolution shall be 0.2 shall be selected for performance testing.
lb (10 g) with an uncertainty of 0.2 lb (10 g).
6.19 Hotel Pans, for ice loads, solid 12 by 20 by 21⁄2-in. 9. Preparation of Apparatus
(300 by 500 by 65-mm) stainless steel, weighing 2.8 6 0.2 lb 9.1 Install the appliance in accordance with the manufactur-
(1.3 6 0.1 kg), with a temperature sensor located in the center er’s instructions under a 4 ft (1.2 m) deep canopy exhaust hood
of each pan 5⁄8 in. (16 mm) from the bottom. A convenient mounted against the wall, with the lower edge of the hood 6 ft,
method is to have Type T thermocouple probes with a 6 in. (2.0 m) from the floor. Position the steam cooker so that
stainless-steel protective sheath fabricated in the shape shown the front edge is 6 in. (150 mm) inside the front edge of the
in Fig. 2. The sensing point is exposed and isolated thermally hood. In addition, both sides of the steam cooker shall be a
from the stainless-steel sheath. The probe is strapped to the pan minimum of 3 ft (1.1 m) from any wall, side partition, or other
using steel shim stock welded to the pan using a strain gage operating appliance. Equipment configuration is shown in Fig.
welder. The thermocouple lead TFE-fluorocarbon sheath is 3. The exhaust ventilation rate shall be 150 cfm per linear foot
minimum thickness (TFE-fluorocarbon wrap rather than ex- (230 L/s per linear meter) of hood length. The associated
truded TFE-fluorocarbon) to minimize the escape of steam heating or cooling system shall be capable of maintaining an
through the door gasket where the thermocouple exits the ambient temperature of 75 6 5°F (24 6 3°C) within the testing
cooking compartment. The lead is long enough to allow environment when the exhaust ventilation system is working
connection to the monitoring device while the ice loads are in without the appliance being operated.
the freezer, while they are being weighed, and while they are in 9.2 Connect the steam cooker to a calibrated energy test
the steam cooker. meter. For gas installations, a pressure regulator shall be
installed downstream from the meter to maintain a constant
7. Reagents and Materials pressure of gas for all tests. Both the pressure and temperature
7.1 Quality of water used to fill the boiler shall meet the of the gas supplied to a steam cooker, as well as the barometric
manufacturer’s specifications. pressure, shall be recorded during each test so that the
7.2 Green peas shall be fresh-frozen, grade A, stabilized at measured gas flow can be corrected to standard conditions. For
0 6 5°F (–18 6 2°C). a steam cooker that uses either a direct external potable steam

FIG. 2 Hotel Pan with Thermocouple Probe

4
F 1484 – 04

FIG. 3 Equipment Configuration

source or a steam coil steam generator, there shall be a pressure 10.1.1.1 Higher heating value,
gage and steam flow meter to verify that the manufacturer’s 10.1.1.2 Standard gas conditions for calculation in 11.3.2,
specified steam requirements are met. For electric installations, 10.1.1.3 Measured gas temperature,
a voltage regulator may be required during tests if the voltage 10.1.1.4 Measured gas pressure,
supply is not within 62.5 % of the manufacturer’s nameplate 10.1.1.5 Barometric pressure, and
voltage. 10.1.1.6 Measured peak input rate during or immediately
9.3 For an electric steam cooker, confirm (while the steam prior to test.
cooker elements are energized) that the supply voltage is
within 62.5 % of the operating voltage specified by the NOTE 4—The preferred method for determining the heating value of
manufacturer. The test voltage shall be recorded for each test. gas supplied to the steam cooker under test is by using a calorimeter or gas
chromatography in accordance with accepted laboratory procedures. It is
NOTE 2—If an electric steam cooker is rated for dual voltage (for recommended that all testing be performed with gas having a heating
example, 208/240 V), the voltage selected by the manufacturer or tester, value between 1000 and 1075 Btu/ft3 (37 300 to 40 100 kJ/m3).
or both, shall be reported. If an oven is designed to operate at two voltages
without a change in the resistance of the heating elements, the perfor- 10.1.2 For gas steam cookers, energy calculations shall be
mance of the oven (for example, preheat time) may differ at the two in accordance with 11.3.
voltages. 10.1.3 For gas steam cookers, electric energy consumption
9.4 For a gas steam cooker, adjust (during a boiler preheat) shall also be measured and added to gas energy for all tests,
the gas pressure downstream from the appliance pressure with the exception of the maximum energy input rate test
regulator to within 62.5 % of the operating manifold pressure (10.2). If it is clear (from the equipment manual or another
specified by the manufacturer. Also make adjustments to the source of information) that the electric energy consumption
appliance following the manufacturer’s recommendations for rate is constant during a test, then an instantaneous power
optimizing combustion. measurement can be made when convenient during that test,
9.5 Install a flow meter (6.10) to the steam cooker water rather than continuous monitoring of accumulated energy
inlet such that total water flow to the appliance (both boiler consumption. Energy can be estimated later, based on the
supply water and condensate cooling water) is measured. power measurement and the duration of the test.
9.6 Install a pressure gage (6.6) to measure boiler pressure. 10.1.4 For electric steam cookers, the following shall be
9.7 Install a temperature sensor (6.13) such that it is obtained and recorded for each run of every test.
immersed in the condensate water path just as it exits the steam 10.1.4.1 Voltage while elements are energized, and
cooker. 10.1.4.2 Measured peak input rate during or immediately
9.8 Tape a temperature sensor (6.13) firmly to the surface of prior to test.
a section of the metal tubing through which city water enters 10.1.5 For steam cookers that use either a direct external
the boiler. potable steam source or a steam coil steam generator, the
supplied steam pressure and average flow rate shall be recorded
10. Procedure
for each run of every test.
NOTE 3—Prior to starting these tests, the tester should read the 10.1.6 For each run of every test, confirm that the peak input
operating manual and fully understand the operation of the appliance. rate is within 65 % of rated nameplate input. If the difference
10.1 General: is greater than 5 %, testing shall be terminated and the
10.1.1 For gas steam cookers, the following shall be ob- manufacturer contacted. The manufacturer may make appro-
tained and recorded for each run of every test. priate changes or adjustments to the steam cooker.

5
F 1484 – 04
10.1.7 If a steam cooker is able to operate in more than one operated under this idle condition for a minimum of 2 h. For
pressure mode (for example, both low pressure and pressure- gas steam cookers, monitor electric energy in addition to gas
less), the tester shall record the operating mode selected for consumption.
testing and conduct all tests herein using the same operating 10.4.1.1 If there is a separate boiler for each compartment,
mode. then apply this test (and report an idle rate) for each compart-
10.2 Maximum Energy Input Rate: ment separately and then for all compartments simultaneously.
10.2.1 This step applies to gas steam cookers only. (For 10.4.2 This step applies to non-atmospheric boilers only. In
electric steam cookers, proceed directly to step 10.2.2, and for addition to monitoring total energy for the test period, record
steam coil steam cookers, proceed directly to step 10.2.3.) For the quantity of energy consumed during each individual cycle
some gas appliances, the maximum energy input rate changes for three cycles of the boiler. Record the average of these
as the orifices heat up. If the steam cooker under test is gas values as the energy required to raise the boiler from minimum
powered, conduct a boiler fill and preheat, then immediately operating pressure/temperature to maximum pressure/
purge the boiler and proceed to step 10.2.3. temperature. This value is used in the green pea load and potato
10.2.2 This step applies to electric steam cookers only. load energy efficiency calculations.
Monitor power during a steam cooker operation where the 10.4.3 In accordance with 11.6, calculate and report idle
maximum power is drawn. Proceed directly to step 10.2.4. energy rate(s).
10.2.3 Allow the boiler(s) or reservoir to fill with water. As 10.5 Pilot Energy Rate (Gas Models with Standing Pilots):
soon as the boiler(s) or reservoir is (are) full, start the preheat 10.5.1 With the pilot lit and the boiler off, record time and
(some boilers may start automatically after filling). Begin gas consumption for a minimum of 8 h. In accordance with
monitoring energy consumption and time as soon as all the 11.7, calculate and report pilot energy rate.
burners, elements, or steam coils energize. Continue until the 10.6 Green Pea Load Preparation:
first burner, element, or steam coil turns off. Record final time 10.6.1 This section outlines preparation of the frozen green
and energy. peas used in the green pea load cooking energy-efficiency and
10.2.4 In accordance with 11.4, determine the maximum production-capacity test (10.7).
energy input rate for the steam cooker under test. Report the 10.6.2 The number of green pea loads to be prepared
measured input rate and confirm that it is within 5 % of the depends on which loading scenario is to be performed. There
rated nameplate input. If the difference is greater than 5 %, are two loading scenarios: light and heavy. The heavy load is
testing shall be terminated and the manufacturer contacted. The the manufacturer’s stated capacity of 12 by 20 by 21⁄2-in. (300
manufacturer may make appropriate changes or adjustments to by 500 by 65-mm) hotel pans. Consult Table 1 for the number
the steam cooker. of green pea loads to prepare for the light loading scenarios.
10.3 Preheat Energy Consumption and Duration:
10.3.1 Fill the boiler or reservoir. Record the time required NOTE 5—When the test calls for a less than capacity number of loads
for a compartment, the loads should be placed in the most centrally
to fill it. Monitor the average temperature of the water as it
located slots. When symmetry about the center is not possible, then use the
enters the boiler or reservoir. If the average temperature was upper central slots first. For example, one pan in a four-pan capacity
not 70 6 5°F (21 6 3°C), then allow the filled boiler or compartment should be located in the second slot from the top. Two loads
reservoir to sit until the temperature is within that range. in a four-pan capacity compartment should be located in the second and
Temperature of the water in the boiler can be estimated by third slots from the top (yielding symmetry about the center). One load in
measuring the boiler surface temperature using a surface a three-pan capacity compartment would be located in the center, and two
temperature probe (6.17). loads would be located in the top and middle slots. Two pans in a five-pan
capacity compartment would be located in the second slot from the top
10.3.2 Record the temperature of the water in the boiler or and third slot from the top (center slot).
reservoir. Start the preheat. Begin monitoring energy consump-
tion and time as soon as the boiler is turned on. For a gas steam 10.6.3 The perforated hotel pans shall be as specified in
cooker, the recorded preheat time shall include any delay 6.14.
between the time the unit is turned on and when the burners 10.6.4 Number each pan and record the weight of each of
actually ignite. For a gas steam cooker, measure and record any the (empty) pans. The weight of the pan(s) will be the total
electric energy consumption as well. Preheat is judged com- weight of all pans used for the test.
plete when the primary burners, elements, or steam coil cycles 10.6.5 Load each pan with 8.0 6 0.2 lb (3.6 6 0.1 kg) (see
off or when the steamer compartment reaches 210°F (boilerless 7.2) of green peas sealed in plastic zip bags. Record the weight
steamers). Record preheat energy consumption, duration, and of the frozen green peas in each pan. Place the green pea load
final pressure (if applicable). in the freezer and allow the temperature to stabilize at 0 6 5°F
10.3.3 In accordance with 11.5, report preheat energy con- (–18 6 2°C). For a 24 h period. The weight of the frozen green
sumption and duration. peas will be the total weight of the green peas in each of the
10.4 Idle Energy Rate: pan(s).
10.4.1 If the steamer is equipped with a standby (idle) 10.6.6 The water-bath calorimeter shall be as specified in
mode, then set the appliance controls to this mode. Allow the 6.15. Record the weight of the empty calorimeter using the
steamer to idle, that is, operate in standby for at least 60 min platform balance scale (6.6).
after the preheat. Then commence monitoring the elapsed time 10.6.7 Place 10 lb of potable water for every pan of green
and the energy consumption of the steam cooker while it is peas into the calorimeter drum. (For example, the total weight

6
F 1484 – 04
TABLE 1 Number of Loads for Light Loading Scenario production capacity, condensate temperature, and water con-
Light Loading Scenario sumption shall be the average of the replications (runs).
1 Compartment 1 Pan 10.7.2 Prepare the frozen green pea load(s) in accordance
3 Pan Capacity with 10.6. Record the weight of the empty pan(s) and the
1 Compartment 1 Pan
weight of the green pea load(s).
4 Pan Capacity 10.7.3 Measure and record the average temperature of the
green peas by probing the content of the sealed bags. Confirm
1 Compartment 1 Pan
5 Pan Capacity
that they are at 0 6 5°F (–18 6 3°C).
10.7.4 Choose a cooking time either based on the manufac-
1 Compartment 1 Pan turer’s recommendation or by experience.
6 Pan Capacity
10.7.5 Allow the steam cooker to sit idle, that is, stabilize in
2 Compartments 1 Pan in top compartment a ready-to-cook state (boiler(s) on) for a minimum of 1 h. If the
3 Pan Capacity Per None in bottom manufacturer recommends leaving the cooking cavity doors
Compartment
open when not cooking, then leave them open during the
2 Compartments 1 Pan in top compartment stabilization period and record the door position during the
4 Pan Capacity Per None in bottom stabilization period.
Compartment
NOTE 7—The steamer shall be stabilized in the same operating mode
2 Compartments 2 Pans in top compartment that will be used for the cooking test. If the steamer is to be tested in a
5 Pan Capacity Per None in bottom
Compartment
reduced-input mode, then the steamer shall be stabilized in the same mode
for at least 1 h prior to loading with food product.
2 Compartments 2 Pans in top compartment
6 Pan Capacity Per None in bottom 10.7.6 After the stabilization period, wait for the burners,
Compartment elements, or steam coil to cycle on and then off again. This
assures that the boiler is at maximum operating pressure/
2 Compartments 2 Pans in top compartment
8 Pan Capacity Per None in bottom temperature when the efficiency test cooking starts.
Compartment 10.7.7 Start monitoring time. Transport the green pea loads
to the testing location. Empty the bagged green peas into the
3 Compartments 2 Pans in middle compartment
3 Pan Capacity Per None in top pan(s). Open one steam compartment, load the pan(s) into it,
Compartment None in bottom close it, and start steam to it. Open the next steam compartment
(if applicable), load it, close it, start it, and note the starting
3 Compartments 2 Pans in middle compartment
4 Pan Capacity Per None in top time. Open, load, close and start the last compartment (if
Compartment None in bottom applicable). After starting steam to the first compartment,
3 Compartments 2 Pans in middle compartment
commence monitoring energy consumption, water consump-
5 Pan Capacity Per None in top tion, and condensate temperature. For gas steam cookers,
Compartment None in bottom monitor and record the electric energy as well as gas consump-
3 Compartments 2 Pans in middle compartment
tion. The total loading time (the time from opening the first
6 Pan Capacity Per None in top compartment to closing and starting the last compartment)
Compartment None in bottom shall be the total of 5 s per compartment plus 5 s for each load
3 Compartments 2 Pans in middle compartment
used. (For example, the total loading time for a heavy load test
8 Pan Capacity Per None in top of a six-pan capacity, two-compartment steam cooker would be
Compartment None in bottom 5 s/compartment 3 2 compartments + 5 s/load 3 6 loads = 40
s).
NOTE 8—Care shall be taken to minimize heat gain by the frozen green
pea loads on the way from the freezer to the steam cooker. During that
of water for a heavy load test of a six-pan capacity, steamer time they shall be isolated from any warmer surface by R10 or better
would be 10 lb water/pan 3 6 pans = 60 lb). insulation. PG&E found 2 in. (50 mm) thick square-edged polystyrene
NOTE 6—The initial water temperature for the water-bath need not be boards to be convenient as an insulating surface.
70 6 5°F (21 6 3°C). As long as the initial and final temperatures are NOTE 9—For gas steamers, the “electric energy rate” during the heavy
recorded, the change in water-bath temperature can be obtained. load test will be reported separately from the gas “cooking energy rate.”
The two values are reported separately so that the respective fuel prices
10.6.8 Record the weight of the water in the water-bath may be applied to estimate energy costs.
calorimeter. NOTE 10—The boiler is at maximum pressure when the test starts, but
10.7 Green Pea Load Cooking Energy Effıciency, Produc- it may be at a lower pressure at the end of the test. This difference between
tion Capacity, Water Consumption, and Condensate Tempera- the initial and final energy content (pressure/temperature) of the boiler
ture : must be added back to the boiler to correctly calculate the energy
efficiency. Maximum, minimum and final boiler pressure is measured so
10.7.1 This procedure applies to two possible loading sce- that this energy deficit can be estimated. There are situations where the
narios: light and heavy. Repeat each loading scenario a measurement of pressure in step 10.7.8 is not necessary, as noted in steps
minimum of three times. Additional test runs may be necessary 10.7.10 and 10.7.12.
to obtain the required precision for the reported test results NOTE 11—The average condensate temperature for the final 3 min of
(Annex A1). The reported values of cooking energy efficiency, the run is what will be reported, rather than the average over the entire run;

7
F 1484 – 04
therefore, condensate temperature monitoring need not begin immediately 10.7.19 Confirm that the multi-test (three run) average final
upon commencement of the test run. pea temperature is 180 6 2°F (82 6 1°C). If the average final
10.7.8 For three cycles of the boiler pressure near the end of pea temperature does not fall within this range, then repeat
the test, measure the maximum and minimum pressures. 10.7.2-10.7.18 with an appropriately adjusted cook time to
Record the average maximum and average minimum boiler achieve this average temperature.
pressure. 10.7.20 Calculate the cooking energy efficiency, production
10.7.9 Terminate steam to the compartments as the prede- capacity, water consumption, and average condensate tempera-
termined cooking time elapses for each compartment. After ture in accordance with 11.8 and report the results as the
stopping steam to the last compartment, record the final time, average of three replications.
water consumption, and average condensate temperature. 10.8 Whole Potato Load Preparation:
10.8.1 This section outlines preparation of the potato loads
10.7.10 If the boiler is on when the cooking time for the last
used in the whole potato load cooking energy efficiency and
compartment has elapsed, continue to monitor energy con-
production capacity test (10.9). The number of potato loads to
sumption until the primary burners, elements, or steam coils
be prepared depends on which loading scenario is to be
cycle off. Record final energy. Note that the initial and final
performed. There are two loading scenarios: light and heavy.
energy content of the boiler is the same; therefore, the pressure
The heavy load is the manufacturer’s stated capacity of 12 by
measurements in step 10.7.8 are not needed.
20 by 21⁄2 in. (300 by 500 by 65 mm) hotel pans. Consult Table
10.7.11 If the boiler is not on when the last compartment 1 for the number of potato loads to prepare for the light loading
cooking time elapsed, proceed to one of the next two condi- scenario. For each loading scenario, prepare enough potato
tional steps (10.7.12 or 10.7.13). loads for a minimum of three runs.
10.7.12 Perform this step if the boiler pressure is controlled 10.8.2 The perforated hotel pans shall be as specified in
by a pressure switch that can be manually actuated. Otherwise, 6.14. Number each pan and record the weight of each (empty)
proceed directly to step 10.7.13. When the time for the last pan.
compartment has elapsed, continue to monitor energy con- 10.8.3 Load each pan with 8.0 6 0.2 lb (3.6 6 0.1 kg) of red
sumption and actuate the pressure switch. This returns the potatoes (7.3). Each pan shall contain between 48 and 52 red
boiler energy content to the initial test condition; therefore, the potatoes. Record the actual weight and count of the potato load
pressure measurements in step 10.7.8 and the energy measure- in each pan.
ments in step 10.4.2 are not necessary. Record the final energy.
NOTE 12—If the weight of the potatoes on a pan is outside the 8.0 6 0.2
10.7.13 Perform this step if the boiler pressure control
lb (3.6 6 0.1 kg) weight range specified above, substitute smaller or larger
cannot be manually actuated. When the cooking time for the potatoes, as necessary, until the weight of the potatoes on each pan is
last compartment has elapsed, record the final energy and the within the required weight range while maintaining a count of 50 6 2
boiler pressure (used to calculate the energy deficit of the potatoes per pan.
boiler, as described in Note 10).
10.9 Whole Potato Load Cooking Energy Effıciency, Pro-
10.7.14 Record the initial temperature of the water-bath duction Capacity, Water Consumption, and Condensate Tem-
calorimeter immediately before the cook time elapsed. The perature :
unloading time shall be the same as the loading time. Remove
10.9.1 This procedure applies to two possible loading sce-
the calorimeter lid and empty the cooked green pea load(s) into
narios: light and heavy. Each loading scenario shall be repeated
the water-bath calorimeter. Replace the lid on the water-bath
a minimum of three times. Additional test runs may be
calorimeter.
necessary to obtain the required precision for the reported test
10.7.15 Using the stirrer, agitate the content for 1 min, then results (Annex A1). The reported values of cooking energy
allow the contents of the water-bath calorimeter to stabilize for efficiency, production capacity, condensate temperature, and
5 min. Repeat the agitation and stabilization process every 5 water consumption shall be the average of the replications
min until the bulk temperature fluctuation is less than 60.1°F (runs).
within a 5 min period. Record this temperature as the final bulk 10.9.2 Prepare the potato loads in accordance with 10.8.
temperature. Record the weight of the empty pans, the weight of the potato
10.7.16 Record the total weight of the water-bath calorim- load in each pan, and the number of potatoes in each pan.
eter containing the cooked green peas and water with the Record the number of potato loads to be used for each run.
platform balance scale. This will be used to determine the 10.9.3 Choose a cooking time either based on the manufac-
weight of the cooked green peas. turer’s recommendation or by experience.
10.7.17 In accordance with 11.8.2, calculate the final 10.9.4 Randomly select potatoes from each pan for tem-
cooked bulk temperature of the green peas. The cook tempera- perature monitoring. For single-pan tests (light loads), record
ture must be 180 6 5°F (82 6 3°C) for the test run. If the the temperature of at least 15 potatoes. For two to six pan
temperature does not fall within this range, the test must be loads, record the temperature of at least five potatoes per pan.
repeated with an adjusted cook time. For loads of seven or more pans, record the temperature of at
10.7.18 If the temperature is within the range, prepare the least three potatoes per pan.
next frozen green pea load (10.6) and the water-bath calorim- 10.9.5 Shortly before each test run, place a hypodermic-
eter, unless this was the final run (Run No. 3), and perform the style thermocouple probe into the center of the randomly-
test again (10.7). selected potatoes. Secure each thermocouple lead wire in such

8
F 1484 – 04
a manner that its junction will remain at the center of the potato loading time for a heavy load test of a six-pan capacity,
throughout the cooking period. The temperature of the potatoes two-compartment steam cooker would be: 5 s/compartment3 2
at the start of each test shall be 75 6 5°F (24 6 3°C). compartments + 5 s/load 3 6 loads = 40 s).
NOTE 13—Steamers that operate with the cooking compartment under
10.9.9 For three cycles of the boiler pressure near the end of
pressure or vacuum may not function properly with thermocouples the test, measure the maximum and minimum pressures.
passing through the door seal. For these steamers, it may not be possible Record the average maximum and average minimum boiler
to monitor potato temperature during the cooking cycle. pressure.
10.9.6 Allow the steam cooker to stabilize in a ready-to- NOTE 16—For gas steamers, the “electric energy rate” during the heavy
cook state (boiler on) for a minimum of 1 h. If the manufac- load test will be reported separately from the gas “cooking energy rate.”
turer recommends leaving the cooking cavity doors open when The two values are reported separately so that the respective fuel prices
not cooking, leave them open during the stabilization period. may be applied to estimate energy costs.
Record the door position during the stabilization period. Fig. 4 NOTE 17—The average condensate temperature for the final 5 min of
shows the cooking energy efficiency test sequence. the run is what will be reported, rather than the average over the entire run;
therefore, condensate temperature monitoring need not begin immediately
NOTE 14—The steamer shall be stabilized in the same operating mode upon commencement of the test run.
that will be used for the cooking test. If the steamer is to be tested in a
reduced-input mode, then the steamer shall be stabilized in the same mode 10.9.10 Terminate steam to the compartments when the
for at least 1 h prior to loading with food product. average potato temperature reaches 195 6 2°F (91 6 1°C).
10.9.7 After the stabilization period, wait for the burners, After stopping steam to the last compartment, record the final
elements, or steam coil to cycle on and then off again. This time, water consumption, average potato temperature and
assures that the boiler is at maximum operating pressure/ average condensate temperature.
temperature when the efficiency test cooking starts. 10.9.11 If the boiler is on when the cooking time for the last
compartment has elapsed, continue to monitor energy con-
NOTE 15—The boiler is at maximum pressure when the test starts, but sumption until the primary burners, elements, or steam coils
it may be at a lower pressure at the end of the test. This difference between cycle off. Record the final energy. Note that the initial and final
the initial and final energy content (pressure/temperature) of the boiler
must be added back to the boiler to correctly calculate the energy
energy content of the boiler is the same; therefore, the pressure
efficiency. Maximum, minimum and final boiler pressure is measured so measurements in step 10.9.9 are not needed. Proceed directly
that this energy deficit can be estimated. There are situations where the to step 10.9.15.
measurement of pressure in step 10.9.9 is not necessary, as noted in steps 10.9.12 If the boiler is not on when the cooking time for the
10.9.11 and 10.9.13. last compartment has elapsed, then proceed to one of the next
10.9.8 Start monitoring time. Open one steam compartment, two conditional steps (10.9.13 or 10.9.14).
load it with potato loads, close it, and start steam to it. Note the 10.9.13 Perform this step if the boiler pressure is controlled
starting time for that compartment. Open the next steam by a pressure switch that can be manually actuated. Otherwise,
compartment (if applicable), load it, close it, start it, and note proceed directly to step 10.9.14. When the cooking time for the
the starting time. Open, load, close, start, and note starting time last compartment has elapsed, continue to monitor energy
of the last compartment (if applicable). After starting steam to consumption and actuate the pressure switch. This returns the
the first compartment, commence monitoring energy consump- boiler energy content to the initial test condition; therefore, the
tion, water consumption, potato temperature and condensate pressure measurements in step 10.9.9, and the energy measure-
temperature. For gas steam cookers, monitor and record ments in step 10.4.2 are not necessary. Record the final energy.
electric energy as well as gas consumption. The total loading Proceed directly to step 10.9.15.
time (the time from opening the first compartment to closing 10.9.14 Perform this step if the boiler pressure control
and starting the last compartment) shall be the total of 5 s per cannot be manually actuated. When the cooking time for the
compartment plus 5 s for each load used (for example, the total last compartment has elapsed, record the final energy and the

FIG. 4 Cooking Energy Efficiency Test Sequence

9
F 1484 – 04
boiler pressure (used to calculate the energy deficit of the applicable). After starting steam to the first compartment,
boiler, as described in Note 15). commence monitoring the temperature of the ice loads. The
10.9.15 Confirm the cooked potato temperature by measur- total loading time (the time from opening the first compartment
ing and recording the temperature of five randomly selected to closing and starting the last compartment) shall be the total
potatoes for each pan. Ensure that each quadrant in each pan is of 5 s per compartment plus 5 s for each ice load used. (For
represented. Temperature shall be measured immediately after example, the total loading time for a heavy load test of a
cooking is terminated. The last temperature taken shall be no six-pan capacity, two-compartment steam cooker would be 5
more than 3 min after cooking is terminated. The average bulk s/compartment 3 2 compartments + 5 s/ice load 3 6 ice loads
temperature (including monitored and spot-checked potatoes) = 40 s.)
must be 195 6 2°F (91 6 1°C). If the temperature does not fall NOTE 18—Care shall be taken to minimize heat gain by the ice loads on
in this range, the test must be repeated with an adjusted cook the way from the freezer to the steam cooker. During that time, they shall
time. be isolated from any warmer surface by R10 or better insulation. PG&E
10.9.16 Remove the potato loads, and unless this was the found 2-in. (50-mm) thick square-edged polystyrene boards to be conve-
final run (Run No. 3), start timing the 10 min stabilization nient as an insulating surface.
period before the next run (see Fig. 4). Return to step 10.9.7. NOTE 19—Care shall be taken to minimize heat loss out of the cooking
compartment where the sensor leads pass under the door gasket. PG&E
10.9.17 In accordance with 11.9, calculate and report cook- found that heat loss was not significant as long as the sensor leads were not
ing energy efficiency, production capacity, water consumption, bunched or paired as they passed under the door gasket.
and average condensate temperature. After performing this test
10.10.11 When the first pan reaches 170°F (77°C), stop the
(10.9) three times for each loading scenario, report results as
steam to that compartment. If there are two or more compart-
the average of the replications.
ments under test, continue to monitor the ice load temperature
10.10 Ice Load Cooking Uniformity:
of the other compartments, stopping steam to the compart-
10.10.1 The cooking uniformity test must be repeated three ments as the first pan reaches 170°F (77°C). When the last (or
times. The reported final pan temperatures shall be the average only) compartment’s first pan reaches 170°F (77°C), terminate
of the replications (runs). steam to the compartment and record total elapsed time.
10.10.2 The number of ice loads required depends on the 10.10.12 Remove the ice loads, and unless this was the final
steamer capacity. The heavy load is the manufacturer’s stated run (Run No. 3), start timing the 10-min stabilization period
capacity of 12 by 20 by 21⁄2-in. (300 by 500 by 65-mm) hotel before the next run. Return to 10.10.5.
pans. Prepare enough ice loads for three runs. 10.10.13 In accordance with 11.10, calculate and report the
10.10.3 The solid hotel pans shall be as specified in 6.19. average cook time and cooking uniformity. After performing
10.10.4 Number each pan and record the weight of each of this test at least three times, report the results as the average of
the (dry) pans. the replications.
10.10.5 Fill the pans with enough water such that there will
be 8.0 6 0.2 lb (3.6 6 0.1 kg) of ice after freezing (some water 11. Calculations and Reporting
will evaporate during freezing, especially if hotel pan lids are 11.1 Test Steam Cooker:
not used). Accurate measurement of the weight of the pans plus 11.1.1 Using Specification F 1217 classifications, summa-
the water prior to freezing is not required since they will be rize the physical and operating characteristics of the steam
weighed again just prior to testing. cooker. Use additional text to describe any design characteris-
10.10.6 Freeze the loads to 0 6 5°F (−18 6 2°C). tics that may facilitate the audience’s interpretation of the test
10.10.7 Record the initial average ice load temperature. results.
Confirm that they are at 0 6 5°F (−18 6 3°C). 11.2 Apparatus and Procedure:
10.10.8 Allow the steam cooker to stabilize in a ready-to- 11.2.1 Confirm that the testing apparatus conformed to all of
cook state (boiler(s) on) for a minimum of 1 h. If the the specifications in Section 9. Describe any deviations from
manufacturer recommends leaving the cooking cavity doors those specifications.
open when not cooking, leave them open during the stabiliza- 11.3 Gas and Steam Energy Calculations:
tion period and record the door position during the stabilization 11.3.1 For gas steam cookers, electric energy consumption
period. shall be added to gas energy for all tests, with the exception of
10.10.9 Near the end of the stabilization period, remove the maximum energy input rate test (10.2).
each pan from the freezer, remove the lid, and weigh. Record 11.3.2 For gas steam cookers, energy consumed ( Egas) shall
the weight of each ice load (including the pan itself) for that be calculated using the following formula:
run. Record the dry pan weights as determined in 10.10.4. After Egas 5 HV 3 V (1)
the stabilization period, wait for the burners, elements, or
steam coil to cycle on and then off again (if applicable). This where:
ensures that the boiler is at maximum operating pressure and E gas = energy consumed by steam cooker,
temperature when the cooking uniformity test cooking starts. HV = higher heating value
10.10.10 Start monitoring time. Open one steam compart- = energy content of gas measured at standard condi-
ment, load it with ice loads, close it, and start steam to it. Open tions, Btu/ft3 (kJ/m3), and
V = actual volume of gas corrected to standard condi-
the next steam compartment (if applicable), load it, close it,
tions, ft3(m3)
and start it. Open, load, close, and start the last compartment (if

10
F 1484 – 04

= Vmeas 3 T cf 3 Pcf 11.6 Idle Energy Rate:


11.6.1 Calculate and report the idle energy rate (Btu/h (kJ/h)
where: or kW) based on the energy consumption of the steam cooker
V meas = measured volume of gas ft3(m 3),
during the idle period in accordance with the following
= absolute standard temperature °R ~°K!
relationship:
absolute actual gas temperature °R ~°K!
= standard temperature° R ~°K! E 3 60
qidle 5 (4)
@gas temp °F~°C! 1 459.67~273!# °R~°K!, and t
Pcf = pressure correction factor where:
= actual gas pressure psia ~kPa! q idle = idle energy rate, Btu/h (kW),
standard pressure psia ~kPa! E = energy consumed during the test period, Btu
= gas gage pressure psig ~kPa! (kWh), and
1 t = test period, min.
barometric pressure psia ~kPa!
absolute standard pressure psia ~kPa! 11.6.2 Report the average compartment temperature during
the 2-h idle period.
11.7 Pilot Energy Rate:
NOTE 20—Absolute standard gas temperature and pressure used in this
calculation should be the same values used for determining of the heating 11.7.1 Calculate and report the energy input rate (Btu/h
value. Standard conditions using Practice D 3588 are 14.696 psia (101.33 (kJ/h) or kW) based on the energy consumed by the steam
kPa) and 60°F (519.67 °R (288.71 °K)). cooker during the pilot test period according to the following
11.3.3 For steam cookers that use either a direct external relationship:
potable steam source or a steam coil steam generator, steam E 3 60
qpilot 5 t (5)
energy shall be calculated as follows:
Esteam 5 Ws 3 t 3 hs (2) where:
q pilot = pilot energy rate, Btu/h,
where: E = energy consumed during the test period, Btu, and
W s = steam flow rate, lb (kg)/h, t = test period, min.
t = steam flow duration, h, and
hs = latent heat of steam as derived from the measured 11.8 Frozen Green Pea Load Cooking Energy Effıciency,
supply steam pressure (10.1.5) and thermodynamic Production Capacity, Water Consumption, and Condensate
properties of water at saturation (see 2.4), Btu/lb Temperature:
(kJ/g). 11.8.1 Report a minimum of three run average value of
11.4 Maximum Energy Input Rate: frozen green pea load cooking energy efficiency, production
11.4.1 Report the manufacturer’s rated input in Btu/h for a capacity, and water consumption.
gas steam cooker, kW for an electric steam cooker, and lb (kg) 11.8.2 Calculate the final cooked green pea load tempera-
steam/h for direct steam or steam coil steam cookers. ture by applying the following relationship:
11.4.2 For gas steam cookers calculate and report the
Wwater 3 Cpwater
maximum energy input rate (Btu/h (kJ/h)) based on the energy Tpeas, f 5 W 3 ~Twater, f 2 Twater, i! 1 Twater, f (6)
peas 3 Cppeas
consumed by the steam cooker during the input period accord-
ing to the following relationship: where:
E 3 60 T pea, f = temperature of the cooked peas, °F,
qinput 5 t (3) Wwater = weight of water in water-bath calorim-
eter, lb,
where: Cpwater = specific heat of water, Btu/lb°F,
q input = measured peak energy input rate, Btu/h (kW), = 1 Btu/lb°F (see 2.2),
E = energy consumed during period of peak energy Wpeas = weight of cooked green pea load, lb,
input, Btu (kWh), and = Wfull calorimeter – W calorimeter – Wwater,
t = period of peak energy input, min. Twater, i = initial water temperature in water-bath
11.4.3 For electric steam cookers, report the measured calorimeter, °F,
maximum energy input rate (kW). Twater, f = final equilibrium temperature of water
11.4.4 For direct steam or steam coil steam cookers, report and cooked green peas mixture in water-
the measured maximum rate of steam consumption (lb(kg)/h). bath calorimeter, °F, and
11.5 Preheat Energy Consumption and Duration: Cppeas,thawed = specific heat of thawed green peas, Btu/
11.5.1 Report the preheat energy consumption (Btu(kJ) or lb°F
= 0.84 Btu/lb°F (see 2.2).
kWh) and preheat time (min) where the preheat time is the time
elapsed from initiation at the controls to the time that the 11.8.3 Calculate the green pea load cooking energy effi-
primary burner, element, or steam coil cycles off. This includes ciency according to the following relationship:
any delay between initiation at the controls and actual energiz- Epeas 1 Epan 1 E boiler re – init
ing or ignition of the elements, steam coil, or burners. hpeas 5 Esteam cooker 3 100 % (7)

11
F 1484 – 04

where: Eboiler re-init = energy required to restore the final boiler


h peas = cooking energy efficiency (%), and energy content (pressure) to the initial
Epeas = heat gained by the green pea load, boiler energy content (Btu(kJ)). Calcula-
= [ Wpeas, frozen 3 Cppeas, frozen 3 DTpeas, frozen] + tion of this energy quantity is required
[Wpeas, cooked3 Cppeas, cooked3 DTpeas, cooked] + only if the conditional step 10.7.13 was
[Wmoisture 3 Efusion]. applicable. Otherwise this energy quan-
tity is already included in the E steam cooker
where:
value. If conditional step 10.7.13 was
W peas, frozen = weight of frozen green peas, lb,
Cppeas, frozen = specific heat of frozen green peas, Btu/ applicable, then Eboiler re-init is calculated
lb°F as follows:
= 0.44 Btu/lb°F (see 2.2), Pmax – Pfinal
5 Ecycle 3 P – P (8)
DT peas, frozen = temperature rise in frozen green peas, max min
°F,
= 32°F – initial temperature of frozen where:
green pea load, E cycle = energy required to raise the boiler pressure from
W peas, cooked = weight of cooked green peas, lb, minimum operating pressure to maximum oper-
= weight of full calorimeter – weight of ating pressure, Btu (kJ),
empty calorimeter – weight of water in Pmax = the average maximum boiler pressure, psi (kPa),
calorimeter, Pmin = the average minimum boiler pressure, psi (kPa),
Cppeas, cooked = specific heat of cooked green peas, and
Btu/lb°F, Pfinal = the boiler pressure at the end of the test, psi
= 0.84 Btu/lb°F (see 2.2), (kPa).
DT peas, cooked = temperature rise in cooked green peas, 11.8.4 Calculate the green pea load cooking energy rate as
°F, follows:
= final temperature of cooked pea load – E steam cooker 1 E boiler re 2 init
32°F, q peas 5 t 3 60 (9)
E fusion = latent heat of fusion of ice,
= 144 Btu/lb (see 2.2), where:
Wmoisture = weight of moisture in frozen green q peas = green pea load cook-
peas—81 % (see 2.2), ing energy rate, Btu/h
= 0.81 3 Wpeas,frozen, and (kJ/h),
Epan = heat gained by the stainless-steel hotel t = test period, min, and
pan(s) Esteam cooker and Eboiler re-init = are as defined in
= Wpan 3 Cp pan 3 DTpan 11.8.3.
where: For gas steam cookers, Esteam cooker in the above equation
W pan = weight of pan(s), lb, does not include the electric energy. The electric energy rate is
Cppan = specific heat of stainless-steel, Btu/lb°F, reported separately in 11.8.5. For direct steam or steam coil
= 0.11 Btu/lb°F (see 2.4), steam cookers, report the cooking energy rate in both Btu(kJ)/h
DT pan = temperature rise in pan °F, and lb(kg)steam/h.
= Tpan, f – T pan, i,
11.8.5 This step applies to heavy load tests of gas, direct
= T pea, f – Tpea, i,
= final temperature of cooked green pea steam, and steam coil steam cookers only. Calculate the green
load - initial temperature frozen green pea pea load electric energy rate as follows:
load, Esteam cooker, ele
Esteam cooker = total energy consumed by the steam qpeas,ele 5 t 3 60 (10)
cooker, Btu(kJ). Includes sum of all fuel
types used (for example, gas energy for where:
heating plus electric energy used by q peas,ele = green pea load electric cooking en-
steam circulating fans or controls, or ergy rate, Btu/h (kJ/h),
both), and t = test period, min, and

12
F 1484 – 04

Esteam cooker, ele = electric energy consumed by the Eboiler re-init = energy required to restore the final boiler
steam cooker, Btu (kWh). energy content (pressure) to the initial
11.8.6 Calculate green pea load production capacity (lb boiler energy content (Btu (kJ)). Calcula-
(kg)) using the following definition: tion of this energy quantity is required
only if the conditional step 10.9.14 was
Wpea
PCpeas 5 t 3 60 (11) applicable. Otherwise this energy quan-
tity is already included in the E steam cooker
where: value. If conditional step 10.9.14 was
PC peas = production capacity, lb/h (kg/h), applicable, then Eboiler re-init is calculated
Wpeas = weight of green pea load, lb (kg), and as follows:
t = test period, min. Pmax – Pfinal
Ecycle 3 P – P (14)
11.8.7 Report the green pea load cooking water consump- max min
tion rate, gal/h (L/h) (10.7.9).
where:
11.8.8 Report the average temperature of the green pea load E cycle = energy required to raise the boiler pressure from
cooking condensate during the last 5 min of the test, °F (°C) minimum operating pressure to maximum oper-
(10.7.9). ating pressure, Btu (kJ),
11.9 Whole Potato Load Cooking Energy Effıciency, Pro- Pmax = the average maximum boiler pressure, psi (kPa),
duction Capacity, Water Consumption, and Condensate Tem- Pmin = the average minimum boiler pressure, psi (kPa),
perature : and
Pfinal = the boiler pressure at the end of the test, psi
11.9.1 Report a minimum of three run average value of
(kPa).
whole potato load cooking energy efficiency, production ca-
pacity and water consumption. 11.9.3 Calculate the potato load cooking energy rate as
follows:
11.9.2 Calculate whole potato load cooking energy effi-
E steam cooker 1 E boiler re 2 init
ciency according to the following relationship: qpotato 5 3 60 (15)
t
Epotato 1 Epan 1 E boiler re 2 init
hpotato 5 Esteam cooker 3 100 % (12) where:
q potato = potato load cooking
where: energy rate, Btu/h (kJ/
h potato = cooking energy efficiency, %, h),
Epotato = heat gained by the potato, t = test period, min, and
= Wp 3 Cp p 3 DT, Esteam cooker and Eboiler re-init = are as defined in
11.9.2.
where:
Wp = weight of potatoes, lb, For gas steam cookers, Esteam cooker in the above equation
Cpp = specific heat of potatoes, Btu/lb°F, does not include the electric energy. The electric energy rate is
= 0.87 Btu/lb°F (see 2.3), reported separately in 11.9.4. For direct steam or steam coil
DT = temperature rise in potatoes, °F, steam cookers, report the cooking energy rate in both Btu
= Tpotato, f – Tpotato, i, (kJ)/h and lb (kg)steam/h.
Epan = heat gained by the stainless-steel hotel pan(s), 11.9.4 This step applies to heavy load tests of gas, direct
Wpan 3 Cppan 3 ~Tf – T i! (13) steam, and steam coil steam cookers only. Calculate the potato
load electric energy rate as follows:
where: Esteam cooker, ele
W pan = weight of pan(s), lb, qpotato,ele 5 3 60 (16)
t
Cppan = specific heat of stainless-steel, Btu/lb°F,
= 0.11 Btu/lb°F (see 2.4), and where:
DT = temperature rise in stainless-steel pan, °F, q potato,ele = potato load electric cooking energy,
= Tpan, f – T pan, i rate, Btu/h (kJ/h),
Esteam cooker = total energy consumed by the steam t = test period, min, and
cooker, Btu (kJ). Includes sum of all fuel Esteam cooker, ele = electric energy consumed by the
types used (for example, gas energy for steam cooker, Btu (kWh).
heating plus electric energy used by 11.9.5 Calculate whole potato load production capacity
steam circulating fans and/or controls). (lb(kg)) using the following equation:

13
F 1484 – 04
Wpotato 12. Precision and Bias
PCpotato 5 t 3 60 (17)
12.1 Precision:
where: 12.1.1 Repeatability (within laboratory, same operator and
PC potato = production capacity, lb/h (kg/h), equipment):
Wpotato = weight of potatoes, lb (kg), and 12.1.1.1 For the cooking energy efficiency, cooking energy
t = test period, min. rate, and production capacity results, the percent uncertainty in
11.9.6 Report the potato load cooking water consumption each result has been specified to be no greater than 610 %
rate, gal/h (L/h) (see 10.9.10). based on at least three test runs.
11.9.7 Report the average temperature of the potato load 12.1.1.2 The repeatability of each remaining reported pa-
cooking condensate during the last 5 min of the test, °F (°C) rameter is being determined.
(see 10.9.10). 12.1.2 Reproducibility (multiple laboratories):
11.10 Cooking Uniformity: 12.1.2.1 The interlaboratory precision of the procedures in
11.10.1 For each pan, report the final temperature of the these test methods for measuring each reported parameter is
water in the pans at the end of the test using the corresponding being determined.
average temperatures for the three test runs. 12.2 Bias—No statement can be made concerning the bias
11.10.2 Calculate and report the maximum temperature of the procedures in these test methods because there are no
difference between the hottest pan and the coolest pan in each accepted reference values for the parameters reported.
compartment.
11.10.3 Report the average test time for the three test runs. 13. Keywords
11.10.4 Generate a graph showing pan temperature versus 13.1 efficiency; energy; performance; production capacity;
time for each pan during the cooking uniformity test. steam cooker; test method; throughput

ANNEX

(Mandatory Information)

A1. PROCEDURE FOR DETERMINING THE UNCERTAINTY IN REPORTED TEST RESULTS

NOTE A1.1—This procedure is based on the ASHRAE method for TABLE A1.1 Uncertainty Factors
determining the confidence interval for the average of several test results Test Results, n Uncertainty Factor, Cn
(ASHRAE Guideline 2-1986(RA90)). It should only be applied to test
3 2.48
results that have been obtained within the tolerances prescribed in this 4 1.59
method (for example, thermocouples calibrated, appliance operating 5 1.24
within 5 % of rated input during the test run). 6 1.05
7 0.92
A1.1 For the cooking-energy efficiency and production 8 0.84
9 0.77
capacity results, the uncertainty in the averages of at least three 10 0.72
test runs is reported. For each loading scenario, the uncertainty
of the cooking energy efficiency and production capacity must
be no greater than 610 % before any of the parameters for that
loading scenario can be reported. A1.4 Procedure:
A1.2 The uncertainty in a reported result is a measure of its NOTE A1.2—A1.5 shows how to apply this procedure.
precision. If, for example, the production capacity for the A1.4.1 Step 1—Calculate the average and the standard
appliance is 30 lb/h, the uncertainty must not be greater than deviation for the test result (cooking energy efficiency or
63 lb/h. Thus, the true production capacity is between 27 and production capacity) using the results of the first three test runs,
33 lb/h. This interval is determined at the 95 % confidence as follows:
level, which means that there is only a 1 in 20 chance that the
A1.4.1.1 The formula for the average (three test runs) is as
true production capacity could be outside of this interval.
follows:
A1.3 Calculating the uncertainty not only guarantees the Xa 3 5 ~1/3!3 ~X1 1 X2 1 X3! (A1.1)
maximum uncertainty in the reported results, but is also used to
where:
determine how many test runs are needed to satisfy this Xa3 = average of results for three test runs, and
requirement. The uncertainty is calculated from the standard X1 , X 2 , X 3 = results for each test run.
deviation of three or more test results and a factor from Table
A1.4.1.2 The formula for the sample standard deviation
A1.1, which lists the number of test results used to calculate the
(three test runs) is as follows:
average. The percent uncertainty is the ratio of the uncertainty
to the average expressed as a percent. S3 5 ~1/=2!3 =~A3 – B3! (A1.2)

14
F 1484 – 04

where: X1, X 2, X3, X 4 = results for each test run.


S 3 = standard deviation of results for three test runs, A1.4.6.2 The formula for the standard deviation (four test
A3 = (X1)2 + ( X2)2 + (X3) 2, and runs) is as follows:
B3 = (1/3) 3 (X1 + X2 + X3)2.
S4 5 ~1/=3! 3 =~A4–B4! (A1.6)
NOTE A1.3—The formulas may be used to calculate the average and
sample standard deviation. However, a calculator with statistical function where:
is recommended, in which case be sure to use the sample standard S 4 = standard deviation of results for four test runs,
deviation function. The population standard deviation function will result A4 = (X1)2 + ( X2)2 + (X3) 2 + (X4)2, and
in an error in the uncertainty. B4 = (1⁄4) 3 (X1 + X2 + X 3 + X4)2.
NOTE A1.4—The “A” quantity is the sum of the squares of each test
result, and the “B” quantity is the square of the sum of all test results A1.4.7 Step 7—Calculate the absolute uncertainty in the
multiplied by a constant (1/3 in this case). average for each parameter listed in Step 1. Multiply the
A1.4.2 Step 2—Calculate the absolute uncertainty in the standard deviation calculated in Step 6 by the uncertainty
average for each parameter listed in Step 1. Multiply the factor for four test results from Table A1.1.
standard deviation calculated in Step 1 by the uncertainty A1.4.7.1 The formula for the absolute uncertainty (four test
factor corresponding to three test results from Table A1.1. runs) is as follows:
A1.4.2.1 The formula for the absolute uncertainty (three test U 4 5 C4 3 S 4 (A1.7)
runs) is as follows: U4 5 1.59 3 S4
U3 5 C3 3 S3, (A1.3)
where:
U3 5 2.48 3 S 3
U 4 = absolute uncertainty in average for four test runs, and
where: C4 = the uncertainty factor for four test runs (Table A1.1).
U 3 = absolute uncertainty in average for three test runs, A1.4.8 Step 8—Calculate the percent uncertainty in the
and parameter averages using the averages from Step 6 and the
C3 = uncertainty factor for three test runs (Table A1.1). absolute uncertainties from Step 7.
A1.4.3 Step 3—Calculate the percent uncertainty in each A1.4.8.1 The formula for the percent uncertainty (four test
parameter average using the averages from Step 1 and the runs) is as follows:
absolute uncertainties from Step 2.
% U4 5 ~U4/ Xa4! 3 100 % (A1.8)
A1.4.3.1 The formula for the percent uncertainty (three test
runs) is as follows: where:
% U3 5 ~U3/ Xa3! 3 100 % (A1.4) % U 4 = percent uncertainty in average for four test runs,
U4 = absolute uncertainty in average for four test runs,
where: and
% U 3 = percent uncertainty in average for three test runs, Xa4 = average of four test runs.
U3 = absolute uncertainty in average for three test runs, A1.4.9 Step 9—If the percent uncertainty, % U4, is not
and greater than 610 % for the cooking energy efficiency and
Xa3 = average of three test runs.
production capacity, report the average for these parameters
A1.4.4 If the percent uncertainty, % U3, is not greater than
along with their corresponding absolute uncertainty, U4, in the
610 % for the cooking-energy efficiency and production
following format:
capacity, report the average for these parameters along with
Xa 4 6 U4
their corresponding absolute uncertainty, U3, in the following
If the percent uncertainty is greater than 610 % for the
format:
cooking energy efficiency or production capacity, proceed to
Xa3 6 U 3
Step 10.
If the percent uncertainty is greater than 610 % for the
cooking energy efficiency or production capacity, proceed to A1.4.10 Step 10—The steps required for five or more test
Step 5. runs are the same as those described above. More general
A1.4.5 Step 5—Run a fourth test for each loading scenario formulas are listed below for calculating the average, standard
whose percent uncertainty was greater than 610 %. deviation, absolute uncertainty, and percent uncertainty.
A1.4.6 Step 6—When a fourth test is run for a given loading A1.4.10.1 The formula for the average ( n test runs) is as
scenario, calculate the average and standard deviation for test follows:
results using a calculator or the following formulas: Xan 5 ~1/n!3 ~X 1 1 X2 1 X 3 1 X4 1 . . . 1 Xn! (A1.9)
A1.4.6.1 The formula for the average (four test runs) is as
follows: where:

SD
n = number of test runs,
1 Xan = average of results n test runs, and
Xa 4 5 4 3 ~X1 1 X2 1 X3 1 X 4! (A1.5)
X1, X2, X 3, X4,... Xn = results for each test run.
where: A1.4.10.2 The formula for the standard deviation (n test
Xa 4 = average of results for four test runs, runs) is as follows:
and Sn 5 ~1/= ~n21!! 3 ~=~ An2Bn! (A1.10)

15
F 1484 – 04

where: A1.5.2.3 The new standard deviation for the PC is as


Sn = standard deviation of results for n test runs, follows:
An = (X1) 2 + (X2)2 + (X3)2 + (X 4)2 + ... + (X n)2, and S3 5 ~1/=2! 3 = ~3266 – 3260!, (A1.15)
Bn = (1/n) 3 (X1 + X2 + X 3 + X4 + ... + Xn)2.
S3 5 1.73 lb/h
A1.4.10.3 The formula for the absolute uncertainty (n test
runs) is as follows: A1.5.3 Step 2—Calculate the uncertainty in average.
U n 5 Cn 3 S n (A1.11) U3 5 2.48 3 S 3, (A1.16)
U3 5 2.483 1.73,
where:
Un = absolute uncertainty in average for n test runs, and U3 5 4.29 lb/h
C n = uncertainty factor for n test runs (Table A1.1). A1.5.4 Step 3—Calculate percent uncertainty.
A1.4.10.4 The formula for the percent uncertainty (n test
% U3 5 ~U3/Xa3! 3 100 %, (A1.17)
runs) is as follows:
% U3 5 ~4.29/33.0! 3 100 %,
% Un 5 ~ Un/Xan! 3 100 % (A1.12)
% U3 5 13.0 %
where: A1.5.5 Step 4—Run a fourth test. Since the percent uncer-
% Un = percent uncertainty in average for n test runs,
tainty for the production capacity is greater than 610 %, the
Un = absolute uncertainty in average for n test runs, and
Xan = average of n test runs. precision requirement has not been satisfied. An additional test
is run in an attempt to reduce the uncertainty. The PC from the
When the percent uncertainty, % Un, is less than or equal to
fourth test run was 32.5 lb/h.
610 % for the cooking energy efficiency and production
capacity, report the average for these parameters along with A1.5.6 Step 5—Recalculate the average and standard devia-
their corresponding absolute uncertainty, Un, in the following tion for the PC using the fourth test result:
format: A1.5.6.1 The new average PC is as follows:
Xan 6 Un Xa4 5 ~1/4! 3 ~X1 1 X2 1 X3 1 X4!, (A1.18)

NOTE A1.5—The researcher may compute a test result that deviates Xa 4 5 ~1/4! 3 ~33.8 1 34.1 1 31.0 1 32.5!,
significantly from the other test results. Such a result should be discarded Xa4 5 32.9 lb/h
only if there is some physical evidence that the test run was not performed
according to the conditions specified in this method. For example, a A1.5.6.2 The new standard deviation is. First calculate A4
thermocouple was out of calibration, the appliance’s input capacity was and B4:
not within 5 % of the rated input, or the food product was not within
A4 5 ~X1!2 1 ~ X2!2 1 ~X3! 2 1 ~X4!2, (A1.19)
specification. To assure that all results are obtained under approximately
2 2 2 2
the same conditions, it is good practice to monitor those test conditions A4 5 ~33.8! 1 ~34.1! 1 ~31.0! 1 ~32.5! ,
specified in this method.
A4 5 4322
A1.5 Example of Determining Uncertainty in Average Test B 4 5 ~1/4! 3 [X1 1 X2 1 X3 1 X4!2#,
Result: B4 5 ~1/4! 3 [~33.8 1 34.1 1 31.0 1 32.5! 2#,
A1.5.1 Three test runs for the full load cooking scenario B4 5 4316
yielded the following production capacity (PC) results:
A1.5.6.3 The new standard deviation for the PC is as
Test PC
Run No. 1 33.8 lb/h follows:
Run No. 2 34.1 lb/h
Run No. 3 31.0 lb/h S4 5 ~1/=3! 3 = ~4322 – 4316!, (A1.20)
S4 5 1.41 lb/h
A1.5.2 Step 1—Calculate the average and standard devia-
tion of the three test results for the PC. A1.5.7 Step 6—Recalculate the absolute uncertainty using
A1.5.2.1 The average of the three test results is as follows: the new standard deviation and uncertainty factor.
Xa3 5 ~1/3! 3 ~X1 1 X2 1 X3!, (A1.13) U4 5 1.59 3 S4, (A1.21)
Xa3 5 ~1/3! 3 ~33.8 1 34.1 1 31.0!, U4 5 1.59 3 1.41,
Xa3 5 33.0 lb/h U4 5 2.24 lb/h
A1.5.2.2 The standard deviation of the three test results is as A1.5.8 Step 7—Recalculate the percent uncertainty using
follows. First calculate A3 and B3: the new average.
A3 5 ~X1! 2 1 ~X2!2 1 ~X3!2, (A1.14) % U4 5 ~ U4/Xa4! 3 100 %, (A1.22)
% U4 5 ~2.24/32.9!3 100 %,
A3 5 ~33.8!2 1 ~34.1!2 1 ~31.0! 2,
% U 4 5 6.8 %
A3 5 3266
B3 5 ~1/3! 3 [~X1 1 X 2 1 X3!2#,
A1.5.9 Step 8—Since the percent uncertainty, % U4, is less
than 610 %; the average for the production capacity is
B3 5 ~1/3! 3 [~33.8 1 34.1 1 31.0! 2#, reported along with its corresponding absolute uncertainty, U 4
B3 5 3260 as follows:

16
F 1484 – 04
PC: 32.9 6 2.24 lb/h (A1.23) ing cooking energy efficiency value. The cooking energy
The production capacity can be reported assuming the efficiency and its absolute uncertainty can be calculated fol-
610 % precision requirement has been met for the correspond- lowing the same steps.

APPENDIXES

(Nonmandatory Information)

X1. PROCEDURE FOR DETERMINING THE ICE LOAD COOKING ENERGY EFFICIENCY, PRODUCTION CAPACITY,
WATER CONSUMPTION, AND CONDENSATE TEMPERATURE

INTRODUCTION X1.3.4 Condensate temperature is monitored during the last


The following procedure evaluates the steam cooker effi- 3 min of the cooking energy efficiency tests.
ciency, production capacity, water consumption, and conden-
X1.4 Significance and Use
sate temperature when heating ice loads. Experience indicates
that the ice load test is a simple yet valuable tool for product X1.4.1 The ice load test may be used as a quick indicator of
development. Ice load tests are easily and inexpensively improvement in steam cooker design.
prepared while yielding repeatable and reproducible results.
X1.5 Apparatus
The test may be used as a quick indicator of improvements in
steam delivery mechanism, insulation, or other design features. X1.5.1 Hotel pans, for ice loads, solid 12 by 20 by 21⁄2-in.
Accordingly, it is referenced as an appendix to these test (300 by 500 by 65-mm) stainless steel, weighing 2.8 6 0.2 lb
methods as a research and development tool. (1.3 6 0.1 kg), with a temperature sensor located in the center
The ice load test does not replicate or represent the efficiency of each pan 5⁄8 in. (16 mm) from the bottom. A convenient
and production capacity of steam cookers when cooking for the method is to have Type T thermocouple probes with a
following technical reasons: stainless-steel protective sheath fabricated in the shape shown
(1) The physical properties, such as specific heat, of ice and in Fig. X1.1. The sensing point is exposed and isolated
food products are often different. thermally from the stainless-steel sheath. The probe is strapped
(2) Ice loads have lower production rate due to smaller to the pan using steel shim stock welded to the pan using a
surface area. Food products generally exhibit greater surface strain gage welder. The thermocouple lead TFE-fluorocarbon
area allowing a faster rate of condensation. sheath is minimum thickness (TFE-fluorocarbon wrap rather
(3) Solid hotel pans, which restrict convection in the cavity, than extruded TFE-fluorocarbon) to minimize the escape of
must be used for ice load test. Loads closer to the steam source steam through the door gasket where the thermocouple exits
are heated quicker while further loads lag. the cooking compartment. The lead is long enough to allow
The ice load test may be used as a research and development connection to the monitoring device while the ice loads are in
tool, but shall not be used to imply the overall steamer the freezer, while they are being weighed, and while they are in
performance during actual cooking operations. the steam cooker.
NOTE X1.1—PG&E found that 10-ft (3-m) sensor leads allowed for
X1.1 Scope flexibility in test equipment setup while still being manageable (tangle
free).
X1.1.1 The test procedure in this appendix determines the
efficiency, production capacity, water consumption, and con- X1.6 Reagents and Materials
densate temperature.
X1.6.1 Water used shall have a maximum hardness of three
grains per gallon. Distilled water may be used.
X1.2 Terminology
X1.2.1 ice load, n—12 by 20 by 21⁄2-in. (300 by 500 by X1.7 Sampling
65-mm) hotel pan filled with 8.0 6 0.2 lb (3630 6 90 g) of X1.7.1 Steam Cooker— A representative production model
water and subsequently frozen to 0 6 2°F (–18 6 1°C). shall be selected for performance testing.

X1.3 Summary of Test Methods X1.8 Preparation of Apparatus


X1.3.1 Ice load cooking energy efficiency is determined by X1.8.1 Install the appliance under a canopy exhaust hood in
cooking a capacity number of ice loads from 0 to 180°F (–18 accordance with 9.1-9.8.
to 82°C).
X1.3.2 Ice load production capacity (lbice/h (kgice/h) is X1.9 Procedure
determined by the respective cooking energy efficiency tests. X1.9.1 Ice Load Preparation:
X1.3.3 Water consumption (gal/h (L/h)) is monitored during X1.9.1.1 This section outlines preparation of the ice loads in
the cooking energy efficiency tests to determine the rate of the ice load cooking energy efficiency and production-capacity
water usage. tests.

17
F 1484 – 04

FIG. X1.1 Hotel Pan with Thermocouple Probe

X1.9.1.2 The number of ice loads required depends on the is at maximum operating pressure and temperature when the
steamer capacity. The heavy load is the manufacturer’s stated efficiency-test cooking starts.
capacity of 12 by 20 by 21⁄2-in. (300 by 500 by 65-mm) hotel X1.9.2.6 Start monitoring time. Open one steam compart-
pans. Prepare enough ice loads for three runs. ment, load it with ice loads, close it, and start steam to it. Open
X1.9.1.3 The solid hotel pans shall be as specified in X1.5.1. the next steam compartment (if applicable), load it, close it,
X1.9.1.4 Number each pan and record the weight of each of and start it. Open, load, close, and start the last compartment (if
the (dry) pans. applicable). After starting steam to the first compartment,
X1.9.1.5 Fill the pans with enough water such that there will commence monitoring energy consumption, water consump-
be 8.0 6 0.2 lb (3.6 6 0.1 kg) of ice after freezing (some water tion, condensate temperature, and, for each compartment under
will evaporate during freezing, especially if hotel pan lids are test, monitor the average temperature of the ice loads. For gas
not used). Accurate measurement of the weight of the pans plus steam cookers, monitor and record electric energy as well as
the water prior to freezing is not required since they will be gas consumption. The total loading time (the time from
weighed again just prior to testing. opening the first compartment to closing and starting the last
X1.9.1.6 Freeze the loads to 0 6 5°F (–186 2°C). compartment) shall be the total of 5 s per compartment plus 5
X1.9.2 Ice Load Cooking Energy Effıciency, Production s for each ice load used. (For example, the total loading time
Capacity, Water Consumption, and Condensate Temperature: for a heavy load test of a six-pan capacity, two-compartment
X1.9.2.1 This procedure applies to two possible loading steam cooker would be 5 s/compartment3 2 compartments + 5
scenarios: light and heavy. Repeat each loading scenario at s/ice load 3 6 ice loads = 40 s.)
least three times. The reported values of cooking energy NOTE X1.2—For gas steamers, the electric energy rate during the heavy
efficiency, production capacity, condensate temperature, and load test will be reported separately from the gas cooking energy rate. The
water consumption shall be the average of the replications two values are reported separately so that the respective fuel prices may
(runs). be applied to estimate energy costs.
X1.9.2.2 Prepare the ice loads in accordance with X1.9.1. NOTE X1.3—Care shall be taken to minimize heat gain by the ice loads
Record the quantity of ice loads for the test. on the way from the freezer to the steam cooker. During that time, they
X1.9.2.3 Record the initial average ice load temperature. shall be isolated from any warmer surface by R10 or better insulation.
PG&E found 2-in. (50-mm) thick square-edged polystyrene boards to be
Confirm that they are at 0 6 5°F (–18 6 3°C).
convenient as an insulating surface.
X1.9.2.4 Allow the steam cooker to sit idle (boiler(s) on) for NOTE X1.4—Care shall be taken to minimize heat loss out of the
a minimum of 1 h. If the manufacturer recommends leaving the cooking compartment where the sensor leads pass under the door gasket.
cooking cavity doors open when not cooking, leave them open PG&E found that heat loss was not significant as long as the sensor leads
during the idle period and record the door position during the were not bunched or paired as they passed under the door gasket.
idle period. NOTE X1.5—The boiler is at maximum pressure when the test starts,
X1.9.2.5 Near the end of the idle period, remove each pan but it may be at a lower pressure at the end of the test. This difference
from the freezer, remove the lid, and weigh. Record the weight between the initial and final energy content (pressure and temperature) of
the boiler must be added back to the boiler to calculate the energy
of each ice load (including the pan itself) for that run. Record efficiency correctly. Maximum, minimum, and final boiler pressure is
the dry pan weights as determined in X1.9.1.4. After the idle measured so that this energy deficit can be estimated. There are situations
period, wait for the burners, elements, or steam coil to cycle on in which the measurement of pressure in X1.9.2.7 is not necessary, as
and then off again (if applicable). This ensures that the boiler noted in X1.9.2.9 and X1.9.2.11.

18
F 1484 – 04
NOTE X1.6—The average condensate temperature for the final 3 min of X1.9.2.13 Remove the ice loads, and unless this was the
the run will be reported rather than the average over the entire run; final run (Run No. 3), start timing the 10-min idle period before
therefore, condensate temperature monitoring need not begin immediately the next run (see Fig. X1.2). Return to X1.9.2.5.
upon commencement of the test run.
X1.9.2.14 In accordance with X1.10, calculate and report
X1.9.2.7 Measure the maximum and minimum pressures for the cooking energy efficiency, cooking energy rate, electric
three cycles of the boiler pressure near the end of the test. energy rate (if applicable, for gas steam cookers), production
Record the average maximum and average minimum boiler capacity, water consumption, and condensate temperature.
pressure. After performing this test at least three times, report the results
X1.9.2.8 When the average ice load temperature of any as the average of the replications.
cooking compartment has reached 180°F, stop the steam to that
compartment. If there are two or more compartments under X1.10 Ice Load Cooking Energy Effıciency, Production
test, continue to monitor the average ice load temperature of Capacity, Water Consumption, and Condensate Temperature:
the others, stopping steam to the compartments as the average X1.10.1 Report the three run average value of ice load
temperature reaches 180°F (82°C). When the last (or only) cooking-energy efficiency, production capacity, and water con-
compartment’s average ice load temperature reaches 180°F, sumption.
terminate steam to the compartment and record time, water X1.10.2 Calculate ice load cooking energy efficiency ac-
consumption and condensate temperature. cording to the following relationship:
X1.9.2.9 If the boiler is on when the last compartment ice Eice 1 E pan 1 Eboiler re 2 init
load temperature reaches 180°F (82°C), continue to monitor hice 5 E steam cooker 3 100 % (X1.1)
energy consumption until the primary burners, elements, or
steam coils cycle off. Record the final energy. Note that the where:
initial and final energy content of the boiler is the same; the h ice = cooking energy efficiency, %,
pressure measurements in X1.9.2.7 are therefore not necessary. Eice = heat gained by the ice load, and
= [ Wice 3 Cpice 3 DTice] + [ Wwater 3 Cpwater 3
X1.9.2.10 If the boiler is not on when the last compart-
DTwater] + [ Wice 3 Efusion]
ment’s average ice load temperature reaches 180°F (82°C),
proceed to one of the next two conditional steps (X1.9.2.11 or where:
X1.9.2.12). W ice = weight of ice load, lb,
X1.9.2.11 Perform this step if the boiler pressure is con- Cpice = specific heat of ice, Btu/lb°F,
trolled by a pressure switch that can be actuated manually. = 0.5 Btu/lb°F (see 2.2)
Otherwise, proceed directly to X1.9.2.12. When the last DTice = temperature rise in ice, °F,
compartment’s average ice load temperature reaches 180°F = 32°F - initial temperature of ice loads,
W water = weight of water (same as Wice), lb,
(82°C), continue to monitor energy consumption and actuate
Cpwater = specific heat of water, Btu/lb°F,
the pressure switch. This returns the boiler energy content to = 1 Btu/lb°F (see 2.2),
the initial test condition; the pressure measurements in DT water = temperature rise in water, °F,
X1.9.2.7 and energy measurements in 10.4.2 are therefore not = final water temperature - 32°F,
necessary. Record the final energy. E fusion = latent heat of fusion of ice,
X1.9.2.12 Perform this step if the boiler pressure control = 144 Btu/lb (see 2.2), and
cannot be actuated manually. When the last compartment Epan = heat gained by the stainless-steel hotel pan(s),
average ice load temperature reaches 180°F (82°C), record the = Wpan 3 Cp pan 3 DTpan
final energy and boiler pressure (used to calculate the energy
deficit of the boiler, as described in Note X1.5). where:

FIG. X1.2 Cooking Energy Efficiency Test Sequence

19
F 1484 – 04

W pan = weight of pan(s), lb where:


Cppan = specific heat of stainless-steel, Btu/lb°F, q ice = ice load cooking en-
= 0.11 Btu/lb°F (see 2.4) ergy rate, Btu/h (kJ/
DT pan = temperature rise in ice, °F, h),
= final pan temperature - initial pan tem- t = test period, min, and
perature, Esteam cooker and Eboiler re-init = as defined in X1.10.2.
= final water temperature - initial ice tem- For gas steam cookers, Esteam cooker in the above equation
perature, does not include the electric energy. The electric energy rate is
Ti = initial temperature of steel pan(s), °F,
Esteam cooker = total energy consumed by the steam reported separately in X1.10.4. For direct steam or steam coil
cooker, Btu (kJ). Includes sum of all fuel steam cookers, report the cooking energy rate in both Btu
types used (for example, gas energy for (kJ)/h and lb (kg)steam/h.
heating plus electric energy used by X1.10.4 This step applies to heavy load tests of gas, direct
steam circulating fans and/or controls), steam, and steam coil steam cookers only. Calculate the ice
E boiler re-init = energy required to restore the final boiler load electric energy rate as follows:
energy content (pressure) to the initial Esteam cooker, ele
boiler energy content (Btu (kJ)). Calcula- qice,ele 5 t 3 60 (X1.4)
tion of this energy quantity is required
only if the conditional step X1.9.2.11 was where:
applicable. Otherwise this energy quan- q ice,ele = ice load electric cooking energy rate,
tity is already included in the Esteam cooker Btu/h (kJ/h),
value. If conditional step X1.9.2.11 was t = test period, min, and
applicable, then Eboiler re-init is calculated Esteam cooker,ele = electric energy consumed by the
as follows: steam cooker, Btu (kWh).
Pmax – Pfinal X1.10.5 Calculate ice load production capacity (lb (kg))
Ecycle 3 P – P (X1.2) using the following equation:
max min

Wice
where: PCice 5 t 3 60 (X1.5)
E cycle = energy required to raise the boiler pressure from
minimum operating pressure to maximum oper- where:
ating pressure, Btu (kJ), PCice = production capacity, lb/h (kg/h),
Pmax = the average maximum boiler pressure, psi (kPa), Wice = weight of ice load, lb (kg), and
Pmin = the average minimum boiler pressure, psi (kPa), t = test period, min.
and X1.10.6 Report the ice load cooking water consumption
Pfinal = the boiler pressure at the end of the test, psi
rate, gal/h (L/h) (see X1.9.2.8).
(kPa).
X1.10.3 Calculate the ice load cooking energy rate as X1.10.7 Report the average temperature of the ice load
follows: cooking condensate during the last three minutes of the test, °F
(°C) (see X1.9.2.8).
E steam cooker 1 E boiler re 2 init
qice 5 t 3 60 (X1.3)

X2. RESULTS REPORTING SHEETS

Manufacturer _________________________
Model _________________________ _____ Class 1 – 208 V, 60 Hz, 1 phase
_____ Class 2 – 208 V, 60 Hz, 3 phase
Date _______________ _____ Class 3 – 240 V, 60 Hz, 1 phase
Test Reference Number (optional) ____________ _____ Class 4 – 240 V, 60 Hz, 3 phase
_____ Class 5 – 480 V, 60 Hz, 1 phase
X2.1 Test Steam Cooker _____ Class 6 – 480 V, 60 Hz, 3 phase
_____ Class 7 – 120 V, 60 Hz, 1 phase
Specification F 1217 Classification (check one for each classification) _____ Class 8 – 220 V, 60 Hz, 3 phase
_____ Type IA – Table or counter mounted unit with permanent water _____ Class 9 – 230 V, 50 Hz, 1 phase
connection _____ Class 10 – 400 V, 50 Hz, 3 phase
_____ Type IB – table or counter mounted unit without water connection _____ Class 11 – 440 V, 60 Hz, 3 phase (shipboard use)
(connectionless steamer)
_____ Type II – Floor mounted on an open stand _____ Size a – One compartment steamer
_____ Type III – Floor mounted on a cabinet base _____ Size b – Two compartment steamer
_____ Size c – three compartment steamer
_____ Grade A – Zero to 2.9 psig (Zero to 20 kPa) compartment pressure
_____ Grade B – Three to 9.9 psig (21 to 68 kPa) compartment pressure _____ Style I – Direct connection to potable external steam source
_____ Grade C – Ten to 15 psig (69 to 103 kPa) compartment pressure

20
F 1484 – 04
_____ Style ii – Self-contained steam coil steam generator M Pea load water consumption rate (gal/h (L/h)) _____
_____ Style iii – Self-contained gas fired steam generator
_____ Style iv – Self-contained electric steam generator M Condensate temperature (°F (°C)) _____

_____ Maximum three full size pans capacity M Light Load:


_____ Maximum five full size pans capacity
_____ Maximum six full size pans capacity M Pea load cook time (min) _____
_____ Maximum ten full size pans capacity
_____ Maximum 12 full size pans capacity M Pea load cooking energy efficiency (%) _____
_____ Maximum 16 full size pans capacity
_____ Maximum 18 full size pans capacity M Pea load cooking energy rate (Btu/h (kJ/h), lb(kg)steam/h,
_____ Maximum 24 full size pans capacity or kW) _____

Additional description of operational characteristics: __________________ M Electric energy rate (kW, gas or steam coil steam cookers
__________________________________________________________ only) _____
__________________________________________________________
__________________________________________________________ M Pea load water consumption rate (gal/h (L/h)) _____
__________________________________________________________
__________________________________________________________ M Condensate temperature (°F (°C)) _____
__________________________________________________________
X2.8 Whole Potato Load Cooking Energy Efficiency,
Manufacturer’s Rated Input __________ (Btu/h, kW or lbsteam/h)
Production Capacity, Water Consumption, and
X2.2 Apparatus Condensate Temperature
_____ Check if testing apparatus conformed to specifications in Section 9. M Heavy Load:
Deviations ________________________________________________
________________________________________________________ M Whole potato load cook time (min) _____

X2.3 Maximum Energy Input Rate M Whole potato load cooking energy efficiency (%) _____
M Measured (Btu/h (kJ/h) or kW) _____
M Whole potato load cooking energy rate (Btu/h (kJ/h),
lb (kg)steam/h, or kW) _____
M Rated (Btu/h (kJ/h) or kW) _____
M Electric energy rate (kW, gas or steam coil steam cookers only) _____
M Percent Difference between Measured and Rated _____ %
M Whole potato load production capacity (lb/h (kg/h)) _____
X2.4 Preheat Energy Consumption and Duration
M Energy Consumption (Btu (kJ) or kWh) _____ M Whole potato load water consumption rate (gal/h (L/h)) _____

M Duration (min) _____ M Condensate temperature (°F (°C)) _____

X2.5 Idle Energy Rate M Light Load:

M Idle Energy Rate (Btu/h (kJ/h) or kW) _____ M Whole potato load cook time (min) _____
M Average Compartment Temperature (°F (°C)) _____
M Whole potato load cooking energy efficiency (%) _____
X2.6 Pilot Energy Rate
M (Btu/h (kJ/h) or kW) _____ M Whole potato load cooking energy rate (Btu/h (kJ/h),
lb (kg)steam/h, or kW) _____
X2.7 Frozen Green Pea Load Cooking Energy Efficiency,
M Electric energy rate (kW, gas or steam coil steam cookers only) _____
Production Capacity, Water Consumption, and
Condensate Temperature M Whole potato load water consumption rate (gal/h (L/h)) _____
M Heavy Load:
M Condensate temperature (°F (°C)) _____
M Pea load cook time (min) _____
X2.9 Cooking Uniformity
M Pea load cooking energy efficiency (%) _____
Pan Pan Temperature (°F (°C))
1 (top) _____
M Pea load cooking energy rate (Btu/h (kJ/h), lb (kg)steam/h,
2 _____
or kW) _____
3 _____
4 _____
M Electric energy rate (kW, gas or steam coil steam cookers
5 _____
only) _____
6 (bottom) _____
M Pea load production capacity (lb/h (kg/h)) _____
Cooking Time (min) _____

21
F 1484 – 04

X3. PROCEDURE FOR CALCULATING THE ENERGY CONSUMPTION OF A STEAMER


BASED ON REPORTED TEST RESULTS

X3.1 Appliance test results are useful not only for bench- PC = the steamer’s potato load production capacity as
marking appliance performance, but also for estimating appli- determined in 11.9.5, lb/h.
ance energy consumption. The following procedure is a guide- X3.4.3.2 The heavy load energy consumption is calculated
line for estimating steamer energy consumption based on data using the following set of equations. For gas steamers, any
obtained from applying the appropriate test method. electric energy shall be determined separately using the electric
equations.
X3.2 The intent of this appendix is to present a standard Egas,h 5 qgas,h 3 th (X3.2)
method for estimating steamer energy consumption based on
ASTM performance test results. The examples contained Eelec,h 5 qelec,h 3 th
herein are for information only and should not be considered an where:
absolute. To obtain an accurate estimate of energy consumption Egas,h = total gas heavy load energy consumption, Btu,
for a particular operation, parameters specific to that operation qgas,h = gas heavy load cooking energy rate as deter-
should be used (for example, operating time, and amount of mined in 11.9.3, Btu/h,
food cooked under heavy and light loads). Eelec,h = total electric heavy load energy consumption,
kWh, and
X3.3 The appropriate steamer performance parameters are qelec,h = electric heavy load cooking energy rate as deter-
obtained from Section 11 in the test method. mined in 11.9.3, kW.
X3.4.4 Step 3—Calculate the time and energy involved in
X3.4 Procedure: cooking light loads. Light loads are the equivalent of cooking
a single pan in one steamer compartment.
NOTE X3.1—Sections X3.5 and X3.6 show how to apply this proce-
dure. X3.4.4.1 The total time cooking light loads is determined as
follows:
X3.4.1 The calculation will proceed as follows: first, deter-
mine the appliance operating time and total number of pre- %l 3 W
tl 5 PRl (X3.3)
heats. Then estimate the quantity of food cooked and establish
the breakdown among heavy (compartment loaded to capacity) where:
and light (single pan) loads. For example, a steamer operating tl = total time cooking light loads, h,
for 12 h a day with one preheat cooked 100 lb of food: 90 % %l = the percentage of food cooked under light load
of the food was cooked under heavy load conditions and 10 % conditions during the day,
was cooked under light load conditions. Calculate the energy W = total weight of food cooked per day, lb, and
due to cooking at heavy and light load cooking rates, and then PRl = the steamer’s light load production rate as deter-
calculate the idle energy consumption. This is added to a mined in 11.9.5, lb/h.
residual amount of energy which accounts for the times that a X3.4.4.2 The light load energy consumption is calculated
compartment is drawing steam, but is not cooking food. The using the following set of equations. For gas steamers, any
total daily energy is the sum of these components plus the electric energy shall be determined separately using the electric
preheat energy. For simplicity, it is assumed that subsequent equations.
preheats require the same time and energy as the first preheat Egas,l 5 qgas,l 3 tl (X3.4)
of the day.
Eelec,l 5 qelec,l 3 tl
X3.4.2 Step 1—For each compartment, determine the
steamer operating time, number of preheats, and amount of where:
food cooked under heavy (full compartment) and light (single- Egas,l = total gas light load energy consumption, Btu,
pan) load conditions. qgas,l = gas light load cooking energy rate as determined
X3.4.3 Step 2—Calculate the time and energy involved in in 11.9.3, Btu/h,
cooking heavy loads. Heavy loads are the equivalent of loading Eelec,l = total electric light load energy consumption, kWh,
the compartment with the maximum allowable number of pans. qelec,l = electric light load cooking energy rate as deter-
X3.4.3.1 The total time cooking heavy loads is determined mined in 11.9.3, kW.
as follows: X3.4.5 Step 4—Calculate the total idle time and energy
%h 3 W consumption and the residual energy consumption.
th 5 PC (X3.1) X3.4.5.1 The total idle time is determined as follows:
n p 3 tp
where: ti 5 ton 2 th 2 tl 2 60 (X3.5)
th = total time cooking heavy loads, h,
%h = the percentage of food cooked under heavy load where:
conditions during the day, ti = the total idle time, h,
W = total weight of food cooked per day, lb, and ton = the total daily on-time, h,

22
F 1484 – 04

np = the number of preheats, and np = the total number of preheats per day,
tp = preheat time, as determined in 11.5, min. Egas,p = gas preheat energy consumption as deter-
X3.4.5.2 The idle energy consumption is calculated using mined in 11.5, Btu,
the following set of equations. For gas steamers, any electric Eelec,daily = the total daily electric energy consumption,
energy shall be determined separately using the electric equa- Btu/d, and
tions. Eelec,p = electric preheat energy consumption as deter-
Egas,i 5 qgas,i 3 ti (X3.6)
mined in 11.5, Btu.
Eelec,i 5 qelec,i 3 ti
The complete formulae for calculating daily energy con-
sumption are as follows:
where: %h 3 W %l 3 W
Egas,i =
total gas idle energy consumption, Btu, Egas,daily 5 PC 3 qgas,h 1 PRl 3 qgas,l (X3.9)
qgas,i =
gas idle energy rate as determined in 11.6, Btu/h,
Eelec,i
qelec,i
=
total electric idle energy consumption, kWh, and
=
electric idle energy rate as determined in 11.6,
S
1 ton 2
%h 3 W % l 3 W n p 3 tp
PC 2 PRl 2 60 3 qgas,i D
kW.
X3.4.5.3 The residual energy consumption is calculated S
1 ton 2
% h 3 W % l 3 W n p 3 tp
PC 2 PRl 2 60 D
3 fr 3 qgas,r 1 np 3 Egas,p
using the following set of equations. For gas steamers, any %h 3 W %l 3 W
electric energy shall be determined separately using the electric Eelec,daily 5 PC 3 qelec,h 1 PRl 3 qelec,l

S D
equations. %h 3 W % l 3 W n p 3 t p
Egas,r 5 fr 3 qgas,h 3 ti (X3.7) 1 ton 2 PC 2 PRl 2 60 3 qelec,i

where:
Eelec,r 5 fr 3 qelec,h 3 ti
S
1 ton 2
%h 3 W % l 3 W n p 3 t p
PC 2 PRl 2 60 D
3 fr 3 qelec,r 1 np 3 Eelec,p

Egas,r = total gas residual energy consumption, Btu, X3.4.7 Step 6—The average electric demand for steamers
fr = the steamer’s residual energy usage factor (see may be calculated according to the following equation:
Table X3.1),
Eelec,daily
qgas,h = gas heavy load cooking energy rate as determined qavg 5 (X3.10)
ton
in 11.4.2, Btu/h,
Eelec,r = total electric residual energy consumption, kWh, where:
and qavg = the average demand for the steamer, kW,
qelec,h = electric heavy load energy rate as determined in Eelec,daily = the total daily electric energy consumption,
11.4.2, kW. kWh/d, and
ton = the total daily on-time, h.

TABLE X3.1 Steamer Residual Energy Usage Factors NOTE X3.3—It has been assumed that the appliance’s probable contri-
bution to the building’s peak demand is the average demand for the
Residual Energy
Steamer Type appliance. This is useful because the probability of an appliance drawing
Usage Factor
its average rate during the period that the building peak is set is
Type I—0 to 2.9 psig compartment pressure 16 %
significantly higher than for any other input rate for that appliance. If data
Type II—3 to 9.9 psig compartment pressure 12 %
Type III—10 to 15 psig compartment pressure 10 % exists otherwise for a given operation, the probable contribution to
Connectionless—0 to 2.9 psig compartment pressure 8% demand can be other than the average demand.
Connectionless—3 to 9.9 psig compartment pressure 6%
X3.4.8 Step 7—The estimated monthly appliance energy
cost may be determined as follows:
NOTE X3.2—The residual energy factor approximates the human factor Egas,daily
in steamer energy usage. It has been observed that steam compartments Cgas,monthly 5 rgas 3 Btu 3 dop (X3.11)
may be turned on (that is, drawing steam) with no food in the compart- 100 000 therm
ment. This usage pattern has a varying impact on steamer energy
consumption, based on the type of steamer. For example, atmospheric Celec,monthly 5 relec 3 Eelec,daily 3 dop 1 rdemand 3 qavg (X3.12)
pressure steamers typically consume more steam (hence, more energy)
during these periods than pressurized compartment steamers. where:
Cgas,monthly = the monthly appliance gas cost, $/mo,
X3.4.6 Step 5—The total daily energy consumption is rgas = the appropriate utility gas rate, $/therm,
calculated as follows: Egas,daily = the total daily gas energy consumption,
Egas,daily 5 qgas,h 1 qgas,l 1 Egas,i 1 Egas,r 1 np 3 Egas,p (X3.8) Btu/d,
Eelec,daily 5 qelec,h 1 qelec,l 1 Eelec,i 1 Eelec,r 1 np 3 Eelec,p dop = the average number of operating days per
month,
where: Celec,monthly = the monthly appliance electric cost, $/mo,
Egas,daily = the total daily gas energy consumption, relec = the appropriate utility electric rate,
Btu/d, $/kWh,

23
F 1484 – 04

Eelec,daily = the total daily electric energy consump- Eelec,l 5 8.6 kW 3 0.48 h
tion, kWh/d, Eelec,l 5 4.1 kWh
rdemand = the appropriate utility demand charge, X3.5.5 Step 4—Calculate the total idle time and energy
$/kW, consumption and the residual energy consumption.
qavg = the average demand for the steamer, kW. X3.5.5.1 The total idle time is determined as follows:
X3.5 Example of Calculating the Daily Energy Consump- n p 3 tp
ti 5 ton 2 th 2 tl 2 60 (X3.17)
tion for an Electric Steamer:
X3.5.1 Application of the test method to an electric steamer 1 preheat 3 17.0 min
ti 5 12.0 h 2 0.70 h 2 0.48 h 2 60 min/h
yielded the following results:
ti 5 10.5 h
TABLE X3.2 Electric Steamer Test Results—Example X3.5.5.2 The idle energy consumption is then calculated as
Test Result follows:
Steamer Type Type I, 2-compartment, 6-pan capacity Eelec,i 5 qelec,i 3 ti (X3.18)
Preheat Time 17.0 min
Preheat Energy 5.3 kWh Eelec,i 5 1.3 kW 3 10.5 h
Idle Energy Rate 1.3 kW Eelec,i 5 13.6 kWh
Heavy Load Cooking Energy Rate 16.8 kW
Light Load Cooking Energy Rate 8.6 kW X3.5.5.3 The residual energy consumption is then calcu-
Production Capacity 128 lb/h lated as follows:
Light Load Production Rate 21 lb/h
Eelec,r 5 fr 3 qelec,h 3 ti (X3.19)
Eelec,r 5 16 % 3 16.8 kW 3 10.5 h
X3.5.2 Step 1—The following appliance operation is as- Eelec,r 5 28.2 kWh
sumed: X3.5.6 Step 5—The total daily energy consumption is
calculated as follows:
TABLE X3.3 Steamer Operation Assumptions
Eelec,daily 5 Eelec,h 1 Eelec,l 1 Eelec,i 1 Eelec,r 1 np 3 Eelec,p
Operating Time 12 h (X3.20)
Number of Preheats 1 preheat
Total Amount of Food Cooked 100 lb Eelec,daily 5 11.8 kWh 1 4.1 kWh 1 13.6 kWh 1 28.2 kWh 1 1 3 5.3 kWh
Percentage of Food Cooked Under 90 % (3 100 lb = 90 lb)
Heavy Load Conditions
Eelec,daily 5 63.0 kWh/day
Percentage of Food Cooked Under 10 % (3 100 lb = 10 lb) X3.5.7 Step 6—Calculate the average demand as follows:
Light Load Conditions
Eelec,daily
qavg 5 ton (X3.21)

X3.5.3 Step 2—Calculate the total heavy load energy. 63.0 kWh
qavg 5 12.0 h
X3.5.3.1 The total time cooking heavy loads is as follows:
%h 3 W qavg 5 5.25 kW
th 5 PC (X3.13)
X3.6 Example of Calculating the Daily Energy Consump-
90 % 3 100 lb
th 5 tion for a Gas Steamer:
128 lb/h
th 5 0.70 h
X3.6.1 Application of the test method to a gas steamer
yielded the following results:
X3.5.3.2 The total heavy load energy consumption is then
calculated as follows:
Eelec,h 5 qelec,h 3 th (X3.14) TABLE X3.4 Gas Steamer Test Results—Example
Test Result
Eelec,h 5 16.8 kW 3 0.70 h
Steamer Type Type I, 2-compartment, 6-pan capacity
Eelec,h 5 11.8 kWh Preheat Time 11.0 min
X3.5.4 Step 3—Calculate the total light load energy. Preheat Energy 28 000 Btu
Idle Energy Rate 17 000 Btu/h
X3.5.4.1 The total time cooking light loads is as follows: Heavy Load Cooking Energy Rate 143 000 Btu/h
%l 3 W Light Load Cooking Energy Rate 85 000 Btu/h
tl 5 PRl (X3.15) Production Capacity 156 lb/h
Light Load Production Rate 26 lb/h
10 % 3 100 lb
tl 5 21 lb/h
tl 5 0.48 h
X3.6.2 Step 1—The following appliance operation is as-
X3.5.4.2 The total light load energy consumption is then sumed:
calculated as follows: X3.6.3 Step 2—Calculate the total heavy load energy.
Eelec,l 5 qelec,l 3 tl (X3.16) X3.6.3.1 The total time cooking heavy loads is as follows:

24
F 1484 – 04
TABLE X3.5 Steamer Operation Assumptions Egas,l 5 85 000 Btu/h 3 0.38 h
Operating Time 12 h Egas,l 5 32 300 Btu
Number of Preheats 1 preheat
Total Amount of Food Cooked 100 lb X3.6.5 Step 4—Calculate the total idle time and energy
Percentage of Food Cooked Under 90 % (3 100 lb = 90 lb)
Heavy Load Conditions
consumption and residual energy consumption.
Percentage of Food Cooked Under 10 % (3 100 lb = 10 lb) X3.6.5.1 The total idle time is determined as follows:
Light Load Conditions
n p 3 tp
ti 5 ton 2 th 2 tl 2 60 (X3.26)

%h 3 W 1 preheat 3 11.0 min


th 5 PC (X3.22) ti 5 12.0 h 2 0.58 h 2 0.38 h 2 60 min/h
90 % 3 100 lb ti 5 10.9 h
th 5 156 lb/h
X3.6.5.2 The idle energy consumption is then calculated as
th 5 0.58 h
follows:
X3.6.3.2 The total heavy load energy consumption is then Egas,i 5 qgas,i 3 ti (X3.27)
calculated as follows:
Egas,i 5 17 000 Btu/h 3 10.9 h
Egas,h 5 qgas,h 3 th (X3.23)
Egas,i 5 185 300 Btu
Egas,h 5 143 000 Btu/h 3 0.58 h
Egas,h 5 82 940 Btu
X3.6.5.3 The residual energy consumption is then calcu-
lated as follows:
X3.6.4 Step 3—Calculate the total light load energy.
Egas,r 5 fr 3 qgas,h 3 ti (X3.28)
X3.6.4.1 The total time cooking light loads is as follows:
Egas,r 5 16 % 3 143 000 Btu/h 3 10.9 h
%l 3 W
tl 5 PRl (X3.24) Egas,r 5 249 390 Btu
10 % 3 100 lb X3.6.6 Step 5—The total daily energy consumption is
tl 5 26 lb/h calculated as follows:
tl 5 0.38 h Egas,daily 5 qgas,h 1 qgas,l 1 Egas,i 1 Egas,r 1 np 3 Egas,p (X3.29)
X3.6.4.2 The total light load energy consumption is then Egas,daily 5 82 940 Btu 1 32 300 Btu 1 185 300 Btu 1 249 390 Btu 11
calculated as follows: 3 28 000 Btu
Egas,l 5 qgas,l 3 tl (X3.25) Egas,daily 5 577 930 Btu/day 5 5.78 therms/day

ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.

This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 610-832-9585 (phone), 610-832-9555 (fax), or service@astm.org (e-mail); or through the ASTM website
(www.astm.org).

25

You might also like