Presupuesto de Obra

VALORIZACION Nº01 FEBRERO - 2019 Periodo: (12.02.19 - 28.02.19)

OBRA: "MEJORAMIENTO DE CALLES EN EL P.J. LA UNION,DISTRITO DE CHIMBOTE, PROVINCIA DEL SANTA-ANCASH" III ETAPA PLAZO DE EJECUCION DE OBRA: 60 DIAS CALENDARIO
ENTIDAD: MUNICIPALIDAD PROVINCIAL DEL SANTA FECHA DE INICIO DE OBRA: 12 DE FEBRERO DEL 2019
MONTO: S/1,726,876.53 FECHA DE TERMINO DE OBRA: 12 DE ABRIL DEL2019
CONTRATISA: CONSORCIO LA UNION ING. INSPECTOR: Ing. Segundo Melchor Carbonel Ticona
SUB PRESUPUESTO: : 002 VEREDAS ING. RESIDENTE: Ing. Luis Fernando Graus Flores
ING. INSPECTOR Ing. SEGUNDO MELCHOR CARBONEL TICONA

AVANCEE DEL MES: 28.00% SALDO POR VALORIZAR: 72.00%

PRESUPUESTO BASE ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADA SALDO POR VALORIZAR
ITEM DESCRIPCIÓN
UNIDAD METRADO P.UNIT. PRESUP. METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %

01 TRABAJOS PREELIMINARES
01.01 TRANSPORTE DE EQUIPO, MATERIALES Y HERRAMIENTAS glb 1.00 1,392.80 1,392.80 0.00 0.00 0.00 1.00 1,392.80 100.00 1.00 1,392.80 100.00 0.00 0.00 0.00
01.02 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR m2 2,610.62 0.72 1,879.65 0.00 0.00 0.00 2,610.62 1,879.65 100.00 2,610.62 1,879.65 100.00 0.00 0.00 0.00
01.03 DEMOLICION DE VERREDAS DE 0.10 M C/MAQUINA m2 1,598.38 7.36 11,764.08 0.00 0.00 0.00 1,598.38 11,764.08 100.00 1,598.38 11,764.08 100.00 0.00 0.00 0.00
01.04 DEMOLICION MANUAL DE VEREDAS DE 0.10M m2 399.60 15.85 6,333.66 0.00 0.00 0.00 399.60 6,333.66 100.00 399.60 6,333.66 100.00 0.00 0.00 0.00
01.05 DEMOLICION DE CERCO PERIMETRICO EN ZONA DE CONSTRUCCION m2 30.25 27.18 822.20 0.00 0.00 0.00 30.25 822.20 100.00 30.25 822.20 100.00 0.00 0.01 0.00
01.06 TALA Y RETIRO DE ARBOLES und 2.00 423.73 847.46 0.00 0.00 0.00 2.00 847.46 100.00 2.00 847.46 100.00 0.00 0.00 0.00
02 MOVIMIENTO DE TIERRAS 0.00
02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20M m3 522.12 31.92 16,666.07 0.00 0.00 0.00 522.12 16,666.07 100.00 522.12 16,666.07 100.00 0.00 0.00 0.00
02.02 EXCAVACION DE ZANJA PARA UÑA DE VEREDA m3 62.62 31.92 1,998.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.62 1,998.83 100.00
02.03 PREPARACION SUBRASANTE VEREDA m2 2,610.62 6.69 17,465.05 0.00 0.00 0.00 2,088.50 13,972.04 80.00 2,088.50 13,972.04 80.00 522.12 3,493.01 20.00
02.04 AFIRMADO DE 4" PARA VEREDAS m2 2,610.62 10.45 27,280.98 0.00 0.00 0.00 2,306.51 24,103.01 88.35 2,306.51 24,103.01 88.35 304.11 3,177.97 11.65
02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINA DM=10KM m3 961.43 13.90 13,363.88 0.00 0.00 0.00 961.43 13,363.88 100.00 961.43 13,363.88 100.00 0.00 0.00 0.00
03 VEREDAS 0.00
03.01 CONCRETO VEREDA Y RAMPA F^c= 175 kg/cm2 E= 4" ACABADO 1:2/BRUÑADO CURADO (Cemento Tipo MS) m2 2,610.62 62.98 164,416.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,610.62 164,416.85 100.00
03.02 UÑA DE VERDA Y RAMPA CONCRETO F`c= 175 kg/cm2(Cemneto Tipo MS) m 1,565.57 20.25 31,702.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,565.57 31,702.79 100.00
PINTADO DE BORDE DE VEREDA P=0.30M m 2,127.78 4.68 9,958.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,127.78 9,958.01 100.00
04 JUNTAS 0.00
04.01 JUNTAS ASFALTICAS E=1" m 664.85 2.97 1,974.60 0.00 0.00 0.00 664.85 1,974.60 100.00
05 AREAS VERDES 0.00
05.01 CORTE SUPERFICIAL CON MAQUINARIA H= 0.20M m3 647.43 7.79 5,043.48 0.00 0.00 0.00 647.43 5,043.48 100.00 647.43 5,043.48 100.00 0.00 0.00 0.00
05.02 ELIMINACCION DE MATERIAL EXCEDENTE C/MAQ D=10KM m3 776.91 13.90 10,799.05 0.00 0.00 0.00 776.91 10,799.05 100.00 776.91 10,799.05 100.00 0.00 0.00 0.00
05.03 RELLENO CON TIERRA DE CULTIVO m3 809.28 43.58 35,268.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 809.28 35,268.42 100.00
05.04 PREPARACION DE TERRENO PARA SEMBRADO m2 3,237.13 5.17 16,735.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,237.13 16,735.96 100.00
05.05 SEMBRADO DE GRASS EN CHAMPAS m2 3,237.13 12.79 41,402.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,237.13 41,402.89 100.00
05.06 CONSERVACION Y RIEGO DE JARDINES HASTA ENTREGA DE OBRA glb 1.00 500.00 500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 500.00 100.00
06 VARIOS 0.00
06.01 SUM. NIVELACION Y COLOCACION DE CAJAS DE AGUA und 146.00 175.86 25,675.56 0.00 0.00 0.00 73.00 12,837.78 50.00 73.00 12,837.78 50.00 73.00 12,837.78 50.00
06.02 SUM. NIVELACION Y COLOCACION DE CAJAS DE DESAGUE und 146.00 133.77 19,530.42 0.00 0.00 0.00 73.00 9,765.21 50.00 73.00 9,765.21 50.00 73.00 9,765.21 50.00
COSTO DIRECTO 462,822.70 0.00 129,590.35 129,590.35 333,232.34
GASTOS GENERALES 8% 37,025.82 0.00 10,367.23 10,367.23 26,658.59
UTILIDAD 7% 32,397.59 0.00 9,071.32 9,071.32 23,326.26
SUB TOTAL 532,246.11 0.00 149,028.90 149,028.90 383,217.21
IGV 18% 95,804.30 0.00 26,825.20 26,825.20 68,979.10
TOTAL PRESUPUESTO 628,050.41 0.00 175,854.11 175,854.11 452,196.30
AVANCES 100% 0.00% 28% 28.00% 72.00%
Presupuesto de Obra
VALORIZACION Nº02 MARZO - 2019 Periodo: (01.03.19 - 31.03.19)

OBRA: "MEJORAMIENTO DE CALLES EN EL P.J. LA UNION,DISTRITO DE CHIMBOTE, PROVINCIA DEL SANTA-ANCASH" III ETAPA PLAZO DE EJECUCION DE OBRA: 60 DIAS CALENDARIO
ENTIDAD: MUNICIPALIDAD PROVINCIAL DEL SANTA FECHA DE INICIO DE OBRA: 12 DE FEBRERO DEL 2019
MONTO: S/1,726,876.53 FECHA DE TERMINO DE OBRA: 12 DE ABRIL DEL2019
CONTRATISA: CONSORCIO LA UNION ING. INSPECTOR: Ing. Segundo Melchor Carbonel Ticona
SUB PRESUPUESTO: : 002 VEREDAS ING. RESIDENTE: Ing. Luis Fernando Graus Flores
ING. INSPECTOR: Ing. SEGUNDO MELCHOR CARBONEL TICONA

AVANCEE DEL MES: 51.00% SALDO POR VALORIZAR: 21.00%

PRESUPUESTO BASE ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADA SALDO POR VALORIZAR
ITEM DESCRIPCIÓN
UNIDAD METRADO P.UNIT. PRESUP. METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %

01 TRABAJOS PREELIMINARES
01.01 TRANSPORTE DE EQUIPO, MATERIALES Y HERRAMIENTAS glb 1.00 1,392.80 1,392.80 1.00 1,392.80 100.00 0.00 0.00 0.00 1.00 1,392.80 100.00 0.00 0.00 0.00
01.02 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR m2 2,610.62 0.72 1,879.65 2,610.62 1,879.65 100.00 0.00 0.00 0.00 2,610.62 1,879.65 100.00 0.00 0.00 0.00
01.03 DEMOLICION DE VERREDAS DE 0.10 M C/MAQUINA m2 1,598.38 7.36 11,764.08 1,598.38 11,764.08 100.00 0.00 0.00 0.00 1,598.38 11,764.08 100.00 0.00 0.00 0.00
01.04 DEMOLICION MANUAL DE VEREDAS DE 0.10M m2 399.60 15.85 6,333.66 399.60 6,333.66 100.00 0.00 0.00 0.00 399.60 6,333.66 100.00 0.00 0.00 0.00
01.05 DEMOLICION DE CERCO PERIMETRICO EN ZONA DE CONSTRUCCION m2 30.25 27.18 822.20 30.25 822.20 100.00 0.00 0.00 0.00 30.25 822.20 100.00 0.00 0.01 0.00
01.06 TALA Y RETIRO DE ARBOLES und 2.00 423.73 847.46 2.00 847.46 100.00 0.00 0.00 0.00 2.00 847.46 100.00 0.00 0.00 0.00
02 MOVIMIENTO DE TIERRAS
02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20M m3 522.12 31.92 16,666.07 522.12 16,666.07 100.00 0.00 0.00 0.00 522.12 16,666.07 100.00 0.00 0.00 0.00
02.02 EXCAVACION DE ZANJA PARA UÑA DE VEREDA m3 62.62 31.92 1,998.83 0.00 0.00 0.00 62.62 1,998.83 100.00 62.62 100.00 0.00 1,998.83 0.00
02.03 PREPARACION SUBRASANTE VEREDA m2 2,610.62 6.69 17,465.05 2,088.50 13,972.04 80.00 522.12 3,493.01 20.00 2,610.62 17,465.05 100.00 0.00 0.00 0.00
02.04 AFIRMADO DE 4" PARA VEREDAS m2 2,610.62 10.45 27,280.98 2,306.51 24,103.01 88.35 304.11 3,177.97 11.65 2,610.62 27,280.98 100.00 0.00 0.00 0.00
02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINA DM=10KM m3 961.43 13.90 13,363.88 961.43 13,363.88 100.00 0.00 0.00 0.00 961.43 13,363.88 100.00 0.00 0.00 0.00
03 VEREDAS 0.00
03.01 CONCRETO VEREDA Y RAMPA F^c= 175 kg/cm2 E= 4" ACABADO 1:2/BRUÑADO CURADO (Cemento Tipo MS) m2 2,610.62 62.98 164,416.85 0.00 0.00 0.00 2,088.50 131,533.48 80.00 2,088.50 131,533.48 80.00 522.12 32,883.37 20.00
03.02 UÑA DE VERDA Y RAMPA CONCRETO F`c= 175 kg/cm2(Cemneto Tipo MS) m 1,565.57 20.25 31,702.79 0.00 0.00 0.00 1,252.46 25,362.23 80.00 1,252.46 25,362.23 80.00 313.11 6,340.56 20.00
PINTADO DE BORDE DE VEREDA P=0.30M m 2,127.78 4.68 9,958.01 0.00 0.00 0.00 1,151.76 5,390.26 54.13 1,151.76 5,390.26 54.13 976.02 4,567.75 45.87
04 JUNTAS 0.00 0.00 0.00
04.01 JUNTAS ASFALTICAS E=1" m 664.85 2.97 1,974.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 664.85 1,974.60 100.00
05 AREAS VERDES
05.01 CORTE SUPERFICIAL CON MAQUINARIA H= 0.20M m3 647.43 7.79 5,043.48 647.43 5,043.48 100.00 0.00 0.00 0.00 647.43 5,043.48 100.00 0.00 0.00 0.00
05.02 ELIMINACCION DE MATERIAL EXCEDENTE C/MAQ D=10KM m3 776.91 13.90 10,799.05 776.91 10,799.05 100.00 0.00 0.00 0.00 776.91 10,799.05 100.00 0.00 0.00 0.00
05.03 RELLENO CON TIERRA DE CULTIVO m3 809.28 43.58 35,268.42 0.00 0.00 0.00 404.64 17,634.21 50.00 404.64 17,634.21 50.00 404.64 17,634.21 50.00
05.04 PREPARACION DE TERRENO PARA SEMBRADO m2 3,237.13 5.17 16,735.96 0.00 0.00 0.00 1,563.91 8,085.42 48.31 1,563.91 8,085.42 48.31 1,673.22 8,650.54 51.69
05.05 SEMBRADO DE GRASS EN CHAMPAS m2 3,237.13 12.79 41,402.89 0.00 0.00 0.00 1,294.85 16,561.16 40.00 1,294.85 16,561.16 40.00 1,942.28 24,841.74 60.00
05.06 CONSERVACION Y RIEGO DE JARDINES HASTA ENTREGA DE OBRA glb 1.00 500.00 500.00 0.00 0.00 0.00 0.40 200.00 40.00 0.40 200.00 40.00 0.60 300.00 60.00
06 VARIOS
06.01 SUM. NIVELACION Y COLOCACION DE CAJAS DE AGUA und 146.00 175.86 25,675.56 73.00 12,837.78 50.00 73.00 12,837.78 50.00 146.00 25,675.56 100.00 0.00 0.00 0.00
06.02 SUM. NIVELACION Y COLOCACION DE CAJAS DE DESAGUE und 146.00 133.77 19,530.42 73.00 9,765.21 50.00 73.00 9,765.21 50.00 146.00 19,530.42 100.00 0.00 0.00 0.00
COSTO DIRECTO 462,822.70 129,590.35 236,039.57 365,629.92 97,192.78
GASTOS GENERALES 8% 37,025.82 10,367.23 18,883.17 29,250.39 7,775.42
UTILIDAD 7% 32,397.59 9,071.32 16,522.77 25,594.09 6,803.49
SUB TOTAL 532,246.11 19,438.55 271,445.50 290,884.06 241,362.05
IGV 18% 95,804.30 3,498.94 48,860.19 52,359.13 43,445.17
TOTAL PRESUPUESTO 628,050.41 22,937.49 320,305.70 343,243.19 284,807.22
AVANCE 100% 28.00% 51% 79.00% 21.00%
Presupuesto de Obra
VALORIZACION Nº03 ABRIL- 2019 Periodo: (01.04.19 - 12.04.19)

OBRA: "MEJORAMIENTO DE CALLES EN EL P.J. LA UNION,DISTRITO DE CHIMBOTE, PROVINCIA DEL SANTA-ANCASH" III ETAPA PLAZO DE EJECUCION DE OBRA: 60 DIAS CALENDARIO
ENTIDAD: MUNICIPALIDAD PROVINCIAL DEL SANTA FECHA DE INICIO DE OBRA: 12 DE FEBRERO DEL 2019
MONTO: S/1,726,876.53 FECHA DE TERMINO DE OBRA: 12 DE ABRIL DEL2019
CONTRATISA: CONSORCIO LA UNION ING. INSPECTOR: Ing. Segundo Melchor Carbonel Ticona
SUB PRESUPUESTO: : 002 VEREDAS ING. RESIDENTE: Ing. Luis Fernando Graus Flores
ING. INSPECTOR: Ing. SEGUNDO MELCHOR CARBONEL TICONA

AVANCEE DEL MES: 21% SALDO POR VALORIZAR: 0.00%

PRESUPUESTO BASE ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADA SALDO POR VALORIZAR
ITEM DESCRIPCIÓN
UNIDAD METRADO P.UNIT. PRESUP. METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %

01 TRABAJOS PREELIMINARES
01.01 TRANSPORTE DE EQUIPO, MATERIALES Y HERRAMIENTAS glb 1.00 1,392.80 1,392.80 1.00 1,392.80 100.00 0.00 0.00 0.00 1.00 1,392.80 100.00 0.00 0.00 0.00
01.02 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR m2 2,610.62 0.72 1,879.65 2,610.62 1,879.65 100.00 0.00 0.00 0.00 2,610.62 1,879.65 100.00 0.00 0.00 0.00
01.03 DEMOLICION DE VERREDAS DE 0.10 M C/MAQUINA m2 1,598.38 7.36 11,764.08 1,598.38 11,764.08 100.00 0.00 0.00 0.00 1,598.38 11,764.08 100.00 0.00 0.00 0.00
01.04 DEMOLICION MANUAL DE VEREDAS DE 0.10M m2 399.60 15.85 6,333.66 399.60 6,333.66 100.00 0.00 0.00 0.00 399.60 6,333.66 100.00 0.00 0.00 0.00
01.05 DEMOLICION DE CERCO PERIMETRICO EN ZONA DE CONSTRUCCION m2 30.25 27.18 822.20 30.25 822.20 100.00 0.00 0.00 0.00 30.25 822.20 100.00 0.00 0.01 0.00
01.06 TALA Y RETIRO DE ARBOLES und 2.00 423.73 847.46 2.00 847.46 100.00 0.00 0.00 0.00 2.00 847.46 100.00 0.00 0.00 0.00
02 MOVIMIENTO DE TIERRAS
02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20M m3 522.12 31.92 16,666.07 522.12 16,666.07 100.00 0.00 0.00 0.00 522.12 16,666.07 100.00 0.00 0.00 0.00
02.02 EXCAVACION DE ZANJA PARA UÑA DE VEREDA m3 62.62 31.92 1,998.83 62.62 1,998.83 100.00 0.00 0.00 0.00 62.62 1,998.83 100.00 0.00 0.00 0.00
02.03 PREPARACION SUBRASANTE VEREDA m2 2,610.62 6.69 17,465.05 2,610.62 17,465.05 100.00 0.00 0.00 0.00 2,610.62 17,465.05 100.00 0.00 0.00 0.00
02.04 AFIRMADO DE 4" PARA VEREDAS m2 2,610.62 10.45 27,280.98 2,610.62 27,280.98 100.00 0.00 0.00 0.00 2,610.62 27,280.98 100.00 0.00 0.00 0.00
02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINA DM=10KM m3 961.43 13.90 13,363.88 961.43 13,363.88 100.00 0.00 0.00 0.00 961.43 13,363.88 100.00 0.00 0.00 0.00
03 VEREDAS
03.01 CONCRETO VEREDA Y RAMPA F^c= 175 kg/cm2 E= 4" ACABADO 1:2/BRUÑADO CURADO (Cemento Tipo MS) m2 2,610.62 62.98 164,416.85 2,088.50 131,533.48 80.00 522.12 32,883.37 20.00 2,610.62 164,416.85 100.00 0.00 0.00 0.00
03.02 UÑA DE VERDA Y RAMPA CONCRETO F`c= 175 kg/cm2(Cemneto Tipo MS) m 1,565.57 20.25 31,702.79 1,252.46 25,362.23 80.00 313.11 6,340.56 20.00 1,565.57 31,702.79 100.00 0.00 0.00 0.00
PINTADO DE BORDE DE VEREDA P=0.30M m 2,127.78 4.68 9,958.01 1,151.76 5,390.26 54.13 976.02 4,567.75 45.87 2,127.78 9,958.01 100.00 0.00 0.00 0.00
04 JUNTAS
04.01 JUNTAS ASFALTICAS E=1" m 664.85 2.97 1,974.60 0.00 0.00 0.00 664.85 1,974.60 100.00 664.85 1,974.60 100.00 0.00 0.00 0.00
05 AREAS VERDES
05.01 CORTE SUPERFICIAL CON MAQUINARIA H= 0.20M m3 647.43 7.79 5,043.48 647.43 5,043.48 100.00 0.00 0.00 0.00 647.43 5,043.48 100.00 0.00 0.00 0.00
05.02 ELIMINACCION DE MATERIAL EXCEDENTE C/MAQ D=10KM m3 776.91 13.90 10,799.05 776.91 10,799.05 100.00 0.00 0.00 0.00 776.91 10,799.05 100.00 0.00 0.00 0.00
05.03 RELLENO CON TIERRA DE CULTIVO m3 809.28 43.58 35,268.42 404.64 17,634.21 50.00 404.64 17,634.21 50.00 809.28 35,268.42 100.00 0.00 0.00 0.00
05.04 PREPARACION DE TERRENO PARA SEMBRADO m2 3,237.13 5.17 16,735.96 1,563.91 8,085.42 48.31 1,673.22 8,650.54 51.69 3,237.13 16,735.96 100.00 0.00 0.00 0.00
05.05 SEMBRADO DE GRASS EN CHAMPAS m2 3,237.13 12.79 41,402.89 1,294.85 16,561.16 40.00 1,942.28 24,841.74 60.00 3,237.13 41,402.89 100.00 0.00 0.00 0.00
05.06 CONSERVACION Y RIEGO DE JARDINES HASTA ENTREGA DE OBRA glb 1.00 500.00 500.00 0.40 200.00 40.00 0.60 300.00 60.00 1.00 500.00 100.00 0.00 0.00 0.00
06 VARIOS
06.01 SUM. NIVELACION Y COLOCACION DE CAJAS DE AGUA und 146.00 175.86 25,675.56 146.00 25,675.56 100.00 0.00 0.00 0.00 146.00 25,675.56 100.00 0.00 0.00 0.00
06.02 SUM. NIVELACION Y COLOCACION DE CAJAS DE DESAGUE und 146.00 133.77 19,530.42 146.00 19,530.42 100.00 0.00 0.00 0.00 146.00 19,530.42 100.00 0.00 0.00 0.00
COSTO DIRECTO 462,822.70 365,629.92 97,192.77 462,822.69 0.00
GASTOS GENERALES 8% 37,025.82 29,250.39 7,775.42 37,025.82 0.00
UTILIDAD 7% 32,397.59 25,594.09 6,803.49 32,397.59 0.00
SUB TOTAL 532,246.10 420,474.41 111,771.69 532,246.10 0.00
IGV 18% 95,804.30 75,685.39 20,118.90 95,804.30 0.00
TOTAL PRESUPUESTO 628,050.40 496,159.80 131,890.59 628,050.39 0.00
AVANCE 100% 79.00% 21% 100.00% 0.00%