CLIENT: OMAN ELECTRICITY TRANSMISSION COMPANY S.A.O.

C Contract Duration : 6Weeks + 18Months
CONSULTANT: ENERGOPROJEKT ENTEL LLC TENDER No 67/2016 ‐ CONSTRUCTION OF 400kV OHL AND 132kV CABLE FROM 400kV SFZ GS TO SHINAS 1 GS Contract Period: 01/01/2018 TO 12/08/2019
ID Task Name Duration Start Finish Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 TENDER 67/2016 ‐ CONSTRUCTION OF  425 days Mon 01/01/18 Sat 11/05/19
400kV OHL AND 132kV CABLE FROM SFZ 
TO SHINAS 1GS ‐ IMPACTED‐1
2 CONTRACT COMMENCEMENT 0 days Mon 01/01/18 Mon 01/01/18 01/01

3 CONSTRUCTION 306 days Mon 30/04/18 Sun 21/04/19


4 CIVIL WORKS 201 days Mon 30/04/18Wed 19/12/18
5 ACCESS ROADS & TOWER BENCHING 120 days Sun 08/07/18 Sat 24/11/18
6 PLAIN AND HILL 120 days Sun 08/07/18 Sat 24/11/18 Access Road Team

7 SOIL INVESTIGATION 90 days Mon 30/04/18 Sun 12/08/18


8 PLAIN AND HILL 90 days Mon 30/04/18 Sun 12/08/18 Soil Investigation Team

9 FOUNDATION & EARTHING WORKS 135 days Mon 16/07/18Wed 19/12/18


10 PLAIN AND HILL ‐ 1 90 days Mon 16/07/18 Sun 28/10/18 Foundation Team 1

11 PLAIN AND HILL ‐ 2 90 days Thu 06/09/18Wed 19/12/18 Foundation Team 2

12 ELECTRICAL & MECHANICAL WORKS 210 days Mon 20/08/18 Sun 21/04/19


13 TOWER ERECTION WORKS 160 days Mon 20/08/18 Thu 21/02/19
14 TOWER ASSEMBLY 135 days Mon 20/08/18Wed 23/01/19
15 PLAIN AND HILL ‐ 1 120 days Mon 20/08/18 Sun 06/01/19 Tower Assembly Team 1

16 PLAIN AND HILL ‐ 2 90 days Thu 11/10/18Wed 23/01/19 Tower Assembly Team 2

17 TOWER ERECTION 150 days Sat 01/09/18 Thu 21/02/19


18 PLAIN AND HILL 150 days Sat 01/09/18 Thu 21/02/19 Tower Erection Team

19 STRINGING WORKS 133 days Sun 18/11/18 Sun 21/04/19


20 OPGW STRINGING 90 days Sun 18/11/18 Sat 02/03/19
21 2 Nos ‐ OPGW 90 days Sun 18/11/18 Sat 02/03/19 Stringing Team (OPGW)

22 CONDUCTOR STRINGING 100 days Wed 26/12/18 Sun 21/04/19


23 2Ckt ‐ 3Phs/Ckt ‐ Quad Cond 100 days Wed 26/12/18 Sun 21/04/19 Stringing Team (Conductor)

24 FINAL INSPECTION / TESTING &  30 days Sun 07/04/19 Sat 11/05/19 KEC/EPE & OETC Inspection/Commissioning team

COMMISSIONING
25 COMPLETION OF PROJECT 0 days Sat 11/05/19 Sat 11/05/19

Task Rolled Up Milestone Project Summary Manual Task Start-only Critical


Milestone Rolled Up Progress Group By Summary Duration-only Finish-only Critical Split
TENDER NO. 67/2016
Summary Split Inactive Milestone Manual Summary Rollup External Tasks Progress
Rolled Up Task External Tasks Inactive Summary Manual Summary External Milestone Deadline

Date: Tue 07/05/19 Page 1 of 1