You are on page 1of 1

SONAULI EXISTING GORAKHPUR BYPASS (PROJECT END)

A1 P1 P2 A2

NOTES:-

LONGITUDINAL ELEVATION

A1 P1 P2 A2

REFERENCE DRAWINGS :-

LEGENDS

(HALF TOP PLAN) (HALF BOTTOM PLAN)


PLAN)

DESIGN CONSULTANT :- CLIENT:- National Highway Authority Of India EPC CONTRACTOR :- MONTECARLO LIMITED AUTHORITY ENGINEER:- DRAWING TITLE :- DRAWING NO:- CICPL/D1008/FLY/16+219.938/GAD/01
(Ministry of Road Transport & Highways BUILDING A BRIGHT FUTURE
CIVIL BABA INFRA CONSULTANT PVT. LTD.
Government of India) DRAWN DESIGNED CHECKED APPROVED
7th Floor, Shilp Complex, Near Municipal
SCO-4 G-5 & 6. Sector 10, Dwarka, New Delhi Market, Chimanlal Girdharlal Rd, Mithakhali, SA Infrastructure Consultants Pvt. Ltd. GENERAL ARRANGEMENT DRAWING
First Floor,Jharsa Chowk,
Navrangpura, Ahmedabad, Gujarat 380009
Tower A-II, 11th Floor, Ansal Corporate Park, FOR FLYOVER AT CH: 16+219.938
Tel.:+91-79-26409333, 26409777.
PROJECT :- CONSTRUCTION OF GORAKHPUR BYPASS FROM EXISTING Sector - 142, Noida, Uttar Pradesh 201301
Sector-31, Gurgaon 122022 KM 79.670 OF NH-29E TO EXISTING KM 251.700 OF NH-28 Fax: +91 - 79-26408444
THROUGH AN ENGINEERING, PROCUREMENT AND E-Mail : mail@mclindia.com
Website : www.mclindia.com REVISION :R-0 DATE: SEP 2018 SCALE: SHEET SIZE: A2
REV DATE REVISION / PURPOSE CONSTRUCTION (EPC) IN THE STATE OF UTTAR PRADESH.