Professional Documents
Culture Documents
1. INTRODUCTION
Taking over is the critical part of any construction project. Issuing of taking over
certificate is major milestone in construction contract. In FIDIC contract, taking
over certificate is generally issued by Engineer or sometime by Employer. The
issuance of taking over certificate means the project or work has been
satisfactorily completed by contractor (except minor defects and outstanding
items of works) and should signify the point that the project or work become
revenue generating asset or the project or work become worthy to be used by
Employer for their intended purpose. The issue of taking over certificate also
means the work or the project has been taken over by Employer. The effective
date of issue of taking over certificate is the commencement date of defect
liability/notification period.
For issuing a taking over certificate, every items of the project or work is not
necessarily to be completed in a micro scale. Minor outstanding works can be
completed in defect liability/notification period. Further, defect liability/notification
period is not added for those items which are completed during defect
liability/notification period except for those which have been performed
intentionally defective by Contractor. Generally, defect liability period of
construction contract is 1 year and it may be two year depending upon the nature
of work.
The Employer is required to take over the works when they are complete in
accordance with the Contract except for minor outstanding works that doesnot
1
affect the use of works or section for their intended purposes when they have
passed the tests on completion. The contractor applies for taking over certificate
by written notice to the Employer/Engineer which may precede the completion
and/ or passing of the tests. The Engineer/Employer either shall issue the taking
over certificate to the contractor stating the date on which the works are
completed in according to the contract( except some outstanding works which
doesnot affect the works or section for its intended purpose of use) including the
passing the tests on completion, or reject the application giving the reasons and
specifying the work required to be done further by Contractor to enable taking
over certificate to be issued: the contractor shall than complete such works
before issuing the further notice. It is stipulated in the contract that upon
submission of contractor’s application of TOC, within 28 days Engineer/Employer
shall give their response. If Engineer/Employer fails to either issue TOC or reject
the contractor’s application within 28 days and if the works or sections are
substantially completed in accordance with the contract, the TOC shall be
deemed to have been issued on the last day of that period (FIDIC Red Book
1999). Provision in FIDIC 1987 is slightly different as it doesnot have criteria of
automatically issuance of TOC in the event of failure of response from
Engineer/Employer on Contractor’s application for TOC within 21 days even if the
works or section substantially completed and precede the test on completion in
accordance with contract.
The TOC can be issued as part or sections where contract allows separate time
of completion for that parts or section or if such parts or section after completion
occupied by Employer or Employer has elected to occupy or use prior to
completion (where such prior occupation or use is not provided for in the contract
or has not been agreed by the contractor as temporary measures) or substantial
completion of parts of the works.
The Employer grand the Contractor possession of the site as per the Clause 2.2.
Taking over certificate brings the possession to the End. If the Employer
expected to take over any part of the Works, it should have been defined, in the
Appendix to Tender, as a Section. Upon issuance of TOC, following sub-clauses
of Contract based on FIDIC 199 Red book will be affected and some of the
clauses will cease. For detail, readers are requested to study the clauses.
It is important to note that upon the issue of TOC, the possession of risk in the
work transfer from Contractor to Employer. It is therefore vital that the Employer
ensures that it has adequate insurance for the works (i.e. in respect of loss of
use, damage and destruction) as upon the issuance of TOC the Contractor’s
insurance obligation will also be ceased. Taking over May also has very
significant impact on the performance security and retention under the contract.
The value of performance bond may be reduced to 50%, while percentage of
retention money (i.e. usually up to 50%) needs to be paid to the Contractor.
3
Contractor is liable to be compensated to those losses. However, there is not
mentioned expressly about the extension of time due to delay of taking over as
part or section but Contractor may claim as per related clauses.
The Contractor has to complete outstanding works as listed in TOC and remedy
any defect due to his action or inaction within the DLP/DNP and execute all the
works as instructed by Engineer/Employer. The definition of contract period is the
period from commencement to the period a year or period mentioned in contract
after taking over. Before completion of DLP/DNP, a joint site visit shall be made
and Contractor shall be notified any defects to be rectify before expire of
DLP/DNP. The DLP/DNP may also be extended to some period under the
situation that if for a work or section that cannot be used for the purpose for
which they are intended by reason of defect or damage after issuing TOC. It is
stated in FIDIC 1999 red book that DNP shall not be extended by more than two
years. The Contractor has to remedy any defects or damages within the
reasonable time within DLP/DNP. The Employer/Engineer shall notify the
Contractor a date by which the defects or damages are to be remedied. If
Contractor fails to remedy the damages or defects, such remedy may be carried
out at the cost of the Contractor. The expiration of DLP/DNP is the completion of
4
project or contract. Upon accepted DLP/DNP the contractor shall be discharged
and all his securities will be released.
4. CONCLUSION
The taking over of the project and defect liability/notification period is the major
event of the project. While issuing the taking over certificate careful assessment
has to be made for project’s components which are completed and outstanding
list has to be prepared. An agreement may be made with contractor for time
period to complete the outstanding work during DLP/DNP. Any defects that occur
during defect notification/liabilities have to be assessed well and remedial work
has also to be carried out. The Engineer/Employer has to play a vital role for
successful completion of project and effective discharge of contract to avoid
unnecessary disputes in that period.