: 115 /BMS/PL-CS/X/14
REV :0
PROJECT DATE : 19 Nop 2014
PAGE : 1|P a g e 4
Revised Revised
No Remarks No Remarks
0 1 2 3 4 5 6 0 1 2 3 4 5 6
1 X
2 X
3 X
4 X
A. PROJECT CLOSE-OUT
During the period of the Contract, Energy Equity Epic Sengkang Pty.Ltd.(EEES)
will issue Contract Award to PT Borneo Mitra Sinergi (BMS) to covering all required
Project Work should be done and accomplished and after that should be reported. After
finished, all document should be signed by BMS representative persons and submitted to
EEES for approval.
During the performance of project work BMS will issue the timesheet for labour and
equipment by daily until the work is finish. Those timesheet should be approved by EEES
representative persons and BMS will record those approved timesheet for Total man hour
and equipment km driven.
BMS will keep records of materials supplied by EEES and issued to perform of the
service. At the time of completion of Services, BMS will be required to reconcile materials
supplied by EEES with materials incorporated into the Services, materials returned to
EEES and including scrap.
Mechanical Completion means that the Services for such Facility is:
Complete – the Facility have been installed in accordance with specifications, design
drawings, and other written requirements of EEES.
Tagged – all signs, stencils, and tags required for identification are complete
Checked and in working order – including loop check, instrument calibration, electrical
control check, lubricants added to machinery, equipment alignment and operability check,
etc.
Ready to be operated or used – the Facility has been inspected and is ready to be operated
or used in accordance with specifications, design drawings, and other written requirements
of EEES.
Well documented –documents has been handed over to EEES by BMS and accepted by
EEES.
Inspection report
Purchase order