URAIAN ANALISA ALAT ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (I)

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT E01
2. Tenaga Pw 294,0 HP
3. Kapasitas Cp 60,0 T/Jam
4. Alat a. Umur Ekonomis A 10,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1.500,0 Jam
c. Harga Alat B 3.500.000.000,0 Rupiah

5 Kapastas tangki aspal Ca 30.000,00 liter


1.
B. BIAYA PASTI PER JAM KERJA 2.
1. Nilai Sisa Alat = 10 % x B C 350.000.000 Rupiah 3.
4.
2. Faktor Angsuran Modal = i x (1 + i)^A D 0,16275 - 5.
(1 + i)^A - 1 6.
3. Biaya Pasti per Jam : 7.
a. Biaya Pengembalian Modal = ( B- C ) x D E 341.765,33 Rupiah 8.
W 9.
10.
b. Asuransi, dll = 0,002 x B F 4.666,6667 Rupiah/jam 11.
W 12.
13.
Biaya Pasti per Jam = ( E+ F ) G 346.432,00 Rupiah 14.
15.
C. BIAYA OPERASI PER JAM KERJA 16.
1. Bahan Bakar = (12%-15%) x Pw x Ms H1 396.900,00 Rupiah 17.
Bahan Bakar Pemanasan Material = 12 ltr x Ms H2 4.536.000,00 Rupiah Khusus AMP 18.
dan aspal (Oil Heater) 19.
Bahan Bakar Pemanas Aspal =1/1000 *Ca*Ms H3 270.000,00 Rupiah 20.
21.
2. Pelumas = (2.5%-3%) x Pw x Mp I 132.300,00 Rupiah 22.
23.
3. Biaya bengkel (6.25% dan 8.75%) x B J 204.167 Rupiah 24.
W 25.
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 408.333,33 Rupiah 26.
W 27.
5 Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah 28.
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 42.857,14 Rupiah 29.
30
Biaya Operasi per Jam = (H+I+J+K+L+M) P 6.007.700,00 Rupiah 31.
32.
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 6.354.132,00 Rupiah 33.
34.

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7 PPN diperhitungkan pada lembar Rekapitulasi ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (II)
Biaya Pekerjaan
8 Bahan bakar Batubara 500,00 Rp/kg
URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER E02
2. Tenaga Pw 72,4 HP
3. Kapasitas Cp 10,0 Ton
4. Alat Baru : a. Umur Ekonomis A 6,0 Tahun 12000 jam/6thn
b. Jam Kerja Dalam 1 Tahun W 1.400,0 Jam
c. Harga Alat B 1.200.000.000 Rupiah 35.
5. 36.
37.
38.
39.
B. BIAYA PASTI PER JAM KERJA 40.
1. Nilai Sisa Alat = 10 % x B C 120.000.000 Rupiah 41.
42.
2. Faktor Angsuran Modal = i x (1 + i)^A D 0,22961 - 43.
(1 + i)^A - 1 44.
3. Biaya Pasti per Jam : 45.
a. Biaya Pengembalian Modal = ( B- C ) x D E 177.125,69 Rupiah 46.
W 47.
48.
b. Asuransi, dll = 0,002 x B F 1.714,29 Rupiah/jam 49.
W 50.
51.
Biaya Pasti per Jam = ( E+ F ) G 178.839,98 Rupiah 52.
53.
C. BIAYA OPERASI PER JAM KERJA 54.
55.
1. Bahan Bakar = (12%-15%) x Pw x Ms H 97.740,00 Rupiah 56.
57.
2. Pelumas = (2.5%-3%) x Pw x Mp I 32.580,00 Rupiah 58.
59.
Biaya bengkel (6.25% dan 8.75%) x B J 53.571 60.
W 61.
62.
3. Perawatan dan (12,5 % - 17,5 %) x B K 150.000,00 Rupiah 63.
perbaikan = W 64.
65.
4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah 66.
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah 67.
68.
Biaya Operasi per Jam = (H+I+K+L+M) P 365.320,00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 544.159,98 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER E03
2. Tenaga Pw 4,0 HP
3. Kapasitas Cp 850,0 Liter
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 60.000.000 Rupiah

5 Kapastas tangki aspal Ca 850 Liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 6.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 7.122,53 Rupiah
W

b. Asuransi, dll = 0,002 x B F 60,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 7.182,53 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 4.320,00 Rupiah


Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 7.650,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 1.500,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 2.625 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 3.750,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 51.273,57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 58.456,10 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 20,0 HP
3. Kapasitas Cp 500,0 Liter
4. Alat Baru : a. Umur Ekonomis A 2,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1.500,0 Jam
c. Harga Alat B 11.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1.100.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,57619 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 3.802,86 Rupiah
W

b. Asuransi, dll = 0,002 x B F 14,67 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 3.817,52 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 27.000,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 9.000,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 642 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 1.283,33 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 69.353,57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 73.171,10 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3.5 TON E08
2. Tenaga Pw 100,0 HP
3. Kapasitas Cp 3,5 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 350.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 35.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 41.548,10 Rupiah
W

b. Asuransi, dll = 0,002 x B F 350,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 41.898,10 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 108.000,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 37.500,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 15.313


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 21.875,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 214.116,07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 256.014,17 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 133,0 HP
3. Kapasitas Cp 0,93 M3
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.100.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 110.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 130.579,75 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.100,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 131.679,75 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 143.640,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 49.875,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 48.125 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 68.750,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 341.818,57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 473.498,32 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 135,0 HP
3. Kapasitas Cp 10.800,0 -
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.700.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 170.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 201.805,07 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.700,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 203.505,07 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 145.800,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 50.625,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 74.375 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 106.250,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 408.478,57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 611.983,64 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17
2. Tenaga Pw 82,0 HP
3. Kapasitas Cp 8,1 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 900.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 90.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 106.837,98 Rupiah
W

b. Asuransi, dll = 0,002 x B F 900,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 107.737,98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 88.560,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 30.750,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 39.375 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 56.250,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 246.363,57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 354.101,55 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19
2. Tenaga Pw 82,0 HP
3. Kapasitas Cp 7,050 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 800.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 80.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 94.967,09 Rupiah
W

b. Asuransi, dll = 0,002 x B F 800,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 95.767,09 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 88.560,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 30.750,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 35.000 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 50.000,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 235.738,57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 331.505,66 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm E22
2. Tenaga Pw 6,0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 3,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 6.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 600.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,40211 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 1.085,71 Rupiah
W

b. Asuransi, dll = 0,002 x B F 6,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 1.091,71 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 6.480,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 2.250,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 263 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 375,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 40.796,07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 41.887,78 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R A IA N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100,0 HP
3. Kapasitas Cp 4.000,0 Liter
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 350.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 35.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B- C ) x D E 41.548,10 Rupiah
W

b. Asuransi, dll = 0,002 x B F 350,00 Rupiah


W

Biaya Pasti per Jam = ( E+ F ) G 41.898,10 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 108.000,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 37.500,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 15.313 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 21.875,00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17.142,86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14.285,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 214.116,07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 256.014,17 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10,00 % / Tahun
2. Upah Operator / Sopir U1 17.142,86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14.285,71 Rp./Jam
4. Bahan Bakar Bensin Mb 7.850,00 Liter
5. Bahan Bakar Solar Ms 9.000,00 Liter
6. Minyak Pelumas Mp 15.000,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan