CUADRO No 30

DETERMINACION DE LA GRANULOMETRIA DE LA MUESTRA TOTAL

PROYECTO : PUENTE URABAMBA

Tamiz Peso Retenido Factor Peso Ret


Denominacion % Retenido % Acum Pasa Di x Pri
(plg) (mm) (gr) Correccion Corregido (gr)
15"@17" 406.40
CANTOS 13"@15" 355.60
RODADOS 11"@13" 304.80
9"@11" 254.00 100.00
7"@9" 203.20 13,424 1.5% 201 12.05 87.95 2,449
5"@7" 152.40 11,326 1.5% 170 10.17 77.78 1,549
3"@5" 101.60 5,369 1.5% 81 4.82 72.96 490
2"@3" 63.50 5,561 1.5% 83 4.99 67.97 317
GUIJARROS Y 1 1/2" 37.50 121 100.0% 121 7.24 60.73 272
GRAVAS 1" 25.40 205 100.0% 205 12.27 48.46 312
3/4" 19.00 62 100.0% 62 3.72 44.74 71
1/2" 12.70 20 100.0% 20 1.20 43.55 15
3/8" 9.50 50 100.0% 50 2.99 40.55 28
Nº 04 7.14 205 100.0% 205 12.25 28.31 87
Nº 10 2.00 157 100.0% 157 9.40 18.91 19
Nº 20 0.85 169 100.0% 169 10.11 8.80 9
LIMOS Nº 40 0.43 70 100.0% 70 4.19 4.61 2
Nº 60 0.25 52 100.0% 52 3.11 1.50 1
Nº 100 0.15 25 100.0% 25 1.50 0.00 0
36,816 1,671 Dm = 0.01 ∑ Di X Pri 56

ANALISIS GRANULOMETRICO - MUESTRA TOTAL

91
Porcentaje Pasante (%)

81

71

61

51

41

31

21
GRAVA GRUESA GRAVA FINA ARENA GRUESA ARENA MEDIA ARENA FINA

11

Abertura Tamicez (mm)

d50 27 mm
d84 183 mm
d95 233 mm
CUADRO Nº 31

TABLA DE COWAN PARA DETERMINAR LA INFLUENCIA DE DIVERSOS FACTORES SOBRE EL COEFICIENTE (n)

DESCRIPCION SIMBOLO REFERENCIA LECHO TALUDES


Tierra 0.020
Roca 0.025
Superficie del canal No 0.024 0.025
Grava fina 0.024
Grava gruesa 0.028
Suave 0.000
Menor 0.005
Irregularidad N1 0.005 0.005
Moderada 0.010
Severa 0.020
Gradual 0.000
Variacion de la seccion Ocasional N2 0.005 0.005 0.005
Frecuente 0.010 - 0.015
Despreciable 0.000
Menor 0.010 - 0.015
Efecto de la obstruccion N3 0.000 0.010
Apreciable 0.020 - 0.030
Severo 0.040 - 0.060
Bajo 0.005 - 0.010
Medio 0.010 - 0.025
Vegetacion N4 0.005 0.010
Alto 0.025 - 0.050
Muy alto 0.050 - 0.100
Menor 1.000
Intensidad de meandros Apreciable M5 1.150 1.000 1.000
Severo 1.300
n=(No+N1+N2+N3+N4).M5 0.039 0.055
CUADRO Nº 32

CARACTERISTICAS HIDRAULICAS DEL FLUJO DE AGUA


SECCION TRANSVERSALES DEL RIO URABAMBA
PROYECTO : PUENTE URABAMBA
River PROG Tr Caudal Cota Fondo Cota Espejo Cota E.Crit. Cota. L.E. E.G. Slope Tirante Velocidad Area Perim Espejo RH Num
Station (KM) (AÑOS) (m3/s) (m) (m) (m) (m) (m/m) (m) (m/s) (m2) (m) (m) (m) Froude
13 25 440 3946.2 3949.15 3948.24 3949.44 0.0027 2.95 2.68 205.57 87.91 0.51
13 0+000 100 578 3946.2 3949.76 3948.59 3950.07 0.0023 3.56 2.81 259.41 89.6 0.48
13 175 637 3946.2 3950.01 3948.71 3950.33 0.0021 3.81 2.85 281.95 90.29 0.47
12 25 440 3,945.89 3,948.89 3,949.36 0.0039 3.00 3.22 158.99 67.64 0.61
12 0+020 100 578 3,945.89 3,949.47 3,949.99 0.0035 3.58 3.44 199.16 71.72 0.59
12 175 637 3,945.89 3,949.71 3,950.25 0.0033 3.82 3.51 216.83 73.60 0.59
11 25 440 3,945.60 3,948.74 3,949.31 0.0048 3.14 3.65 147.70 63.81 0.68
11 0+030 100 578 3,945.60 3,949.32 3,949.95 0.0043 3.72 3.88 185.77 67.20 0.66
11 175 637 3,945.60 3,949.56 3,950.21 0.0041 3.96 3.95 202.38 68.77 0.65
10 25 440 3,945.40 3,948.27 3,948.16 3,949.20 0.0099 2.87 4.80 115.15 54.71 0.95
10 0+040 100 578 3,945.40 3,948.94 3,949.86 0.0074 3.54 4.84 152.54 58.10 0.86
10 175 637 3,945.40 3,949.20 3,950.13 0.0068 3.80 4.88 167.73 59.50 0.83
9 25 440 3,945.20 3,948.30 3,949.06 0.0073 3.10 4.36 127.40 55.84 0.83
9 0+050 100 578 3,945.20 3,948.96 3,949.74 0.0058 3.76 4.49 165.45 59.30 0.77
9 175 637 3,945.20 3,949.22 3,950.02 0.0055 4.02 4.55 180.99 60.60 0.75
8 25 440 3,945.00 3,948.33 3,948.96 0.0049 3.33 3.84 130.30 47.02 0.69
8 0+060 100 578 3,945.00 3,948.95 3,949.68 0.0045 3.95 4.16 159.78 48.53 0.68
8 175 637 3,945.00 3,949.19 3,949.96 0.0044 4.19 4.29 171.67 49.36 0.68
7 25 440 3,944.80 3,947.76 3,947.64 3,948.85 0.0088 2.96 4.79 102.20 42.43 0.91
7 0+070 100 578 3,944.80 3,948.33 3,948.14 3,949.57 0.0079 3.53 5.14 126.94 43.97 0.89
7 175 637 3,944.80 3,948.52 3,948.33 3,949.85 0.0080 3.72 5.34 135.22 44.39 0.90
6.8 25 440 3,944.74 3,947.87 3,947.54 3,948.78 0.0068 3.13 4.33 108.50 40.89 42.07 2.65 0.81
6.8 0+072 100 578 3,944.74 3,948.43 3,948.03 3,949.51 0.0064 3.69 4.73 130.87 40.89 43.47 3.20 0.81
6.8 175 637 3,944.74 3,948.62 3,948.22 3,949.79 0.0065 3.88 4.93 138.37 40.89 43.91 3.38 0.82
25 440 3,944.65 3,947.62 3,947.46 3,948.66 0.0085 2.97 4.63 102.23 40.87 41.75 2.50 0.89
6.6 - pte 0+075 100 578 3,944.65 3,948.13 3,947.93 3,949.38 0.0083 3.48 5.10 122.37 40.87 43.09 2.99 0.90
175 637 3,944.65 3,948.33 3,948.13 3,949.67 0.0081 3.68 5.26 130.64 40.87 43.57 3.20 0.90
6.5 25 440 3,944.55 3,947.37 3,947.37 3,948.54 0.0102 2.82 4.93 95.95 40.85 41.43 2.35 0.97
6.5 0+078 100 578 3,944.55 3,947.82 3,947.82 3,949.25 0.0102 3.27 5.47 113.86 40.85 42.70 2.79 0.99
6.5 175 637 3,944.55 3,948.04 3,948.04 3,949.54 0.0097 3.49 5.59 122.91 40.85 43.22 3.01 0.98
6 25 440 3,944.20 3,946.76 3,947.03 3,948.29 0.0152 2.56 5.70 86.19 41.59 1.17
6 0+090 100 578 3,944.20 3,947.22 3,947.53 3,949.01 0.0143 3.02 6.20 105.46 43.18 1.17
6 175 637 3,944.20 3,947.41 3,947.73 3,949.29 0.0139 3.21 6.37 113.58 43.74 1.16
5 25 440 3,943.57 3,945.56 3,946.27 3,947.99 0.0335 1.99 7.02 66.14 39.07 1.66
5 0+100 100 578 3,943.57 3,945.96 3,946.76 3,948.71 0.0293 2.39 7.49 82.10 39.86 1.60
5 175 637 3,943.57 3,946.13 3,946.96 3,949.00 0.0278 2.56 7.66 88.79 40.19 1.58
4 25 440 3,943.35 3,945.44 3,946.05 3,947.61 0.0279 2.09 6.64 70.13 39.25 1.52
4 0+110 100 578 3,943.35 3,945.82 3,946.54 3,948.38 0.0261 2.47 7.23 85.17 40.01 1.52
4 175 637 3,943.35 3,945.97 3,946.73 3,948.69 0.0255 2.62 7.46 91.31 40.31 1.52
3 25 440 3,943.10 3,945.22 3,945.80 3,947.31 0.0263 2.12 6.52 71.43 39.32 1.48
3 0+120 100 578 3,943.10 3,945.58 3,946.29 3,948.12 0.0257 2.48 7.20 85.58 40.03 1.51
3 175 637 3,943.10 3,945.72 3,946.49 3,948.43 0.0254 2.62 7.45 91.40 40.31 1.51
2 25 440 3,942.89 3,945.09 3,945.59 3,947.02 0.0233 2.20 6.28 74.27 39.46 1.40
2 0+130 100 578 3,942.89 3,945.43 3,946.08 3,947.83 0.0235 2.54 7.01 88.04 40.16 1.45
2 175 637 3,942.89 3,945.57 3,946.28 3,948.15 0.0235 2.68 7.28 93.67 40.41 1.46
1 25 440 3,942.69 3,944.54 3,945.18 3,946.71 0.0357 1.85 6.58 68.63 45.69 1.67
1 0+140 100 578 3,942.69 3,944.81 3,945.61 3,947.51 0.0360 2.12 7.35 81.21 46.40 1.72
1 175 637 3,942.69 3,944.92 3,945.78 3,947.83 0.0359 2.23 7.63 86.39 46.69 1.73
CUADRO Nº 33

CALCULO DE LA SECCION DE EQUILIBRIO

PROYECTO : PUENTE URABAMBA


METODO DE SIMMONS Y HENDERSON - B = K Q 1/2
Item Condiciones de fondo de rio K
1 Fondo y orillas de arena 5.7
2 Fondo de arena y orillas de material cohesivo 4.2
3 Fondo y orillas de material cohesivo 3.6
4 Fondo y orillas de grava 2.9
5 Fondo de arena y orillas de material no cohesivo 2.8
6 Valor asumido 2.80
7 Caudal de diseno (m3/s) 578
8 Ancho Estable (m) - B = K Q1/2 67

METODO DE LACEY - B = 4.831 Q 1/2


Item Descripcion Valores
1 Caudal de diseno (m3/s) 578
2 Ancho Estable (m) 116

METODO DE PETTIS - B = 4.44 Q 1/2


Item Descripcion Valores
1 Caudal de diseno (m3/s) 578
2 Ancho Estable (m) 107

PROMEDIO TEORICO 97
CUADRO Nº 34

CARACTERISTICAS HIDRAULICAS DEL FLUJO DE AGUA


SECCION ENCAUZADA DEL RIO - LUZ=40m

PROYECTO : PUENTE URABAMBA

Periodo de TIRANTE COTA


COTA RADIO ANCHO NUMERO
CAUDAL RIO EN NIVEL DE PERIMETR AREA VELOCIDA
retorno (m3/s) TALWEG
FONDO
AGUA O (m) (m2)
HIDRAULICO SUPERIOR
D (m/s)
DE
(anos) (msnm) (m) (m) FROUDE
(m) (msnm)
25 440 2.97 3,944.65 3,947.62 40.87 102.23 2.50 41.75 4.30 0.88
100 578 3.48 3,944.65 3,948.13 40.87 122.37 2.99 43.09 4.72 0.89
175 637 3.68 3,944.65 3,948.33 40.87 130.64 3.20 43.57 4.88 0.90
CUADRO Nº 35

SOCAVACION GENERAL EN EL TALWEG DEL RIO


(METODO DE LISCHTVAN - LEBEDIEV)
Coef. Rugosidad (n) 0.039 Diám. (mm) 56
Pendiente del río (S) 0.015 Coeficiente (a) 3.140
Coef.contraccion (u) 1.00 x 0.28
1/(1+x) 0.78
SOCAVACION
PERIODO DE GENERAL (m)
CAUDAL (m 3/s) Beta Ho (m) Hs (m)
RETORNO (años)
440 25 0.92 2.82 5.61 2.79
578 100 0.98 3.27 6.47 3.20
637 175 1.01 3.49 6.90 3.41
.

CUADRO Nº 36

SOCAVACION GENERAL EN TALWEG DEL RIO - SECCION ENCAUZADA - L=40M


(METODO DE LISCHTVAN - LEBEDIEV)
Coef. Rugosidad (n) 0.039 Diám. (mm) 56.00
Pendiente del río (S) 0.015 Coeficiente (a) 3.140
Coef.contraccion (u) 1.00 x 0.28
1/(1+x) 0.78
SOCAVACION
CAUDAL PERIODO DE Ho Hs
Beta GENERAL (m)
(m 3/s) RETORNO (años) (m) (m)
440 25 0.92 2.97 6.01 3.04
578 100 0.98 3.48 7.01 3.53
637 175 1.01 3.68 7.41 3.72
CUADRO Nº 37

SOCAVACION GENERAL AL PIE DE MUROS DEL RIO - L=40M


(METODO DE LISCHTVAN - LEBEDIEV)

Coef. Rugosidad (n) 0.055 Diám. (mm) 100.00


Pendiente del río (S) 0.015 Coeficiente (a) 2.227
Coef.contraccion (u) 1.00 x 0.27
1/(1+x) 0.79
SOCAVACION
PERIODO DE Ho
CAUDAL Hs GENERAL (m)
RETORNO Beta
(m 3/s) (m)
(años) (m)
440 25 0.92 1.76 2.07 0.31
578 100 0.98 2.41 2.97 0.56
637 175 1.01 2.60 3.22 0.62
CUADRO Nº 38

SOCAVACION LOCAL AL PIE DE MUROS (METODO DE ARTAMONOV)

PROYECTO : PUENTE URABAMBA

SOCAVACION LOCAL EN PUENTE (m)


LUZ Caudales en m3/s
440 578 637

40 1.76 2.41 2.60

Ho 1.76 2.41 2.60

VALORES DE (Q1/Q)
EJE Caudales en m3/s
(KM) 440 578 637

0+075 0.058 0.065 0.056

VALORES DE (Pq)
Luz Caudales en m3/s
Puente 440 578 637

40 2.00 2.00 2.00


CUADRO Nº 39

SOCAVACION TOTAL EN SECCION ENCAUZADA DEL RIO - Luz=40m


PROYECTO : PUENTE URABAMBA

TALWEG TIRANTE PIE DE ESTRIBOS


COTA
COTA FONDO COTA DE DEL RIO COTA DE
CAUDAL TIRANTE COTA NIVEL SOCAVACION NIVEL DE
EN TALWEG FONDO AL PIE DE GENERAL LOCAL TOTAL FONDO
(m3/s) DEL RIO EN DE AGUA GENERAL EN AGUA
(msnm) EROSIONADO ESTRIBO (m) (m) (m) EROSIONADO
TALWEG (m) (msnm) TALWEG (m) (msnm)
(msnm) (m) (msnm)
440 3,944.66 3.13 3,947.79 3.04 3,941.62 1.76 3,947.79 0.31 1.76 2.07 3,943.96
578 3,944.66 3.69 3,948.35 3.53 3,941.13 2.41 3,948.35 0.56 2.41 2.97 3,942.97
637 3,944.66 3.88 3,948.54 3.72 3,940.94 2.60 3,948.54 0.62 2.60 3.22 3,942.72
CUADRO No 40

CAPACIDAD DE ARRASTRE DEL RIO URABAMBA EN EJE DE PUENTE


PROYECTO : PUENTE URABAMBA

PERIODO DE RADIO DIAMETRO DE


CAUDAL PENDIENTE DEL Fuerza Tractiva
RETORNO HIDRAULICO ARRASTRE
(m3/s) RIO (Kg/m2)
(años) (m) (cm)

440 25 2.65 0.020 53.07 66

578 100 3.20 0.020 64.01 80

637 175 3.38 0.020 67.68 85


.
CUADRO No 41

DISENO DE PROTECCION CONTRA LA EROSION


ESTRIBOS

PROYECTO : PUENTE URABAMBA


Perido de Tamano
Caudal Tirante del Pendiente Numero de Constante (n) Constante (K) Dens.Rel.
Retorno medio D50
(m3/s) rio "Y" (m) del rio Froude depende de Fr Pilar Vertical Roca (S)
(años) (m)
440 25 1.76 0.015 0.88 0.28 0.69 2.60 0.73
578 100 2.41 0.015 0.89 0.28 0.69 2.60 1.01
637 175 2.60 0.015 0.90 0.28 0.69 2.60 1.09
.
Tamano de la roca (m)
% menor que % del total
calculado asumido
1.61 1.60 100 15
1.31 1.30 85 35
1.13 1.10 50 35
0.50 0.50 15 15
CUADRO Nº 42

NIVELES DE ENROCADO PARA PROTEGER SUBESTRUCTURAS


PUENTE URABAMBA
(Q = 578 m3/s - Tr = 100 anos)

PROYECTO : PUENTE URABAMBA

Profundidad de Socavacion (m)


Tipo de socavación
Estribos Talweg

General 0.56 3.53


Local 2.41
Total calculado 2.97 3.53
asumido 3.00 1.70

Nivel del fondo 3,946.77 3,944.66


Socavacion 3.00 1.70
Nivel de cimentacion 3,943.77 3,942.96

Nivel de cimentacion 3,942.96


Altura de enrocado 1.60
Nivel superior de enrocado 3,944.56