TIMELINE IN WEEKS FOR COMPLETION OF FOUR SITE

DESCRIPTION

wk 1

wk 2

wk 3

wk 4

wk 5

wk 6

wk 7

wk 8
ITEM

PRELIMINARIES - Adminstrative, banking, design, geophysical survey etc


Borehole
1.1 Mobilization and transportation rotary drilling rig and all other equipments and materials to the locoation of the drilling site
1.2 Drilling through all basement formation(1-100m), collect formationn samples at 3m interval or at any perceptible change in the lithoiogy
1.4 Supply and install 125mm(5inch) diamⅩ3m lengths of upvc casings of 10 bars pressure with male and female threaded couplings

1.5 Supply and install 125mm(5inch) diamⅩ3m lengths of upvc screens of 10 bars pressure with male / female threaded coupling ends with factory slotted sizes of
0,25-0.5mm
1.6 Supply and place approved filter pack (natural river gravel) of 3-5mm size to ensure a gravel envelope around the screen.

1.7 Provide and place cement grout around borehole from surface to depth 6m to protect from surface water infiltration and construct borehole well head with fittings
water meter etc
1.8 Borehole cleaning and development till water is clear, sand free
1.9 Conduct pumping test (well performance and aquifer)
Construction of elevated and ground water reservior
2.1 Construction of elevated 4m water steel structure and installation of 8m 3 plastic water reservior
2.2 Supply and install 10m3 plastic water reservior including concrete base installed at ground level
2.3 Allow for plumbing works to connect the borehole and reserviors including fittings(water meter etc)
Installation of Water Treatment Unit
3.1 Installtion of sand and carbon filtration media including the concrete base
3.2 Installation of UV sterilizer
3.3 Install 1 HP Surface Pump including cabbles and switches
3.4 Installion of plumbing pipes and accessories
Selling Kiosk for sale of provisions
4.1 Construction of kiosk accoding the specification of 3m x 3m, and internal wood shelves, including electrical wiring, fittings and lightning bulbs
External Civil Works and Washing Bay

5.1 Construction of the wash/laundry area using 4inches steel pipes support and metal rafters to support installation of solar modules. Installation of water taps
including pipe connection to the tank and soak away and tile finishing on the walls and floor

5.2 Construction of taps for drinking water fetching points and pipe connections to the elevated water reservoir, kiosk including tile finishing for water fetching area

5.3 Construction of Soakaway pit for collection of water from wash area and water fetching points including pipe connections and chambers.
5.4 Construction of Chain-Link perimeter fencing for the completed water center with gate and poles at 3m interval and landscaping
Off-grid solar power system
6.1 300watts polycrystalline solar modules
6.2 5KVA Automatic Full Logic Automatic inverter
6.3 12V-200AH Deep-Cycle batteries
6.4 60amps/48V MPPT Solar charge controllers
6.6 battery rack
Backup Generator
7.1 Installation of 5KVA Generator
7.2 Installation materials (cables, changeover switches, metal steel protector e.t.c)
Pumping
8.1 Supply and install 1 Hp electric submersible pump and all associated components/accessories
8.2 Riser pipes for installation of the submersible pump
9.1 Testing and Handover