Item System Job From TO Notes

Cable installation @Penta 20-4 21-4


Cable installation @4th F 20-4 21-4
Cable installation @3rd F 21-4 22-4
Cable installation @2nd F 22-4 23-4
Cable installation @1st F 22-4 23-4
Cable installation @M 23-4 24-4
1- CCTV Cable installation @S 15-5 16-5
Cable installation @B1 22-5 23-5
Cable installation @B2 22-5 23-5
Cameras installation 28-6 3-7 After wall painting
Finishing and
windows, glasses
installation
Cable plugs and tagging 5-6 6-6
Cable installation @Penta 21-4 21-4
Cable installation @4th F 22-4 23-4 After removing the
Cable installation @3rd F 22-4 23-4 building glasses
Cable installation @2nd F 24-4 25-4
Cable installation @1st F 24-4 25-4
Cable installation @M 26-4 27-4
2- Telephone Cable installation @S 16-5 17-5
Cable installation @B1 22-5 23-5
Cable installation @B2 22-5 23-5
Plugs termination at floor 5-6 6-6
JBs
Cables tagging 5-6 7-6
PBX installation 13-6 14-6
PBX programming 15-6 16-6
Installation of server rack 13-6 14-6
NVR programming 16-6 18-6
3- Server rack Fire wall programming 1-7 2-7
Master switch setting 15-6 16-6

Cable installation @Penta 25-4 26-4


Cable installation @4th F 21-4 22-4
Cable installation @3rd F 22-4 23-4
Cable installation @2nd F 22-4 23-4
Cable installation @1st F 23-4 24-4
Cable installation @M 26-4 27-4
Cable installation @S 16-5 17-5
4- Data Cable installation @B1 0 0
Cable installation @B2 0 0
Plugs termination at floor 2-6 3-6
JBs
Cables tagging 10-6 12-6
AP cable installation 2-5 5-5
AP fixation 15-6 18-6
Switch racks installation 5-6 10-6
5- Telephone 1-Outside to PBX cable 2-6 3-6
And DATA installation muti pairs
2- from outside data
cable installation
6- Equipment 1-Cameras 3-7 4-7
tags 2-Switches
7- Telephones test 20-7 22-7
CCTV test 23-7 26-7
Data test 27-7 29-7