Project: Sunway Bangi Gandaria, Bandar Baru Bangi Sek 9

Sub: ELV Installation Works Obstruct by others

Photo No.: 01 Level: UG until L20 Location: TEL Riser Date Taken: 02/03/2019
System: FTTH System Grid Line: B4
Description:
FTTH Panel and trunking cannot install due to construction pipe in riser.
Project: Sunway Bangi Gandaria, Bandar Baru Bangi Sek 9
Sub: ELV Installation Works Obstruct by others

Photo No.: 02 Level: LG Location: MDU Room Date Taken: 21/03/2019


System: FTTH Grid Line: A12
Description:
Fiber optic cable main ODF Rack cannot installation due to floor finishing not complete yet.

Photo No.: 03 Level: 10 Location: Unit 07 Date Taken: 21/03/2019


System: Smatv,Tel & Data Grid Line: B6
Description: TV / DATA / TEL Socket outlets’ cover dirty and scratches due to finishing wall
repairing & touch up works in all units.