Professional Documents
Culture Documents
TABLE OF CONTENTS.
PAGE
Introduction . . . . . . . . . . . . . . . . . . . . 384
The
site . . . . . . . . . . . . . . . . . . . . . 385
Materials . . . . . . . . . . . . . . . . . . . . . 385
Theropeway . . . . . . . . . . . . . . . . . . . . 385
Plant. . . . . . . . . . . . . . . . . . . . . . 386
Description of the bridge . . . . . . . . . . . . . . . . 387
Construction of thearchrib . . . . . . . . . . . . . . . 388
Anchorage of thearch . . . . . . . . . . . . . . . . . 391
Closure of thearchspan . . . . . . . . . . . . . . . . 393
Removal of archanchorties . . . . . . . . . . . . . . . 396
Acknowledgements . . . . . . . . . . . . . . . . . . 396
INTRODUCTION.
THE Coronation bridge spans the Tista river at Sevoke, in the fourteenth
mile of the Tista Valley road from Siliguri railhead, North Bengal.
The project was first considered in 1913. In 1931, it was decided that,
owing to erosion and floods in the Tista valley, an outlet from the north-
west connecting the Bengal Dooars railhead(E.B.Rly.), a t Bagrakote
with Sevoke in the Darjeeling district, was an urgent necessity if the
Dooars was to be assured of outsidecommunication throughout all
seasons. Hitherto, theonly means of crossing the river had been by means
of a ferry a t Sevoke, which could not operate during the monsoon. Work
commenced on the roads in 1933.
The bridge provided the most northerly access from Bengal to Assam,
and therefore had considerable strategic value.
At this point the Tista valley is subject to heavy rainfall, the average
throughout the year amounting to more than 200 inches. The monsoon
breaks in May and rain ismore or less continuous until theend of Septem-
ber, the maximum intensity being reached in June and July. On the
eve of 1 July, 1940, 19 inches of rain fell at the site of the bridge, causing
.~~ . . ~~ ~~~
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
OVER THE TISTA RIVER, NORTH BENGAL, INDIA. 385
the destruction of bridges and long lengths of track on the Darjeeling-
Himalayan Railway by landslides. The road from Siliguri to Kalimpong
a t deck level was frequently impassable for days a t a time. Maximum
shade temperatures reached 100" F. during the day, but theeffect of heavy
rain, coupled with a stiff breeze blowing downstream, could reduce the
evening temperature over thearchto 40" F. The climateduring the
monsoon months was humid and unhealthy, and strict precautions had to
be taken against malarial and sandfly fevers, and dysentery. From mid-
October until the end of February, theclimate was delightful.
THE SITE.
At the bridge site the river flows through a deep gorge, the slopes on
either side being covered with a dense jungle growth. The existing road
on the Sevoke side is 160 feet above the river, and carries motor t r a 5 c
between Siliguri railhead and Kalimpong. The new road brought to the
bridgehead on the Bagrakote side is about 20 feet lower. The road on
either side had been cut into the side of the gorge so that the fall to the
river was very steep. On therightbank of the river below runsthe
Darjeeling-Himalayan Railway (2-foot gauge), and the contractor had to
rely on this for the delivery of materials. Only very limited space was
available for the storage of materials and stores and for the installation of
plant, but by cutting and clearing at the bridgehead on the Sevoke side,
it was found possible to locate offices, stores, power-house, batching-plant,
and water storage.
MATERIALS.
Stone boulders, found a t a point 3 miles upstream, were collected and
brought to the site by rail and stackedupstream of the bridge against the
track. Here they were broken down by hand to 6-inch size and later were
crushed and stacked for use.
Sand from a point 3 miles downstream of the bridge was brought to
the site by rail, and stacked downstream. Cement was brought by rail
via Siliguri.
Steel reinforcement arrived by rail andwas stacked downstream of the
bridge, where it was bent to design before transport to the actualwork.
THE ROPEWAY.
In view of the unusual height of the work and the general features of
the cross-section, and also in consideration of the proposal to build the
main arch withouta fixed centre, it was decided to erect a ropeway to span
the gorge over and above the bridge. This ropeway was designed and con-
structed by the contractors and proved very satisfactory (Pig. 1, Plate 1)
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
386 SEXTON ON THE CONSTRUCTION OF THE CORONATION BRIDGE
The anchorages for this ropeway were founded a t level 708.0 on the
Sevoke side and at 730.0 on the Bagrakote side, in mass concrete keyed
into rock with steel dowels. The span of the rope between the anchor-
ages was 800 feet and the unloaded rope was adjusted to a sag of 35 feet
below the Sevoke anchorage. This allowed for aclearance of 16 feet
between the bridge deck at the centre and the fully loaded rope. Owing
to difficulties in placing the anchorages the rope had to be sited 9 feet
downstream of the centre-line of the bridge.
The main rope consisted of a l$-inch diameter cable which had seen
service in an old suspension bridge across the Tista. The lifting rope was
of Q-inch diameter steel cable, and the traversing rope of &-inch diameter
steel cable. Buttons of steel plate, running by means of pulleys on the
main rope, controlled the sag in the lifting and traversing ropes. The
carriage was steel-framed and balanced on the main rope by means of four
pulleys placed at the top of the carriage, whilst at the bottom were two
pulleys over which passed the lifting rope. The loop of the lifting rope
passed under a 17-inch pulley attached to and suspended from the skip.
The skip was of steel plate and angle construction, designed for bottom
opening with an outside step as a balance. The capacity of the skip w a ~
14 cubic feet.
The driving units consisted of two electric winches operated by direct-
current motors taking 90 amperes a t 230 volts. Grooved winding-drum
driven by the motorsoperated the lifting and traversing ropes. The drum
for the lifting rope was designed with sufficient turns toenable the skip to
be dropped down to rail-level. One man operated the ropeway, and the
driving units were arranged so that it was possible to lift and traverse at
the sametime. Bothdrums were controlled by foot-operatedclutch
brakes and also by electric solenoid brakes. Difficulty was experienced
during windy weather indropping the skip down to rail-level, the tendency
being for the skip to turn and rope the to twist, causing spiking of the rope.
Duringthese times a guide ropeoperatedfrom below was used. The
lifting rope was renewed twice during the course of the work. The main
rope was tightened and adjusted by means of $-inch diameter steel cable
passing through five-sheave pulley-blocks and on to hand-operated winches
at theSevolre anchorage-level.
PLANT.
The power-house, situated a t road-level, containeda 35-horse-power
Ruston diesel engine with a generator producing 90 amperes a t 230 volts
direct current, and a 10-horse-power Petter diesel engine with convertor
producing 20 amperes at 230 volts. The power was supplied through a
control panelto thevarious units of the plant. A small convertorproduced
alternating current a t 4-40 volts for the vibrating units used in placing the
concrete, which were of the " Sinex " type, clamped to the outside of the
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
OVER THE TISTA RIVER, NORTH BENGAL, INDIA. 387
forms. In a separate housing, a direct-current motor and exciter produced
alternating current at 440 volts for operating a 14-ton Scotch derrick crane
driven by a 10-horse-power motor for lifting materials fromrail-level.
The batching plant consisted of the usual electrically driven scraper
conveyor and an elevator discharging into overhead bins feedingweighing
hoppers, where the materials were automatically recorded before passing
into the mixer below. The plant and the winch-house were situated SO
that the mixer could discharge easily into the ropeway skip.
Water for all purposeswas stored in overhead tanks behind the power-
house, fed by gravity from reservoirs formed by damming two nearby
cascading streams. Water for curing the work on the Bagrakote side was
pumped from the river.
Skilled labour was not obtainable at or near the site, but had to be
imported.
The work is described from the contractor's point of view, and the
design of the structure is not discussed, except in so far as it has a direct
bearing on the construction.
DESCRIPTION
OF THE BRIDGE.
On the Sevoke side there are two straight approach spans of 52 feet,
with a fixed shore end. Roller bearings are provided at the main abut-
mentpier.Theoriginal design called for rockerbearings at the shore
end of the spans, but the contractors obtained permission to change this
arrangement for afixed end for construction purposes, reasons
for explained
later. In between the shore end and the main pier is a column group sup-
porting the spans, consisting of three units, the outsides being of ('T "-
section and the interior column of ('crucifix "-section, 4 feet by 4 feet.
These columns are braced horizontally across the bridge at every 20 feet
of their height, and spring from a mass foundation built into rock against
rail-level. The decking of the shore spans isof beam and slab construction.
Two main abutment piers, 40 feet 10 inches by 10 feet overall on plan,
founded on rock, arise from each bank. The underside of the shore span
bearing on the Sevoke pier is 134.7 feet above arch springing, and on the
Bagrakotepier l 2 5 5 feet. These piersare of hollow construction, fhe
outside walls being 7-inchthickreinforcedconcrete. Four cross walls,
9 inches thick, stiffen the shell vertically, whilst 6-inch thick horizontal
diaphragms are introduced at every 20 feet of height. The ends of the
piers on plan are hexagonal, and at the springing the pier increases in
section forthe foundation.
The main arch springs from the abutment piers and has a span of 276
feet and a rise of 132 feet from springing to crown. The arch rib is of
hollow construction, ranging indepth from 7 feet 6 inches at thespringing
to 4 feet 6 inches at the crown. Longitudinal walls 9 inches thick, in
addition to the face walls, also 9 inches thick, run between and stiffen
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
388 SEXTON ON THE CONSTRUCTION OF THE CORONATION BRIDGE
the intrados and extrados slabs, and form a series of boxes, as shown in
Fig. 2, Plate 1. Radial diaphragms 9 inches thick are built across the arch
a t approximately 20 feet apart centre to centre along the arch line. The
extrados and intrados slabs vary inthickness from 9 inches at thespringing
to 6 inches at the crown. The width of the arch ranges from 32 feet a t
the springing to 20 feet at the crown. The central portion of the deck
over the archis monolithic with the archrib about thecrown for a distance
either side of the centre of26 feet 6 inches, where a seating with rocker
bearings is provided to support the ends of the spans between this point
and the main abutments. Four spans of 26 feet6 inches run between
the crown deck and the main abutment piers, on either side of the arch
centre, and each is supported on three column groups. Roller bearings
are provided at the main abutment piers. Each column group consists
of three columns similar to those constructed under the approach spans,
but varying in size according to their height. The column groups sit on
contjnuous pedestals built from the arch rib.
The approach spans on the Bagrakote side are in three units of 56 feet
6 inches built in plan on a radius of 120 feet to meet the end of the new
road on that side. The deck is superelevated 1in 12 to meet traffic require-
ments. The three spans arc supported on two column groups similar to
those under the Sevoke approaches, founded on mass concrete into rock,
as shown in Fig. 2 . Roller bearings are provided at the main abutment
piers and rocker bearings at the shore end.
The bridge deck throughout consists of a 7-inch thick slab spanning
in two directions between cross beams 8 feet 6inches apart centre to centre
and main longitudinal beams a t 9 feet apart centre to centre. A feature
of the main longitudinalbeams is the soffit profile, which makes a parabolic
curve from the bearing to a distance of one-third the span on each side
of the centre-line of the span.
The wearing surface over the deck slab consists of 4 inches of 1 :3 : 6 mix
and 2 inches of 1 : 2 : 4 mix, without reinforcement. Between this and
the deck slab a $-inch layer of bitumen dressing forms a waterproofing
medium. Expansion joints 2 inches wide are constructed a t all bearing
points, from angle framesbuilt into the wearing surface. A copper U-
strip seals the ga,p and makes aseatingfora compressed bitumastic
compound.
The parapetsare of panelled reinforced-concrete construction,with
expansion joints carried up from the road. Over the main abutment piers
are refuges from the footways, and thepier walls are carried up to form the
enclosures.
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
3%) SEXTON ON THE CONSTRUCTION O P THE COR,ONATION R R l l X l T
out in preparation for the next concreting. After a little practice, the
removal and re-erection of the frames was carried out in quite good time
to the following schedule for one complete cycle of 6 fcet.
Dap.
(U) l>isuantling, moving forward, ancl refixing frames including intrados
timber centering . . . . . . . . . . . . . . 11
( b ) Fixing extrados, face, and interior timber centering . . . . . 4
(c) Fixingandtying steel reinforcement . . . . . . . . .
( d ) Concreting of first lift . . . . . . . . . . . . . 4
( e ) Wait before removal of innercentering (36 hours) . . . . . 14
( * f ) Strike, lift, and refixing of timber centcring to ext.~xtlos, rkcr,
and interior,including tying of steelreinforcement . . . . 1
(g) Concreting second lift of 3 feot . . . . . . . . . . . 4
( h ) Wait before removal of frame for lifting on the next cyclc . . . 3
__
time Total . . . . . . . . . . 9
By working both sides of the arch together, the speed of erection was
12 feet in 9 days. This was the maximum speed attained on the straight-
forward run of the arch, but the difficulties from cross diaphmgms and
column pedestals, added to the slowness a t starting with a new system,
gave a reduced average speed. Actually for the Bagrakote arm, which
started a little after the Sevoke side, thirty-eight lifts of concrete, that is,
nineteen lifts of the cantilever frames, covering 114 feet of arch rib, were
carried out in 210 working days between 23 September, 1939, and 8 May,
1940. This gavea progress of 6 feet in 11 days for the one side, and,
taking the speed of the arch building as a whole, of 12 feet in 11 days.
The method of construction worked well, the only rcal difficulty being
experienced where the frames came over the pedestals from which the
column groups were supported. Here the horizontalframing had to be
amended to accommodate the mass of steel projecting from the arch rib.
Measurement.-Horizontal lines set across the arch profile a t 3-foot
intervals, starting from the springing, located standard points at the inter-
section of these lines with the arch intrados. Corresponding horizontal
distances and vertical ordinates from the springing to these points were
calculated and tabulated, together with the thicknesses of the arch rib,
arch width, and thickness of intrados and extrados slabs a t these points.
The levels of these points were then marked on the face of each main
abutment pier, both upstream and downstream, and indicated by a thin
paint-line, with the level noted.
The main abutment piers already constructed were then plumbed a t
the points of level, the difference in or out of plumb noted plus or minus,
and the horizontal distances corrected to suit.
Timber platforms for the theodolite work were constructed on the canti-
lever frames. At measurementtime the instrument was set up on the
platform, and a staff A was held at the level marked on the main pier,
whilst a staff B was held against the intrados, the centering having been
fixed in the approximate position. Levels were taken first on the up-
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
OVER THE TISTA RIVER, NORTH BENGAL, INDIA. 39 l
stream face, and thereading, on A were noted, and also the deviation on B.
The centering was then lowered or raised by the application of wedges
until thelevel a t B corresponded to thatat A, simultaneous with the read-
ing of the horizontal distance for the point set with a steel tape between
the pier and the arch. Levels were then taken on the downstream face
and the centering was corrected in a similar manner.
In order to allow for the drop of the centering under the concrete load,
the centering was set up an amount based on the calculated extensionof the
tie-rods. This became more important as the arch went out.
After the inside timber centering had been wedged up and the steel
tied, the horizontal distances were again checked before concreting took
place, and again after thecast had been made.
ANCHORAGE
OF THE ARCH.
Details of the method used for tying back the arch cantilever as the
construction proceeded are illustrated in Fig. 4,Plate 2. Each set of ties
consisted of seven li-inch-diameter mild steel bars made up, in the case
of the internal ties, of two lengths coupled by a union. The rods were
screwed on the site by means of a power machine.
Galvanized pipes of 2-inch diameter were left in the arch during con-
creting to form the holes for passing the tie-bars at the required levels,
and .set in position for angle by means of passing lines from the shackle
positions on the main pier through the pipes in the arch. The pipes were
withdrawn from the concrete 4 hours after casting.
The lower two systems on the Sevoke side had inclined components on
the shore side, so that the main piers took the vertical component of the
anchor load direct. The higher three groups of ties all culminated a t the
top of the main pier, so that at this point the pier held 21 shackle anchor-
ages. These anchor bars were passed horizontally through the pier in the
thickness of the diaphragm concrete, having an eye in each case on the
arch side of the pier, whilst screwed ends at the shore side were tied to-
gether by means of a continuous channel iron.
The horizontal pull from the combined anchorage at the top of the
Sevoke main pier was transferred into the shore span main beams by
means of eighteen l$-inch-diameter high-tensile steel bars, six to each beam.
The beams of the shore spans were designed to take the resolved horizontal
tension component of 164 tons plus the end shear dueto the totalinclined
load of 214 tons from the twenty-one tie-bars acting during construction.
At the end of the shore spans this tension was again picked up and
distributed through three anchor tie-beams, the beams being fanned out
in plan and tailed into rock anchorage blocks against the road.
The interior anchorages of the Sevoke and Bagrakote arch cantilevers
were similar, except that the higher anchorage group shackles on the main
piers were 9 feet 3 inches higher on the Sevoke pier.
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
392 SEXTON ON THE CONSTRUCTION OB THE COBONATION BRIDGE
REMOVAL
OF ARCHANCHOR
TIES
Ten days after thefinal concreting of the arch rib thefirst set of seven
anchor ties each side of thearch was released and removed, and the
remaining groups were released a t 5-day intervals thereafter ; within
30 days of final concreting the arch was completely free from suspension.
The steel bars, holding the main beams of the Sevoke shore span a t the
head of the main abutment pier, were cut through in the2-inch roller gap,
and all shackle-ends projecting from the face of the piers were burned off
flush by means of oxy-acetylene plant.
The fixed portion of the decking over the arch on either side of the
crowD, with rocker bearings and seatings a t each end, was then constructed.
Levels recorded at thistime showed a variation of only $-inch in from the
height of the arch crown as designed. The erection of the column groups
and the decking over the archfollowed, the load on the archbeing balanced
as far as practicable.
The whole of the work of erecting in position the arch steel trusses,
and the concreting of the arch rib central 120-foot span was carried out
during the monsoon period of 1940.
ACKNOWLEDGEMENTS.
The bridge was designed by Mr. John Chambers, O.B.E., A.M.I.C.E.,
bridge designer to theGovernment of Bengal.
The contractors for the bridge and approach spans were Messrs. J. c.
Gammon, Ltd., of Bombay, for whom the Author actedas Resident
Engineer.
Acknowledgements are due to the Chief Engineer, Bridges and Roads,
Government of Bengal, for permission to publish this Paper, andto Messrs.
J. C. Gammon, Ltd., Engineers and Contractors, Bombay, for their help
towards its preparation.
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
THE C O N S T R U C T I O N OF THE CORONATION BRIDGE OVER THE TISTA RIVER, NORTH BENGAL, INDIA. PLATE i.
FIG. 3
FIG. I
I
tI iSprn of rope 800'-0'.
I
l >Holes to provide adiustrnent
FIG.2
Distance of traverie 480'-0"
1 I
l
l
Savoke side
r4
ISevoke end
A.
I
eolarch
\
6"X3,.rnchor c h a n n e l V a r , e r ( r o m 2 9 ' - 0 ' ' t r o 2 3 ' - 4 ? '
I c
-2-a
Anchor /Winch I
of bridge-. - of
n I t rioprs
Barching f 'LRope SECTION A-A
pianr
I .
M A I N A R C H RIB
The Institution of Civil Engineers. Journal. May 1946. scale L Inch = 1foot.
C. G. SEXTON.
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.
PLATE 2. I
THE CONSTRUCTION OF THE CORONATIQN BRIDGE OVER THE TISTA RIVER, NOR rH BENGAL, INDIA.
---._._--
-._------- FIG. 5
--'I (---- -----
.. 'I 'on~.~i't-<
SpJCe leh for vertical round
r--,",16----=:'
rods to facilitate drlvln& of
ne.1 wed,es behind seatl",
--:-----
Steel Wire rurs
1 durl"l erection cemre sections 88'·0" long of
~~~
!7 11" d,•. rod. Sevoke
Inner downufum truss erected
molln pIer
on Bagnkote decklnl and brought
~~~
SOl"ng 612·18 Sld. out by rope way (see planJ 8agrlkote
111'-6"lromX uun main pIer
Frlme E End sections 22'·OR lon&:.o(
Inne'r and outer downstream
trusses c~ntllevered out .lnd
Sc.l. I Inch = 1 loo, SECTION OF ARCH AT C~OWN br.lced tOlether
SHOWING STEEL TRUSSES.
Downloaded by [ Purdue Univ Lib TSS] on [19/09/16]. Copyright © ICE Publishing, all rights reserved.