Manhours Estimation is a Critical Activity during Bid Stage as well as during project execution.
It helps keep design cost in control. Piping Manhours are generally divided into 4 Categories.
Sr Activity/Unit Hours
1 Study of Project Specificaitons and Bid Documents. 40
2 Creation of Stress Design Criteria/Instructions from Bid Documents. : Total 40
3 Listing/Defining Stress Systems from PID : Total 20
4 Preparation of Stress Critical Lines List : Total 40
5 Stress Analysis and Supporting of Critical Lines/ Per Line 12
6 Preparation of Stress Reports / Per Report 10
7 Spring Data Sheets, Index, TBE / Per Spring 3
8 Special Support Design and Index / Per Support 4
9 Expansion Joint Data Sheet, Index, TBE / Per Joint 3
10 Sway Braces Data Sheets, Index, TBE / Per Brace 4
11 Struts Data Sheets, Index, TBE / Per Stress 4
12 Support Markup of Non Critical Lines / Per Line 1
13 Trunions Calculations / Per Calculation 2
14 AFC Isometric Stress and Support Review / Per Iso 0.5
15 Supervision and Co-ordination : % of Total of Above 10%
1. Checklist : Basic Engineering Package Review Piping Lead Engineer shall review Basic
Engineering Package (BEP) from...
2. The Piping Engineering Blog thumb-pblog.pngHello Friends, Welcome to “The Piping
Engineering Blog”…! I hope...
3. Piping Material Engineering Piping Material Engineering concerns with design, selection and
procurement of...
4. Privacy Policy for The Piping Engineering Blog This Privacy Policy governs the manner in
which The Piping...