Setia Precast Sdn Bhd

IBS SCORING IN MALAYSIA


HOW CAN CIDB AND INDUSTRY PLAYERS WORK
HAND IN HAND TO PROMOTE USAGE OF IBS

IBS SCORING SYSTEM & CASE STUDY

1
Setia Precast Sdn Bhd

CONTENT :

1) IBS SCORING SYSTEM


2) CASE STUDY 1 – RESIDENTIAL
3) CASE STUDY 2 – NON-RESIDENTIAL
4) FURTHER ENHANCEMENT TO IBS SCORE SYSTEM
5) CONCLUSION

2
Setia Precast Sdn Bhd

1. IBS Scoring System – IBS Score

First Published : January 2005


First Revision : April 2010

Objective :-

To provide a systematic and structured


assessment system to measure the
usage of IBS in a consistent way.

3
Setia Precast Sdn Bhd
2. Emphasis of IBS Scoring System
- The use of fabricated and precast components.
- Off-site production of components
- The use of standardised components
- Repeatability
- Modular Coordination (MC) in building MS1064

4
Setia Precast Sdn Bhd

Components of IBS Scores


Part 1

Structural Systems (Table 1)


(50 IBS Points)

Full IBS Factors :


- Precast Concrete Columns, Beams &
Slabs
- Prefabricated Steel Structures
- Timber Framed System

Partial IBS Factors :


- Reusable System Formworks for in-
situ concrete structures

Nil IBS Factor :


- Timber Formwork

5
IBS Scoring Attributes

Setia Precast Sdn Bhd

Components of IBS Scores

Part 1

Roof (Table 1A)


Full IBS Factors :
- Prefab Timber Roof Truss
- Prefab Metal Roof Truss

Partial IBS Factors :


- Precut Metal Roof Truss

Nil IBS Factors :


- Timber Roof Trusses

6
IBS Scoring Attributes

Setia Precast Sdn Bhd

Total Score for Part 1

7
Setia Precast Sdn Bhd

Components of IBS Scores Part 2

Wall Systems
(20 IBS Points)

Full IBS Factors :


- Precast Concrete Panel
- Wall Cladding
- Prefabricated Timber Panel
- Full Height Galss Panel
- Dry Wall System
- Pre-Assemble Blockwall

Partial IBS Factors :


- In-situ Concrete With Reusable
System Formwork
- Blockwork System

Nil IBS Factors :


- Common Brickwall
8
IBS Scoring Attributes

Setia Precast Sdn Bhd

Total Score for Part 2

9
Setia Precast Sdn Bhd

Components of IBS Scores


Part 3

Other Simplified
Construction Solutions
(30 IBS Points)

Emphasis on :

- Utilisation of MS1064 Guidelines

- Horizontal & Vertical Repetition

- Buildability

10
Setia Precast Sdn Bhd

Case Study 1 - Residential


Seri Jati Apartment, Setia Alam
948 Units, 6 Blocks, 10 Storey Apartment in a single phase development

11
Setia Precast Sdn Bhd

Prefabricated Steel Roof Trusses

Precast Walls for Roof

In-Situ Typical Floor Slabs


Precast Components
- Precast Load Bearing Walls
- Precast Non-Bearing Walls
- Precast Staircases & Landing Slabs
- Precast Lift Core Walls
- Precast Bathroom Slabs
- Precast Air-Cond Ledges

Conventional Construction
- Foundation
- Ground Floor
- Transfer Beam
- RC Slab

CONSTRUCTION SYSTEMS
12
Setia Precast Sdn Bhd

IBS Score for Seri Jati Part 1 :

Scoring point :
Use Precast Structural Frames
Part 1 39.1 / 50 with in-situ concrete floor using
Reusable System Formwork
13
Setia Precast Sdn Bhd

IBS Score for Seri Jati Part 2 & 3:

Part 2 18.8 / 20

Scoring point :

Part 3 24.0 / 30 Use Precast Walls


Follow MS1064
81.9 /100
Vertical & Horizontal Repetition
14
Setia Precast Sdn Bhd

IBS Score Advantages


- Project has high degree of repetitions for both horizontal and vertical plain.
- Architectural and Structural designs with precast intention to capitalise on
precast advantages.
- High economy of scale with >900 units apartment with a single unit layout.
- Construction logistic is fully considered at planning stage
e.g. wall layout, work sequencing, crane’s capacity and movement.

15
Setia Precast Sdn Bhd

IBS Score Disadvantages


- Brickwork/plastering in stand alone amenities building, box-out for M&E
services/risers and kitchen/yard walls.
- Non-compliance in Modular Coordination for structural elements and
architectural design input.

16
Setia Precast Sdn Bhd
An exciting external facade with different architecture features reduce the
monotonous of the internal repetitive layout.

17
Setia Precast Sdn Bhd

No columns and projected beams


Steel moulds provide consistent quality Consistent squareness
in architecture features Consistent quality

18
Setia Precast Sdn Bhd

Case Study 2 – Non-Residential


Hospital Kuala Lumpur (SACCHKL)

FLOOR HEIGHT : 9 STOREYS

FLOOR AREA : 600,000 SQ

USAGE : DAY CARE SPECIALIST CENTRE


COME WITH OPERATION THEATRES
: BUILT IN 3 FLOORS OF INTERNAL CARPARKS

OTHERS : SEPARATE M&E BLOCKS

19
Setia Precast Sdn Bhd

ACCHKL - Method to Achieve 70% IBS Score Requirement


a) Columns : Sizes are too heavy for lifting if in precast
components.
Cast in-situ using aluminium formwork

b) Beams : Precast components by Setia Precast

c) Slabs : All wet areas are in-situ construction


Other areas used Precast Hollow Core Slab
by Eastern Pretech supported by PC Beams
from Setia Precast

20
Setia Precast Sdn Bhd

ACCHKL - Method to Achieve 70% IBS Score Requirement


d) Walls : Structural walls used aluminium formwork & other internal and external walls
Lightweight Blocks

e) Staircases : Precast

21
Setia Precast Sdn Bhd

IBS Score :

Part 1
39.2 / 50

Part 2
15.0 / 30

Part 3
16.0 / 20

Total
70.2 /100 22
Setia Precast Sdn Bhd

Logistic Planning to resolve proximity of existing buildings and roads


Crane Passage
Area 1 : Construction up to Roof Level
Area 2 : Remain void for crane movement while
constructing Area 1.
Area 1
: Construct each bay up to RF
and crane retreat to next
bay and repeat sequence.

Area 1 Area 1
Area 2
Area 1

Internal Crane Passage – Maximise Cranage Radius

Area 1 Area 1

Area 2
23
Setia Precast Sdn Bhd

Completed External Facade

24
Setia Precast Sdn Bhd

Completed Internal Views

25
Setia Precast Sdn Bhd
Further Enhancement to IBS Score System
1. Prefabrication
a) Bathroom Pods/Prefabricated Pre-finished Volumetric Construction (PPVC )
- Truly industrialised system of construction, prefabrication and assembled at
factory.
- Eliminate on-site brickworks, plastering, tilings, waterproofing, site wirings
and plumbing works and fittings the smallest room with the most number of
trades.
- Previous IBS Score (2005) allows a maximum of 1 point at Part 3 Prefabricated
Components.
- Proposed to increase IBS points at Part 2 as it comes complete with wall system
and finishes.

26
Setia Precast Sdn Bhd

Further Enhancement to IBS Score System


b) Off-site prefabrication of reinforcement cage for columns, beams and walls
- To consider additional points under previous IBS Score Part 3 (Other labour saving
product / solution).

27
Setia Precast Sdn Bhd
Further Enhancement to IBS Score System
2. Elimination of Labour Intensive Process
a) Use of skin walls/cladding to conceal wirings and pipings, instead of traditional
hacking and plastering.
- Process is clean and systematic
- Good quality finished surface
- No hacking of RC walls and brickworks

28
Setia Precast Sdn Bhd

b) Replacement of brickwalls by using Dry Wall System (including cementitious


panels and gypsum boards).
- Bricklaying is a labour intensive process
- Involved lot of construction logistic in moving bricks, sand, cement, water, mixing
equipment, scaffoldings etc. for work to be executed.
- Wet & dirty
- Dry wall system is clean, fast, labour efficient and quality is easily control

Where apply as a full replacement for brickwalls, should be incentively considered


under previous IBS Score Part 3 (Other labour saving solution).

29
Setia Precast Sdn Bhd
3. Revision of IBS Score 2010
a) Propose Revision to IBS Score Part 3 2010
- Reinstate 2005 Part 3 Item 3 (Other Prefabricated Component and Labour Saving
Solution) to include more prefab structural / finished components e.g.
prefab staircases, prefab bathroom unit & unitized building modules.
2005 2010

30
Setia Precast Sdn Bhd

Conclusion
To target a higher IBS Score :
1) Design shall be modular coordinated, compliance to MS1064 (Utilisation of
Standardise Components).

2) Developers & Contractors to plan for the use of IBS from the beginning including
any simplified construction method.

3) Prefabrications where possible.

4) Minimise labour intensive works where possible e.g. brickwork & plastering.

5) Developers should have a preference for IBS construction so that the project sites
are cleaner, less labour intensive and better quality.

6) Contractors should always be looking at more efficient construction methods.