Project Start Date 9/3/2018 (Monday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead 3 Sep 2018 10 Sep 2018 17 Sep 2018 24 Sep 2018 1 Oct 2018 8 Oct 2018 15 Oct 2018 22 Oct 2018
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PREDEC WORK AMOUNT
WBS TASK OWNER ESSOR START END DAYS % DONE EV % M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DAYS (PHP)
1 INITIATING - - 2,500,000.00 1450000
0.1 Project kick off Mon 9/03/18 Tue 9/04/18 2 60% 2 500,000.00 500,000.00 4 2.07 2.07
0.1 High Level Planning Wed 9/05/18 Fri 9/07/18 3 0% 3 500,000.00 250,000.00 4 1.4 1.4 1.4
0.1 Sign Project Charter Mon 9/10/18 Mon 9/10/18 1 0% 1 500,000.00 200,000.00 4 4
0.1 Stake Holder Meeting Wed 9/12/18 Wed 9/12/18 1 0% 1 1,000,000.00 500,000.00 8 8.26
2.1 Project Management Plan Fri 9/07/18 Tue 9/11/18 5 0% 3 700,000.00 500,000.00 6 1.2 1.2 1.16 1 1
2.2 Utilities and supplies Fri 9/07/18 Sun 9/16/18 10 0% 6 2,000,000.00 1,000,000.00 17 1.7 1.7 1.65 2 2 1.65 1.65 1.65 1.65 1.65
2.3 Man power Fri 9/07/18 Fri 9/14/18 8 0% 6 5,000,000.00 3,000,000.00 41 5.2 5.2 5.17 5 5 5.17 5.17 5.17
3.8 Other regulatory permits (SAQ Issues) Tue 1/22/19 Wed 2/20/19 30 0% 22
3.12 PAC (Provisional Acceptance Certificate) Mon 7/01/19 Tue 2/25/20 240 0% 172
4.1 Weekly Meeting Mon 9/17/18 Fri 2/28/20 530 0% 380 500000 4
4.2 Risk Meeting Mon 9/17/18 Fri 2/28/20 530 0% 380