SERVICIO DE ELABORACION DEL EXPEDIENTE TECNICO “USO DEL DERECHO DE VIA DE LA

CARRETERA EL REPOSO – SARAMIRIZA (Km. 239+750), PARA EL MANTENIMIENTO DEL OLEODUCTO


NOR PERUANO (Km. 326+400)”

ITEM DESCRIPCION UNIDAD METRADO


1.00 OBRAS PRELIMINARES
1.10 MOVILIZACION Y DESMOVILIZACION GBL 2.00
1.20 TRAZO GBL 1.00
1.30 MANTENIMINETO DE TRANSITO Y SEGURIDAD VIAL MES 1.00
2.00 MOVIMIENTO DE TIERRAS
2.10 EXCAVACION PARA ACCESOS M3 299.70
2.20 AFIRMADO PARA ACCESO M3 120.90
3.00 PAVIMENTOS
3.10 EXCAVACION ZONA DE EMPALME M2 63.48
3.20 REPOSICION MATERIAL DE RELLENO M2 277.40

3.30 M2 269.20
REPOSICION CAPA GRANULAR ESTABILIZADO CON CEMENTO
3.40 IMPRIMACION M2 210.40
3.50 MICROPAVIMENTO DE APERTURA RAPIDA M2 420.00
4.00 OBRAS DE ARTE Y DRENAJE
4.10 EXCAVACION PARA ESTRUCTURAS M3 1055.53
4.20 RELLENO PARA ESTRUCTURAS M3 181.83
4.30 ENCOFRADO Y DESENCOFRADO M2 328.86
4.40 ACERO DE REFUERZO FY=4200 KG/CM2 KG 6823.12
4.50 CONCRETO F'C=100KG/CM2 M3 8.69
4.60 CONCRETO F'C=280 KG/CM2 M3 89.39
4.70 LOSA DE PROTECCION 1.50 x 1.00 x 0.15 UNID 9.00
5.00 SEÑALIZACION
5.10 SEÑALIZACION HORIZONTAL M2 20.00
6.00 VARIOS
6.10 SOPORTE TUBERIA ONP UNID 2.00
6.20 PORTON METALICO UNID 2.00
6.30 PROTECCION AMBIENTAL GBL 1.00
6.40 RETIRO DEL ENTIBADO EXISTENTE GBL 1.00
PARTIDA
1 OBRAS PRELIMINARES
1.1 MOVILIZACION Y DESMOVILIZACION
UNIDAD : MES

PARTIDA UNIDAD METRADO

MOVILIZACION Y DESMOVILIZACION MES 2.00


Sub Total - 01 2.00

Total 2.00
PARTIDA
1 OBRAS PRELIMINARES
1.2 TRAZO
UNIDAD : GBL

PARTIDA UNIDAD METRADO

TRAZO GBL 1.00


Sub Total - 01 1.00

Total 1.00
PARTIDA
1 OBRAS PRELIMINARES
1.3 MANTENIMINETO DE TRANSITO Y SEGURIDAD VIAL
UNIDAD : GBL

PARTIDA UNIDAD METRADO

MANTENIMINETO DE TRANSITO Y SEGURIDAD VIAL GBL 1.00


Sub Total - 01 1.00

Total 1.00
PARTIDA
2.00 MOVIMIENTO DE TIERRAS
2.10 EXCAVACION PARA ACCESOS
UNIDAD : M3

LONGITUD AREA METRADO


PROGRESIVA
(M) (M2) (M3)

00+000.00 0.00
00+010.00 10.00 1.00 5.00
00+020.00 10.00 1.62 13.10
00+030.00 10.00 1.96 17.90
00+040.00 10.00 4.91 34.35
00+050.00 10.00 4.87 48.90
00+060.00 10.00 4.81 48.40
00+070.00 10.00 3.38 40.95
00+080.00 10.00 3.54 34.60
00+090.00 10.00 0.81 21.75
00+100.00 10.00 3.07 19.40
00+110.00 10.00 0.00 15.35

Sub Total - 01 299.70

Total 299.70
PARTIDA
2.00 MOVIMIENTO DE TIERRAS
2.20 AFIRMADO PARA ACCESO
UNIDAD : M3

LONGITUD AREA METRADO


PROGRESIVA
(M) (M2) (M3)

00+000.00 0.00
00+010.00 10.00 1.07 5.35
00+020.00 10.00 1.08 10.75
00+030.00 10.00 1.09 10.85
00+040.00 10.00 1.27 11.80
00+050.00 10.00 1.42 13.45
00+060.00 10.00 1.44 14.30
00+070.00 10.00 1.37 14.05
00+080.00 10.00 1.20 12.85
00+090.00 10.00 1.07 11.35
00+100.00 10.00 1.08 10.75
00+110.00 10.00 0.00 5.40

Sub Total - 01 120.90

Total 120.90
PARTIDA
3.00 PAVIMENTOS
3.10 EXCAVACION ZONA DE EMPALME
UNIDAD : M2

LONGITUD ANCHO METRADO


PROGRESIVA
(M) (M) (M2)

239+690.00
239+700.00 39.77

239+705.00
239+715.00 23.71

Sub Total - 01 63.48

Total 63.48
PARTIDA
3.00 PAVIMENTOS
3.20 REPOSICION MATERIAL DE RELLENO
UNIDAD : M2

LONGITUD ANCHO METRADO


PROGRESIVA
(M) (M) (M2)

239+680.00 5.87
239+690.00 10.00 5.87 58.70
239+700.00 10.00 8.00 69.35
239+710.00 10.00 8.00 80.00
239+720.00 10.00 5.87 69.35

Sub Total - 01 277.40

Total 277.40
PARTIDA
3.00 PAVIMENTOS
3.3 REPOSICION CAPA GRANULAR ESTABILIZADO CON CEMENTO
UNIDAD : M2

LONGITUD ANCHO METRADO


item
(M) (M) (M2)

239+680.00 5.46 0.00


239+690.00 10.00 5.46 54.60
239+700.00 10.00 8.00 67.30
239+710.00 10.00 8.00 80.00
239+720.00 10.00 5.46 67.30

Sub Total - 01 269.20

Total 269.20
PARTIDA
3.00 PAVIMENTOS
3.4 IMPRIMACION
UNIDAD : M2

LONGITUD ANCHO METRADO


item
(M) (M) (M2)

239+680.00 5.26
239+690.00 10.00 5.26 52.60
239+700.00 10.00 5.26 52.60
239+710.00 10.00 5.26 52.60
239+720.00 10.00 5.26 52.60

Sub Total - 01 210.40

Total 210.40
PARTIDA
3.00 PAVIMENTOS
3.5 MICROPAVIMENTO DE APERTURA RAPIDA
UNIDAD : M2

ANCHO METRADO
PROGRESIVA LONGITUD (M)
(M) (M2)

239+660.00 5.25
239+680.00 20.00 5.25 105.00
239+690.00 10.00 5.25 52.50
239+700.00 10.00 5.25 52.50
239+710.00 10.00 5.25 52.50
239+720.00 10.00 5.25 52.50

239+760.00 5.25
239+780.00 20.00 5.25 105.00

Sub Total - 01 420.00

Total 420.00
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.10 EXCAVACION PARA ESTRUCTURAS
UNIDAD : M3

LONGITUD AREA METRADO


ITEM
(M) (M2) (M3)

Corte general 8.47 108.78 921.37

Sub Total - 01 921.37

Excavacion Descarga de Alcantarilla


LONGITUD ANCHO METRADO
PROGRESIVA
(M) (M) (M2)

00+000.00 18.708 0.000


00+005.00 5.00 8.397 67.763
00+010.00 5.00 4.653 32.625
00+015.00 5.00 2.889 18.855
00+020.00 5.00 1.376 10.663
00+025.00 5.00 0.164 3.850
00+030.00 5.00 0 0.410

Sub Total - 01 134.165


Total 1055.53
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.20 RELLENO PARA ESTRUCTURAS
UNIDAD : M3

Longitud de Alcantarilla de 11.81 m

LONGITUD AREA METRADO


item
(M) (M2) (M3)

Mat. Relleno 11.81 15.40 181.83

Sub Total - 01 181.83

Total 181.83
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.30 ENCOFRADO Y DESENCOFRADO
UNIDAD : M2

AREA METRADO
ITEM
(M2) (M2)

ALCANTARILLA 207.85 207.85


CABEZAL DE ENTRADA 60.78 60.78
CABEZAL DE SALIDA 60.23 60.23

Sub Total - 01 328.86

Total 328.86
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.40 ACERO DE REFUERZO FY=4200 KG/CM2
UNIDAD KG

AREA METRADO
ITEM
(M2) (M2)

Acero de refuerzo fy=4200 kg/cm2 6823.12 6823.12

Sub Total - 01 6823.12

Total 6823.12
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.50 CONCRETO F'C=100KG/CM2
UNIDAD M3

VOLUMEN METRADO
ITEM
(M3) (M3)

ALCANTARILLA 5.55 5.55


CABEZAL DE ENTRADA 1.54 1.54
CABEZAL DE SALIDA 1.60 1.60

Sub Total - 01 8.69

Total 8.69
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.60 CONCRETO F'C=280 KG/CM2
UNIDAD M3

VOLUMEN METRADO
ITEM
(M3) (M3)

ALCANTARILLA 63.90 63.90


CABEZAL DE ENTRADA 12.37 12.37
CABEZAL DE SALIDA 13.11 13.11

Sub Total - 01 89.39

Total 89.39
PARTIDA
4.00 OBRAS DE ARTE Y DRENAJE
4.70 LOSA DE PROTECCION 1.50 x 1.00 x 0.15
UNIDAD UNID

METRADO
ITEM CANTIDAD
(UND)

LOSA DE PROTECCION 1.50X1.00X0.15 9.00 9.00

Sub Total - 01 9.00

Total 9.00
PARTIDA
5.00 SEÑALIZACION
5.10 SEÑALIZACION HORIZONTAL
UNIDAD : M2

LONGITUD ANCHO METRADO


item
(M) (M) (M3)

239+660.00 0.2
239+670.00 10.00 0.2 2.00
239+680.00 10.00 0.2 2.00
239+690.00 10.00 0.2 2.00
239+700.00 10.00 0.2 2.00
239+710.00 10.00 0.2 2.00
239+720.00 10.00 0.2 2.00
239+730.00 10.00 0.2 2.00
239+740.00 10.00 0.2 2.00
239+760.00 20.00 0.2 4.00
239+780.00 20.00 0.2 4.00

Sub Total - 01 16.00

Total 20.00
PARTIDA
6.00 VARIOS
6.10 SOPORTE TUBERIA ONP
UNIDAD : UNID

PARTIDA UNIDAD METRADO

SOPORTE TUBERIA ONP UNID 1.00


Sub Total - 01 1.00

Total 1.00

PARTIDA UNIDAD METRADO

SOPORTE TUBERIA ONP UND 1.00


Sub Total - 02 1.00

Total 2.00
PARTIDA
6.00 VARIOS
6.20 PORTON METALICO
UNIDAD : UNID

PARTIDA UNIDAD METRADO

PORTON METALICO ENTRADA UNID 1.00


Sub Total - 01 1.00

Total 1.00

PARTIDA UNIDAD METRADO

PORTON METALICO SALIDA UND 1.00


Sub Total - 02 1.00

Total 2.00
PARTIDA
6.00 VARIOS
6.30 PROTECCION AMBIENTAL
UNIDAD : GBL

PARTIDA UNIDAD METRADO

PROTECCION AMBIENTAL GBL 1.00


Sub Total - 01 1.00

Total 1.00

PARTIDA UNIDAD METRADO

00+000.00 0.00 2.00


Sub Total - 02 2.00

Total 2.00
PARTIDA
6 VARIOS
6.40 RETIRO DEL ENTIBADO EXISTENTE
UNIDAD : GBL

PARTIDA UNIDAD METRADO

RETIRO DEL ENTIBADO EXISTENTE GBL 1.00


Sub Total - 01 1.00

Total 1.00
TAG Empalme DIAM LONG. # Veces. 3/8"

Longitudinal 1 0.58 3/8" 12.64 20 252.8

Longitudinal 2 0.58 3/8" 12.64 20 252.8

Transversal 3 5/8" 5.00 51 0

Transversal 4 5/8" 5.00 51 0

P1

Transversal 5 5/8" 2.74 27 0

Transversal 6 5/8" 2.74 27 0

7 5/8" 2.74 26 0

8 5/8" 2.74 26 0

9 0.58 3/8" 12.64 20 252.8

10 0.58 3/8" 12.64 20 252.8

11 5/8" 5.00 51 0

12 5/8" 5.00 51 0

T1

13 5/8" 2.71 27 0

14 5/8" 2.71 27 0

15 5/8" 2.74 26 0
16 5/8" 2.74 26 0

17 5/8" 4.80 85 0

18 1/2" 4.00 85 0

M1

19 0.58 3/8" 12.77 15 191.55

20 0.58 3/8" 12.77 15 191.55

21 5/8" 4.80 77 0

22 1/2" 4.00 77 0

M2

23 0.58 3/8" 12.83 15 192.45

24 0.58 3/8" 12.83 15 192.45

25 3/8" 3.42 9 30.78

26 3/8" 3.42 9 30.78

27 3/8" 2.12 3 6.36

A1 28 3/8" 2.12 3 6.36

29 1/2" 3.74 9 0

30 3/8" 3.74 8 29.92

31 1/2" 2.82 2 0
32 3/8" 2.68 9 24.12

33 3/8" 2.68 9 24.12

34 3/8" 1.96 4 7.84

A2 35 3/8" 1.96 4 7.84

36 1/2" 3.74 9 0

37 3/8" 3.74 8 29.92

38 1/2" 2.86 2 0

39 3/8" 3.24 9 29.16

40 3/8" 3.42 9 30.78

41 3/8" 2.12 3 6.36

A3 42 3/8" 2.12 3 6.36

43 3/8" 3.74 9 33.66

44 3/8" 3.74 8 29.92

45 1/2" 2.00 2 0

46 3/8" 2.55 9 22.95

47 3/8" 2.68 9 24.12


48 3/8" 1.96 4 7.84

A4 49 3/8" 1.96 4 7.84

50 1/2" 3.74 9 0

51 3/8" 3.74 8 29.92

52 1/2" 2.26 2 0

53 3/8" 6.35 2 12.7

PP-1 54 1/2" 6.35 2 0

55 3/8" 1.50 25 37.5

56 3/8" 6.60 2 13.2

PP-2 57 1/2" 6.60 2 0

58 3/8" 1.50 26 39

59 1/2" 7.12 6 0

U-1

60 3/8" 1.58 29 45.82

61 1/2" 7.27 6 0

U-2

62 3/8" 1.58 30 47.4

63 1/2" 2.37 30 0
64 1/2" 2.37 30 0

65 1/2" 1.36 7 0

P1-A

66 1/2" 1.36 7 0

67 1/2" 7.10 8 0

68 1/2" 7.10 8 0

69 1/2" 2.19 13 0

70 1/2" 2.19 13 0

71 1/2" 2.44 4 0

P1-B

72 1/2" 2.44 4 0

73 1/2" 3.24 4 0

74 1/2" 3.24 4 0

75 1/2" 1.75 10 0

76 1/2" 1.75 10 0

P1-C

77 1/2" 2.17 7 0

78 1/2" 2.17 7 0

79 1/2" 2.37 28 0
80 1/2" 2.37 28 0

81 1/2" 1.75 10 0

82 1/2" 1.75 10 0

P2-A

83 1/2" 7.52 8 0

84 1/2" 7.52 8 0

85 1/2" 1.44 9 0

86 1/2" 1.44 9 0

87 1/2" 3.35 4 0

88 1/2" 3.35 4 0

89 1/2" 1.86 4 0

P2-B

90 1/2" 1.86 4 0

91 1/2" 1.81 13 0

92 1/2" 1.81 13 0

93 1/2" 2.37 4 0

94 1/2" 2.37 4 0

95 1/2" 2.76 4 0

P2-C
P2-C

96 1/2" 2.76 4 0

97 1/2" 1.63 10 0

98 1/2" 1.63 10 0

Peso Total de Acero


1/2" 5/8" Peso (Kg)

0 0 141.57

0 0 141.57

0 255 395.76

0 255 395.76

0 73.98 114.82

0 73.98 114.82

0 71.24 110.56

0 71.24 110.56

0 0 141.57

0 0 141.57

0 255 395.76

0 255 395.76

0 73.17 113.56

0 73.17 113.56

0 71.24 110.56
0 71.24 110.56

0 408 633.22

340 0 337.96

0 0 107.27

0 0 107.27

0 369.6 573.62

308 0 306.15

0 0 107.77

0 0 107.77

0 0 17.24

0 0 17.24

0 0 3.56

0 0 3.56

33.66 0 33.46

0 0 16.76

5.64 0 5.61
0 0 13.51

0 0 13.51

0 0 4.39

0 0 4.39

33.66 0 33.46

0 0 16.76

5.72 0 5.69

0 0 16.33

0 0 17.24

0 0 3.56

0 0 3.56

0 0 18.85

0 0 16.76

4 0 3.98

0 0 12.85

0 0 13.51
0 0 4.39

0 0 4.39

33.66 0 33.46

0 0 16.76

4.52 0 4.49

0 0 7.11

12.7 0 12.62

0 0 21.00

0 0 7.39

13.2 0 13.12

0 0 21.84

42.72 0 42.46

0 0 25.66

43.62 0 43.36

0 0 26.54

71.1 0 70.67
71.1 0 70.67

9.52 0 9.46

9.52 0 9.46

56.8 0 56.46

56.8 0 56.46

28.47 0 28.30

28.47 0 28.30

9.76 0 9.70

9.76 0 9.70

12.96 0 12.88

12.96 0 12.88

17.5 0 17.40

17.5 0 17.40

15.19 0 15.10

15.19 0 15.10

66.36 0 65.96
66.36 0 65.96

17.5 0 17.40

17.5 0 17.40

60.16 0 59.80

60.16 0 59.80

12.96 0 12.88

12.96 0 12.88

13.4 0 13.32

13.4 0 13.32

7.44 0 7.40

7.44 0 7.40

23.53 0 23.39

23.53 0 23.39

9.48 0 9.42

9.48 0 9.42

11.04 0 10.97
11.04 0 10.97

16.3 0 16.20

16.3 0 16.20

so Total de Acero 6823.12


OBRAS DE ARTE
EXPEDIENTE TECNICO "USO DE DERECHO DE VIA DE LA CARRETERA EL REPOSO - SARAMIRIZA (KM. 239+750), PARA EL MANTENIMIENTO DEL OLEODUCTO NOR PERUAN

SUSTENTO DE ALCANTARILLAS TIPO MC


CONCRETO, SOLADO Y ENCOFRADO x METRO LINEAL DE ALCANTARILLA

CARACTERISTICAS GEOMETRICAS CONCRETO MARCO SOLADO MARCO


Concreto Clase (f'c = 280 kg/cm ) 2
Concreto Clase H (f'c = 100 k
Espesor Espesor
Nº Espesor
N° SECCIÓN B H LONGITUD Losa Losa Chaflán Losa Paredes Losa VOLUMEN
OJOS Pared Ancho Espesor
Superior Inferior Superior Laterales Inferior TOTAL
BxH (m) (m) (m) (m) (m) (m) (m 2 ) (m 3 ) (m 3) (m 3) (m 3) (m) (m)
4.00 x 3.00 (Hmax=0.60m) 4.00 3.00 11.81 1.00 0.350 0.350 0.350 0.00500 19.55 24.80 19.55 63.90 55.51 0.100

Estudio Definitivo de Rehabilitación y Mejoramiento de la Carretera Huancavelica - Lircay


Tramo: km 1+550 (Av. Los Chancas) - Lircay
+750), PARA EL MANTENIMIENTO DEL OLEODUCTO NOR PERUANO (KM. 326+400 ONP)"

CANTARILLAS TIPO MC
ADO x METRO LINEAL DE ALCANTARILLA

SOLADO MARCO ENCOFRADO Y DESENCOFRADO MARCO


Concreto Clase H (f'c = 100 kg/cm )2
Áreas de Encofrado
VOLUMEN Losa Paredes Losa ÁREA
TOTAL Superior Laterales Inferior TOTAL
(m 3) (m 2) (m 2) (m 2) (m 2)
5.55 47.24 158.25 2.36 207.85

Estudio Definitivo de Rehabilitación y Mejoramiento de la Carretera Huancavelica - Lircay


Tramo: km 1+550 (Av. Los Chancas) - Lircay
OBRAS DE ARTE
EXPEDIENTE TECNICO "USO DE DERECHO DE VIA DE LA CARRETERA EL REPOSO - SARAMIRIZA (KM. 239+750), PARA EL MANTENIMIENTO DEL OLEODUCTO NOR PERUANO (KM. 326+400 O

SUSTENTO DE ALCANTARILLAS TIPO MC


CONCRETO - CABEZAL DE ALCANTARILLA

CARACTERISTICAS GEOMETRICAS CABEZAL ENTRADA - ALERO INCLINADO


Concreto Clase (f'c = 280 kg/cm 2)
N° Sección B H Paredes Laterales Losa Cimentación Uña
h (min) h (max) a (sup) a (inf min) a (inf max) l (min) l (max) N ° de Volumen h Área N ° de Volumen h a l
BxH (m) (m) (m) (m) (m) (m) (m) (m) (m) elementos (m 3) (m) (m )
2 elementos (m 3) (m) (m) (m)
4.00 x 3.00 (Hmax=0.60m) aleta 1 4.00 3.00 2.25 3.45 0.46 0.25 0.46 1.80 1.81 1.00 2.10 0.350 8.83 1.00 3.09 0.65 0.25 4.51
4.00 x 3.00 (Hmax=0.60m) aleta 2 4.00 3.00 2.25 3.45 0.35 0.25 0.35 2.48 2.55 1.00 2.33 0.350 6.52 1.00 2.28 0.65 0.25 2.69

Estudio Definitivo de Rehabilitación y Mejoramiento de la Carretera Huancavelica - Lircay


Tramo: km 1+550 (Av. Los Chancas) - Lircay
NTENIMIENTO DEL OLEODUCTO NOR PERUANO (KM. 326+400 ONP)"

CANTARILLAS TIPO MC
EZAL DE ALCANTARILLA

ZAL ENTRADA - ALERO INCLINADO SOLADO CABEZAL


oncreto Clase (f'c = 280 kg/cm )
2
Concreto Clase H
Uña Parapeto Volumen (f'c = 100 kg/cm 2)
Volumen h a l Volumen Total h Área N ° de Volumen
(m )
3
(m) (m) (m) (m )
3
(m )
3
(m) (m )
2 elementos (m 3)
0.73 1.17 0.20 3.00 0.70 6.62 0.100 8.83 1.00 0.88
0.44 1.17 0.20 3.00 0.70 5.75 0.100 6.52 1.00 0.65
12.37 1.54

Estudio Definitivo de Rehabilitación y Mejoramiento de la Carretera Huancavelica - Lircay


Tramo: km 1+550 (Av. Los Chancas) - Lircay
OBRAS DE ARTE
EXPEDIENTE TECNICO "USO DE DERECHO DE VIA DE LA CARRETERA EL REPOSO - SARAMIRIZA (KM. 239+750), PARA EL M

SUSTENTO DE A
CONCRETO - CA

CARACTERISTICAS GEOMETRICAS C

N° Sección B H Paredes Laterales


h (min) h (max) a (sup) a (inf min) a (inf max) l (min) l (max)
BxH (m) (m) (m) (m) (m) (m) (m) (m) (m)
4.00 x 3.00 (Hmax=0.60m) Aleta 1 4.00 3.00 2.25 3.45 0.35 0.25 0.35 1.66 1.80
4.00 x 3.00 (Hmax=0.60m) Aleta 2 4.00 3.00 2.25 3.45 0.35 0.25 0.35 2.54 2.55
(KM. 239+750), PARA EL MANTENIMIENTO DEL OLEODUCTO NOR PERUANO (KM. 326+400 ONP)"

SUSTENTO DE ALCANTARILLAS TIPO MC


CONCRETO - CABEZAL DE ALCANTARILLA

CABEZAL SALIDA - ALERO INCLINADO


Concreto Clase D (f'c = 280 kg/cm 2)
Losa Cimentación Uña Parapeto
N ° de Volumen h Área N ° de Volumen h a l Volumen h a l Volumen
elementos (m 3) (m) (m )
2 elementos (m 3) (m) (m) (m) (m )
3
(m) (m) (m) (m 3)
1.00 1.60 0.350 6.38 1.00 2.23 0.65 0.25 5.78 0.94 1.13 0.20 2.99 0.68
1.00 2.36 0.350 9.62 1.00 3.37 0.65 0.25 7.78 1.26 1.13 0.20 2.99 0.68
SOLADO CABEZAL
Concreto Clase H
(f'c = 100 kg/cm 2)
Volumen
Total h Área N ° de Volumen
(m )
3
(m) (m )
2 elementos (m 3)
5.45 0.100 6.38 1.00 0.64
7.66 0.100 9.62 1.00 0.96
13.11 1.60
OBRAS DE ARTE
EXPEDIENTE TECNICO "USO DE DERECHO DE VIA DE LA CARRETERA EL REPOSO - SARAMIRIZA (KM. 239+750), PARA EL MANTENIMIENTO DEL OLEODUCTO NOR PERU

SUSTENTO DE ALCANTARILLAS TIPO MC


ENCOFRADO Y DESENCOFRADO - CABEZAL DE ALCANTARILLA

CARACTERISTICAS GEOMETRICAS CABEZAL - ALERO INCLINADO


Encofrado y Desencofrado
N° Sección B H Paredes Laterales Losa Cimentación Uña
h (min) h (max) a (sup) a (inf min) l (min) l (max) N ° de Área h Perimetro N ° de Área h a l
BxH (m) (m) (m) (m) (m) (m) (m) (m) elementos (m )
2
(m) (m )
2 elementos (m )
2
(m) (m) (m)
CABEZALES - ENTRADA
4.00 x 3.00 (Hmax=0.60m) aleta 1 4.00 3.00 2.25 3.45 0.46 0.25 1.80 1.81 1.00 11.09 0.350 12.16 1.00 4.26 0.65 0.25 4.51
4.00 x 3.00 (Hmax=0.60m) aleta 2 4.00 3.00 2.25 3.45 0.35 0.25 2.48 2.55 1.00 15.01 0.350 15.34 1.00 5.37 0.65 0.25 2.69
CABEZALES - SALIDA
4.00 x 3.00 (Hmax=0.60m) aleta 1 4.00 3.00 2.25 3.45 0.35 0.25 1.66 1.80 1.00 10.54 0.35 12.09 1.00 4.23 0.65 0.25 2.56
4.00 x 3.00 (Hmax=0.60m) aleta 2 4.00 3.00 2.25 3.45 0.35 0.25 2.54 2.55 1.00 15.18 0.35 15.97 1.00 5.59 0.65 0.25 4.79

Estudio Definitivo de Rehabilitación y Mejoramiento de la Carretera Huancavelica - Lircay


Tramo: km 1+550 (Av. Los Chancas) - Lircay
PARA EL MANTENIMIENTO DEL OLEODUCTO NOR PERUANO (KM. 326+400 ONP)"

LCANTARILLAS TIPO MC
FRADO - CABEZAL DE ALCANTARILLA

CABEZAL - ALERO INCLINADO


Encofrado y Desencofrado
Uña Parapeto Solado ÁREA
Área h a l Área h Perimetro Área TOTAL
N ° de
(m 2) (m) (m) (m) (m 2 ) (m) (m 2) elementos (m 2) (m 2)

6.19 1.17 0.20 3.00 7.49 0.100 12.16 1.00 0.04 29.05
3.82 1.17 0.20 3.00 7.49 0.100 15.34 1.00 0.04 31.72

3.65 1.13 0.20 2.99 7.21 0.100 12.09 1.00 0.04 25.66
6.55 1.13 0.20 2.99 7.21 0.100 15.97 1.00 0.04 34.57
121.01

Estudio Definitivo de Rehabilitación y Mejoramiento de la Carretera Huancavelica - Lircay


Tramo: km 1+550 (Av. Los Chancas) - Lircay