PAKISTAN OILFIELDS LIMITED

POLGAS KARACHI

Date; 9.11.2018

To
AGM (S&M)

Pakistan Oil Fields Ltd,


POL house Morgah,
Karachi

Subject: Calibration of LPG tanks at POLgas plant Karaxchi

Sir,

As it is decided to calibrate LPG Tanks of POL Gas Plant Karachi


And work is awarded to UNI_TEAM but date of starting work is not yet
Decided.
Date of Re-inspection of tanks is also near.Previous inspection was done in year
2010 by SGS. Date of inspection of each tank +is attached.
Next inspection is due after 10 years gap as per API-653 (6.4.2.2) swtandard.

In order to avoid reopening tanks 6 to 8 months after calibration and to


Avoid wasting of LPG product it is suggested that calibration and internal inspection
Should be done at same time

Please advise.

(Murad Ali Shah)


Consultant Engineer
POL.
LPG INSPECTION RECORD.
S.N TANK NO. Previous inspection Re-Inspection Remarks
Date Date
Dumbar Field:

S.N Description Measurement Remarks


o:
1 Dismantling reinforced cement, concrete (1:2:4) 12027.25 cft.
2 Dismantling plain cement, concrete (1:4:8) 6142.44 cft.
3 Dismantling block masonry (Non recoverable) 5281.97 cft.
4 Dismantling plain cement, concrete (1:2:4) 899.41 cft.
5 Dismantling plain cement, concrete (1:3:6) 4649.16 cft.
6 Removing and shafting of blocks from soakage pits including 2239.79
loading/unloading
7 Cutting of steel Gr.40 using gas cutter set and labor 18737.31 kg.
8 Removing GI-sheets width 3 inch 11433 sft.
9 Removing GI. Barbed wire 81553 kg.
10 Removing galvanized chain link fence 30488 sft
11 Recovery of angle iron poles. 316 in nos.
12 Recovery of cement Blocks 2045.53 cft.
13 Recovery of Geomemberene sheet removing crush from sheet 84667.21 sft
14 transport of geomemberene sheet 1=trip
15 Back filling of excavated earth using Bulldozer D85 (Caterpiller) 150 hrs
16 Shifting of concrete, blocks & derbies including loading/unloading 29000.23 cft.
17 Supply of bulldozer D-85 Cat. For leveling camp site restoration 150 hrs.
18 Supply of excavator for service (Chain driven) 10 hrs.
19 Removing loose crush from foot path 36100 cft.
Estimate

Part A: Dismantling of RIG Pad \ Size 85’x40’x2.17’

Part B: Dismantling of Cellar (wall size:15’x2’6’)

SCOPE OF WORK:

s.n. Description Quantity

A Dismantling of rig pad

1 Dismantling of reinforcement cement concrete ) (!:2:4 7280 cft.

2 Dismantling of plain cement concrete ) (!:4:8) 1587.5 cft

3 Dismantling of block masonry 312.5 cft.

4 Cutting of steel Gr,40 using gas cutter set & labor 11711.33

5 Shifting of concrete & blocks debris including 9180 cft.


loading/unloading

Description Quantity
s.n.

B Dismantling of cellar (walls)

1 Dismantling of reinforcement cement concrete ) (!:2:4) 624 cft.


(Walls)
2 Dismantling of plain cement concrete ) (!:4:8) 501.08

3 Dismantling of block masonry 116.16cft.

4 Cutting of steel Gr,40 using gas cutter set & labor 1101.93

5 Shifting of concrete & blocks debris including 1241.24


loading/unloading
Estimate

Part A: Dismantling of engine Pad \ Size 44.61’x40’x1’

Part B: Dismantling of mud pumps pad (size:26.57x29.70x1’&23x9.84’x1’)

SCOPE OF WORK:

s.n. Description Quantity

A Dismantling of engine pad

1 Dismantling of reinforcement cement concrete ) (!:2:4 1902.17 cft.

2 Dismantling of plain cement concrete ) (!:4:8) 1902.17 cft

3 Dismantling of block masonry 312.5 cft.

4 Cutting of steel Gr,40 using gas cutter set & labor 11711.33

5 Shifting of concrete & blocks debris including 9180 cft.


loading/unloading

Description Quantity
s.n.

B Dismantling of mud pump pad.

1 Dismantling of reinforcement cement concrete ) (!:2:4) 102.16 cft.


(Walls)
2 Dismantling of plain cement concrete ) (!:4:8) 501.08

3 Dismantling of block masonry 116.16cft.

4 Cutting of steel Gr,40 using gas cutter set & labor 1101.93 kg

5 Shifting of concrete & blocks debris including 719.4 cft.


loading/unloading
Estimate

Part A: Dismantling of mud tank Pad \ Size 41.67’x10.1’x1’

Part B: Dismantling of shale shaker slope & drains

SCOPE OF WORK:

s.n. Description Quantity

A Dismantling of mud tank pad

1 Dismantling of plaincement concrete ) (!:2:4) 127.85 cft.

2 Dismantling of plain cement concrete ) (!:4:8) 1650.61 cft

3 Dismantling of block masonry walls (1:6) 841.55 cft

4 Removing steel re-bars 2118.93 cft.


\
5 Dismantling of RCC (1:2:4} 2118.92 cft

Shifting of concrete & blocks debris including 4738.93 cft.


6 loading/un loading.

s.n. Description Quantity

B Dismantling of shale shaker slope

1 Dismantling of block masonry 500.41 cft.

2 Dismantling of plain cement concrete ) (!:2:84) 279.13 cft.

3 hifting of concrete & blocks debris including


loading/unloading 779.54 cft.

C Dismantling of drains

1 Dismantling of plain cement concrete (1:3:6) 167.14 cft.

2 Dismantling block masonry walls (1:6)


3 Shifting of concrete & blocks debris including
loading/unloading.
Estimate

Part A: Dismantling of barite pad


Part B: Demolshing of waste water pit

SCOPE OF WORK:

s.n. Description Quantity

A Dismantling of barite pad

1 Dismantling of plain cement concrete ) (!:3:46 2865.44 cft

2 Dismantling of block masonry 1064.18 cft.

3 Shifting of concrete & blocks debris including


loading/unloading 3929.62 cft.

Description Quantity
s.n.

B Demolishing of waste water pit.

1 Removing of geo-membrane sheet including removing 84667 sft..


of slush from sheet.
501.08
2 Shifting of geo-membrane including of loading/
unloading. 1 trip.

3 Back filling of excavated earth using bulldozer. 100 hrs.


Estimate

Part A: Dismantling of fresh water pond

Part B: Dismantling of walk ways at Rig/Camp area

Part C: Dismantling Soakage pit for Camp/Rig area

Part D: Dismantling septic tank for Camp/Rig area.

SCOPE OF WORK:

s.n. Description Quantity

A Dismantling of fresh water pond.

1 Dismantling of reinforcement cement concrete ) (!:2:4 767.58 cft.

2 Dismantling of plain cement concrete ) (!:3:6) 461.21 cft

3 Dismantling of block masonry 290 cft.

4 Shifting of concrete & blocks debris including 1518.79


loading/unloading cft.
s.n. Description Quantity

B Dismantling walk ways Rig/Camp area.)

1 Removing of cement blocks(12x6x8) quantity 575.53 cf 1718 rft.


Removing loose crush foot paths
2 361 cft.

C Dismentling soakage pit for camp/rig area

Removing & shifting of broken blocks including loading/un-loading 2239.79 cft

D, Dismantling septic tanks for camp/rig area

Dismantling of blocks masonry. 1422.28 cft.

Part A: Recovery of fence from Rig & camp area

SCOPE OF WORK:

s.n. Description Quantity

A Recovery of fence from Rig & camp area

1 Removing of GI.sheet 3 inch wide 11433 sft.


e
2 Removing of GI.barbed wire 815.3 kg.

3 Removing of galvanized chain link fence 30488 sft.

4 Recovery of angle lron poles 316 nos.

5 Dismantling of cement concrete (1:3:6) 1155.36

6 Shifting of concrete debris including loading/un


loading.
Estimate

Part A: Dismantling of Beams &Dyke walls for Diesel storage Tank


&plate form for tank lorry.

Part B: Levelling & Dressing of well & camp site

SCOPE OF WORK:

s.n. Description Quantity

Dismantling of beam & dyke for diesel storage


tanks, kitchen, guard room, store, prayer place,
segregation unit & platform for tank lorries,

1 Recovery of cement blocks 1470 cft.

2 Dismantling of pcc(1:2:4) 492.43 cft.

Description Quantity
s.n.

B Leveling & Dressing of well & camp site.

Supply of bulldozer D-85 (CATERPILLER)


1 SERVICES for area leveling. 150 hrs.

2 Supply excavator services ( Chain driven) 10 hrs.