Professional Documents
Culture Documents
Overview of Sha Tin Wai Station and its neighbourhood in early 2003.
Construction of City One Station
as seen from a nearby building.
The building on the far left side is
the Prince of Wales Hospital.
Construction of a series of
portal beams and column
head supports for the
viaduct near the Shek
Mun Interchange.
Typical twin-section A 35 m span portal
column head support beam near the Heng
with the cast-in-situ On Interchange with
matching segments in the hanging girder
position for receiving fixed above the
the forthcoming portal to facilitate
segments to form the erection of the
viaduct section. precast segments.
The girder was tied
down to the ongoing
segment by tendons
and the full span of
the viaduct was
erected by using the
balanced cantilever
method repeatedly.
The assembly of a set of overhead gantries used to erect the precast segments to form the viaducts. Note the
rural village at the rear of the assembly yard; one of the oldest inhabited tribal villages in the Shatin area.
Placing the last segment for a span of the viaduct. After the
correct positioning of the last segment, all the segments in the
span were fine-tuned to adjust the alignment and level.
Temporary stressing was applied afterwards to allow the span to
rest temporarily on the column heads. Final adjustment was done
again at the final stage when nearby spans were also in position.
A closer look at the overhead gantry on the deck level with the segments in position before sliding A section of long-span viaduct structure constructed using the balanced cantilever method
it forward to the next span. near Tai Shui Hang Station.
Detail of the supporting frame erected on top of a pier for mounting the overhead gantry. On the The viaduct section crossing the Siu Lek Yuen River channel heading to Shek Mun Station. Two
left side is the Shing Mun River channel. sets of underslung gantries can be seen in the background for erection of the precast segments
that formed the viaduct section.
Close-up view of the Siu Lek
Yuen River channel with the
cofferdams in place for
construction of the piers of
the portal beams.
Completed sections of viaduct crossing the junction of Lion Rock Tunnel Road and
Tai Chung Kui Road.
Close-up view at the side of the viaduct near City One Station with the track and
power system being completed.
Viaduct approaching
Heng On Station at its
final completion stage.
Viaduct crossing the Heng On Roundabout before entering Heng On Station. Viaduct section with a train between Ma On Shan and Wu Kai Sha Stations.
Track Laying
A detailed look at the viaduct on the railway level before the laying of the tracks. The rows of link bars were
embedded in the precast segments for forming the side curb to hold the float slabs that restrain the rail tracks.
Forming the side curb to restrain
the float slab using a specially
designed travelling form system.
Forming the side curb using a track-mounted curb-forming machine. This machine comprised Placing the resilient compound into slot holes in the float slab holding the bolts and base plates
the curb moulding panels, concrete conveyor and feeder, and the track pads that helped the that grasp the rail tracks.
machine to move forward continually to form the curb.
Close-up of the rail tracks
inside a noise barrier hood
with bypass track provisions.
Final touch-up of
facilities and installation
works within an open-
platform station.
Ma On Shan Station as seen from Sai Sha Road with the associated pedestrian facilities in place before handover.
Wu Kai Sha Station and associated nearby road reinstatement work, as seen before handover.