Professional Documents
Culture Documents
A
REPORT ON FINAL YEAR PROJECT
ON
“PRE-FEASIBILITY STUDY OF YANKHUWA KHOLA
HYDROPOWER PROJECT”
(As a partial fulfillment of Bachelor’s Degree in Civil Engineering)
(Course Code: CE755)
July, 2018
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
PREFACE
Tribhuvan University has offered civil engineering project as course content for
Bachelor level in civil engineering. To introduce the students with the real civil
engineering and idea of practical working in professional field with the application of
theoretical knowledge gained during the whole four years, there is provision of
project work. It involves the desk study and field study of a civil engineering projects
and the preparation of the final report along with final defense and presentation. It
helps the students to be acquainted with the practical aspects which a professional
may encounter in the field thus preparing them towards any future problems that may
arise during practicing.
The objective of this project is to study the pre-feasibility and propose a design, for
the development of small-scale hydropower of Yankhuwa Khola. The goal of the
project is to benefit the people through the development of income from sale of power
to a utility. The design will include site locations of major components, estimations of
power generation capability, and a life cycle economic analysis. We have attempted to
design a project in which power generation accomplished with minimal negative
impact on environment.
ii
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
ACKNOWLEDGEMENT
We would like to express our sincere gratitude to Er. Sunil Duwal (Principal of
Khwopa College of Engineering) and Er. Ramesh Bala (Head of Civil Engineering
Department) for their kind help and assistance.
We are also indebted to our Supervisor Er. Satyaram Jyakhwa for assisting,
suggesting, motivating and supervising in every aspects of our study. Without his help
this study would probably be impossible.
At last but not the least, we would like to thank all our friends who directly or
indirectly help during the completion of this project work.
iii
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
ABSTRACT
The Yankhuwa khola hydropower project is a run off type hydropower project located
at latitude 27°15’38’’N and 87°8’17’’E. The proposed site is located on the tributary
of Arun River.
The pre-feasibility study is carried out in order to find out whether the project is
feasible or not in the initial stage. From the study, if the project is feasible then other
study are performed. For the pre-feasibility study of hydropower, collection of data,
hydrology, topography etc. are performed. In the project Yankhuwa Khola
Hydropower Project, the prefeasibility analysis is to be performed.
The objective of this project is to study the feasibility and proposed a design for
Yankhuwa Khola hydropower project. In the first part all the hydrological analysis
including flood duration curve, comparison between high flood and low flood analysis
are carried out. Along with this hydraulic design of components, rate analysis, cost
estimation and financial analysis were carried out in the second part of the project.
iv
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
TABLE OF CONTENTS
PREFACE ............................................................................................................................ii
ACKNOWLEDGEMENT ................................................................................................. iii
ABSTRACT ........................................................................................................................ iv
TABLE OF CONTENTS ..................................................................................................... v
CHAPTER 1 ........................................................................................................................ 1
INTRODUCTION TO HYDROPOWER ............................................................................ 1
1.1 Study Background ........................................................................................... 1
1.2 Objective of the study ..................................................................................... 2
1.3 Generation of Hydropower.............................................................................. 2
1.4 Sources of energy ............................................................................................ 3
1.4.1 Hydropower ............................................................................................. 3
1.4.2 Thermal Power ......................................................................................... 5
1.4.3 Nuclear power .......................................................................................... 5
1.5 Hydropower potential ...................................................................................... 6
1.6 History of Hydropower Development ............................................................. 7
1.7 Hydropower Development history in Nepal ................................................... 8
1.8 Hydropower Development in Nepal ............................................................... 9
1.9 Hydropower Potential in Nepal ..................................................................... 10
1.10 Nepal’s Power Supply/Demand Scenario ..................................................... 12
1.11 Challenges and Issues in Power Sector ......................................................... 13
1.12 Advantages of Hydropower over other sources of energy ............................ 14
1.13 Justification of role of Mini Hydropower in Nepal ....................................... 15
CHAPTER 2 ...................................................................................................................... 17
2.1 PROJECT DESCRIPTION ........................................................................... 17
2.2 Location of project site:................................................................................. 17
2.3 Geology of project site .................................................................................. 17
CHAPTER 3 ...................................................................................................................... 18
METHODOLOGY ............................................................................................................ 18
CHAPTER 4 ...................................................................................................................... 19
HYDROLOGY .................................................................................................................. 19
v
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
vi
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
vii
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
ABBREVIATIONS
AC Alternating Current
BM Bench Mark
Ch. Chainage
cm Centimeter
D/S Downstream
FY Fiscal Year
GM Silty Gravel
viii
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Ha Hectare
HT High Tension
Hz Hertz
Km kilometer
kV Kilovolt
LF Load Factor
LT Low Tension
m Meter
Max Maximum
Min Minimum
MW Mega Watt
ix
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
nos Numbers
SC Sandy Clay
T Ton
U/S Upstream
V Volt
x
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Nepal has huge hydropower potential. It has many numbers of rivers with the
significant head from which hydropower can be generated easily. In the developing
country, like Nepal, the major problem of people is scarcity of food for the
nourishment due to population growth. So we need energy for the efficient production
of food to cope with such challenging scenario. The scenario of energy consumption
is at the increasing rate. This causes depletion in non-renewable and exhaustive
sources of energy, which may cause energy crisis in the future. Also, it is essential to
meet the concept of sustainable development which means that our children should
get at least this much resource that we are consuming at present. So, energy
consumers should be encouraged on using non-exhaustive and renewable sources of
energy. Hydropower, one of the most reliable and common renewable sources of
energy, is abundantly available in the hilly regions like Nepal. Again, hydraulic
conveyance circuit can be beneficial for multipurpose use (irrigation, water supply
etc.). Hydropower production does not consume water, so it is considered as
renewable source of energy. Consumption of this energy is environmental friendly
because it uses water as fuel and no harmful by-products are produced. It does not
1
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
emit greenhouse gases that cause ozone layer depletion and global warming. Because
of abundant water resources and potential hydropower sites available, there is huge
possibility of hydropower production. Large projects involve huge amount of funds
and the gestation period is large hence activities regarding development of Mini
Hydropower Projects are accelerating in these days which is technically, financially
and socially sustainable at the present scenario.
To fulfill the partial requirement of the final year project for the Bachelor
Degree in Civil Engineering.
The meaning of hydropower is the power that can be generated in the form of
electric power or any other mechanical power on account of the energy head
associated with the flowing or still water. The technical aspects of the development of
a physical scheme that is for the generation of hydropower comes under hydropower
engineering, which is also branch of water resources engineering. Hydropower in the
2
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
form of electrical energy is obtained from the generator coupled with turbines, which
converts hydraulic energy into mechanical energy. The high head required for running
turbine is either created by constructing a dam across river or diverting its flow to a
location lower than the head pond or a fore bay. The electric power is very important
form of energy to energize a country for its economic growth and maintaining living
standard. Per capita consumption of electricity of a country gives us an indication as
to how developed the country is.
• Hydropower
• Thermal power
• Nuclear power
Besides these, there are other unconventional sources of energy which are
listed as below. These are still under development and their costs of development are
yet to be competitive, hence, unable to take up substantial fraction of total installed
capacity of any country.
• Tidal power
• Solar power
• Geo-thermal energy
• Wind power
1.4.1 Hydropower
Hydropower uses the power of water to produce energy. Flowing water has
three types of energy heads, namely – potential head, pressure head and kinetic head.
While flowing, one type of energy head can be increased at the cost of others
3
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
depending on conditions. The running water with one or a combination of more than
one types of energy heads causes spinning of a turbine that runs generator, which
produces electricity. Types of hydropower generation plants are:
4
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
This type doesn’t have the storage or reserving capacity. The water flows and
passes through the turbines. It is continuously moving and should not remain
static. So the water coming from upstream should be used at the moment or it
should go around the dam. Weir is constructed across the river to maintain
the water level and discharge to the power plant.
Storage plants
These types of plant have storage capacity which regulates the hydrograph of
the river by one or more seasons. Dam is constructed across the river to store
the water. These plants require high initial investment but provides a much
more efficient and controlled use of the available water.
Nuclear power plants are similar to fossil fuel steam plants except that nuclear
fission produces the heat required to generate the steam. The nuclear systems are
operated at a lower pressure and temperature.
Unconventional sources
•Tidal power
5
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
•Solar power
•Wind power
•Geo-thermal
A. Gross Potential:
The power, which can theoretically be generated, is known as gross potential power
(Physically based upper limit for power production, can never be attained due to
difficulties in construction, loss, etc.).A river basin is divided into several cascades.
Based on the head and hydrograph of that particular cascade the power can be
calculated. Then, the total power in a river basin can be calculated using the following
relation.
∑n
i=1 ηγQH
P= 100
H = net head, m
n = number of cascades
Therefore P = 9.81QH; in kW
B. Technical Potential
6
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
All the theoretically possible power in nature cannot be produced due to various
constraints like unfavorable geology, topography, climatic conditions, accessibility,
etc. So, the power, which is technically viable to produce, is known as technical
potential. Technically potential power is about 43000MW.
C. Economically Potential
The technically feasible projects cannot be implemented if they do not give a good
return once the investment is made. Moreover, it is not always economically feasible
if the internal rate of return is higher than the prevailing interest rate and the
benefit/cost ratio is more than unity.
Human have been harnessing water to perform work for thousands of years.
By using water for power generation, people have worked with nature to achieve a
better lifestyle. There are evidences of it in Greek and Roman civilization. Though,
Michael Faraday demonstrated that mechanical energy could be converted into
electrical energy and vice versa, in 1831, development and use of electrical energy
began gaining momentum after 1890. By 1900, hydropower plants had become a
common source for obtaining electricity. In the early 19th century, progress in the
hydropower development was slow because of less efficiency in power transmission
over the long distance. The pace of hydropower development increased dramatically
after 1930. United States made a policy to invest in water based projects to create jobs
for unemployed and to stimulate economic recovery in the country when it faced
severe economic hardship in 1929. In the former Soviet Union, hydropower was
considered synonymous with industrialization and economic prosperity after 1920.
After World War II, leaders of African and Asian nations replicated the Western US
model to meet energy and water needs of their own countries and many large scale
hydropower projects were built in India, Pakistan and Egypt between 1950 and 1980.
None of the projects in US, former Soviet Union and India had the objective
of exporting energy to its neighboring to earn revenue for the country. In recent
decades, the concept of production of electrical energy has been changed. Now, it has
been traded between two or more nations after agreement upon certain terms of trade.
7
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
8
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
the former policy was replaced by the Hydropower Development Policy 2001 to
provide further impetus to active participation of private sectors.
9
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Nepal, lying between India and China against the impressive Himalayas
comprises of the most diverse climatic ranges and physical environment in the world.
From the Gangetic plains at about 70m altitude to the Mt. Everest at 8,848 m altitude,
there is only the distance of about 170 km. These slopes are the steepest slopes in the
world resulting high hydropower potential. Because of the existence of snow fed
perennial rivers, several tributaries and countless streams, Nepal is considered as the
World's second richest country in the gross hydropower potential. Gross hydropower
potential of Nepal is 83,000 MW out of which about 43,000 MW is techno-
economically feasible. Approximately 6,000 rivers and rivulets, with a total drainage
area of about 194,471 km2, flow through Nepal, 76% of this drainage area is
contained within Nepal. Drainage area of 33 rivers of Nepal is greater than 1,000
km2. Based on available hydrological data estimated annual runoff from the rivers of
Nepal is 220 billion cubic meters, with an average annual precipitation of 1530 mm.
In addition to surface water resources, Nepal is also endowed with extensive
groundwater resources. Groundwater is found in most of the Terai and in some mid-
hill valleys like Kathmandu and Dang. The minimum possible annual recharge is
estimated to be 5.80 billion cubic meters. Table 1.1 describes Nepal’s economic
hydropower potential relative to development size. (Source: Water Resources in
Nepal. S. K. Sharma)
10
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Identified MW GWh/yr.
Source: WECS estimate, 2000 (excludes micro, mini and small hydropower Source)
Saptakoshi 40 10.86
Karnali 7 24.00
Mahakali 2 1.125
Total 66 42.133
11
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
The annual peak power demand of the Integrated Nepal Power System (INPS)
in fiscal year 2011/12 is estimated to be 1,026.65 MW, with 448 MW power
estimated to have been shed. Out of the 578.65 MW of power actually supplied,
349.71 MW was contributed by NEA hydro, 5.3 MW by NEA thermal, 102.2 MW
by IPP hydro and the rest 121.44 MW was import. Compared to the preceding fiscal
year’s figure of 946.1 MW, the annual peak power demand of the INPS registered a
growth rate of 8.5%.
www.nea.org.np
12
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
13
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Donors and friends of Nepal are requested to come ahead in helping it in making best
use of these opportunities.
Nepal has given priorities for the use of electricity in transport, tourism,
industry and agriculture sectors. Special attention is provided to increase the load
factor of small and isolated generations through the use of electricity in domestic
industries. Considering high liquidity in the local financial market, efforts should be
made to channelize local resources in electricity sector through various initiatives
such as establishment of rural electricity fund, power development fund and
encouraging other financial instruments. The involvement of private sector in
generation is encouraging. The government is open to public-private partnership.
Hydropower is the only feasible and rational solution in solving the energy
crisis in case of Nepal. It is environment friendly and non-polluting system of energy.
Moreover, water being recurrent in nature's streams, it is a renewable source of energy
and causes no strain on non-renewable sources of energy like fossil fuels which are
not in abundance in Nepal, thus, reducing the dependency on them.
This source not only assists environment but also the economy, as no fossil
fuel is used. So, no imports are needed to be made which saves money. The cost of
this electricity is less than the electricity produced from fossil fuel and nuclear power.
The energy production value of the water doesn't deplete once it has been used,
meaning a number of cascade projects are feasible on the same river thus optimizing
the energy yield given the suitability of terrain.
Hydro turbines can convert at least 95% of the energy into electricity, thus the
system is very efficient. Hydropower plants provide benefits in addition to clean
14
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Our nation’s economy is seldom able to sustain the cost of construction of big
projects and almost inevitably requires foreign donors or loan investments. Also, it
needs to be realized that we may not be able to utilize the power produced from such
big projects immediately after project completion depending on the PPA. Small hydro
might be the solution which the nation’s private sector can also afford to invest in.
Another advantage with micro hydropower is that with a sufficient head the
hydro scheme can be quite compact and a small amount of water is enough to produce
the electricity needed for light and other equipment. Mini Hydropower causes less
environmental impact compared to big hydropower projects. They can be effective
tools to elevate the overall economic standards of a particular group of people.
15
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
16
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
CHAPTER 2
The project area lies in Lesser Himalayan zone. The Lesser Himalayan Zone is
bounded to the north by the Main Central Thrust (MCT) and to the south by Main
Boundary Thrust (MBT). Generally two types of sequences namely autochthonous
and allochthonous can be distinguished in this Zone throughout the Himalayas. The
both sequences of the Lesser Himalaya mainly have unfossiliferous, sedimentary, and
meta-sedimentary rocks such as slate, phyllite, schist, quartzite, limestone, dolomite,
etc., ranging in age from Precambrian to Eocene. There are also some granitic
intrusions in this zone.
17
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
CHAPTER 3
METHODOLOGY
18
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
CHAPTER 4
HYDROLOGY
4.1 General
In the case of Yankhuwa Khola, there are flow or rainfall records around
headwork. However there is processed long term stream flow data available in the
hydrological catchments for a gauging station established by Department of
Hydrology and Meteorology (DHM). Hence, care should be taken to predict the flow
available in the river. Other empirical methods used in case of ungauged river can
also be used to compute the flow.
The Yankhuwa Khola is a perennial and non-snow fed river. Yankhuwa Khola
19
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
is one of the tributaries of Arun River. The catchment area of the Yankhuwa Khola at
the proposed intake site is calculated to be 64.6 km2.The catchment area below
5000m is about 64.6km2. Geographically, the basin is located in the Bhojpur District,
Eastern Development Region of Nepal. The river bed is gently sloping towards west-
east direction.
20
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Parameters
Location Headwork
Precipitation data is needed for the analysis of surface runoff and to know the
nature of the catchment with respect to the river flow. The DHM is responsible for
the collection of all precipitation data throughout Nepal. There are more than 250
DHM precipitation stations throughout Nepal and station no. 1324 (Bhojpur), station
no. 1321 (Tumlingtar), and station no. 1325 (Dingla) are the nearest to the catchment
and is being used in this project. Details of meteorological station are presented in
table no 4.2 below:
21
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
For ungauged basin, the flow estimation methods are used to estimate the mean
monthly flow and flow duration curve. The various methods which is generally used
in the context of Nepal are listed below:
CAR method is the applied in case the considered basins are hydro-meteorologically
similar. Discharge at base station (proposed site) is obtained by multiplying available
long term data at the hydrometric station with the ratio of basin area of base station
and the index hydrometric station or Hydrologically Similar Catchment (HSC) i.e.
𝐴𝑏 𝐴𝑏 𝑃𝑏
𝑄𝑏 = 𝑄𝑜 ∗ 𝑜𝑟 𝑄𝑏 = 𝑄𝑜 ∗ ∗
𝐴𝑜 𝐴𝑜 𝑃𝑜
Where, Qb, Qo are the discharge at the base and index station respectively
Ab, Ao are the catchment area of a base and index stations respectively
Pb, Po are the annual average precipitation of base and index stations
respectively
22
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Discharge (m3/s)
23
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
10
Hydrograph for CAR method
9
6
Discharge
5 CAR
Hewa
4
3
CAR
2
Sabha
1
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Month
24
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
If the major data is on 15th of the particular month, the coefficient given in the
table is directly used. For other data of measurement, coefficient for the data is found
by interpolation.
25
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
26
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
27
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
28
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
8
Hydrograph for MIP method
7
5
Discharge
From
4 Nov
From Dec
3
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Month
29
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
It is developed for predicting river flows for catchment area larger than 100 km 2 of
ungauged river based on hydrological theories, empirical equations and statistics. In
this method, the total catchment area, areas between 5000 m to 3000m are required as
input. Flow contribution per unit area (km2) for 5000 to 3000m and from lower
elevations, i.e., below 3000m is assumed to be in different proportion during flood.
However, for long term average monthly flow, all areas below 5000m are assumed to
contribute flows equally per km2 area.
From WECS method, long term flow was calculated by using equation:
Qmean(month)=C *(Total basin area) A1*(Basin area below 5000m +1) A2*(Monsoon
wetness index)A3
Where Qmean(month) is the mean flow for particular month in m3/s, C, A1, A2, and A3 are
coefficient of the different months given in Table 3.8
The catchment area can be calculated from the topographical maps. The input data
required in the equation are total basin area (km2), basin area below 5000m (km2) and
the average monsoon precipitation (mm) estimated from isohyetal map.
30
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
C A1 A2 A3
31
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
The method was developed by WECS/DHM in 1990 for determining the hydrological
characteristic of ungauged catchment. This method is used to determine the
instantaneous peak flood, long term and mean monthly flow by using computer
software or manually. But in this project we have used excel spreadsheet.
32
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
JAN 0.850
FEB 0.725
MAR 0.641
APR 0.628
MAY 0.806
JUN 2.613
JUL 8.059
AUG 9.785
SEP 7.458
OCT 3.342
NOV 1.379
DEC 0.920
33
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
12
Hydrograph for WECS method
10
8
Discharge
Discharge
6 from
WECS
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Month
34
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
MIP derived
CAR derived CAR derived MIP derived from
MONTH WECS from Dec
from Hewa from Sabha Nov discharge
discharge
35
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
12
Hydrograph at intake
10
8
Discharge
6 CAR
derived
from
4 Henwa
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Month
36
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
37
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
10
8
Discharge
CAR1
6 CAR2
WECS
4 MIP 1
MIP 2
2
0
0% 20% 40% 60% 80% 100% 120%
Percentage of exceedence
38
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
We have selected the design discharge from MIP method as our design discharge. The
selection is done on the criteria that the WECS method uses empirical equation’s to
predict the long term flow and moreover, the method is reliable for catchments above
100 km2. The CAR method on the other hand is based on the conversion of actual
measured discharges of Hydrologically Similar Catchment (HSC) and hence more
reliable.
39
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Interpretation of observation.
Search for hydrologic probabilistic regularities.
Extraction of maximum information from hydrological data.
Presentation of hydrologic information.
There are three types of asymptotic distribution developed to fit the extreme
values like maximum values or minimum values. It is general practice to use
extreme value type I distribution also known as Gumbel’s distribution to fit the
flood discharges of various rivers. Gumbel (1941) proposed this concept. He
defined the largest of 365 days flow as the flood. According to him, probability of
y
40
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
y = (x-a)
a = x – 0.45005 x
= 1.2828 / x
y = 1.2825(x-x) / x + 0.577
y
p 1 e e
Y p ln ln 1 p
Noting that the return period T = 1/p and designating YT for the value of Yp,
commonly called the reduced variate, for a given T.
T
YT ln ln
T 1
T
YT 0.834 2.303 log log
T 1
yT y n
K where value of yn = 0.5453 and Sn = 1.148 are obtained from table for
Sn
n = 43.
Log Pearson type III distribution is extensively used in USA for frequency
analysis of annual maximum floods. In this method, the variate is first transferred
into logarithmic form base 10.
Steps
1. First transform the all of X values i.e. variate of random hydrologic series
into logarithmic form (base 10).
41
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Y = log X
2. For this Y series recurrence interval T is given by
YT = Y+ KTY
3. Calculate the coefficient of skewness.
Cs = N (z-z) 3/ ((N-1) (N-2)z 3)
4. Obtain the variation of KT= f(Cs, T) from the table for Log Pearson type III
distribution or by using the following formula and steps.
p = 1/T
1
w = √𝑙𝑛
𝑝2
2.51557+0.80285 𝑤+0.010328 𝑤2
z = w – 1+1.432788𝑤+0.189269𝑤2+0.001308 𝑤3
Steps
1. First transform the all of X values i.e. variate of random hydrologic series
into logarithmic form (base 10).
Y = log X
2. For this Y series recurrence interval T is given by
YT = Y+ KTY
3. Calculate probability of exceedence p by p = 1/T
42
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
2.51557+0.80285 𝑤+0.010328 𝑤2
z = w – 1+1.432788𝑤+0.189269𝑤2+0.001308 𝑤3
5. Now find YT = Y+ KTY, where the frequency factor KT for the normal
distribution is equal to z. So YT = Y+ zY
6. After finding the YT by above equation, find the XT = antilog (YT).
Comparision between Log Normal, Gumbel, Log Pearson for High Flood
Analysis
Estimated value
Time Period Observed value
Gumbel's Log Pearson Log Normal
43
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
The lowest standard error occurred in WECS method. But since the values of the
constants used in this method are not updated since a long time the method is not
much reliable. Hence we take Log normal distribution which has second lowest
standard deviation. i.e. Q100= 59.178 m3/sec is taken as 100 years design flood.
Information of low flow is needed to determine the maximum power that a run-of-
river plant can generate during the peak of the dry season. The minimum usable flow
in a stream determines the value of reliable firm power and then firm energy.
Knowledge of minimum stream flow is essential also for determination of minimum
water level that can goes down to the river at the intake. Therefore, Low flow analysis
is essential in the planning of hydropower in run off river and pondage run off river
modes. The duration curve of the long-term daily inflow series predicts the flow
duration for an average hydrological year. Individual dry and wet years would display
different flow duration characteristics. For a hydroelectric plant, sustained low flows
experienced in the dry years are critical to the operation resulting in nil energy
generation when the flow becomes less than the minimum permissible flow to avoid
considerable cavitations. In order to predict the likelihood of this occurring, a
probabilistic low flow analysis was carried out by analyzing the mean daily project
inflow time series the Yankhuwa Khola at the intake sites using the minimum
instantaneous flow series. In addition to the frequency analysis, regional approaches
WECS-DHM and DHM-2004 were also applied to estimate the likely hood of the low
flow values.
The regional prediction methods used in the study include followings frequency
distribution functions for prediction of extreme floods.
44
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
45
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
CHAPTER 5
5.1 Headworks
Headworks are all structural components to divert water from river and to
draw sediment free water in a hydropower projects. In hydropower projects, the
diversion work is generally constructed in boulder stage of river with steep gradient.
So, in river wide variety of sediment sizes are occurred in concentration during flood
time. Hydrology of Nepalese rivers comprise of high variation of flow during dry
season and wet season. Head works is constructed in the river to divert water in steep
river profile. So to overcome these issues, the headwork site should be carefully
selected constructed and wisely operated for sustainable hydropower generation.
Hence head works cover the structure from diversion weir to settling basin to achieve
the function of diversion and to draw sediment free water from the river to the project.
The main components of run of river head works with side intake are weir, intake,
under sluice, divide wall, flood wall, gravel trap, approach canal and settling basin.
The diversion works control the flow of water from the source river into the
headrace. They comprise a diversion weir (usually), an intake and sometimes river
training works. The diversion works are part of the head works, and serve the
following functions:
1. Maintain the design flow with nominal head losses during both
monsoon and dry seasons.
2. Prevent, or at least minimize, the bed load and other floating materials
(ice, timber, leaves etc.) entering the canal.
3. Safely contain peak flows in the river and away from the hydro system
so that damage is not caused to the structures.
46
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
The principle maintenance task associated with civil works is often the
removal of sediment and debris carried by the incoming water, which can cause
damage to the turbines. It is therefore, essential that the adopted intake design
prevents sand, bed load and debris from entering the intake as much as possible.
5.2.1.1 Weir
A weir is a structure built across a river to raise the river water and store it for
diverting a required flow towards the intake. If the major part or the entire ponding of
water is achieved by a raised crest and smaller part or nil part of it is achieved by the
shutters then it is called weir. If most of the ponding is done by gates and smaller or
nil part of it is done by the raised crest, then it is called Barrage or River Regulator. A
diversion weir is required at the intake only if adequate flow cannot be diverted
towards the intake during the low flow season. The weir may be temporary, semi-
permanent or permanent construction. As the weir receives the direct impact of a
flood, it is the most vulnerable civil structure so should be designed properly in
hydropower projects. While constructing weir, attention must be given to the
geomorphology of the river, and any changes that may be taking place. It should also
be noted whether the river is eroding, aggrading, or shifting its course. Possible future
change also should be taken into account.
47
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
capacity under sluice should be designed to pass flood water and high
sediment concentration. Divide wall separate the weir portion and under sluice
portion.
c. Height: The weir should be sufficiently high to create enough submergence
and driving head. The height should be such that the water level rises above
the upper edge of the intake mouth.
d. Operation: The weir profile should be such that movement of bed load is
possible and boulders can roll over it.
e. Stability: Weir should be designed to prevent from overturning, lifting or
sliding during the high flows and floods.
f. Seepage control: Proper arrangement of cutoff wall and clay blanket should
be designed as an integral part of weir to control seepage through weir.
g. Surface protection: The surface of the weir should be properly designed to
withstand the impact of heavy boulders. Heavy boulder lining, hard stone
lining, steel lining etc. are possible protection measure of the weir surface.
There are various factors that affect the elevation of the crest, but in our case,
diversion of water is the purpose and the height should be sufficient to pond the water
at a level that can facilitate design flow in the intake. The height of the weir is
governed by the height of intake sill, depth of intake orifice and depth of the river at
the intake site.
Length of weir
The length of the weir depends upon the width of the waterway at the intake site.
Crest length should be taken as the average wetted width during the flood. The
upstream and downstream should be properly examined for the protection
consideration.
The rise in water level on the upstream of the structures after construction of the weir
is called afflux. Fixation of afflux depends on the topographic and geomorphologic
48
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
factors. A high afflux shortens the length of the weir but increases the cost of the river
training and river protection works. For alluvial reaches it is generally restricted to 1
m but for mountainous region it may be high. The water way must be sufficient to
pass high floods with desired afflux. A weir with crest length smaller than the natural
river width can severely interfere the natural regime of flow thus altering the
hydraulic as well as the sediment carrying characteristics of the river.
• lf weir across part of the river length is sufficient, then it should not be
extended across the entire width. Apart from adding extra cost it also encourages
sediment deposition upstream of the weir.
• The weir height should be as low as possible (i.e. Weir crest level = h, just
sufficient to maintain the water level in the intake). This makes the structure
more stable, less susceptible to flood damage and also minimizes sediment
deposition.
• The design of weir includes computing the elevation of weir crest, length of weir,
computing the forces acting on the weir and checking the safety of the weir from all
aspects like overturning, sliding, crushing etc.
• The height of the crest affects the discharge coefficient and consequently the water
head above the weir as well as the back water curve.
• The elevation of the weir crest has to be fixed such that the design flood is safely
discharged to the downstream without severe damage to the downstream.
• The elevation of the weir determines the head of the power production.
• The height of the weir crest affects the shape and location of the jump and the design
of the basin.
49
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
• The height of the weir crest affects the discharge that can be diverted into the canal.
5.2.1.2 Spillway
Shape of spillway
Ogee spillway is modified type of vertical drop spillway which has a control weir that
is ogee-shaped (S-shaped) in profile. It is an improvement upon the free over fall
spillway and is widely used with concrete, masonry, arch and buttress dams. Ogee
spillway works effectively only on one particular head called designed head. If this
exceeds lower nappe will separate from spillway profile causing cavitation and if it
decreases, extra positive hydrostatic pressure will be created causing reduction in
discharge. The discharge capacity of Ogee shaped spillway is maximum as compared
to that of other type of weirs. Ogee shaped weir increases hydraulic efficiency and
prevent cavitation.
50
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Location of spillways
Spillways are required in headrace canals to spill excess flows during the monsoon
and in case of obstruction in the canals. Similarly, spillways are also required at the
fore bay to spill the entire design flow in case of sudden valve closure at the
powerhouse.
The excess flows that are discharged via a spillway should be safely diverted into the
streams or nearby gully such that they do not cause any erosion or damage to other
structures. Sometimes, this may require the construction of a channel to the natural
water course. Locating spillways close to a gully will save the cost of channel
construction.
3. Design discharge for spillway should be appropriate (1000 years return period is
taken for design of large dams).
4. As the flow velocity is very high through the passage of the spillway, its surface
should have sufficient erosion and cavitation resistance capacity.
51
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
the intake to flush out the sediments deposited in front of it and thus controls the bed
levels in its approach area. Hydraulic design of the under sluice shall consist of
determining its location, length, profile and opening size. The under sluice shall be
provided in continuation with the overflow section, separated from the latter by a
divide wall.
1. The length shall be capable of passing at least twice the diverted discharge to
ensure efficient flushing capacity.
3. The length shall be capable of passing fair weather freshets and low monsoon
floods for obviating overtopping and/or operation of crest gates.
4. The crest and upstream floor levels are generally kept at lowest bed level of the
deep channel of the river.
5. The bed load is kept off by intake sill in front of the sluice.
6. Solid matter that is deposited in front of the sluice can be led off to the downstream
side by continuous or intermittent flushing after a sluice has been opened.
7. The under sluice may consist of one or more bays and a single bay with smaller
opening is preferred for small river flows. The bay opening shall be sized to pass
the largest possible boulders brought along by the river. Generally, the minimum
opening shall be twice the boulder size expected in the river stretch in the vicinity
of the head works.
52
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1. It separates the under-sluices from the weir proper. The crest level of the under-
sluices is lower than that of the weir proper, so these two are separated by divide
wall.
2. It helps in providing a comparatively less turbulent pocket near the canal head
regulator, resulting in deposition of silt in this pocket and, thus, to help in the entry
of silt free water into the canal.
3. Divide wall may keep the cross currents, if at all they are formed, away from the
weir. Cross currents lead to vortices and deep scours, and therefore, prove
hazardous to weirs.
The divide walls can be designed as cantilever retaining walls subjected to silt
pressure and water pressure from the under-sluices side. For the worst case, the design
should be checked for full silt pressure on the pocket side with equal water on two
sides during low floods, and also for maximum differential water-head, when full
discharge is passing through the under-sluices and no discharge is passing the weir.
The value of differential pressure may be taken, arbitrarily, as 1.0 m for water head
and about 2.0 m for silt pressure.
53
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
The entrances to intakes and dam outlets are generally covered with trash
racks to prevent the entry of debris, ice, etc. into the conduit. These racks are nothing
but bar screens, made from steel bars spaced at 5 to 15 cm center to center (in both
directions) depending upon the maximum size of the debris required to be excluded
from entering the conduit. The velocity of flow through the rack is kept low
(generally less than 0.62 m/s), so as to minimize losses. The floating debris, ice, etc.
which are stopped by the racks and thus get collected on them, are removed by
manual labor when required.
When the flow is spilled through the Spillway, the potential energy possessed
by the flow is converted into the kinetic energy. This excessive kinetic energy should
be dissipated so that it could not cause any damage downstream of the dam. Energy
dissipation below the overflow sections of river diversion structures of run-of-river
hydropower projects shall be achieved through one of the following structures:
Stilling basins may be defined as the structure in which the energy dissipating action
is confined. If the phenomenon of hydraulic jump is basically used for dissipating this
energy, it may be called a hydraulic jump type stilling basin.
The stilling basins shall consist of an apron provided with one or more of the
following appurtenances to make them more economical:
a) Chute blocks
b) Baffle blocks
c) End sills
The auxiliary devices like chute blocks, baffle piers, sill and dented sills may be used
as additional measures for controlling the jump.
54
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Chute blocks
They are kind of serrated device and provided at the entrance of the stilling basin. The
incoming jet of water is furrowed and partly lifted from the floor, producing a shorter
length of the jump than what would have been without them. They also help in
stabilizing the flow and thus improve the jump performance.
According to the Froude number, the stilling basin may be U.S.B.R. stilling basin –II
(Fr > 4.5) and U.S.B.R basin IV (Fr lies between 2.5 to 4.5).
The provisions of the sheet piles, cutoff walls, impermeable concrete floor and
protective works have been designed considering various factors as presented in the
detailed design of the weir structure. The parameters under considerations are
→ Seepage Pressure
→ Erosion characteristics
The main forces which are acting on the weir when it will be operation are water
pressure, uplift pressure, silt pressure and weight of weir.
Weight of weir
The weight of weir and its foundation is the major stabilizing or resisting force. While
calculating the weight, the cross section is spitted into rectangle and triangle. The
weight of each along with their C.G. is determined. The resultant of all these forces
55
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
will represent the total weight of dam acting at the C.G. of dam. The sectional area of
each part is multiplied by unit weight of concrete to obtain the weight of that part.
The weir is designed with ogee profile for spilling over its length. Hence weight is
calculated by knowing its section and multiplying by its unit weight.
Hydrostatic Pressure
It is the largest external force acting perpendicular on the surface of the weir. It has
the largest capacity for disturbing the stability of the dam. Its magnitude is given by:
P = 0.5*γ*H2 *b
Where, γ= unit weight of water, H=depth of water, b=width of the weir surface
Since pressure distribution diagram due to water is triangular, the value of the total
horizontal pressure due to water will be area of the triangle. The pressure P acts at
C.G. of the pressure distribution triangle i.e. H/3 from the base.
Uplift pressure
Water seeping through the pores, cracks and fissures of the foundation material,
seeping through the weir body itself and seepage from the bottom joint between the
weir and its foundation exerts an uplift pressure on the base of the weir. Uplift
pressure tries to tilt or topple the weir, a part of the weir would get neutralized by
uplift pressure and thus net foundation reaction due to vertical forces will be reduced.
Intensity of uplift pressure is maximum at upstream end of the weir and less at
downstream end of the weir. The analysis of seepage is done using Khosla’s theory. It
is the mathematical solution of the Laplacian equation and it is easy and accurate
method for seepage analysis.
56
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Silt pressure
Silt gets deposited at the bottom, along the upstream face of the weir. The silt exerts
the horizontal and vertical pressure as exerted by the water. So, flushing of the silt
should be done regularly to reduce its effect of destabilizing the weir. It is done by the
use of under sluice gate. The silt pressure is given by the relation:
Psilt=0.5*γsub*H2 *Ka
Where, γsub = submerged unit weight of silt, H = depth of silt deposited and Ka =
coefficient of active earth pressure and is given by,
(1−sin ∅)
Ka= (1+sin ∅) , ∅ =Angle of internal friction of silt. The silt pressure force also acts at
If the resultant of all the possible forces (internal and external) acting on the dam cuts
the base of the weir downstream of the toe, the weir would overturn unless it can
resist tensile stresses. In real practice, such condition will not arise because the weir
will fail much earlier by compression. To safeguard the weir against overturning, the
resultant of the forces should never be allowed to go downstream of the toe. The ratio
of resisting moment to the overturning moment about the toe is the factor of safety
against overturning and it should be greater than 2.
Both cement concrete and masonry are very weak in tension. So, from safety point of
view the tension is not allowed to be developed in the dam anywhere. The minimum
𝑉 6𝑒
compressive stress in the weir is (1 − ) 𝑒. The nature of this stress remains
𝐵 𝐵
compressive till value of e is less than (B/6) .When e exceeds (B/6) the value of
𝑉 6𝑒
(1 − ) becomes negative. The negative sign shows that the nature of this stress is
𝐵 𝐵
57
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Sliding
In this mode, the weir as a whole slides over its foundation or one part of the weir
may slide over the other. Sliding will occur when the net horizontal force above any
plane in the weir or at the base of the weir exceed the frictional resistance developed
at that level. For safety, the factor of safety should be always greater than 1.
Design summary:
The weir is a concrete gravity type non-gated overflow weir. The ogee shaped
diversion weir is designed to divert the design discharge of 16.16m3/s in normal flow
condition through the side intake situated on the left bank. The diversion weir is 130m
long and 3.9m above the river bed. The crest level of the weir is set at EL. 487.81m
and the bottom of the weir is set at EL. 483.91m. The overflow weir is designed to
pass the 100 year flood of 2589.80m3/s. The high flood level (HFL) corresponding to
100 year return period flood is determined at 490.06m. The surface of the overflow
weir will be lined with high strength concrete to prevent erosion during monsoon
floods. Rock foundation is placed on the upstream part of the diversion weir to
prevent the river bed from scouring.
The under sluice is designed for 10% of design flood. It is 10m wide in total with the
provision of 2 gates of 5m each. The under sluice gate is designed for passing
boulders and other bed load. 2 bays of 5m under sluice is provided. The crest level of
the under sluice is kept at EL.483.91m. The under sluice which is 10m long is
separated from the weir portion by thick concrete divide wall of 0.5m. There are 2
openings and width of each opening is 5m. Lining is done at side walls and at bottom
to protect erosion of concrete.
58
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Intake is the structure to obtain the required quantity of water from the river or the
reservoir for the different engineering purpose such as irrigation, power generation,
and water supply, etc. It is a structure to divert water into a conduit leading to the
power plant. An intake structure should ensure good quality of water in proper
quantity and a control over the supply of water. For this purpose, arrangements of
weir and intake structure must be chosen to evacuate necessary amount of water at
any regime to the channel. The peak discharge must be safely evacuated without any
damage. The intake should be provided with trash racks to prevent the entry of debris
into the conveyance canal and to avoid the possible damage to it.
1. The course of the river should be relatively permanent at the intake site, i.e.
the river should not change its course at the intake location at the time.
2. The river should not have a large gradient at the intake site.
3. As far as possible the intake should be placed at the side of rocky outcrop or
large boulders for the stability and the strength.
4. The intake should be on the concave bank of the bend for good performance.
This limits sediment deposition at the intake area and also ensures the flow
availability during the dry season.
5. Generally intake is provided 2-10 m upstream of the diversion weir and the
crest of the intake is raised 1-1.5 m bed of the diversion structure.
6. In case there is a confluence of two rivers in the selected site, the intake should
be located downstream of the confluence to take advantage of the flow of both
rivers.
Generally, one of the following types of intakes shall be used for run-of-river
hydropower projects: (a) Side intake (b) Frontal intake (c) Drop intake
59
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Side intake is a structure built along a river bank and in front of a canal to divert the
required water safely. They are simple, less expensive, easy to build and maintain.
Side intake consists of trash racks, intake opening, gate slot, breast walls, piers and
service platform.
60
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Protection work
Protection works are the river protection and river training works to safeguard the
intake structure against flood, debris and sediment. Trash racks are used to prevent the
entry of trash matters in the canal. To prevent adverse effect of seepage, sheet pile is
used inside the ground below sill.
Design summary:
The intake structure is designed for 20% more than design discharge for flushing
purpose, i.e. Qdesign(intake) =1.2Qdesign. The intake is designed considering free flow
submerged condition at normal flow and gated condition at flood discharge. The sill
height of the intake is raised 1m above bed level, 2-numbers of gated structures are
provided with dimension as 1.3m*0.7m. 50mm coarse trash rack opening is provided
with thickness 10mm.
The design of the intake and trash rack is shown in Appendix –II and drawings are
provided in Appendix –VI.
Gravel trap, as the name denotes are designed to trap gravel that enters the intake
along with the diverted flow. It is constructed close to the intake in order to prevent
gravel from getting into approach channel. In the absence of this structure, gravel can
settle along the gentler section of the head race or in the settling basin and reduce the
discharge capacity of canal and ultimately cause the wearing and choking of the
turbine units. Main function of the gravel trap is to collect the bed load, smaller than
the trash rack opening size, entering through it to the approach canal. Gravel trap’s
location is governed by the site conditions, availability of flushing head and gravel
carrying capacity of the approach canal. Its dimension depends on the flow velocity,
gravel size and specific density of the gravel and it should be sufficient to settle and
flush gravels passing from the coarse trash rack. Gravel trap is generally designed to
collect maximum of 12 hours gravel deposit. A flushing arrangement associated
within the gravel trap is operated to flush out the collected gravels to the river.
61
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Flushing frequency is less during the low flow periods whereas continuous flushing is
recommended during the monsoon. A gravel trap may be equipped with an overflow
spillway. The gravel trap traps the coarse particle greater than 2 mm size.
Protection works
Gates are used to control the flow across the gravel trap. Flushing gates are used to
flush the settled matters. Flushed water and the excess water are safely diverted to the
river using open channel.
a. Gravel trap should be located at a safe place but as close to the intake as
possible or sometimes even within the intake so that debris is not carried a
long distance into the waterways.
b. Flow velocity must not exceed the upper limit so as not to allow suspended
again as boundary friction is predominant for short width, the effective length
may be taken only 85% of provided length. To be able to trap particles greater
than 2 mm diameter, the velocity in the gravel trap should be limited to 0.6
m/s.
c. The length of gravel trap should be at least three times the width of headrace
canal or 2 m, whichever is larger.
d. Generally, continuous flushing is adopted for gravel trap as the sediment load
is high. Gates are used to control flow at flushing orifice at inlet. Sufficient
bed slope and cross slope is required to make the flushing effective. The
concentration approach, which is modern and rational approach, is used for the
design.
e. Continuous flushing system is used in the gravel trap which works
continuously in the monsoon season and can work as intermittent flushing at
the time of low flow. 10% water is used for flushing purpose.
f. Gates are used to control the flow across the gravel trap. Flushing gates are
used to flush the settled matters. Flushed water and the excess water are safely
diverted to the river using open channel.
62
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Design summary
Gates are used to control the flow across the gravel trap. Flushing gates are used to
flush the settled matters. The dimensions of gravel trap are length 5m, width 2m and
height 2m. Length of the inlet zone is 1.27m with inlet angle 11 degrees and for outlet
zone the length is 0.5m and outlet angle 27 degrees. Flushed water and the excess
water are safely diverted to the river using open canal. The opening of flushing canal
is of width 0.5 m and depth 0.2 m in size and the slope is 1 in 30. Fine trash rack is
provided in gravel trap. The thickness of bars is 5mm, spacing between bars is 50mm
and inclination angle is 70 degrees. Design calculation and drawings are presented in
Appendix –II and VI respectively.
The particles escaped from the gravel trap, if allowed to flow through
penstock pipe and turbine, cause abrasion of such units and reduce efficiency as well
as durability. In addition, problem of clogging is always present due to such particles
in turbine units. So, in the finer particles escaped from gravel trap are to be removed
before entering into penstock. For this purpose, a structure is constructed which is
called ‘Settling basin’. Settling basin is the structure to remove suspended sediments
from the conveyance water for power plant.
The main principle of the design of settling basin is to reduce the mean
velocity of the flow, by increasing the cross sectional area (widening its width and
lowering the floor). The basic principle of settling is that the greater the basin surface
area and the lower the through velocity, the smaller the particles that can settle. A
settling basin has a significant larger cross sectional area than the headrace canal and
therefore the flow velocity is lower which allows the settling of the suspended
materials. Settling basins can remove suspended inorganic particles ranging from sand
(2 mm in diameters) to silt (0.002 mm in diameter), depending on basic design.
For more reliable operation, more than one chamber is employed. It will not
interrupt whole system when it is to be stopped for maintenance. To ensure uniform
flow, transitions are provided at inlet and outlet. Both height and width wary
gradually in inlet transition and width varies in outlet transition. Flushing of deposited
63
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
matters is essential for smooth operation of settling basin. The lateral and longitudinal
slope may be provided for this purpose. There must be control of flow in and from
settling tank. For this purpose gates can be used. The flushed water and the excess
water are safely diverted to the river using open channel.
Storage capacity
The basin should be able to store the settled particles for some time unless it is
flush out.
Flushing capacity
The basin should be able to flush all these settled particles along with the
incoming flow in the basin by opening flushing gates or valves.
64
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
granite, basalt, gneiss, etc. concentration of sediments with the river flow,
required removal percentage of suspended sediments.
6. The geometry of inlet, the width of basin and any curvature must be such as to
cause minimum turbulence which might impair the efficiency.
7. Concentration approach is used to design it. Trap efficiency is selected as 90%
removal of 0.2 mm sized sedimentary particles. Vetter’s equation is used for
efficiency calculations. Hazen’s equations and various charts are used to
compute the transit velocity and the settling velocity.
Protection works
Gates are used to control the flow across the gravel trap. Flushing gates are used to
flush the settled matters. Flushed water and the excess water are safely diverted to the
river using open channel.
Design summary:
Settling basin is designed following standard practices. Camp’s equation and Shield’s
graph are used to compute the transit velocity and the settling velocity. The design
discharge for settling basin is taken as 1.32m3/s. Two chambered settling basin of
height 1.3m and 35.7m length including transition length are provided. It can settle
particles greater than 0.2mm in size. Inlet transition is 1.9m long with inlet angle 15
degrees and outlet transition is 3.8m long with outlet angle 30 degrees. Two flushing
canals of size 0.5m width and 0.2m depth are provided. Flushing discharge is taken to
be 20% of Q. Efficiency of the basin is found to be 92% as per vetter formula. Detail
design of settling basin is presented in Appendix – II and drawing is shown in
Appendix – VI.
The conveyance system used to convey the water diverted from the intake to
the settling basin of inlet chamber is termed as headrace canal. Hydropower plants
65
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
exhibit a great deal variety in water conveyance system. A high head diversion plant
is generally associated with tunnel to divert water where as a medium head to low
head diversion plants generally employ canal diversion. Geology, topography and
hydrology are major factors to select such options. For small plants with low heads
intra basin diversion having fairly straight reaches of river, canal is the best option.
Headrace has to convey extra discharge for continuously flushing the settling basin.
a. The canal alignment should be sufficiently diverted away from the river so
that the risk of flood damage is minimum.
b. The alignment should be along the level to slightly sloping ground, pass
through stable terrain and follow the shortest reasonable route with a
minimum crossings and a minimum of head loss and minimum seepage loss
because loss in head or discharge is the loss in power production.
c. From earthwork point of view, the alignment should be selected to balance cut
and fill as far as possible.
A power canal is the canal, which feeds water to a hydropower plant. The flow in
canal is open channel flow i.e. non-pressurized flow. Manning’s equation is the most
widely used formula in open channel flow. From economic point of view, size should
be smallest possible and channel section should be most economical. But, from
constructional feasibility the most economical channel section obtained by
minimizing perimeter may not be always economical. Size and bed slope have inverse
relationship. So, choice of bed slope is dependent on the size of canal.
66
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
The velocity should be non-scouring and non-silting. To get small sections, a high
velocity which does not scour the lining material is usually desired but to save head, a
mild is preferred. The slope is limited by non-settling criteria. Tractive shear approach
is always used to ensure sufficient shear stress to cause scouring of particle
transported by it. The shear stress induced by water on the particles should be greater
than critical tractive shear stress of the particles.
𝑑
For d>6mm, the above relation implies, R*S = 11
The alignment of the canal is selected to ensure maximum stability as far as possible.
As the canal follows the contour and the area is flat at most of the sections, not heavy
protection works would be required.
Design summary:
A rectangular canal from intake to gravel trap is 79.75m long, 1.5m wide and 1.1m
high with freeboard 0.3m. Feeder canal from gravel trap to settling basin is 44.89 m
long, base width is 1.5m and depth is 1.m. Power canal is 897.28m long, 1.5m wide
and 1.1m high. As the canal follows the contour and the area is flat at most of the
sections, not heavy protection works would be required. All the canals are concreted
and are opened type. Detail design of the canal is presented in Appendix – II and the
drawings are shown in Appendix – VI.
67
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
5.10 Forebay
a. The forebay has been designed for storing the water required for running the
turbine for 2 minutes.
b. Stored water is utilized while starting the turbine.
c. The transition canal is provided for lowering the velocity gradually.
d. Forebay is constructed immediately before the inlet of the penstock pipe and
started at the end of the headrace canal.
The forebay is located at a flat area which has been used as the cultivate area. The top
of the structure is above ground level. The downhill is provided with retaining
structures to ensure its stability. The uphill side of it is provided with catch drain. The
excess water from the forebay is allowed to spill form the spillway structure
constructed on it. This water is safely discharge to the river using an open channel
constructed for the purpose. Gates are used at its inlet and outlet for its safe operation
68
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Design summary:
Forebay is designed following standard practices. The design discharge for forebay is
taken as 1.32m3/s. Forebay of width 4m, height 3.6m and 24m length are provided.
Inlet transition is 4.67m long with inlet angle 15 degrees. Two flushing canals of size
0.5m width and 0.2m depth are provided. Flushing discharge is taken to be 20% of Q.
Detail design of forebay is presented in Appendix – II and drawing is shown in
Appendix – VI.
5.11 Penstock
A penstock is a pipe that conveys the flow from the forebay or surge tank to
the turbine. The potential energy of the flow at the inlet chamber is converted into the
kinetic energy at the turbine of a hydropower plant via the pipe known as penstock.
Water flows under pressure in the penstock. It has to bear a very high pressure caused
due to water hammer effect at the sudden closure of the gate by governing mechanism
of the turbine. The thickness should be sufficient to resist hoop stress developed by
water hammer pressure and normal pressure not exceeding the allowable stress.
Penstock alignment should be straight to avoid head loss at bents and the extra cost of
anchor block unless it is mandatory by site condition. The penstock may be embedded
or exposed as per topography, location of inlet chamber/ surge chamber, power house
and construction easiness etc. The penstock alignment should start where the ground
profile gets steeper.
69
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
hm = Vc*(Va/g)
𝑘 1
Va = velocity of wave = √ 𝜌𝑚 ; km = √ 1 𝐷
( + )
𝑘 𝑡𝐸
D= diameter of penstock
T = thickness of penstock
= density of water
4. If the penstock has to feed more than one turbine, it should be decided
considered whether to use independent pipes in number equal to the number of
turbine or to use one pipe and bifurcate it at turbine inlet. Length from inlet
chamber to powerhouse, construction feasibility, reliability transportation and
fabrication feasibility are some important factors to be considered for this.
5.11.1 Optimization
The penstock pipe usually constitutes a significant portion of the total hydro
construction cost. Larger size means higher cost and smaller size means increased
head loss. So, there is always an optimum size of penstock for which the total cost of
loss and the material is minimum. To seek this size, optimization technique is used. It
involves a careful choice of pipe material, an economical diameter such that the head
70
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
loss is within acceptable limits, and wall thickness so the pipe is safe for the design
head and any surge effect that may result from sudden blockage of the flow.
Penstock is very sensitive structure and its failure is of fatal nature. Exposed penstock
is susceptible to temperature stress and hence, should be provided with expansion
joints. Anchor blocks are used to resist vertical and horizontal forces in the penstock.
They prevent yielding of penstock. Expansion joints are provided adjacent to them.
To support at intermediate locations and prevent bending stress, slide blocks are used.
The inner surface of penstock is galvanized and the outer surface is frequently painted
to prevent from corrosion. Frequent checking should be carried out for the safe
operation.
Design summary:
One penstock of diameter 0.8m, length 781.46m and thickness of 8mm is provided.
The total cost of penstock is NRs. 3452150.54. It is partially buried. The penstock is
bifurcated at the just upstream of powerhouse. For first bifurcation, the length and
diameter are 11m and 0.6m respectively, then length is 22m and diameter is 0.6m and
Detail design calculation and drawing are presented in Appendix – II and VI
respectively.
71
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
bends. Support piers are short columns that are placed between anchor blocks along
straight sections of exposed penstock pipe. These prevent the pipe from sagging and
becoming overstressed. However, the support piers need to allow pipe movement
parallel to the penstock alignment which occurs due to thermal expansion and
contraction.
Anchor blocks and support piers are required at the following locations:
Water flowing under pressure when diverted from straight path exerts pressure as the
bends. To resist various forces these blocks are designed. First the structures are
tentatively sized and the various forces that act on them are resolved. The minimum
calculated block size that is safe against bearing, sliding, and overturning is accepted.
The design process includes little iteration. Various forces that can act on anchor
blocks and support piers are:
72
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Design summary:
12 numbers of anchor blocks are used. Design calculation and drawing are presented
in Appendix – II and VI respectively.
Mechanical joints either expansion joint or bolted sleeve type coupling is used in both
exposed and buried penstocks to accommodate the longitudinal movement caused by
the temperature changes and to facilitate the construction. The joints shall allow for
movement where differential settlement or deflections are anticipated. Expansion joint
permit only the longitudinal movements. Expansion joints should be provided just
below the anchor block. Length of the expansion joints = α∆tL.
73
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1. Machine hall
It is a room in which the generating sets are usually arranged in a single line,
the orientation of which will be determined according to the arrangement of the
intake or penstock and of the tailrace.
It mainly depends on the discharge, head, type of turbine and generator, number of
units and the general arrangement in the power house. Sufficient clear space should be
available for installation of various components and for maintenance purpose.
Height of the power house is fixed by the dimensions of lower turbine block and its
superstructure. Height of the lower turbine block from the foundation to the floor of
the machine hall is to be determined by the thickness of foundation plate, dimensions
of the turbine. The height of the power house should be sufficient for the installation
of turbine, generator and shaft and gear mechanism. There should be sufficient space
74
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
for removal and overhaul of any of the components without disturbing other
components. Sufficient clear space is also provided for crane operation etc.
Design summary:
Power house is semi underground type. Length, width and height of the power house
are 31m, 12.5m and 16m respectively. Design calculation and drawing are shown in
Appendix – II and VI respectively.
5.13.4 Tailrace
Tailrace is the final civil structure that conveys the design flow from power house
back to the river where it is disposed off. Open channels or pipes can be tailrace
structure.
Often, inadequate attention is given to the design and construction of the tailrace since
the flow at this stage does not contribute towards power production. However, such a
practice can result in inadequate depth of the tailrace pit or erosion of slopes, which
could threatens the powerhouse structure.
Design criteria
Design of the tailrace canal is similar to that of headrace canal. Since head loss does
not need to be minimized a higher velocity can be allowed in tailrace channel. Note
that at higher velocities higher grade of concrete is required to resist erosion.
Reinforced concrete may become economical for a steep channel. Ideally the
discharge should be disposed off over rock or large boulders.
Design summary:
The bottom width of the rectangular tailrace canal with bed slope 1 in 600 is 1.5m and
the height of canal is 1m and freeboard of 0.3m is provided.
75
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
5.13.5 Turbine
Turbines are machines which convert kinetic energy into mechanical energy and
transmit it to the generator through direct coupling of shaft to it which in turns
converts mechanical energy into electrical energy. Based on the energy conversion,
turbines are classified as impulsive and reactive turbines.
Impulsive turbine
It is a turbine in which the water entering the runner possesses kinetic energy only i.e.
in this case, the pressure is atmospheric pressure at the inlet and outlet of the turbine.
The available kinetic energy is converted into mechanical energy. E.g. Pelton and
Turgo turbine.
Reaction turbine
It is a turbine in which the water entering the runner possesses pressure and kinetic
energy. As the water flows through the runner, the water is under pressure and
pressure energy goes toe changing into kinetic energy. This type of turbine is always
enclosed by an airtight casing and the runner and casing is completely full of water. It
changes kinetic and potential energy into mechanical energy. E.g.: Francis, Kaplan
turbine.
Design criteria
The flow variation is very high in Nepalese rivers and single turbine may not work in
dry season mainly due to very less flow in dry season compared to the design flow.
As per thumb rule, turbine does not rotate if the flow through the turbine is less than
2/3 of the rated discharge i.e. design discharge for the turbine. Even though the
76
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
turbine rotates, the efficiency will be reduced considerably at low flow less than 2/3
of the rated discharge.
Selection of suitable type of turbine for the project depends upon several factors like
head, discharge, power production, load condition and corresponding efficiency,
quality of water, tail water level, size, construction feasibility etc.
77
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Pelton 4 – 70
Francis 60 – 400
For medium high to medium low heads and normal quality of water, Francis turbine is
suitable. Turbine is designed based on the specific speed (Ns), which is the speed of
the geometrically similar (identical in shape, blade angles, gate opening etc.) turbine
that would develop unit power under a unit head. For specific speed between 60 to
400 rpm, Francis turbine is suitable. Since, reaction turbine is susceptible to
cavitation; setting of turbine is made based on the cavitation criteria. A draft tube is
always provided with the reaction turbine to receive the pressure head at the outlet of
the turbine. Efficiency of the Francis turbine decreases substantially at part load
operation. For runoff river plants, discharge of the river becomes lower than the
design discharge of the plant. So, part load operation is essential. If a Francis turbine
is allowed to run at part load for long time, cavitation become more serious. Thus,
these criteria should be kept in mind while designing the turbine.
78
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Design summary:
For Yankhuwa Khola HP, Pelton Turgo turbine is selected. Based on the graph
between the rated discharge and net head i.e. Q rated vs. H, the turbine type is
selected. Also because of head of 106.651m head we have selected Pelton turbine.
Discharge variations in the river would happen as per FDC. The total installed
capacity is 823.165KW. Two turbines are used in the power house. Diameter of each
of the turbine is 1m.
5.13.6 Generator
5.13.7 Exciters
The poles of the rotor have to be fed with field current, which is achieved through
excitation system. This is known as a static excitation scheme. The main requirement
of the exciters is the reliability with a steady and stable excitation current. The whole
excitation system is made automatic achieve quick and accurate control.
The generator cooling can be achieved by air circulation through the stator ducts. This
may be closed circuit air cooling system which feeds air to the blades of fan provides
on the rotor. Cooling by water is the common process. There is a lubrication
arrangement to provide lubrication to the bearing.
79
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
5.13.9 Transformer
The generator voltage (11 KV) has to be step up to the transmission voltage level
(132KV) to minimize loss. This is achieved by the use of step up transformer. These
transformers are oil filled for insulation purpose as well as for cooling purposed. A
specially designed firefighting equipment is always included at the transformer site.
For surface power stations, outdoor locations are common. The numbers of
transformer may be as many as the generating units.
The hydroelectric station has a centralized control for its various components. The
entire system is controlled from the control room. The control includes machine
starting and stopping, machine loading and frequency control, generator and system
voltage control, machine running supervision and hydraulic control.
5.13.11 Switchyard
The term switchyard is a general term applied to all the variety of the apparatus in the
power house employed for making and breaking the circuit. It may consist of
switches, isolators, circuit breakers. The cost of switchgear depends upon the cost of
bus bar voltage. The size of the switchgear assembly depends upon the individual
machine size.
To evacuate power from the project, the project will construct single circuit 132 kV
transmission line with different type conductor from power house to distribution area.
80
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
APPENDIX – I
HYDROLOGICAL
CALCULATION
81
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1. DISCHARGE CALCULATION
1.1 Average Discharge of Sabha Khola
Location Tumlingtar
Latitude 27°18’20”
Longitude 87°13’15”
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1981 4.74 3.96 3.68 9 10.7 17 38.9 49.9 32.8 11.6 7.8 5.77
1982 4.73 4.44 4.15 6.17 11.2 26.1 64 43.1 32 15.1 11.3 8.03
1983 6.05 4.92 4.27 4.51 26.5 33 70.1 49.7 53.9 24.6 13.5 8.8
1984 6.52 5.8 4.63 9.27 28.4 29 69.3 39.9 58.7 23.3 14.4 9.47
1985 6.99 6.25 5.55 6.28 18.1 54.5 85.4 65.8 59.4 25.85 15.9 9.43
1986 6.56 5.01 4.39 7.27 8.96 27.7 46.9 50.8 52 28.4 12.7 7.92
1987 5.64 4.46 5.5 7.06 10.6 19.8 48.3 59.2 77.6 39.3 18.7 10.1
1988 7.07 5.92 5.97 6.55 11.7 21.4 52.4 80.5 67.3 28.8 12.8 8.53
1989 6.96 5.56 6.36 5.21 11.8 27.7 54.1 63 74.4 25.1 16 10.4
1990 6.91 6.43 6.68 9.16 23.1 35.55 50.45 70.65 67.55 24.2 13.5 8.68
1991 7.09 4.91 4.53 7.42 15 43.4 46.8 78.3 60.7 23.3 11 6.96
1992 6.38 5.11 4.06 6.61 9.53 22.9 65.5 52.8 43.3 34.6 12.55 7.38
1993 5.67 5.31 3.58 5.79 18.4 23.1 44.8 77.5 46.3 37.2 14.1 7.79
82
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1994 6.2 4.62 5.05 5.41 10.2 34.5 41.2 68 73.5 24.9 13.8 10
1995 7.5 6.73 5.8 5.08 22.8 51.8 52.5 68.4 49.3 25 16.4 11.2
1996 8.1 4.75 3.96 4.02 32.9 67 77.9 45.32 35.5 20.3 11.2 8.95
1997 7.51 6.79 6.2 6.46 10.2 24.4 23.6 31.5 30.8 17 11.6 9.03
1998 7.732 6.74 6.46 8.49 16.5 30.5 34 40.9 24.4 20.7 11.8 8.61
1999 6.9 5.54 5.24 6.18 33.7 59.7 86.3 58.4 63.2 53 21.2 11.2
2000 7.6 6.53 5.47 5.49 17.9 40.9 72.7 74 24.8 13.4 8.75 6.52
2001 5.05 4.72 4.81 5.8 12.5 16.2 17.8 44.3 43.9 37.5 11.6 8.55
2002 7.15 5.94 5.24 6.19 10 29.8 47.9 53.5 33.4 15.4 8.41 4.45
2003 3.96 4.07 4.52 5.87 5.66 61 54.5 53.1 47.8 43 15.96 7.58
2004 6.74 5.64 4.61 7.37 20.3 38.4 53.6 50.6 77.2 46.8 23.5 10.7
2005 6.48 5.76 4.91 5.29 9.58 26.6 49.4 49.2 45.9 17.4 9.79 7.69
2006 5.86 5.41 5.25 6.92 11 20.2 25.6 35.9 52.4 21.1 15.4 9.26
2007 7.25 6.12 6.61 9.33 17.4 35.5 66.9 64.2 59.8 32.5 20.9 10.8
2008 6.35 4.9 4.21 8.68 17.9 51.1 78.5 81.9 69.8 33.7 15.9 11.5
2009 7.24 4.7 3.13 10.4 13.1 25.6 57.9 119 56.2 16.78 8.04 4.73
2010 3.08 2.05 1.9 4.74 14.6 58.9 83.3 102 112 36.2 9.5 5.2
Avg 6.40 5.30 4.89 6.73 16.01 35.11 55.35 60.71 54.20 27.20 13.60 8.51
83
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Location Pipletar
Latitude 27°17'45"
Longitude 87°13'30"
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1974 2.9 1.96 1.64 2.38 5.27 10.8 33.4 31.3 24.5 17 6.75 2.78
1975 1.83 1.36 0.83 1.03 1.71 11.6 18.9 15.1 18.3 10.8 4.3 2.6
1976 1.85 1.58 1.11 1.52 6.59 16.6 22.9 23.8 17.9 10.7 7.84 6.06
1979 2 1.25 0.89 1.47 3.05 5.66 6.18 9.67 7.56 3.06 1.51 1.15
1984 1.74 1.57 1.24 2.07 7.95 7.57 17.9 13 12.7 6.68 3.53 2.05
1985 1.48 1.29 1.11 1.06 3.07 6.06 19.9 19.5 13.1 8.76 5.52 3.33
1986 2.23 1.53 1.28 1.37 2.13 8.36 11.5 12.6 13.3 8.89 4.39 2.7
1987 1.66 1.27 1.27 1.46 1.6 5.05 8.63 13.1 16.5 11.5 5.01 2.82
1988 1.7 1.2 1.57 0.92 2.12 2.1 10.7 23.4 13.9 8.61 3.99 2.56
1989 2.1 1.52 2.01 1.15 2.51 7.05 12.45 19.4 13 8.65 4.15 2.37
1990 2.14 1.9 1.96 2.17 5.46 12 14.2 15.4 12.1 8.68 4.3 2.18
1991 2.17 1.35 1.29 1.48 3.33 6.65 12.4 20.5 12.6 5.13 2.82 1.67
1992 1.43 1.26 0.98 2.09 3.78 7.52 13.4 20.95 13.95 6.74 3.08 1.97
1993 1.91 2.53 2.02 2.69 4.22 8.39 14.4 21.4 15.3 8.34 3.33 2.26
1994 1.5 1.22 1.08 1.16 2.3 13.2 21.4 20.3 16.45 6.75 4.11 3.43
84
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1995 2.47 2.1 1.86 2.1 4.93 14.8 18.6 21.6 14 9.92 6.46 3.86
1996 2.94 2.17 2.18 1.69 8.07 12.2 19.3 19.7 15.4 12 6.32 3.95
1997 2.82 2.55 1.87 2.04 3.46 7.92 10.21 19.9 15 5.84 3.3 2.13
1998 1.26 0.75 0.56 4.72 11.1 15.7 14.4 12 10.4 6.96 3.72 2.87
1999 2.5 1.97 1.38 1.42 6.24 10.4 15.6 14.1 11.5 10.8 7.65 3.78
2000 2.17 1.67 1.36 2.56 9.62 10 13.2 11.2 8.56 6.25 3.95 2.53
2001 1.83 1.57 1.18 3.72 14.5 19.7 14.1 15.9 13.7 9.71 6.25 4.37
2002 3.23 2.14 1.56 3.87 7.89 11.1 15.5 16 9.82 5.45 4.02 2.86
2003 1.97 1.73 2.55 2.19 6.84 6.84 9.59 10.7 10.2 7.72 5.61 3.2
2004 2.16 1.35 0.85 1.4 3.48 13.7 11.6 10.9 12.2 9.84 5.22 2.85
2005 1.6 0.64 0.52 0.74 1.28 4.1 15.8 13 12.4 10.5 7.87 5.26
2006 2.63 1.88 2.2 7.37 3.22 11.9 15.5 13.4 14.6 9.77 7.87 5.4
2007 2.29 3.11 2.47 4.81 5.44 10.4 15.1 15.6 21.4 12.4 6.92 4.72
2008 1.97 1.59 1.43 1.92 2.4 10.5 14.4 17.6 21.5 15 8.31 5.27
2009 3.41 2.62 3.56 5.87 11.8 11.1 11.4 14 10 6.25 4.38 3.11
2010 2.31 1.9 1.64 1.48 2.08 4.65 12 14.6 13.6 9.57 6.36 3.32
85
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1981 0.384 0.321 0.298 0.730 0.867 1.378 3.154 4.046 2.659 0.940 0.632 0.468
1982 0.383 0.360 0.336 0.500 0.908 2.116 5.189 3.494 2.594 1.224 0.916 0.651
1983 0.490 0.399 0.346 0.366 2.148 2.675 5.683 4.029 4.370 1.994 1.094 0.713
1984 0.529 0.470 0.375 0.752 2.302 2.351 5.618 3.235 4.759 1.889 1.167 0.768
1985 0.567 0.507 0.450 0.509 1.467 4.418 6.924 5.335 4.816 2.096 1.289 0.765
1986 0.532 0.406 0.356 0.589 0.726 2.246 3.802 4.119 4.216 2.302 1.030 0.642
1987 0.457 0.362 0.446 0.572 0.859 1.605 3.916 4.800 6.291 3.186 1.516 0.819
1988 0.573 0.480 0.484 0.531 0.949 1.735 4.248 6.526 5.456 2.335 1.038 0.692
1989 0.564 0.451 0.516 0.422 0.957 2.246 4.386 5.108 6.032 2.035 1.297 0.843
1990 0.560 0.521 0.542 0.743 1.873 2.882 4.090 5.728 5.476 1.962 1.094 0.704
1991 0.575 0.398 0.367 0.602 1.216 3.519 3.794 6.348 4.921 1.889 0.892 0.564
1992 0.517 0.414 0.329 0.536 0.773 1.857 5.310 4.281 3.510 2.805 1.017 0.598
1993 0.460 0.430 0.290 0.469 1.492 1.873 3.632 6.283 3.754 3.016 1.143 0.632
1994 0.503 0.375 0.409 0.439 0.827 2.797 3.340 5.513 5.959 2.019 1.119 0.811
1995 0.608 0.546 0.470 0.412 1.848 4.200 4.256 5.545 3.997 2.027 1.330 0.908
86
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1996 0.657 0.385 0.321 0.326 2.667 5.432 6.316 3.674 2.878 1.646 0.908 0.726
1997 0.609 0.550 0.503 0.524 0.827 1.978 1.913 2.554 2.497 1.378 0.940 0.732
1998 0.627 0.546 0.524 0.688 1.338 2.473 2.756 3.316 1.978 1.678 0.957 0.698
1999 0.559 0.449 0.425 0.501 2.732 4.840 6.997 4.735 5.124 4.297 1.719 0.908
2000 0.616 0.529 0.443 0.445 1.451 3.316 5.894 5.999 2.011 1.086 0.709 0.529
2001 0.409 0.383 0.390 0.470 1.013 1.313 1.443 3.592 3.559 3.040 0.940 0.693
2002 0.580 0.482 0.425 0.502 0.811 2.416 3.883 4.337 2.708 1.249 0.682 0.361
2003 0.321 0.330 0.366 0.476 0.459 4.945 4.418 4.305 3.875 3.486 1.294 0.615
2004 0.546 0.457 0.374 0.598 1.646 3.113 4.346 4.102 6.259 3.794 1.905 0.867
2005 0.525 0.467 0.398 0.429 0.777 2.157 4.005 3.989 3.721 1.411 0.794 0.623
2006 0.475 0.439 0.426 0.561 0.892 1.638 2.075 2.911 4.248 1.711 1.249 0.751
2007 0.588 0.496 0.536 0.756 1.411 2.878 5.424 5.205 4.848 2.635 1.694 0.876
2008 0.515 0.397 0.341 0.704 1.451 4.143 6.364 6.640 5.659 2.732 1.289 0.932
2009 0.587 0.381 0.254 0.843 1.062 2.075 4.694 9.648 4.556 1.360 0.652 0.383
2010 0.250 0.166 0.154 0.384 1.184 4.775 6.753 8.269 9.080 2.935 0.770 0.422
Avg 0.519 0.430 0.397 0.546 1.298 2.846 4.488 4.922 4.394 2.205 1.103 0.690
87
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1974 1.580 1.068 0.894 1.297 2.872 5.885 18.201 17.057 13.351 9.264 3.678 1.515
1975 0.997 0.741 0.452 0.561 0.932 6.321 10.299 8.229 9.972 5.885 2.343 1.417
1976 1.008 0.861 0.605 0.828 3.591 9.046 12.479 12.970 9.754 5.831 4.272 3.302
1979 1.090 0.681 0.485 0.801 1.662 3.084 3.368 5.270 4.120 1.668 0.823 0.627
1984 0.948 0.856 0.676 1.128 4.332 4.125 9.754 7.084 6.921 3.640 1.924 1.117
1985 0.807 0.703 0.605 0.578 1.673 3.302 10.844 10.626 7.139 4.774 3.008 1.815
1986 1.215 0.834 0.698 0.747 1.161 4.556 6.267 6.866 7.248 4.845 2.392 1.471
1987 0.905 0.692 0.692 0.796 0.872 2.752 4.703 7.139 8.992 6.267 2.730 1.537
1988 0.926 0.654 0.856 0.501 1.155 1.144 5.831 12.752 7.575 4.692 2.174 1.395
1989 1.144 0.828 1.095 0.627 1.368 3.842 6.785 10.572 7.084 4.714 2.262 1.292
1990 1.166 1.035 1.068 1.183 2.975 6.539 7.738 8.392 6.594 4.730 2.343 1.188
1991 1.183 0.736 0.703 0.807 1.815 3.624 6.757 11.171 6.866 2.796 1.537 0.910
1992 0.779 0.687 0.534 1.139 2.060 4.098 7.302 11.416 7.602 3.673 1.678 1.074
1993 1.041 1.379 1.101 1.466 2.300 4.572 7.847 11.662 8.338 4.545 1.815 1.232
1994 0.817 0.665 0.589 0.632 1.253 7.193 11.662 11.062 8.964 3.678 2.240 1.869
1995 1.346 1.144 1.014 1.144 2.687 8.065 10.136 11.771 7.629 5.406 3.520 2.103
1996 1.602 1.183 1.188 0.921 4.398 6.648 10.517 10.735 8.392 6.539 3.444 2.153
1997 1.537 1.390 1.019 1.112 1.885 4.316 5.564 10.844 8.174 3.182 1.798 1.161
88
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1998 0.687 0.409 0.305 2.572 6.049 8.556 7.847 6.539 5.667 3.793 2.027 1.564
1999 1.362 1.074 0.752 0.774 3.400 5.667 8.501 7.684 6.267 5.885 4.169 2.060
2000 1.183 0.910 0.741 1.395 5.242 5.449 7.193 6.103 4.665 3.406 2.153 1.379
2001 0.997 0.856 0.643 2.027 7.902 10.735 7.684 8.665 7.466 5.291 3.406 2.381
2002 1.760 1.166 0.850 2.109 4.300 6.049 8.447 8.719 5.351 2.970 2.191 1.559
2003 1.074 0.943 1.390 1.193 3.727 3.727 5.226 5.831 5.558 4.207 3.057 1.744
2004 1.177 0.736 0.463 0.763 1.896 7.466 6.321 5.940 6.648 5.362 2.845 1.553
2005 0.872 0.349 0.283 0.403 0.698 2.234 8.610 7.084 6.757 5.722 4.289 2.866
2006 1.433 1.024 1.199 4.016 1.755 6.485 8.447 7.302 7.956 5.324 4.289 2.943
2007 1.248 1.695 1.346 2.621 2.964 5.667 8.229 8.501 11.662 6.757 3.771 2.572
2008 1.074 0.866 0.779 1.046 1.308 5.722 7.847 9.591 11.716 8.174 4.528 2.872
2009 1.858 1.428 1.940 3.199 6.430 6.049 6.212 7.629 5.449 3.406 2.387 1.695
2010 1.259 1.035 0.894 0.807 1.133 2.534 6.539 7.956 7.411 5.215 3.466 1.809
Avg 1.164 0.923 0.834 1.264 2.768 5.337 8.166 9.134 7.654 4.892 2.792 1.747
89
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
FLOOD ANALYSIS
90
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
91
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
GUMBEL
Discharge
of Decending Return
Year rank Yt Kt Xt(m3/s)
Yankhuwa order Period
Khola(m3/s)
92
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
93
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Return Period Yt kt Xt
94
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
No. of Obseravtion 37
Discharge of
Year y=logX (y-ym)^2 (y-ym)^3
Yankhuwa Khola(m3/s)
95
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
mean 1.234
SD 0.226
Cs 0.0000
96
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Return
P W Z kt yt xt
Period (T)
97
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
LOG NORMAL
98
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Average of Y 1.234
Std 0.226
99
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Return period P W Z Kt Yt Xt
100
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
101
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
100.000
80.000
gumbel
60.000
log person
40.000 log normal
20.000
0.000
2 5 10 15 20 25 30 50 100 200 500 1000
Return Period (yr)
102
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
GUMBEL
Discharge
of Decending Return
S.No Year Rank Yt Kt Xt(m3/s)
Yankhuwa order Period
(m3/s)
103
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Std 0.084
Average 0.313
yn-bar 0.732
Sn 1.066
104
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Return Period Yt kt Xt
105
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Number of Observations: 37
106
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Mean -0.500
SD 0.087
107
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Return
Period P P'= 1-P W=sqrt(ln(1/P'^2)) Z Kt Yt Xt
(T)
108
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
109
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Average of Y -0.500
SD of Y 0.087
110
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
LOG NORMAL
Return
P P'=1-P W=sqrt(1/(P’^2)) Z Kt Yt Xt
period
111
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
112
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
0.600
0.500 log person
0.400
log normal
0.300
0.200
0.100
0.000
2 5 10 15 20 25 30 50 100 200 500 1000
Return Period ( yr)
113
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
GUMBEL
Instantaneous maximum
Discharge Descending Rank Time
Year Yt Kt Xt
Shabha Order (m) Period
Yankhuwa Khola
Khola
114
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
115
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
116
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
117
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
118
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
119
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
LOG NORMAL
120
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Mean 1.23366
Std 0.22552
121
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
122
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
123
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
120
100
Discharge
80
log normal
60 Gumbels
log pearson III
40
20
0
2 5 10 15 20 25 30 50 100 200 500 1000
Return Period
124
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
1. Design of Intake
17 RL of bed 531.436 m
22 Freeboard 0.5 m
125
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
x y
0 -1.302
0.1 -1.302
0.2 -1.301
0.3 -1.299
0.4 -1.296
0.5 -1.293
0.6 -1.289
0.7 -1.284
0.8 -1.279
0.9 -1.272
1 -1.265
1.1 -1.257
1.2 -1.248
1.3 -1.238
1.4 -1.228
1.5 -1.216
1.6 -1.204
1.7 -1.191
1.8 -1.177
126
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
-1.200
-1.220
-1.240
-1.260
-1.280
-1.300
-1.320
DESIGN OF WEIR
127
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
128
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Hence, Safe.
129
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
130
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
DESIGN OF TRASHRACK
131
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
P(35)'=(1-1/T)^35 0.703
P(35)=1-P(35)' 0.297
132
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Adopt Thickness of
133
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
APPROACH CANAL
20% addition on
4 Length L 69.04 m
134
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
4 Temperature 15.000 °C
135
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Outlet zone
1 Outlet angle 27 °
Inlet zone
1 inlet angle 11
Flushing Channel
136
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
20% addition on
1 in
4 Slope S 0.001667 600(adopted)
137
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Temperature 15 0C
Constant a 0.44
Breadth B 2.182687747 m
Length L 17.46150197 m
138
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Actual Length L 20 m
Considering Turbulence
L 2.396789498 m
Adopted L, B and H
Length L 30 m adopted
139
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
TRANSITION ZONE
1 Inlet Transition
2 Outlet Transition
140
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
10 Providing x 0.8 m
141
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
FLUSHING DESIGN
20% of design
1 Discharge of flushing channel (Qf) 0.220 m3/s discharge
Concrete cement
3 Rugosity coefficient (n) 0.012 m finish
142
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
20% addition on
1 in
4 Slope S 0.001667 600(adopted)
143
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
FOREBAY
16 Area 44 m2
17 Length of forebay 24 m
144
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
DESIGN OF TRANSITION
SPILLWAY DESIGN
PENSTOCK
COST OF PENSTOCK
Length 781.460 m
Interest 12.000 %
145
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Diameter
Length Thickness Volume Weight Cost Annual Cost Total Cost
SN (Internal)
146
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
147
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
148
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
149
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Length 781.460 m
Area 0.503 m2
ɳturbine 90%
ɳgenerator 95%
150
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
Jan 31 0.620 0.620 0.558 1.111 0.639 0.064 0.703 3.291 2448.843 20570.283
Feb 28 0.465 0.465 0.419 0.833 0.359 0.036 0.395 1.389 933.128 7838.273
Mar 31 0.336 0.336 0.302 0.602 0.187 0.019 0.206 0.523 389.186 3269.163
Apr 30 0.259 0.259 0.233 0.463 0.111 0.011 0.122 0.238 171.430 1440.012
May 31 0.672 0.672 0.605 1.203 0.750 0.075 0.825 4.185 3113.489 26153.305
Jun 30 1.551 1.100 1.100 2.188 2.480 0.248 2.728 25.166 18119.648 86974.309
Jul 31 3.748 1.100 1.100 2.188 2.480 0.248 2.728 25.166 18723.636 89873.453
Aug 31 6.463 1.100 1.100 2.188 2.480 0.248 2.728 25.166 18723.636 89873.453
Sep 30 4.265 1.100 1.100 2.188 2.480 0.248 2.728 25.166 18119.648 86974.309
Oct 31 2.068 1.100 1.100 2.188 2.480 0.248 2.728 25.166 18723.636 157278.543
Nov 30 1.060 1.060 0.954 1.898 1.865 0.186 2.051 16.410 11815.127 99247.065
Dec 31 0.801 0.801 0.721 1.435 1.066 0.107 1.173 7.093 5277.307 44329.376
151
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
PENSTOCK OPTIMIZATION
152
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
PENSTOCK OPTIMIZATION
12000000.000
10000000.000
8000000.000
Revenue Loss Cost
6000000.000
Annual Material Cost
4000000.000
Total Cost
2000000.000
0.000
0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600
Diameter (m)
DESIGN OF POWERHOUSE
Adopt 13.000 m
153
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
BIFURCATION
154
Pre-feasibility Study of Yankhuwa Khola Hydropower Project
155