3 PCC
FOOTING - F1 3 6 7 0.5 Cu.Ft. 63.00
FOOTING - F2 12 6 6 0.5 Cu.Ft. 216.00
SAND FOR PLINTH BEAM RFT L B
PB1 278 1.25 0.25 Cu.Ft. 86.88
SAND LAYER FOR FLOORING 27 44 0.5 Cu.Ft. 594
959.88
4 BORING OF PILES L
3 8 RFT 24
5 RCC
5.1 CONCRETE FOR FOOTING
FOOTING - F1 3 5 6 1.83 Cu.Ft. 164.70
FOOTING - F2 12 5 5 1.58 Cu.Ft. 474.00
638.7
5.2 CONCRETE FOR COLUMNS UPTO F.L
COLUMN - C1 3 0.75 1.25 3.58 Cu.Ft. 10.07
COLUMN - C2 12 0.75 1 3.08 Cu.Ft. 27.72
37.8
5.3 CONCRETE FOR PLINTH BEAM RFT L B
PB1 278 0.75 1 Cu.Ft. 208.50
208.50
5.4 CONCRETE FOR PILES L B D
3 0.75 0.75 8 Cu.Ft. 14
5.5 CONCRETE FOR LINTEL RFT L B
9"(first floor) 184 0.75 0.5 Cu.Ft. 69
4.5(first floor) 40 0.375 0.375 Cu.Ft. 6
75
5.6 CONCRETE FOR SUNSHADE L B T
7 5.5 2 0.25 Cu.Ft. 19.3
2 7.5 2 0.25 Cu.Ft. 7.5
Cu.Ft. 27
CONCRETE FOR COLUMNS ABOVE F.L
5.7
UPTO G.F SLAB
COLUMN - C1 3 0.75 1.25 12.58 Cu.Ft. 35.38
COLUMN - C2 12 0.75 1 12.58 Cu.Ft. 113.22
148.6
5.8 CONCRETE FOR ROOF BEAM RFT L B
GROUND FLOOR - RB1 142 0.75 0.75 Cu.Ft. 79.88
GROUND FLOOR - RB2 128 0.75 0.75 Cu.Ft. 72.00
FIRST FLOOR - RB1 94 0.75 0.75 Cu.Ft. 52.88
FIRST FLOOR - RB2 73 0.75 0.75 Cu.Ft. 41.06
Cu.Ft. 245.81
5.9 CONCRETE FOR ROOF SLAB L B AREA
GROUND FLOOR 27 44 0.416 Cu.Ft. 494.21
FIRST FLOOR 27 16 0.416 Cu.Ft. 179.71
Cu.Ft. 673.92
5.1 CONCRETE FOR SILL PLATE L B T
7 6 0.75 0.25 Cu.Ft. 7.9
2 8 0.75 0.25 Cu.Ft. 3.0
Cu.Ft. 11
6 STEEL WORK
6.1 REINFORCEMENT FOR FOOTING L B Wt./sq.ft
FOOTING - F1 3 5.5 6.5 1.5 KG 160.88
FOOTING - F2 12 5.5 5.5 1.5 KG 544.50
MT 0.7
10% wastage MT 0.1
MT 0.8
REINFORCEMENT FOR COLUMN UPTO
6.2 wt./ft. ht.
First slab
COLUMN - C1 3 5.5 21.5 KG 354.8
COLUMN - C2 12 5.5 21.5 KG 1419.0
MT 1.77
10% wastage MT 0.2
MT 2.0
6.3 REINFORCEMENT FOR PB-1 wt./ft. RFT
PB1 3 278 KG 834.00
MT 0.83
10% wastage 0.1 0.08
MT 0.92
6.4 REINFORCEMENT FOR PILES wt./Ft. ht.
3 2.5 9.5 KG 71.3
MT 0.07
10% wastage 0.1 0.01
MT 0.08
6.5 REINFORCEMENT FOR LINTEL wt./ft. RFT
9"
3 224 KG 672.00
4.5
MT 0.7
10% wastage 0.1 0.1
0.7
6.6 REINFORCEMENT FOR SUNSHADE wt./s.ft L B
7 1.5 5.5 2 KG 116
2 1.5 7.5 2 KG 45.00
MT 0.12
10% wastage 0.1 0.01
MT 0.13
6.7 REINFORCEMENT FOR ROOF BEAM RFT Wt / ft.
GROUND FLOOR - RB1 142 8 KG 1136.00
GROUND FLOOR - RB2 128 5.5 KG 704.00
FIRST FLOOR - RB1 94 8 KG 752.00
FIRST FLOOR - RB2 73 5.5 KG 401.50
MT 2.994
10% wastage 0.1 0.299
3.293
6.8 REINFORCEMNENT FOR ROOF SLAB
GROUND FLOOR 27 44 Sq.Ft. 1188.00
FIRST FLOOR 27 16 Sq.Ft. 432.00
Sq.Ft. 1620.00
REINFORCEMNENT FOR ROOF SLAB Wt. AREA
1.5 1620.00 KG 2430.00
MT 2.4
10% wastage 0.1 0.2
2.7
6.9 REINFORCEMENT FOR SILL PLATE wt./s.ft. L B
7 6 KG 42
2 6 KG 12
MT 0.05
10% wastage 0.1 0.01
0.06
RFT ht
PLASTERING PARAPET WALL 69.75 7 471
Sq.Ft. 471
INNER WALL PLASTERING
GROUND FLOOR 278.25 9.5 Sq.Ft. 2643.4
DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6
DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1
WINDOW -W 6 4 4 0.75 Sq.Ft. 72.0
WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0
VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0
Sq.Ft. 2513.6
RFT ht
PAINTING PARAPET WALL 69.75 7 471
17 ENAMEL PAINTING(Doors&Windows)
GROUND FLOOR DOOR
MAIN DOOR - MD 1 4.5 7 2 Sq.Ft. 63.00
DOOR - D 3 3 7 2 Sq.Ft. 126.00
DOOR - D1 2 2.5 7 2 Sq.Ft. 70.00
FIRST FLOOR DOOR
MAIN DOOR - MD 1 4.5 7 2 Sq.Ft. 63.00
DOOR - D 2 3 7 2 Sq.Ft. 84.00
DOOR - D1 1 2.5 7 2 Sq.Ft. 35.00
GROUND FLOOR WINDOW
WINDOW - W 6 4 4 2 Sq.Ft. 192.00
WINDOW -W1 1 6 4 2 Sq.Ft. 48.00
FIRST FLOOR WINDOW
WINDOW - W 1 4 4 2 Sq.Ft. 32.00
WINDOW -W1 1 6 4 2 Sq.Ft. 48.00
Sq.Ft. 761.00