Professional Documents
Culture Documents
CONTENT
1. The ‘why’ of the fire safety in part 3 exam
2. UBBL must know
3. Fire safety must know
4. Basic neglect – common ignorance and/or misunderstanding in fire safety
4.1. fire appliance access UBBL 40
4.2. 7th schedule
4.3. Height factor in fire safety
5. Review of past year questions
5.1 UBBL
5.2 Role Of Architect / Engineer (Psp / Sp)
5.3 Staircase
5.4 Unprotected Opening
2
SAFETY OBJECTIVE
5
BOMBA
5
FIRE SAFETY
6
TRIGGER POINTS
14
SAFETY CHECK
REQUIREMENT STRATEGIES
"Adalah saya mencadangkan agar maksud utama cadangan penggunaan projek seperti di atas
adalah dalam Kumpulan Maksud ........ dan keperluan kelengkapan keselamatan kebakaran
adalah seperti berikut: (Keperluan kelengkapan keselamatan kebakaran hendaklah ditentukan
mengikut UBBL pada sesuatu cadangan projek)“
Saya mengakui walaupun apa-apa pelan, lukisan atau kiraan yang diperakukan oleh Jabatan Bomba
dan Penyelamat Malaysia, tanggungjawab bagi kemungkiran kepada mana-mana bangunan atau
sebahagian daripada sesuatu bangunan hendaklah terletak atas orang yang mengemukakan
pelan, lukisan atau kiraan itu.“
(tandatangan)
Nama orang yang mengemukakan
Cop profesional
1
5
FIRE SAFETY MUST KNOW
Keselamatan Kebakaran - Wajib Tahu
DESCRIPTION CALCULATIONS
CRITICAL KNOWLEDGE UBBL FLOOR AREA & VOLUME OCCUPANCY EXIT & STAIRCASE WIDTH
DIMENSION LOAD
a. Fire triangle & how to kill a. Fire prevention a. Occupancy load a. Access a. Exit Type of exits
a fire b. Fire fighting b. Compartmentation b. Compartment b. Staircase a. Door outside
b. In fire – what kills? system c. Exit & staircase c. Active system b. Horizontal exit
c. The philosophy / objective c. Evacuation width and position c. Ramp main exit
of fire safety d. Travel distance d. Escalator
d. Design/Professional e. Dead end limit e. Storey exit
Liability – whose f. Stairs
responsibility?
e. Satisfying Bomba
requirement Rate of discharge
f. Stages of Bomba UBBL 181
submission 60 person per min level
exits
45 person per min stairs
UBBL MUST KNOW
Undang-undang Kecil Bangunan Seragam 1984 - Wajib Tahu
1. UBBL 1984 is a subsidiary legislation to Sreet Drainage and Building Act 1974
2. Amendment 2012 is ratified only in Selangor (2012) and Terengganu (2013), Sabah and Pulau Pinang.
LOCAL GOVERNMENT ORDINANCE 1961 (No. 11 of 1961) LAHAD DATU DISTRICT COUNCIL (BUILDING) BY-
LAWS 1982 (G.N.L 20 of 1983)
3. Sarawak Building Ordinance 1994
4. Only Selangor has gazetted full text. Terengganu still depended on Amendment Act. Penang / Sabah
5. Amendment 2012 omit prescriptive provisions and introduce references to MS (Malaysian Standards)
SPACE LIGHT AND CONSTRUCTIONAL FIRE REQUIREMENT FIRE DETECTION, FIRE S5(1) Purpose Group
VENTILLATION REQUIREMENT ALARM AND FIRE S5(2) Dimensions of Building and
EXTINGUISHMENT Compartments
PASSIVE ACTIVE S6(1) Permitted limit of unprotected area
EVAC ZONE 3
91 M
FIRE PUMP
ROOM
EVAC ZONE 1
ACCESS WAY A
REQUIRED GRAD 1:15 EVAC ZONE 2
PROVIDED LEVEL ACCESS WAY C
MAIN ENTRANCE SECOND ENTRANCE
ACCESS TO FIRE ACCESS TO FIRE
ACCESS ROAD CONTROL ROOM, FIRE
REQUIRED GRAD 1:8.3 CONTROL ROOM,
FIRE PUMP ROOM AND PUMP ROOM AND FIRE
PROVIDED GRAD 1:12 LIFT
FIRE LIFT
HEIGHT FACTOR IN FIRE SAFETY
Faktor Tinggi Dalam Pencegahan
I SMALL RESIDENTIAL NR NR NR
II INSTITUTIONAL
Hospital, nursing homes etc 15 30 45
School 15 45 75
Open Plan NR 30 45
Flexible Plan NR 45 60
III OTHER RESIDENTIAL
Hotels 15 30 45
Flats 20 30 75
Dormitories 15 45 75
IV OFFICE 15 45 75
V SHOPS 15 45 60
VI FACTORY
General and special purpose 15 30 60
High hazards 0 22 35
Open structures NR NR NR
VII PLACES OF ASSEMBLY 15 45 60
VIII STORAGE AND GENERALS
Low and ordinary hazards 15 30 60
High hazards 10 20 35
Parking garages 15 45 60
Aircraft hangars (ground floor) 15 30+ 45+
Aircraft hangars (mezzanine floor) 15 20 20
note
+ refer to aircraft hangar only
The silliest mistake a candidate makes was not to answer on the
Appendix
STEPS TO CALCULATE AND LOCATE STAIRCASES
WIDTH OF STAIRS DETERMINED BY CALCULATION
NO AND LOCATION OF STAIRS DETERMINED BY PLANNING / DISTANCE LIMIT
A. DO A TABLE OF FLOORS
B. DETERMINE PG (SCH 5) OVER OCCUPANCY LOAD (2ND COLUMN SCH 7)
C. CALCULATE FLOOR AREA
D. DETERMINE OCCUPANCY (NO OF PEOPLE) BY DIVIDING AREA WITH
OCCUPANCY LOAD (SCH 7 COLUMN 2)
E. CALCULATE EXIT CAPACITY REQUIRED BY DIVIDING OCCUPANCY (D)
WITH CAPACITY EXIT (SCH 7 COLUMN 2)
F. CALCULATE WIDTH OF STAIRS BY MULTIPYING E WITH 550
G. SKETCH A FLOOR PLAN
H. IDENTIFY HEIGHT OF HABITABLE FLOOR – SEE RULES OF HEIGHT [IF
ABOVE 18M FFAL REQUIRED]
I. IF FFAL REQUIRED THE FARTHEST DISTANCE IN BUILDING TO FIRE LIFT
MAX 45M / IF LESS THAN 18M ONLY STAIRS REQUIRED, MAX DISTANCE
IS 60M.
J. LOCATE STAIRS OR FFAL SO THAT FARTHEST DISTANCE WITHIN LIMIT
K. TRAVEL DISTANCE MEASURED ON PLAN NOT BY RADIUS
QUESTION 3 a
10TH SCHEDULE
A = HOSE REEL QUESTION 3 b
B = SPRINKLER THE SIX TRIGGER POINTS ANALYSES
1 = MANUAL ELECTRICAL ALARM SYSTEM
3 = CENTRAL MONITORING SYSTEM
4 = PUBLIC ADDRESS
5 = FIRE FIGHTING CONTROL ROOM
1 PURPOSE GROUP BASEMENT – PG VIII STORAGE & GENERAL
PODIUM – PG V SHOPS
TOWER – PG IV OFFICE
Why separate purpose group? UBBL building above 30m is a
compartment by itself
2 AREA 4000 X 15 = 60,000
4000 X 1 = 4,000
Topmost habitable floor 90.4m
5000 X 3 = 15,000
Assume floor plate of 64 x 64 5000 X 1 = 5,000
84,000
Max single stage system 60 m. To
Area calculation will give no of staircases required.
provide second pump system at
(But) Location of staircase must be determined from floor
level 13
plan
3 HEIGHT TOTAL HEIGHT FROM ACCES LEVEL: 100.2
TOP HABITABLE HEIGHT: 90.4M
UBBL 197A. Above 18m FIRE FIGHTING ACCESS LOBBY
FFAL – Max distance 45m
Fire Lift – Max distance 75 m
421,500
5 HAZARDS NONE
Fire appliances access are limited to 30m. Building above 30 m require fire fighting from inside the building.
Architects to design for safe passage and appropriate systems
1 Site planning 6 m / 30 tons capacity road for fire trucks
Fire trucks allowable gradient of 1:15
Hydrants at max 45m from entrance and at max 90m interval
Direct access to fire control room
Evacuation place of assembly
Dry/Wet riser breaching inlet max 30m from hydrant
Building volume 421,500 m3 UBBL 140 island site
2 Horizontal / Plan FFAL for building above 30m
FFAL consists of fire lift, staircase, wet or dry riser and fire fighting lobby. Max distance
from fire lift to end of floor 45m. Max distance staircase to end of floor 60m (S7)
Zoning for electrical isolation switch 1000m2
2 Height Top habitable floor at 90.4m.
UBBL require min 2 stairs Staircase to roof level Max height for single stage system 60m. To
provide second pump set at higher floor
3 Active system Refer 10th Schedule
A = Hose Reel
B = Sprinkler
1 = Manual Electrical Alarm System
3 = Central Monitoring System
4 = Public Address
5 = Fire Fighting Control Room
In reading the question, candidates either understand the question as either (a) ANALYSE THE QUESTION
restricting the class to ground floor only / office on 1st and 2nd floor or (b) all floors
usable as classroom / office on ground floor.
Shophouse are
normally an island
development
complying with
7th Schedule Options UBBL 140
1. Use existing stairs, OR 23200
2. Demolish all/some
Options stairs and build new
1. Use existing walls OR
2. Demolish all and
rebuild as per new
10th Schedule compartmentation
UBBL 140
21000
Change from PG IV office and V shop to PG II
Institution
Will require min of 2 stairs
Stairs width need to be re-calculated
OPTION A OPTION B
Classroom at GF Office at GF
Change of PG from shop to institution Change of PG from shops to office
office at F1 and F2 Classrooms at F1 and F2
PG maintained Change of PG from office to institution
Dead end S7(1) 15 m 15 m
Travel distance (unsprinklered) S7(1) 45 45
Occupancy load S7(2) Office 10 gross Classrooms 2 net
Exit Capacity S7(3) Ground II. Institutional - 100 / F1 & F2 officeStairs 60 Ground IV Office -
Compartment S5 Limit of floor area 2000m2 Limit of floor area 2000m2
Active System S10 GF A + 1 Hose Reel + Auto elect Detector/Manual Elect GF No requirement for office
alarm F1 & F2 : A + 1 Hose Reel + Auto elect Detector/Manual
F1 & F2 : No requirement for office Elect alarm
OPTION 2
Building above 30 m
compartmentation by
floor
a. Enclosing Rectangle (ER) calculation
H = 3.9 (6 IN TABLE)
W = 20 (21 IN TABLE)
AREA OF OPENING = 20 m x 3.9 m = 78 m2