You are on page 1of 29

11/7/2018 20 Sample PMP® Questions and Answers

AllProject
CoursesManageme… All Resources Articles E-Books On-Demand Webinars

20 Sample PMP® Questions and Answers

Pradip PMP
Last updated July 6, 2018
Hi there! Are you looking for 1

PMP® certification?
69514 Views 2 Comments

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 1/29
11/7/2018 20 Sample PMP® Questions and Answers

The PMP®, or Project Management Professional, is an exam conducted by the


Project Manageme… All Resources Articles E-Books On-Demand Webinars
Project Management Institute (PMI)®, is a globally recognized certification. The
exam consists of 200 multiple choice questions that outline the five process
groups (Initiation, Planning, Executing, Monitoring and Controlling, and Closing)
and nine knowledge areas (Integration, Scope, Time, Cost, Quality, Human
Resource, Communication, Risk, and Procurement).

Of the 200 questions, 25 of them are pretest questions. Pretest questions


appear randomly during the exam, do not affect the candidate’s score, and are
used in examinations as an effective way to increase the number of examination
questions that can be used in future PMP exams. The passing score for the exam
is almost 61% (106 questions correct out of 175 scored questions).

Here's a video on PMP Certification Training.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 2/29
11/7/2018 20 Sample PMP® Questions and Answers

Project Manageme… All Resources Articles E-Books On-Demand Webinars


Introduction To PMP Certi cation Training: Lesson 1 | Simp…

Related read: Project Management Professional Exam Tips and Tricks

Below are 20 examples of PMP questions and answers.

1. Question:

A project has a 60% chance of a $100,000 profit and a 40 percent of a US


$100,000 loss. The Expected Monetary Value for the project is:

1. $100,000 profit

2. $60,000 loss

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 3/29
11/7/2018 20 Sample PMP® Questions and Answers

3. $Project
20,000 profit
Manageme… All Resources Articles E-Books On-Demand Webinars

4. $40,000 loss

Answer:
Expected Monitory Value (EMV) is computed by EMV = Probability × Impact.

Compute both positive and negative values and then add them:

0.6 × $100,000 = $60,000 0.4 × $100,000 = $40,000 EMV = $60,000 - $40,000


= $20,000 profit

2. Question:

Assuming that the ends of a range of estimates are +/- 3 sigma from the mean,
which of the following range estimates involves the LEAST risk?

Answer:

1. 30 days, plus or minus 5 days

2. 22 – 30 days

3. Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days

4. Mean of 28 days

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 4/29
11/7/2018 20 Sample PMP® Questions and Answers

Project Manageme… All Resources Articles E-Books On-Demand Webinars


The estimate with the smallest range is less risky.

3. Question:

If a risk has a 20 percent chance of happening in a given month, and the project
is expected to last five months, what is the probability that the risk event will
occur during the fourth month of the project?

Answer:

1. Less than 1 percent

2. 20 percent

3. 60 percent

4. 80 percent

4. Question:

An accepted deadline for a project approaches. However, the project


manager realizes only 75% percent of the work has been completed.
The project manager then issues a change request. What should the
change request authorize?

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 5/29
11/7/2018 20 Sample PMP® Questions and Answers

Answer:
Project Manageme… All Resources Articles E-Books On-Demand Webinars

1. Additional resources using the contingency fund

2. Escalation approval to use contingency funding

3. Team overtime to meet schedule

4. Corrective action based on causes

5. Question:

Risk will be identified during which risk management process(es)?

Answer:

1. Perform Quantitative Risk Analysis and Identify Risks

2. Identify Risks and Monitor and Control Risks

3. Perform Qualitative Risk Analysis and Monitor and Control Risks

4. Identify Risks

Reference: The PMBOK® Guide, 5th Edition, Page 312, Figure 11.1

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 6/29
11/7/2018 20 Sample PMP® Questions and Answers

6. Question:
Project Manageme… All Resources Articles E-Books On-Demand Webinars

What is meant by RACI?

Answer:

1. Responsible, Accountable, Confirm, Inform

2. Recommended, Accountable, Consulted, Inform

3. Responsible, Accountant, Consulted, Inform

4. Responsible, Accountable, Consulted, Inform

The RACI chart is an example of the Responsibility Assignment Matrix (RAM),


which shows the relationship between activities and the team members.

7. Question:

Which of the following statement is true about a Program?

Answer:

1. A Program is a group of related projects

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 7/29
11/7/2018 20 Sample PMP® Questions and Answers

2. A Program is group of unrelated projects


Project Manageme… All Resources Articles E-Books On-Demand Webinars

3. A Program is a part of a big project

4. None of above

Reference: The PMBOK® Guide, 5th Edition, Page 9

8. Question:

The project manager meets with the project team to review lessons learned
from previous projects. In what activity is the team involved?

Answer:

1. Performance management

2. Scope identification

3. Risk identification

4. Project team status meeting

9. Question:

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 8/29
11/7/2018 20 Sample PMP® Questions and Answers

During a bidder conference,


Project Manageme…
you see
All Resources that E-Books
Articles one bidder is your
On-Demand close
Webinars
friend. What should your next step be?

Answer:

1. You will pass some confidential info to him

2. You will disclose this relationship to your management

3. You will resign immediately from the bidding process

4. You will try not to give the contract to him to prove your integrity

There is a conflict of interest in this situation. You must inform your bosses
about this relationship.

10. Question:

If a risk event has a 90 percent chance of occurring, and the


consequences will be US $ 10,000, what does US $9,000 represent?

Answer:

1. Risk value

2. Present value

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 9/29
11/7/2018 20 Sample PMP® Questions and Answers

3. Expected monetary value


Project Manageme… All Resources Articles E-Books On-Demand Webinars

4. Contingency budget

EMV = .9 X $ 10,000 = $ 9, 000

11. Question:

Your construction project was damaged by an earthquake. Your contractor says


that he cannot fulfill the terms of the contract due to a specific clause you both
had signed the contract. He is referring to the:

Answer:

1. Force majeure clause

2. Fixed price clause

3. Contract obligation terms

4. None of the above

12. Question:

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 10/29
11/7/2018 20 Sample PMP® Questions and Answers

All ofProject
the following are ALWAYS
Manageme…
inputs
All Resources to the
Articles risk management
E-Books process
On-Demand Webinars
EXCEPT:

Answer:

1. Historical information

2. Lessons learned

3. Work breakdown structure

4. Project status reports

Project Status report can be an input to risk management. However, when


completing risk management for the first time, you wouldn’t have the project
status report yet. Therefore, the project status report is not always an input to
risk management.

13. Question:

When estimating time for activities, a Project Manager should:

Answer:

1. Use the best guess and estimate all activities since there will be changes as
the project progresses and more information becomes available

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 11/29
11/7/2018 20 Sample PMP® Questions and Answers

2. Involve people who will


Project Manageme…
be doing Articles
All Resources the work to getOn-Demand
E-Books estimatesWebinars

3. Estimate for what the cost will allow and include buffers

4. None of the above

14. Question:

Risk tolerance is determined in order to help:

Answer:

1. The team ranks the project risks.

2. The project manager estimates the project.

3. The team schedules the project.

4. Management knows how other managers will act on the project.

If you know the tolerance of the stakeholders, you can predict how they might
react to different situations and risk events. This information can help assign
levels of risk on each work package activity.

15. Question:

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 12/29
11/7/2018 20 Sample PMP® Questions and Answers

You are running a project


Project Manageme… Allto engineer
Resources and implement
Articles a set ofWebinars
E-Books On-Demand business
processes and a software solution for customer relationship
management. The project involves a large number of organizations―a
major corporation and many suppliers of different sizes. During the
project, you observe effects of the differences between the companies’
corporate cultures. This leads to different expectations on how the
project should be handled—as well as to frequent misunderstandings
between stakeholders. Another effect is a growing degree of distrust
and skepticism. What should you try first to integrate the diverse
stakeholder groups?

Answer:

1. Focus on project work. As a project manager, you should not get distracted
by big egos.

2. Let the problems grow further until they are obvious for all. Then escalate
them.

3. Develop a joint quality policy for the project and seek a commitment by all
organizations.

4. Analyze probability and impact of the risks linked with the situation
and plan how to respond to them.

PMBOK® Guide 5th Edition, page 194 (last paragraph).

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 13/29
11/7/2018 20 Sample PMP® Questions and Answers

16. Question:
Project Manageme… All Resources Articles E-Books On-Demand Webinars

You are finding it difficult to evaluate the exact cost impact of risk. You
should evaluate on a(n) :

Answer:

1. Quantitative basis

2. Numerical basis

3. Qualitative basis

4. Economic basis

If you cannot determine an exact cost impact to the event, use qualitative
estimates such as Low, Medium, and High.

17. Question:

A project manager is quantifying risk for her project. Several of her


experts are offsite, but wish to be included. How can this be done?

Answer:

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 14/29
11/7/2018 20 Sample PMP® Questions and Answers

1. Do a Monte Carlo analysis using the Internet as a tool


Project Manageme… All Resources Articles E-Books On-Demand Webinars
2. Apply the critical path method

3. Determine options for recommended corrective action

4. Apply the Delphi Technique

The Delphi technique is commonly used to obtain expert opinions on technical


issues, the necessary project, or product scope.

18. Question:

Being assigned as a project manager, you noticed during project


execution that conflicts arise in the team on both technical and
interpersonal levels. What is an appropriate way of handling conflicts?

Answer:

1. Conflicts distract the team and disrupt the work rhythm. You should always
smooth them when they surface.

2. A conflict should be handled in a meeting so that the entire team can


participate in finding a solution.

3. Conflicts should be addressed early and usually in private, using a


direct, collaborative approach.
https://www.simplilearn.com/pmp-sample-questions-and-answers-article 15/29
11/7/2018 20 Sample PMP® Questions and Answers

4. You should
Project use your coercive
Manageme… powerArticles
All Resources to quickly resolve
E-Books conflictsWebinars
On-Demand and then
focus on goal achievement.

19. Question:

During which risk management process is a determination to transfer a


risk made?

Answer:

1. Identify Risks

2. Perform Quantitative Risk Analysis

3. Plan Risk Response

4. Monitor and Control Risks

Transference is a Risk Response Strategy.

20. Question:

When control charts are used, outliers are…

Answer:
https://www.simplilearn.com/pmp-sample-questions-and-answers-article 16/29
11/7/2018 20 Sample PMP® Questions and Answers

1. singular measurements
Project Manageme… outside Articles
All Resources the bandwidth between Webinars
E-Books On-Demand an upper
and lower control limit.

2. a typical result of a rare random cause which is difficult to replicate and to


verify.

3. insignificant results, often measurement errors, the causes of which should


not be further investigated.

4. measurements inconsistent with a run of 7 results over or under a mean


value.

Reference: Managing Project Quality by Timothy J. Kloppenborg and Joseph A.


Petrick

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 17/29
11/7/2018 20 Sample PMP® Questions and Answers

Project Manageme… All Resources Articles E-Books On-Demand Webinars

Conclusion

If you are considering working toward your PMP exam, Simplilearn offers a
variety of project management courses that will help you pass, including the
PMP Certification Training Course. Our PMP training courses are conducted by
certified, highly experienced professionals with at least 10 years of experience.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 18/29
11/7/2018 20 Sample PMP® Questions and Answers

Interested in learning more? View our video “Introduction to PMP Certification


Project Manageme… All Resources Articles E-Books On-Demand Webinars
Training” below.

Introduction To PMP Certi cation Training: Lesson 1 | Simplilearn

PMI, PMP, and PMBOK are registered marks of the Project Management Institute,
Inc.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 19/29
11/7/2018 20 Sample PMP® Questions and Answers

Find Project
our PMP ® Certification
Manageme… Online Classroom
All Resources training
Articles E-Books classes
On-Demand in top
Webinars
cities:

Name Date Place

PMP® Certification 16 Nov -14 Dec 2018, Weekdays batch Your City View Details

PMP® Certification 24 Nov -22 Dec 2018, Weekend batch Kuala Lumpur View Details

PMP® Certification 26 Nov -11 Dec 2018, Weekdays batch Perai View Details

About the Author

Pradip Dwevedi, PMP is currently the Lead PMP Trainer / Corporate Trainer at
Reputed Global R.E.P.s, India and also the Head – Project Management at Invida
Trans IT Solutions PVT LTD. Prior to this, he was Divisional Manager at Stylo
Graphic Imaging and before this he was working as Facilitator/Team Leader at
Aptara.

Recommended articles for you

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 20/29
11/7/2018 20 Sample PMP® Questions and Answers

Eleven important 10 Important Areas Analytical questions


Projectfor
questions Manageme…
PMP AllProject
of Resources Articles E-Books
from On-Demand
Procurement Webinars
Management Intervi... Management knowl...

Article Article Article

LEAVE COMMENT

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 21/29
11/7/2018 20 Sample PMP® Questions and Answers

2 Comments Simplilearn 
1 Login
Project Manageme… All Resources Articles E-Books On-Demand Webinars

 Recommend 3 t Tweet f Share Sort by Best

Join the discussion…

LOG IN WITH
OR SIGN UP WITH DISQUS ?

Name

Deepti • 3 years ago


Question 5 - The Answer should be B
△ ▽ • Reply • Share ›

Gia Preston • 4 years ago


Don't you mean "B?"
5) Risk will be identified during which risk management process(es)?

Perform Quantitative Risk Analysis and Identify Risks.


Identify Risks and Monitor and Control Risks.
Perform Qualitative Risk Analysis and Monitor and Control Risks.
Identify Risks.

Answer: C Risks are identified during the Identify Risk processes naturally, but emerging risks are
identified in Monitor and Control Risks Processes
△ ▽ • Reply • Share ›

✉ Subscribe d Add Disqus to your siteAdd DisqusAdd 🔒 Disqus' Privacy PolicyPrivacy PolicyPrivacy

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 22/29
11/7/2018 20 Sample PMP® Questions and Answers

Project Manageme… All Resources Articles E-Books On-Demand Webinars

PMBOK® Guide – Sixth Edition is Here! What Project


Managers Should Know

Tim Jerome
Published on Aug 16, 2017

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 23/29
11/7/2018 20 Sample PMP® Questions and Answers

30937 Views 3 Comments


Project Manageme… All Resources Articles E-Books On-Demand Webinars

PMBOK® Guide – Sixth Edition was released in September 2017 and


PMP ® certification exam format will be revised on 26 March 2018 , according to
PMI.

The exam is not about the PMBOK Ⓡ Guide , but the guide does influence the
exam a lot. Here’s what to expect, and what you could see as impacts to the
exam as a result of the updated 6th edition.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 24/29
11/7/2018 20 Sample PMP® Questions and Answers

Project Manageme… All Resources Articles E-Books On-Demand Webinars


Centralization of Effective Leadership

A chapter has been added that talks about what Project Management
Leadership means, and PMI’s expectations of a project management leader. The
new edition also reviews competencies and skills that project management
professionals must possess. This makes sense, considering that we’ve seen the
Exam Content Outline introduce this throughout the last few years, and it was a
logical step to bring it into the guide.

Effective leadership is mentioned in the 5th edition but is now being


consolidated into one section. Consider this as a continuation of PMI’s message—
a call to action that Project Management has three components that aspiring
professionals need to continually develop: technical project management,
business acumen, and leadership.

Preparing for your PMP® Certification? Take this Practice Test to learn
where you stand.

Terminology Changes

The 5th edition of the PMBOK® Guide made great progress in standardizing
phrases, terms, and definitions. This was needed to achieve alignment with the
ISO standard 21500. This, also, was a bigger change than one would consider—
the PMI Lexicon of terms and Exam Content Outline were aligned to match the
same terminology. This was a big step. Once this was achieved, students and

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 25/29
11/7/2018 20 Sample PMP® Questions and Answers

project managers could see a term in one area, knowing it would mean the same
Project
in every otherManageme…
use. All Resources Articles E-Books On-Demand Webinars

This new edition continues towards terminology consistency, with these primary
updates:

Human Resource Management will become Resource Management. This means


you don’t merely manage teams, but also bulldozers, shovels, cases of nuts
and bolts, and bottled water.

Time Management will become Schedule Management. This makes sense; we


don’t manage time, but we manage and control our schedule.

It’s interesting how PMI discusses these changes; they state “… Areas have been
renamed to more accurately reflect which elements can be managed… and which
cannot…”

Knowledge Area Changes

The structure of the Knowledge Areas will be updated, with the following details:

Key Concepts will be organized. You can look to a specific section to review
the core message of the knowledge area.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 26/29
11/7/2018 20 Sample PMP® Questions and Answers

Project
Trends andManageme… All Resources
Emerging Practices haveArticles E-Books Current
been added. On-Demand Webinars
learnings and
business behavior are now seen to be a component that you can integrate and
are expected to consider. The guide is not something static, but something
that we can modify based on needs inside and outside the project. It is moved
closer to a dynamic set of tools supported by thoughtful analysis as well as
best practice.

Tailoring Considerations are now a component of each Knowledge Area.


Again, having each section discuss how to modify it based on constraints,
consideration, organizational preference, and business need is exciting. Having
guidance in modifying the PMBOK® Guide will assist in understanding that this
is a component of control, required if you are to actively manage.

Considerations for Agile/Adaptive Environments are included. Agile is


currently mentioned as a methodology in Project Life Cycle discussions. In the
6th edition, each Knowledge Area will provide considerations for integrating
agile methods based on its skill set and processes.

All these updates support not only increased clarity but also provide a focus on
how this material can be best applied. This is the core of the PMP Certification
Exam; it tests not only one’s knowledge but how well the applicant can apply
what they know as a best practice in ambiguous, often confusing situations.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 27/29
11/7/2018 20 Sample PMP® Questions and Answers

This bodes well for the profession of project management, and it bodes well for
Project Manageme… All Resources Articles E-Books On-Demand Webinars
us, too. The guide gives us not only what we need to do today to make projects
and business better, but what we need to think about and prepare for the future.
Project management and our careers within it are a continuing story, not a
stairway that ends with a closed door.

PMP, PMBOK are registered marks of the Project Management Institute, Inc.

Find our PMP® Certification Online Classroom training classes in top


cities:

Name Date Place

PMP® Certification 16 Nov -14 Dec 2018, Weekdays batch Your City View Details

PMP® Certification 24 Nov -22 Dec 2018, Weekend batch Kuala Lumpur View Details

PMP® Certification 26 Nov -11 Dec 2018, Weekdays batch Perai View Details

About the Author

Tim Jerome, PMP® MBA, has led and supported projects globally for over 15
years. Tim has taught Project Management and PMP® Certification
preparatory courses for over 10 years, assisting in educating and supporting
hundreds of project managers.

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 28/29
11/7/2018 20 Sample PMP® Questions and Answers

Recommended articles for


Project Manageme… you
All Resources Articles E-Books On-Demand Webinars

PMBOK® - A Guide to Rita Mulcahy's PMP Studying PMBOK® 6:


Project Management Prep and PMBOK Why Good Is Better
Body of Knowledge Guide Than Best in Projec...

Article Article Article

LEAVE COMMENT

https://www.simplilearn.com/pmp-sample-questions-and-answers-article 29/29

You might also like