Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : LINE TRAP TEST SHEET NO. AT301X


sh. 1 of 1

Description :

Item :

Single Line : FCD :

Test : 1) Visual Inspection


2) Pre-commissioning Checks
Note : Test Procedure from sheet 2
______________________________________________________________________________

STEP CHECK DESCRIPTION


1. Visual Inspection (Ref. . Dwg. __________)
1.1 Installation completeness
Serial Number :
R_______ Y __________ B ____________
1.2 Equipment integrity (no visual damages)
1.3 Internal Pot completeness
1.4 Connections tight
2. Pre-operational checks
Following nameplate data shall match design characteristics :
2.1 Nominal frequency
2.2 Nominal inductance
2.3 Nominal current
2.4 H.F. band frequency
The equipment is ready for energizing.

TEST METHOD
1. Visual Inspection
Visual Inspection shall be carried out to ensure that the equipment is completed,
correctly installed and without damaged parts.
2 Pre-operational Checks
Pre-operational Checks ensure that the equipment is ready for operation.

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 5

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : LIGHTNING ARRESTER TEST SHEET NO. AT302X


sh. 1 of 1

Description :

Item :

Single Line : FCD :

Test : 1) Visual Inspection


2) Insulation resistance measurement

Note : Test Procedure from sheet 2


______________________________________________________________________________

STEP CHECK DESCRIPTION


1. Visual Inspection (Ref. Dwg. _____________________)
1.1 Installation completed
Serial Number :
R ___________ Y ____________ B ___________
1.2 Steel structure galvanizing painting
Isolator integrity and cleaning
Ground terminal properly connected
Connections tight
Data plate checked
Surge counter : Manufacturer _________________Type ________________
Serial Number :
R ___________ Y ____________ B ___________
Readings / Date :
R ___________ Y ____________ B ___________
____/____/____ ____/____/____ ___/___/___
R ___________ Y ____________ B ___________
____/____/____ ____/____/____ ___/___/___
2. Insulation Resistance Measurement
Between main terminals (lightning arrester)

TEST METHOD
1. Visual Inspection
Visual Inspection shall be carried out of ensure that it is complete, correctly installed and
without any damaged parts.
During visual inspection, surge counter readings shall be checked and recorded.
2. Insulation Resistance Measurement
The test shall be performed applying the voltage of 5000 Vdc between the line terminal
and the ground terminal.

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 6

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303AX
sh. 1 of 1

Description :

Item :

Single Line : FCD :

Test : 1) Visual Inspection


________________________________________________________________________________________

STEP CHECK DESCRIPTION


1. Visual Inspection must be carried out to check for the correct installation of the equipment, and
that it is complete and undamaged.
2. Equipment installation according to assembly dwg. _______________________
3. Completion
4. Cleaning
5. Visual Damage
6. Rating according to drawing
7. H.V. connections
8. M.V. connections
9. Connections according to rating plate
10. Isolators
11. Lighting arrester (if applicable)
12. Arching horns gap check (if applicable)
13. Wheel-locking (if applicable)
14. Ground connection
15. Star-point grounding
16. Silicagel breather Transformer tank
17. Buchholz relay Transformer tank
18. Oil level Transformer tank
19. Silicagel breather O.L.T.C.
20. Buchholz relay O.L.T.C.
21. Oil level O.L.T.C.
22. Auxiliary services panel
23. Oil valves
24. Oil pipes
25. Oil leaks
26. Dial type thermometer
27. Thermal image relay
28. Sufficient oil quantity in the pocket of thermal sensors
29. Safety valves (overpressure)
30. Auxiliary cable connections
31. Oil pumps
32. Cooling fans
33. Fire fighting system
34. Painting checks

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 7

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303BX
sh. 1 of 2

Description :

Item :

Single Line : FCD :

Test : 1) Oil Dielectric Strength


2) Insulation Test
Note : Test Procedure from sheet 2
______________________________________________________________________________

TEST RESULT

1) Oil Dielectric Strength


Sample Trans. Oil OLTC Oil OLTC Oil Ambient
Test Bottom Top Bottom Temperature Note
0
No. kV kV kV C
1.
2.
3.
4.
5.
6.
Average
Date

2) Insulation Resistance

Date Test Readings after Note Date Test Readings after Note
1 min 2 min 3 min 1 min 2 min 3 min
No. Mohm Mohm Mohm No. Mohm Mohm Mohm
2.1) 2.4)
2.2) 2.5)
2.3) 2.6)

Oil temperature : ____ 0 C Ambient temperature : _____ 0 C

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 8

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303BX
sh. 2 of 2

TEST PROCEDURE

1) Oil Dielectric Strength

Test is carried out in accordance with Standards :


I.E.C. 156-1963; I.E.C. 296-1969
The two oil samples must be taken from the bottom of each transformer compartment.
The oil from the transformer tank and the O.L.T.C. (if mounted) must be tested.
Particular care must be taken to avoid pollution by air moisture or dust when the oil
samples are taken.
Glass containers must be used to move the samples. Six tests must be carried out at
reasonable interval on each oil sample (10 minutes interval is suggested). After each
test, the oil must be stirred with a clean glass rod in order to remove any suspended
matter which has formed between the electrodes after the discharge. Value of the
dielectric strength voltage must be given by the average of the above values.
a) ___ 30 kV with spherical electrodes at 2.5 mm. distance on new untreated oil
b) ___ 50 kV with spherical electrodes at 2.5 mm distance on treated oil
c) ___ kV with ______ electrodes at _____ mm distance j

2) Insulation Test
The test must be carried out to check insulation conditions of windings.
The test shall be carried out by applying a voltage of :
2.1) 5000 V dc between H.V. & M.V. winding connected to ground
2.2) 5000 V dc between M.V. & H.V. winding connected to ground
2.3) 5000 V dc between second M.V. & H.V. winding connected to ground (if
applicable)
2.4) 2500 V dc between L.V. & M.V. / H.V. windings connected
2.5) _______ V dc between _____________________________________________
2.6) _______ V dc between _____________________________________________
______________________________________________

Note : After each test, the tested circuits must be grounded. Minimum recommended
winding insulation resistance value is between 300 & 1000 Mohm, unless
otherwise specified by the Manufacturer.

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 9

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303CX
sh. 1 of 2

Description :

Item :

Single Line : FCD :

Test : Ratio measurement


_________________________________________________________________________

TEST PROCEDURE

The test must be carried out by applying voltage (low voltage 380 or 220 V.A.C.
normally) of ____ V to H.V. winding at rated frequency.
The test must be carried out by using two volt-meters; one to read voltage of H.V.
winding and the other to read L.V. winding.
The two voltmeters must be read at the same time.
The test must be carried out on all phases and for each position of the tap changer.

TEST CIRCUIT

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 10

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303CX
sh. 2 of 2

TEST RESULT

OLTC Theoretical Voltmeter Voltmeter Measured


pos. Ratio K ____ side ____ side Ratio
(T) (V1) V (V2) V K (M) = V1
V2
VAB= Vab=
VBC= Vbc=
VCA= Vca=
VAB= Vab=
VBC= Vbc=
VCA= Vca=
VAB= Vab=
VBC= Vbc=
VCA= Vca=
VAB= Vab=
VBC= Vbc=
VCA= Vca=
VAB= Vab=
VBC= Vbc=
VCA= Vca=
VAB= Vab=
VBC= Vbc=
VCA= Vca=
VAB= Vab=
VBC= Vbc=
VCA= Vca=

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 11

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303EX
sh. 1 of 5

Description :

Item :

Single Line : FCD :

Test : Operating commissioning tests

Note : Test Procedure from sheet 4


______________________________________________________________________________

STEP COMMISSIONING TEST DESCRIPTION

1) Power Plant (Ref. Dwg ____________________ )


1.1) Electric power supply OLTC
1.2) Electric power supply to aux.
1.3) Electric power supply to fans
1.4) Electric power supply to pumps
1.5) Electric power supply to heating elements and lamps
2) On-load Tap Changer (if provided)
(Ref. Dwg.____________________)
2.1) Gear box oil level
2.2) Manual operation
2.3) Local electric step-by-step operation
2.4) Limit switches operation
2.5) Remote operation
2.6) Voltage regulating relay tested (if provided)
2.7) Motor overload protection value visual check

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 12

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303EX
sh. 2 of 5

3) Cooling Circuit

3.1) ONAF 3.2) OFAF 3.3) ODAF

FANS OIL CIRCULATING PUMPS


No Motor Dir. Nomin. Over Absorb. No Motor Dir. Nomin. Over Absorb.
Insul. of Power Load Current Insul. of Power Load Pr. Current
Mohm Rot. kW Pr. Sett A Mohm Rot. kW Sett A
A A
1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

9 9

10 10

11 11

12 12

13 13

14 14

15 15

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 13

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303EX
sh. 3 of 5

4) Control, Signalling and Alarm Circuit

4.1) Winding temperature relay 1st step (pump start)


2nd step (fan start)
3rd step (alarm)
4th step (lock)
4.2) Winding temperature relay 1st step (pump start)
2nd step (fan start)
3rd step (alarm)
4th step (lock)
4.3) Oil thermometer 1st step (alarm)
2nd step (lock)
4.4) Transformer gas relay - Air drainage
1st step (1st alarm)
2nd step (lock)
4.5) O.L.T.C. gas relay - Air drainage
1st step (alarm)
2nd step (lock)
4.6) Transformer oil level max. (alarm)
min. (alarm)
4.7) O.L.T.C. oil level max. (alarm)
min. (alarm)
4.8) Safety valve 1st step (lock)
2nd step (lock)
4.9) Temperature detector : 1st step
2nd
3rd
4th
5th
6th

5) Metering and Protection Circuit


5.1) Bushing CTs secondary circuits short circuit jumpers (where necessary)
5.2) Metering Circuits & Protective relays

6) Heating Elements and Compartment Lighting


6.1) Auxiliary board heating element
6.2) Auxiliary board thermostat

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 14

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303EX
sh. 4 of 5

6.3) Auxiliary board lighting lamps


6.4) O.L.T.C. oil level
6.5) O.L.T.C. board thermostat
6.6) O.L.T.C. board lighting lamps

Transformer ready for energizing

TEST PROCEDURE

All tests listed below must be carried out with transformer OUT OF SERVICE.
All control components and external connections must be tested in normal operating
conditions.

Their operation must be checked according to relevant diagram.

1. Power Supplies

Polarity & Voltage supply must be checked, and setting value of associated
protective devices visual checked.

2. On-load Tap Changer

A complete manual scan must be carried out to check the correspondence of each
position and the control device indication.

2.1) Check the oil level in the gear box.


2.2) Check that with the handle inserted local/remote electrical control is not
possible (if possible).
2.3) With control switch in LOCAL position, check relevant indication in Control
Room.
Check that the device runs correctly from one position to the next, step by
step, by means of local buttons INCREASE - DECREASE. Check also that
no operation is possible from distance push buttons.
2.4) Check the correct operation of end limit switches.
2.5) With control switch in REMOTE position, check that no local control is
possible.
Check remote control, remote signalization & steps indicator.
2.6) Check voltage regulating relay (if provided).
2.7) Motor overload protection setting value visual check.

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 15

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (MAIN) TEST SHEET NO. AT303EX
sh. 5 of 5

3) Cooling Circuit

3.1) ONAF cooling system.

Check rating plate, motor insulation, connections at motor terminals, visually


overload protection setting value, direction of rotation and current absorbed
by the electric fans and oil circulating pumps.

3.2) ONAF or ODAF cooling system.

Check rating plate, motor insulation, connections at motor terminals, visually


overload protection setting value, direction of rotation and current absorbed
by the electric fans and oil circulating pumps.

4) Control, Signalling & Alarm Circuits

Check that each component carries out its operative sequence correctly, according
to logic and / or schematic diagrams.
The correct operation of alarms and signals, must be checked and / or simulated.
All devices that when tested are not operative must be manually or electrically
actuated.

5) Metering and Protection Circuit

5.1) Short circuit jumper on CT’s secondary terminals must be removed only
when secondary circuit is a closed loop.
5.2) Metering & Protection circuits shall be tested according to relevant dwg. &
specs.

6) Control Cubicles Heating Elements and Lighting

It shall be checked that heating elements and lighting lamps operate correctly by
actuation of their control equipment.

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 16

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (AUX.) TEST SHEET NO. AT304X
sh. 1 of 4

Description :

Item :

Single Line : FCD :

Test : 1) Visual Inspection/Pre-commissioning


2) Oil Dielectric Strength
3) Insulation Test
4) Ratio Measurement

Note : Test Procedure from sheet 3


______________________________________________________________________________

STEP PRE COMMISSIONING CHECK DESCRIPTION

Visual Inspection/Pre-commissioning
1. - Equipment installation according to assembly dwg.
2. - Completion / Cleaning / Painting.
3. - Visual damages
4. - Rating according to drawing
5. - M.V. / L.V. connections according to rating
plate
6. - Wheel-locking (if applicable)
7. - Ground connection (tank)
8. - Star-point grounding (if applicable)
9. - Silicagel breather
10. - Buchholz relay checks
11. - Oil level and checks
12. - Oil leaks
13. - Dial type thermometer and setting
14. - Safety valves (overpressure)
15. - Auxiliary cable connections
16. - Fire fighting system

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 17

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (AUX.) TEST SHEET NO. AT304X
sh. 2 of 4

2) Oil Dielectric Strength

Sample Test Trans. Oil Trans. Oil Trans. Oil Trans. Oil Note
No. Bottom kV Bottom kV Bottom kV Bottom kV
1
2
3
4
5
6
Average
Amb. Temp.
C
Date

3) Insulation Resistance

Date Test Readings after Note Date Test Readings after Note
No. No.
1 min 2 min 3 min 1 min 2 min 3 min
Mohm Mohm Mohm Mohm Mohm Mohm
3.1)
3.2)
3.3)

Oil temperature : _____ 0 C Ambient temperature : _________ 0 C

4) Ratio Measurement

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 18

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (AUX.) TEST SHEET NO. AT304X
sh. 3 of 4

No-Load Tap Theoretical Voltmeter Voltmeter Measured


Changer Pos. Ratio K _____ side _____ side Ratio
(T) (v1) V (v2) V K (M) = V1
V2
VAB = Vab =
+5 VBC = Vbc =
VCA = Vca =
VAB = Vab =
+ 2, 5 VBC = Vbc =
VCA = Vca =
VAB = Vab =
0 VBC = Vbc =
VCA = Vca =
VAB = Vab =
- 2, 5 VBC = Vbc =
VCA = Vca =
VAB = Vab =
-5 VBC = Vbc =
VCA = Vca =

TEST PROCEDURE

1) Visual Inspection

Visual Inspection must be carried out to check for the correct installation of the
equipment, and that it is complete and undamaged.

2) Oil Dielectric Strength

Test is carried out in accordance with Standards :


I. E. C. 156-1963; I E.C 296 - 1969

Two oil samples must be taken from the bottom of each transformer compartment.
The oil from the transformer tank and the O.L.T.C. (if mounted) must be tested.
Particular care must be taken to avoid pollution by air moisture or dust when the oil
samples are taken.
Glass containers must be used to move the samples.

Six tests must be carried out at reasonable interval on each oil sample (10 minutes
interval is suggested).

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 19

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : OIL IMMERSED TRANSFORMER (AUX.) TEST SHEET NO. AT304X
sh. 4 of 4

After each test, the oil must be stirred with a clean glass rod in order to remove any
suspended matter which has formed between the electrodes after the discharge.

Value of the dielectric strength voltage must be given by the average of the above values.

The minimum value of oil dielectric strength shall be :


a) ___ 30 kV with spherical electrodes at 2.5 mm. distance on new untreated oil
b) ___ 50 kV with spherical electrodes at 2.5 mm. distance on treated oil
c) ___ kV with _________ electrodes at ____ mm. distance

3) Insulation Test

The test must be carried out to check insulation conditions of windings.


Test shall be carried out by applying a voltage of :
3.1) 5000 Vdc between M.V. & L.V. winding connected to ground
3.2) 1500 Vdc between L.V. & M.V. winding connected to ground
3.3) ______ Vdc between ________________________________

NOTE : After each test, the tested circuits must be grounded. Minimum recommended
winding insulation resistance value is between 300 & 1000 Mohm, unless
otherwise specified by the Manufacturer.

4) Ratio Measurement

The test must be carried out by applying voltage (low voltage 380 or 220 V. A. C. normally)
of ___ V to M.V. winding at rated frequency.
The test must be carried out by using two voltmeters; one to read voltage of M.V. winding
and the other to read L.V. winding.
The two voltmeters must be read at the same time. The test must be carried out on all
phases and for each position of the tap changer.

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 20

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : AERIAL INSTALLATION & SUPPORTS TEST SHEET NO. AT306X
sh. 1 of 2

Description :

Item :

Single Line : FCD :

Test : 1) Pre-commissioning & Measurements

Note : Test Procedure from sheet 2


______________________________________________________________________________

STEP TEST DESCRIPTION DESIGN ACTUAL REMARKS


VALUE READING
1) Equipment inspected

2) Installation completeness
(ref. dwg. _____________________________
_____________________________________)

3) Busbar checks : Quantity Check Phase


R Y B
3.1) Clamps bottle tightness
3.2) Sliding supports free
3.3) Oscillation dampers
3.4) Minimum clearance
3.5) Welding checks
If special tests are required, enclose
reports :
3.6) Insulation measure (ph./gnd.) R Y B
(if required)
3.7) D.C. resistance (if required)

Company Name Signature Date


Performed By :

Witnessed By :

Witnessed By :
Doc.No: Revision: Date: Page:
ELE/TSS/AT 300 X 21

Dept.:
COMMISSIONING
ELECTRICAL TEST SHEET Language:
E
Project: STANDARD COMMISSIONING PROCEDURES

Equipment Description : AERIAL INSTALLATION & SUPPORTS TEST SHEET NO. AT306X
sh. 2 of 2

4) Supports checks : R Y B
4.1) Structure integrity
4.2) Painting & galvanizing
4.3) Ground connection
4.4) Insulator cleanliness
4.5) Insulator integrity
4.6) Bolts tightness
4.7) Labelling (if required)

5) Aerial Conductors checks : R Y B


5.1) Oscillation dampers
5.2) Minimum clearance
5.3) Insulation measure (ph. /gnd.) if required
5.4) D.C. ohmic resistance (if required)
5.5) Homopolar impedance Xo (if required)
5.6) Guard conductor connection to ground (if
applicable)
- Ambient temperature

TEST METHOD

Visual Inspection shall be carried out to ensure that the equipment is complete, correctly
installed and without damaged parts.

Company Name Signature Date