You are on page 1of 53

COSTOS DE EQUIPOS

DIESEL (RD$) 174.00


PRECIO HORARIO COMBUSTIBLE LUBRICANTES COSTO TOTAL
RD$/HORA RD$/HORA RD$/HORA RD$/HORA

Tractor Cat D8l/K-155 2,900.00 2,262.00 452.40 5,614.40


Motoniveladora Cat-12G 1,500.00 870.00 174.00 2,544.00
Estabilizadora Cat RM-350B 10,000.00 2,436.00 487.20 12,923.20
Vibrocompactador Ingersoll Rand SD100 1,400.00 609.00 121.80 2,130.80
Vibrocompactador Dynapac CC122 700.00 348.00 69.60 1,117.60
Compactador manual 190.00 43.50 8.70 242.20
Cargardor Cat 950 1,400.00 870.00 174.00 2,444.00
Camion de agua Ford 450 2500 gls 500.00 435.00 87.00 1,022.00
Excavadora Doosan 300 2,100.00 1,392.00 278.40 3,770.40
Excavadora Cat-320 C 1,700.00 1,044.00 208.80 2,952.80
Retroexcavadora Cat 416 1,200.00 435.00 87.00 1,722.00
Camion Daihatsu 2 m3 350.00 348.00 69.60 767.60
Camioneta Toyota 1 cabina 190.00 174.00 34.80 398.80
Generador torre de luz 200.00 174.00 34.80 408.80
CANTIDAD UNIDAD COSTO TOTAL
Acarreo en volteo de 0-5kms 1.00 M3E 70.00
Acarreo en volteo km sub-secuente relleno 1.00 M3E-KM 14.00
Traslado de equipo en la ciudad 1.00 UND 12,000.00

Página 1 de 414200015.xls
COSTOS DE MATERIALES

DESCRIPCION CANTIDAD UNID PRECIO IMPUESTO FLETE PRECIO


BASICO 18.00% A OBRA TOTAL RD$

Diesel 1.00 GL. 170.00 - 4.00 174.00


Gasolina 1.00 GL. 185.00 - 4.00 189.00
Base triturada 1.00 M3E 600.00 375.00 975.00
Grava y gravilla triturada 1.00 M3E 510.00 91.80 375.00 976.80
Material de relleno (prestamo local) 1.00 M3S 125.00 - 200.00 325.00
Derecho de Mina 1.00 M3S 55.00 - 55.00
Equipos menores gastables 1.00 DIA 500.00 90.00 590.00
Cambio Prima Dólar 1.00 US$ 44.75
COSTOS DE MANO DE OBRA

US$ 44.75
FACTOR DE AJUSTE = 1.350

CATEGORIA SALARIO TOTAL SALARIO BASICO EQUIV.

RD$/HR RD$/HR RD$/MES RD$/HR


Ing. Residente $472.50 $ 350.00 $ 66,733.33 $ 350.00
Ing. Control de Obra $371.25 $ 275.00 $ 52,433.33 $ 275.00
Topografo $283.50 $ 210.00 $ 40,040.00 $ 210.00
Nivelador $202.50 $ 150.00 $ 28,600.00 $ 150.00
Porta prisma $101.25 $ 75.00 $ 14,300.00 $ 75.00
Capataz $202.50 $ 150.00 $ 28,600.00 $ 150.00
Chequeador $81.00 $ 60.00 $ 11,440.00 $ 60.00
Op Tractor $175.50 $ 120.00 $ 22,880.00 $ 130.00
Op Cargador $162.00 $ 120.00 $ 22,880.00 $ 120.00
Op Motoniveladora $175.50 $ 140.00 $ 26,693.33 $ 130.00
Ayutande Equipos $81.00 $ 60.00 $ 11,440.00 $ 60.00
Op Excavadora $175.50 $ 120.00 $ 22,880.00 $ 130.00
Op Compactador (5-12 ton) $162.00 $ 100.00 $ 19,066.67 $ 120.00
Peon $67.50 $ 50.00 $ 9,533.33 $ 50.00
Supervisor Seguridad $135.00 $ 100.00 $ 19,066.67 $ 100.00
Parqueador $81.00 $ 60.00 $ 11,440.00 $ 60.00
Mecanico Campo $135.00 $ 100.00 $ 19,066.67 $ 100.00
Sereno $67.50 $ 50.00 $ 9,533.33 $ 50.00
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Ingenieria 3.92

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
Transito, Mira, Nivel, Estacion Total, Prisma, mes 4.00 $20,000.00 $80,000.00
cinta, etc $0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $80,000.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Camion Daihatsu 2 m3 horas 4.00 767.60 3,070.40


Camioneta Toyota 1 cabina horas 4.00 398.80 1,595.20
0.00
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $4,665.60

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Ing. Residente mes 4.00 $66,733.33 $266,933.33


Ing. Control de Obra mes 8.00 $52,433.33 $419,466.67
Topografo mes 4.00 $40,040.00 $160,160.00
Nivelador mes 4.00 $28,600.00 $114,400.00
Porta prisma mes 4.00 $14,300.00 $57,200.00
Peon mes 4.00 $9,533.33 $38,133.33
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $1,056,293.33
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $1,140,958.93

PROFIT / UTILIDAD 5% $57,047.95

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $1,198,006.88


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $305,458.15
s)

Km

AMOUNT
IMPORTE
$0.00
$0.00
$80,000.00
$0.00
$0.00
$0.00
$0.00
$0.00
$80,000.00

AMOUNT
IMPORTE

3,070.40
1,595.20
0.00
0.00
0.00
0.00
0.00
0.00
0.00
$4,665.60

AMOUNT
IMPORTE

$266,933.33
$419,466.67
$160,160.00
$114,400.00
$57,200.00
$38,133.33
$0.00
$1,056,293.33
$1,140,958.93

$57,047.95

$1,198,006.88
$305,458.15
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD PA
Mantenimiento de tránsito 1.00

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $0.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Motoniveladora Cat-12G horas 40.00 2,544.00 101,760.00


Vibrocompactador Ingersoll Rand SD100 horas 40.00 2,130.80 85,232.00
Camion de agua Ford 450 2500 gls horas 40.00 1,022.00 40,880.00
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $227,872.00

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Op Motoniveladora hora 40.000000 $175.50 $7,020.00


Op Compactador (5-12 ton) hora 40.000000 $162.00 $6,480.00
Chequeador hora 40.000000 $81.00 $3,240.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $16,740.00

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $244,612.00

PROFIT / UTILIDAD 5% $12,230.60

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $256,842.60


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $256,842.60
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Campamento, oficina de campo 1.00

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $0.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Acondicionamiento terreno para campamento pa 1.00 5,000.00 5,000.00


Instalaciones Electricas, Sanitarias, Etc. pa 1.00 5,000.00 5,000.00
Sereno, vigilancia nocturna mes 4.00 9,533.33 38,133.33
Oficina furgón 20' mes 4.00 21,240.00 84,960.00
Sanitario Oficina y Obreros mes 4.00 10,620.00 42,480.00
Limpieza y Mantenimiento mes 4.00 3,000.00 12,000.00
Generador torre de luz mes 4.00 42,515.20 170,060.80
Mobiliario pa 1.00 15,000.00 15,000.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $372,634.13

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $0.00
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $372,634.13

PROFIT / UTILIDAD 5% $18,631.71

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $391,265.84


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $391,265.84
s)

PA

AMOUNT
IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

AMOUNT
IMPORTE

5,000.00
5,000.00
38,133.33
84,960.00
42,480.00
12,000.00
170,060.80
15,000.00
0.00
$372,634.13

AMOUNT
IMPORTE

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$372,634.13

$18,631.71

$391,265.84
$391,265.84
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Laboratorio de campo para densidad de materiales 28,630.60

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
Mecanica de Suelos, ensayos und 10.00 $5,000.00 $50,000.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $50,000.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

0.00
Equipo Ganmadensímetro mes 3.00 30,000.00 90,000.00
Camioneta Toyota 1 cabina mes 3.00 35,094.40 105,283.20
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $195,283.20

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

$0.00
Operador mes 3.000000 $25,000.00 $75,000.00
Ayudante mes 3.000000 $15,000.00 $45,000.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $120,000.00
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $365,283.20

PROFIT / UTILIDAD 5% $18,264.16

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $383,547.36


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $13.40
s)

m2

AMOUNT
IMPORTE
$0.00
$0.00
$0.00
$50,000.00
$0.00
$0.00
$0.00
$0.00
$50,000.00

AMOUNT
IMPORTE

0.00
90,000.00
105,283.20
0.00
0.00
0.00
0.00
0.00
0.00
$195,283.20

AMOUNT
IMPORTE

$0.00
$75,000.00
$45,000.00
$0.00
$0.00
$0.00
$0.00
$120,000.00
$365,283.20

$18,264.16

$383,547.36
$13.40
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Laboratorio de campo para pruebas de hormigón 6,563.49

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
Pileta para curado pa 1.00 $10,000.00 $10,000.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $10,000.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

0.00
Rotura de probetas und 937.64 250.00 234,410.36
Camioneta Toyota 1 cabina mes 2.00 35,094.40 70,188.80
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $304,599.16

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

$0.00
Encargado mes 3.000000 $25,000.00 $75,000.00
Ayudante mes 3.000000 $15,000.00 $45,000.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $120,000.00
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $434,599.16

PROFIT / UTILIDAD $0.00

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $434,599.16


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $66.21
s)

m3

AMOUNT
IMPORTE
$0.00
$0.00
$0.00
$10,000.00
$0.00
$0.00
$0.00
$0.00
$10,000.00

AMOUNT
IMPORTE

0.00
234,410.36
70,188.80
0.00
0.00
0.00
0.00
0.00
0.00
$304,599.16

AMOUNT
IMPORTE

$0.00
$75,000.00
$45,000.00
$0.00
$0.00
$0.00
$0.00
$120,000.00
$434,599.16

$0.00

$434,599.16
$66.21
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Nivelacion final hasta subrasante de calles, y areas a desarrollar (Incluye Corte y 28,630.60
Relleno, Compactación, Carguio, Acarreo y Bote)
MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $0.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Motoniveladora Cat-12G hora 286.31 2,544.00 728,362.46


Vibrocompactador Ingersoll Rand SD100 hora 286.31 2,130.80 610,060.82
Camion de agua Ford 450 2500 gls hora 286.31 1,022.00 292,604.73
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $1,631,028.02

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora 286.31 $202.50 $57,976.97


Chequeador hora 286.31 $81.00 $23,190.79
Peon hora 1,145.22 $67.50 $77,302.62
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $158,470.37
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $1,789,498.39

PROFIT / UTILIDAD 5% $89,474.92

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $1,878,973.31


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $65.63
s)

m2

AMOUNT
IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

AMOUNT
IMPORTE

728,362.46
610,060.82
292,604.73
0.00
0.00
0.00
0.00
0.00
0.00
$1,631,028.02

AMOUNT
IMPORTE

$57,976.97
$23,190.79
$77,302.62
$0.00
$0.00
$0.00
$0.00
$158,470.37
$1,789,498.39

$89,474.92

$1,878,973.31
$65.63
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD m2
Escarificación 28,630.60

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $0.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Motoniveladora Cat-12G hora 95.44 2,544.00 242,787.49


0.00
Camion de agua Ford 450 2500 gls hora 95.44 1,022.00 97,534.91
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $340,322.40

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora 95.44 $202.50 $19,325.66


$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $19,325.66

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $359,648.05

PROFIT / UTILIDAD 5% $17,982.40

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $377,630.46


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $13.19
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD m3
Base Granular de pavimento de Calles y Avenidas (0.15m) al 95% de 4,294.59
compactación del proctor modificado
MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
Base triturada m3 5,368.24 $975.00 $5,234,031.56
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $5,234,031.56

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Motoniveladora Cat-12G hora 89.47 2,544.00 227,613.27


Vibrocompactador Ingersoll Rand SD100 hora 89.47 2,130.80 190,644.01
Camion de agua Ford 450 2500 gls hora 89.47 1,022.00 91,438.98
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $509,696.26

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora 89.47 $202.50 $18,117.80


Chequeador hora 89.47 $81.00 $7,247.12
Peon hora 357.88 $67.50 $24,157.07
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $49,521.99

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $5,793,249.81

PROFIT / UTILIDAD 5% $289,662.49

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $6,082,912.30


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $1,416.41
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD m3
Excavaciones generales menores de 1 mt 1.00

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $0.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
Retroexcavadora Cat 416 hora 0.04 2,952.80 118.11
0.00
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $118.11

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Op Excavadora hora 0.040000 $175.50 $7.02


Chequeador hora 0.040000 $81.00 $3.24
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $10.26

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $128.37

PROFIT / UTILIDAD 5% $6.42

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $134.79


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $134.79
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Relleno de Reposición 1.00

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $0.00

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
0.00
Compactador manual hora 0.50 242.20 121.10
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $121.10

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora 0.125000 $202.50 $25.31


Peon hora 0.250000 $67.50 $16.88
Ayutande Equipos hora 0.125000 $81.00 $10.13
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $52.31

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $173.41

PROFIT / UTILIDAD 5% $8.67

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $182.08


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $182.08
s)

m3

AMOUNT
IMPORTE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

AMOUNT
IMPORTE
0.00
121.10
0.00
0.00
0.00
0.00
0.00
0.00
$121.10

AMOUNT
IMPORTE

$25.31
$16.88
$10.13
$0.00
$0.00
$0.00
$0.00
$52.31

$173.41

$8.67

$182.08
$182.08
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

USOH DR HOUSING

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Relleno compactado #REF!

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
Relleno m3 #REF! $325.00 #REF!
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES #REF!

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
0.00
Motoniveladora Cat-12G hora #REF! 2,544.00 #REF!
Vibrocompactador Ingersoll Rand SD100 hora #REF! 2,130.80 #REF!
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO #REF!

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora #REF! $202.50 #REF!


Peon hora #REF! $67.50 #REF!
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA #REF!

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) #REF!

PROFIT / UTILIDAD 5% #REF!

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) #REF!


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) #REF!
s)

m3

AMOUNT
IMPORTE
$0.00
$0.00
#REF!
$0.00
$0.00
$0.00
$0.00
#REF!

AMOUNT
IMPORTE
0.00
#REF!
#REF!
0.00
0.00
0.00
0.00
0.00
#REF!

AMOUNT
IMPORTE

#REF!
#REF!
$0.00
$0.00
$0.00
$0.00
$0.00
#REF!

#REF!

#REF!

#REF!
#REF!
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Nivelacion final hasta subrasante de aceras y areas a desarrollar (Incluye Corte y 28,630.60
Relleno, Compactación, Carguio, Acarreo y Bote)
MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
Material de relleno m3e 1,860.99 $300.00 $558,296.70
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $558,296.70

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Retroexcavadora Cat 416 hora 372.20 1,722.00 640,924.61


Vibrocompactador Dynapac CC122 hora 372.20 1,117.60 415,968.26
Camion de agua Ford 450 2500 gls hora 372.20 1,022.00 380,386.15
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $1,437,279.02

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora 93.05 $202.50 $18,842.51


Chequeador hora 372.20 $81.00 $30,148.02
Peon hora 372.20 $67.50 $25,123.35
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $74,113.89
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $2,069,689.61

PROFIT / UTILIDAD 5% $103,484.48

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $2,173,174.09


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $75.90
s)

m2

AMOUNT
IMPORTE
$0.00
$0.00
$558,296.70
$0.00
$0.00
$0.00
$0.00
$0.00
$558,296.70

AMOUNT
IMPORTE

640,924.61
415,968.26
380,386.15
0.00
0.00
0.00
0.00
0.00
0.00
$1,437,279.02

AMOUNT
IMPORTE

$18,842.51
$30,148.02
$25,123.35
$0.00
$0.00
$0.00
$0.00
$74,113.89
$2,069,689.61

$103,484.48

$2,173,174.09
$75.90
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

USOH DR HOUSING

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Arcilla compactada al 90% #REF!

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
Arcilla m3 #REF! $300.00 #REF!
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES #REF!

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
0.00
Retroexcavadora Cat 416 hora #REF! 1,722.00 #REF!
Vibrocompactador Dynapac CC122 hora #REF! 1,117.60 #REF!
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO #REF!

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora #REF! $202.50 #REF!


Peon hora #REF! $67.50 #REF!
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA #REF!

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) #REF!

PROFIT / UTILIDAD 5% #REF!

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) #REF!


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) #REF!
s)

m2

AMOUNT
IMPORTE
$0.00
$0.00
#REF!
$0.00
$0.00
$0.00
$0.00
#REF!

AMOUNT
IMPORTE
0.00
#REF!
#REF!
0.00
0.00
0.00
0.00
0.00
#REF!

AMOUNT
IMPORTE

#REF!
#REF!
$0.00
$0.00
$0.00
$0.00
$0.00
#REF!

#REF!

#REF!

#REF!
#REF!
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

#REF!

Number / Numero: - UNIT


Description / Descripcion: UNIDAD

Nivelacion final hasta subrasante de aceras y areas a desarrollar (Incluye Corte y #REF!
Relleno, Compactación, Carguio, Acarreo y Bote)
MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
$0.00
$0.00
Material de relleno m3e #REF! $300.00 #REF!
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES #REF!

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Retroexcavadora Cat 416 hora #REF! 1,722.00 #REF!


Vibrocompactador Dynapac CC122 hora #REF! 1,117.60 #REF!
Camion de agua Ford 450 2500 gls hora #REF! 1,022.00 #REF!
0.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO #REF!

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Capataz hora #REF! $202.50 #REF!


Chequeador hora #REF! $81.00 #REF!
Peon hora #REF! $67.50 #REF!
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA #REF!
TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) #REF!

PROFIT / UTILIDAD 5% #REF!

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) #REF!


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) #REF!
s)

m2

AMOUNT
IMPORTE
$0.00
$0.00
#REF!
$0.00
$0.00
$0.00
$0.00
$0.00
#REF!

AMOUNT
IMPORTE

#REF!
#REF!
#REF!
0.00
0.00
0.00
0.00
0.00
0.00
#REF!

AMOUNT
IMPORTE

#REF!
#REF!
#REF!
$0.00
$0.00
$0.00
$0.00
#REF!
#REF!

#REF!

#REF!
#REF!
SCHEDULE 13 - Schedule of Remuneration
Attachment A - Commercial Schedules and Forms
Commercial Schedule B - Unit Prices & Methods of Measurement (Unit Price Analysis)
[ANALISIS DE PRECIO UNITARIO]

USOH DR HOUSING

Number / Numero: - UNIT


Description / Descripcion: UNIDAD und
Arcilla compactada al 90% 1.00

MATERIAL / MATERIALES
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE
Poste H.A. 300-9M und 1.00 $12,500.00 $12,500.00
Lampara tipo led solid state de 50 watts-220-277
V und 1.00 $18,500.00 $18,500.00
Brazo de 6' galv. und 1.00 $1,350.00 $1,350.00
Bombillo 150 watts und 1.00 $450.00 $450.00
Fotocelda und 1.00 $250.00 $250.00
120' alambre vinil 10/2 A RD$24.85/pie rollo 1.00 $2,982.09 $2,982.09
Peron de 2'x1" und 4.00 $450.00 $1,800.00
Plancha de metal 2"x2"x3/4" und 1.00 $850.00 $850.00
Hormigon 210 kg/cm2 m3 0.50 $4,310.54 $2,155.27
SUBTOTAL MATERIALS / SUBTOTAL MATERIALES $40,837.36

EQUIPMENT / EQUIPO
CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Izado de poste und 1.00 250.00 250.00


Transporte de poste und 1.00 750.00 750.00
0.00
0.00
0.00
0.00
0.00
SUBTOTAL EQUIPMENT / SUBTOTAL EQUIPO $1,000.00

LABOR / MANO DE OBRA


CODE UNIT QUANTITY UNIT COST AMOUNT
DESCRIPTION / DESCRIPCION
CODIGO UNIDAD CANTIDAD COSTO IMPORTE

Mano de obra total und 1.000000 $4,286.40 $4,286.40

$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL LABOR / SUBTOTAL MANO DE OBRA $4,286.40

TOTAL DIRECT COST (US$) / TOTAL COSTO DIRECTO (US$) $46,123.76

PROFIT / UTILIDAD 22% $10,147.23

TOTAL PRICE (RD$) / TOTAL PRECIO ( RD%) $56,270.99


TOTAL UNIT PRICE (US$) / TOTAL PRECIO UNITARIO ( RD$) $56,270.99
Clave R Descripción PRESUPUESTO BASE
CanPres Und PrePres ImpPres
1.00 TRABAJOS GENERALES 2,664,261.84
1.01 0 Ingeniería 3.92 Km 305,458.15 1,198,006.88
1.02 0 Mantenimiento de Transito 1.00 PA 256,842.60 256,842.60
1.03 0 Campamento: Oficina de Campo 1.00 PA 391,265.84 391,265.84
1.04 0 Laboratorio de Campo para Densidad de materiales 28,630.60 m 2
13.40 383,547.36
1.05 0 Laboratorio de Campo para Pruebas de Hormigon 6,563.49 m 3
66.21 434,599.16
2.00 TRABAJOS GENERALES 42,409,916.82

MOVIMIENTO DE TIERRA:

Nivelacion final hasta subrasante de calles, y areas a desarrollar (Incluye Corte y


2.01 0 28,630.60 m2 65.63 1,878,973.31
Relleno, Compactación, Carguio, Acarreo y Bote)

2.02 0 Escarificación de Superficie 28,630.60 m2 13.19 377,630.46


Base Granular de pavimento de Calles y Avenidas (0.15m) al 95% de
2.03 0 4,294.59 m3 1,416.41 6,082,912.30
compactación del proctor modificado

CAPA DE RODADURA:
Avenida Principal:
Hormigon Industrial f'c=240 kg/cm2 con malla electrosoldada 2.3 x 2.3 x 100 x
2.04 0 100 (e=0.15m) terminacion rayada con peine metalico 3/4" corte y sellado de 9,198.00 m2 1,225.36 11,270,867.08
juntas ,sellado y curado en base acuosa.
Calles Secundarias:
Hormigon Industrial f'c=240 kg/cm2 con malla electrosoldada 2.3 x 2.3 x 100 x
2.05 0 100 (e=0.15m) terminacion rayada con peine metalico 3/4" corte y sellado de 19,432.60 m2 1,173.26 22,799,533.68
juntas ,sellado y curado en base acuosa.
3.00 OBRAS COMPLEMENTARIAS:

MOVIMIENTO DE TIERRA:

Nivelacion final hasta subrasante de aceras y areas a desarrollar (Incluye Corte y


3.01 0 22,689.00 m2 75.90 1,722,183.50
Relleno, Compactación, Carguio, Acarreo y Bote)

ACERAS Y CONTENES:
Hormigon Industrial f'c=210 Kg/cm2 e=0.10 m terminacion rayada con peine
3.02 0 22,689.00 m2 732.91 16,628,934.49
metalico 3/4" corte y sellado de juntas ,sellado y curado en base acuosa.

3.03 0 Conten (telford) de hormigon pulido fc=180kg/cm2 7,844.00 m 940.43 7,376,716.45


Rampas Discapacitados Hormigon Industrial f'c=210 Kg/cm2 e=0.10 m
3.04 0 terminacion rayada con peine metalico 3/4" corte y sellado de juntas ,sellado y 72.00 Uds 1,099.36 79,153.99
curado en base acuosa.
Borde acera de Delimitacion perimetro de Hormigon F´C=210 Kg/cm2 e=0.10 m
3.05 terminacion rayada con peine metalico 3/4" corte y sellado de juntas ,sellado y 3,170.00 m2 732.91 2,323,316.25
curado en base acuosa.

SENALIZACION:
Señalizacion Vertical para Estacionamiento de Discapacitados 24''x24'', fijo, en
3.06 0 72.00 Uds 4,180.00 300,960.00
tola galvanizada, tubo 2 x 2 (material grado diamante)
Señalizacion Lineas de Estacionamiento en Pintura de Trafico con Microesferas
3.07 0 725.36 m 55.00 39,894.80
de vidrio
3.08 0 Señalizacion Lineas de Calles en Pintura de Trafico con Microesferas de vidrio 3,477.58 m 55.00 191,266.90

3.09 0 Señalizacion Cruces Peatonales en Pintura de Trafico con Microesferas de vidrio 505.00 m2 55.00 27,775.00

3.10 0 Señalizacion Pintura en Pavimento para Estacionamiento de Discapacitados 900.00 m2 440.00 396,000.00

3.11 0 Bolardos 125.00 Uds 3,000.00 375,000.00


SUB-TOTAL: RD$ 74,535,380.03

GASTOS GENERALES:

DIRECCION TECN. Y RESP. ADM. 10.00% 7,453,538.00


GASTOS ADMINISTRATIVOS 2.00% 1,490,707.60
TRANSPORTE 2.00% 1,490,707.60
SEGUROS Y FIANZAS 3.00% 2,236,061.40
SUPERVISION 5.00% 3,726,769.00
IMPREVISTO 5.00% 3,726,769.00
Ley 6-86 1.00% 745,353.80
CODIA 0.10% 74,535.38
ITBIS DEL 10% 1.80% 1,341,636.84

Sub-Total Gastos: RD$ 22,286,078.63

TOTAL GENERAL: RD$ 96,821,458.66

You might also like