Professional Documents
Culture Documents
CHAPTER 1
INTRODUCTION
1.1. GENERAL
It is a practical experience opportunity offered by companies to learn
practical aspects of professional work life which is very different from what we
learn in the class rooms. Since learning happens through education, exposure and
experience, internship provides us a taste of learning through exposure and
experience.
There are many benefits of internship. When you work you learn. It can add
the remarkable value to the student’s career. In an internship, the students are given
the chance to showcase their skills, talents, commitment and value to a prospective
employer.
During site visit I had the chance to explore and observe the construction of
foundation, footings, columns, slab and other finishing works of the residential
apartment buildings.
Quantity Surveying.
Skilled labors.
Good quality materials.
Technical supervision.
Proper curing.
Proper shuttering.
Completing project on time.
Test for all cement concrete works.
Use of ladders.
Proper scaffolding.
Insurance of workers.
Safety helmets, shoes, jackets etc.
First aid.
Fall protection.
CHAPTER 2
2.1 Construction Of “Sai Madhuban Hill View” Apartment
Site Plan
2.1.4 Excavation
Excavation is the first step of construction. It refers to the process of
removing soil or rock from its original location, typically in preparation for constructing
foundations, basements, and underground utility lines and for grading of the ground
surface. Excavated material required for backfill or grading fill is stockpiled on the site
for subsequent use. Excavation work I have seen was including bulk excavation, pit
excavation and trench excavation. The main aim of the excavation work is to remove
organic soils or unwanted soil for the safety of the building from chemical attacking.
Excavation shall be carried out to the lines, levels, width, depth and grades and shown 25
on the drawings, directed by the Engineer or as appropriate to the works to be placed in
the excavation.
Pit excavation: It is an excavation made for foundation footing pad with column by
considering working space of 200 up to 300mm to each side of the dimension. Trench
excavation: It is an excavation made for constructing foundation walls stone masonry
with leaving working area for both sides of the wall of specified width on the plan. This
depth is filled by the stone masonry which placed on 5cm thick lean concrete, Stone
masonry should be laid with specified mortar, well filled joint The stone should be
hard, sound, free from crack and weathering It should be freshly quarried from an
approved quarry, It is not round surface
Figure 3
Table 2
Table 3
Table 4
Classification of beams based on supports:
1) Simply supported: Beams supported on the ends which are free to rotate and
have no moment resistance.
2) Fixed: A beam supported on both ends and restrained from rotation.
3) Over hanging: A simple beam existing beyond its on one end.
4) Double over hanging: A simple beam with both ends extending beyond its
support on both ends.
5) Continuous: A beam extending over more than 2 supports.
6) Cantilever: A projecting beam with both ends extending beyond its supports on
both ends.
7) Trussed: A beam strengthened by adding a cable or rod to form a truss.
DEPARTMENT OF CIVIL ENGINEERING, AGMRCET, Varur Page 13
INTERNSHIP REPORT 2018-19
General shapes:
Most beams in reinforced concrete in the buildings have rectangular cross
sections.
Also other shapes like L (angles), C (channel) or tubes are also used in
construction when there are special requirements.
Stresses acting on the beam:
Most probably compressive, tensile and shear stresses of loads are applied to them.
The masonry walls consist of windows, doors, ventilators, switch boards, arches or
openings etc.
The sizes of doors and windows are-
D= 1.00x2.10m
D1= 0.90x2.10m
D2=0.75x2.10m (kitchen door)
W=1.50x1.20m
W1=1.20x1.20m
W2= 1.20x0.90m (kitchen window)
V= 0.60x0.60m
The walls are also provided with plastering, coping, lintels, slabs, skirting etc.
The sill level of the windows are provided as follows-
2 feet height for bedroom from base.
4 feet height for kitchens from base.
5 feet height for bathrooms from the base.
Table 5
It acts as a supporter to the masonry walls to transfer the loads.
It is mainly provided at the height of the doors.
The thickness of the lintel varies from 150mm - 450mm (5.90 – 17.7 inches).
It is used to take loads which are coming from the above wall and to transfer its
loads to the side walls or to the chejja.
The width of the lintel is same as that of the wall width.
The lintel can also be used as decorative architecture element.
The lintel has 8mm of 2 nos. of bars at the top and 10mm of 2 nos. of bars at the
bottom.
The ring which is used in the lintel is of 6mm bars and 6 inches from centre to
centre.
Lintel is connected with a chejja which projects outwards.
Types of lintel:
Timber lintel.
Stone lintel.
Reinforced concrete lintel.
Brick lintel.
Reinforced brick lintel.
Steel lintel.
2.1.12 Chejja
Chejja is a part of a building which is placed over the opening to prevent adverse
effects of weather in a room.
The chejja is also known as sun shade, which is used to prevent direct entry of
sunlight or rain into the room.
It is also used for aesthetic appearance of the building.
It is adopted at a height of 7ft (2.13m) from the floor level.
It is made up of concrete, it is elongated from the lintel level.
The top surface of the chejja is sloped and compulsorily coated with water
proofing material.
Types of chejja:
RCC chejja.
Stone chejja.
Tile chejja.
Sheet chejja.
Wooden chejja.
2.1.13 Slab
A concrete slab is a common structural element of modern buildings. Horizontal
slabs of steel reinforced concrete, typically between 4 and 20 inches thick, are most often
used to construct floors and ceilings, while thinner slabs are also used for exterior paving.
All the slabs provided are of 13cm (5 inches) thick.
Sunken slabs are provided at places above which toilet is present.
Sunk slabs are slabs which are cast at a certain depth below normal floor level, the
extra depth is used for placing pipes and utility ducts. And the space is filled up to the
normal floor level.
One way slabs and cantilever slabs are provided for Balcony, all remaining slabs
are two way slabs.
One way slab is a slab which is supported by beams on the two opposite sides to
carry the load along one direction, because this slab will bend in one direction i.e. in the
direction along its shorter span. Hence main reinforcement is provided in the shorter span
and distribution reinforcement in the longer span.
Whereas Two way slab is a slab supported by beams on all the four sides and the
loads are carried by the supports along both directions. Hence the main reinforcement is
provided in both direction.
Table 6
2.1.14 Staircase
Stairs are required for ascending and descending from floor to floor. A stair
consists of a number of steps to move from one level to another. The room/space housing
stairs is called staircase.
Figure 6
2.2.2 Excavation:
Excavation is the act or process of digging of certain area of earth mass for
foundation works.
The soil at this site is silty soil.
For the construction of this building excavation is done up to the depth of 6’-7’ as
it is an apartment.
The excavated area is leveled using a tamping rammer.
One side is closed hence permanent retaining wall is installed by using block
masonry.
The blocks are of dimension: 12”8”4”.
Thickness of the retaining wall is 9” to 12”.
Reinforcement is also provided in the retaining walls with 10mm bars of Fe500.
2.2.4 Footing:
A concrete support under a foundation that rests in solid ground is known as
footing. Footings distribute the weight of structure over the ground.
Isolated square footings are adopted on this site.
Concrete used for footing is of M20 grade.
Steel used is of Fe 500 grade.
2.2.5 Columns:
Columns are rigid vertical structural members designed primarily to support axial
compressive loads coming from beams and slabs and then transfer it to ground through
footing.
Total no. of columns at this site are 16.
Cross section of the columns is rectangular in shape.
Grade of concrete used is M20.
Both 2 legged and 4 legged stirrups are used alternatively.
Reinforcement details of the columns are given below.
Figure 14
If the roof area is more, filter pit is provided. Rain water from roof is taken to
collection de silting chambers located on ground. This collection chambers are
interconnected as well as connected to the filter pit through pipes having a slope
of 1:15. The filter pit may vary and shape and size depending upon available
runoff and are top with varying thickness (0.3-0.5m) and may be separated by
screen. The pit is divided into 2 chambers filter material is one chamber and other
chamber is kept empty, on accommodation excess filtered water and monitor
filtered water. A connecting pipe with recharge well is provided at the bottom of
the pit for recharging filtered water through well.
Suitable conditions:
The ground should not be rocky closed to the surface, which can hinder
the digging and conservation process, secondly the ground water table in the area
should not be very below the bottom of the tank. Underground some tanks must
not be built very close to the undergroung sewerage chambers.
there is likelihood of sedimentation and the dirt should be allowed to settle and
remain in the tank until cleaned.
Cylindrical Ferro cement or reinforcement cement concrete recommended as tank
building material plastic or brick is not recommended.
CONCLUSION
This program played an important role to break the conventional thought that field works
can be only implemented by students who hold a degree or people who have an
experience in building construction. We were able to acquire a high level of confidence to
deal with problems that arise in a building construction
Since I took my internship session in the consulting and construction side
HORIZON CONSTRUCTION CO. I got opportunity to work in the different party of the
construction work which helped me to gain more knowledge by seeing what they work in
their own office and what are their main responsibilities to the client and also each other
As per my training , I have conclude that , during my training days I was familiar
with the construction of excavation, Foundation work , Footings,Columns ,Beams , Brick
masonry, slab and Rain Water Harvesting.