A. Estimating Concrete Works # of CHB = 125.115 (12.

5) = 1564 pcs of
CHB
Beam (300 mm x 500 mm)
Mortar for CHB Fill
V = (0.3)(0.5)(4)(6) +(0.3)(0.5)(3.5)(6) =
6.75 m3 Total Wall Area = 125.115 m2

Column (400 mm x 400 mm) Using Table 2-2 (ESTIMATE by Max


Fajardo):
V = (0.4)(0.4)(2.85)(9) = 4.104 m3
(using class A)
Footing (1 m x 1 m) (thickness = 25 cm)
Sand = 125.115 (0.0435) = 5.5 m3
3
V = (1)(1)(0.25)(9) = 2.25 m Cement = 125.115 (0.792) = 99.1 kg of
cement
Slab (thickness = 15 cm)
Mortar for Plastering
V = (4)(3.5)(4)(0.15) = 8.4 m3
Total Wall Area = 125.115 m2
Total Volume = 6.75 + 4.104 + 2.25 + 8.4 =
21.504 m3 Using Table 2-4 (ESTIMATE by Max
Fajardo):
Using Table 1-2 (ESTIMATE by Max
Fajardo): (using class A & thickness = 20 mm)

(using class A & 50 kg of cement bag) Sand = 125.115 (0.020) = 2.6 m3


Cement = 125.115 (0.360) = 46 kg of
Sand = 21.504 (0.50) = 10.8 m3 cement
Gravel = 21.504 (1) = 21.6 m3
Cement = 21.504 (7) = 151 bags of cement C. Estimating Required Steel

B. Estimating Masonry CHB Reinforcement

Concrete Hollow Block (CHB) (using 6 m long steel bars)

Interior Walls = 2.85 (4) + 2.85 (3.5) + 2.85 # of CHB = 1654 pcs of CHB
(1.2) (2) + 2.85 (2) (2) = 39.615 m2
Exterior Walls = 2.85 (8) (2) + 2.85 (7) (2) = Using Table 3-5 (ESTIMATE by Max
85.5 m2 Fajardo):
Total Wall Area = 39.615 + 85.5 = 125.115
m2 (reinforcing every 3 layers at 60 cm vertical
spacing)
(using 10x20x40cm CHB)
Vertical Reinforcement = 1654 (0.171) =
282.834
Horizontal Reinforcement = 1654 (0.172) =
284.488 12.25
req’d steel = = 0.3 kg
Total = 282.834 + 284.488 = 567.322 53
Column Reinforcement
567.322
# of pcs = = 95 pcs of 6 m long
6 (use 6 m long steel bars)
steel bars
2.85 (9) = 25.65
CHB Tie Wire (#16 G.I. Wire)
25.65
= 5 pcs of 6 m long steel bars
(use 40 cm length ties) 6

Total Wall Area = 125.115 m2 Lateral Ties for Columns

Tie = 125.115 (0.042) = 5.3 kg (use 25 cm length of lateral ties)


(all lateral ties are spaced at 50 cm)
Footing Reinforcement
2.85
(use 6 m long steel bars) = 5.7 ≈ 6
0.5
6+1=7
7(0.25) = 1.75

1.75
= 0.1 kg
53

Column Tie Wire

Size of Footing = 1 m x 1 m (use 25cm length ties)

L = 1 – 2(0.075) = 0.85 2.85


Total # of Pieces = 14 # of Lateral Ties = = 5.7 ≈ 6
0.5
Commercial length of steel bars = 6 m 6+1=7
7 x 2 = 14 lateral ties
6
= 7.059 ≈ 7
0.85 # of bars = 5 bars
14 # of Intersections = 14 (5) = 70
= 2 pcs of 6 m long steel bars
7 70 (0.25) = 17.5 m

Footing Tie Wire 17.5


= 0.4 kg
53
(use 25 cm length ties)
Beam Reinforcement
# of Intersections = 7(7) = 49
49(0.25) = 12.25 m (use 6 m long steel bars)
D. Forms, Scaffolding, & Staging

Forms for Columns

P = 2(a+b) + 0.2
P = 2(0.4+0.4) + 0.2 = 1.8 m
Total Length = (2.85)(9) = 25.65 m
Area = 25.65 (1.8) = 46.17 m2

Using Table 4-4 (ESTIMATE by Max


Fajardo):

(use 60 cm x 60 cm)

46.17
# of Pieces =