1 METHODOLOGY
Based on the objectives and scope of the consultancy services, an appropriate methodology has been
developed in order to address the various requirements of the project. Since the scope of the services to be
provided covers both independent and inter-dependent activities, it has been proposed to adopt a Task
Approach to ensure that the entire scope of services is completed comprehensively and with reasonable
accuracy.
1.1.1 Investigations for Bridges and Structures
1.1.1.1 Inventory and Condition Survey for Bridges and Culverts
Inventory and condition survey of culverts, bridges and other structures shall be done to ascertain the need
for reconstruction / widening and rehabilitation of these structures. The condition assessment of bridges will
be carried out by Senior Bridge/Structural Engineer in accordance with guidelines given in IRC-SP:35-1990.
The data shall include construction details, type of foundation, substructure and superstructure, details of
span, waterway, design loading and functioning of the structure in the past, both from hydraulic and
structural considerations.
1.1.1.2 Hydraulic and Hydrological Investigations
These studies will be carried out in accordance with IRC Special Publication No.13 (Guidelines for the
design of small bridges and culverts) and IRC:5-1998 (Standard Specifications & Code of Practice for road,
bridge section 1 - General features of design). These investigations will be carried out for all existing
drainage structures along the road sections under the study. Its quality will be ensured by:
Collection of data by an experienced engineer
Its correct interpretation based on experience, site inspection and behaviour of other structures across
such streams in the near vicinity by such experienced engineers.
For HFL, reliance will be placed on past records, local enquiries and flood marks on structures in the
vicinity.
For road sections getting overtopped during heavy rains will be placed on local enquiries.
3. Overall length more than 60 m Each abutment and each pier locations.
Rotary drilling for 150mm dia.boring in soil for carrying out Standard Penetration test, collection of
disturbed and un-disturbed soil sample and with Diamond bit rotary drillers for 100 mm dia bore shall be
used for collection of rock samples from these boreholes for further testing in the laboratory. The Criteria
for depth of Exploration for Foundations and Road pavement shall be adopted as :
1.5 x width of foundation below expected depth of foundation
1.0 x width of foundation into weathered rock
3.0 m into sound rock
1.5 x estimated length of pile or 15.0m beyond probable length of pile
15 x dia. of pile in weak / Jointed rock
For the road pavement boreholes at each major change in pavement condition or in deflection readings
or at 2 km intervals whichever is less. The depth of the borehole shall be at least 2m below
embankment base or to rock level.
Procedure
Quality Assurance requires that activities at every stage of geo-technical and material investigations shall be
carried out strictly in accordance with the procedures prescribed in the relevant codes, so that the results of
these investigations reflect truly the sub-soil and material characteristics.
Every geo-technical and material investigation will be carried out and completed principally in four
sequential stages, namely:
a) Field Investigations
b) Sampling
c) Laboratory Testing
d) Report Preparation
While the investigations will be carried out by competent technical staff comprising trained technicians and
well qualified engineers, the Materials and Geo-technical Engineer will pay periodic visits to the boring
sites. An experience geo-technical Engineer will be posted at site for the entire duration of the boring work
to have constant check.
The results of the investigations as furnished by the sub-consultants shall be examined by the Materials and
Geo-technical Engineer for consistency and compatibility before acceptance.