SITE PREPARATION
Excavation 636 cu. m 20 cu. m/hr
Gravel Bedding 85 cu. m 1.2 cu. m/hr
Embankment 395 cu. m 9.84 cu. m/hr
STEEL WORKS
Foundation 16787.102 kg 129.094 kg/hr
First Floor 16284.3865 kg 129.094 kg/hr
Second Floor 14863.3365 kg 129.094 kg/hr
Third Floor 10120.77 kg 129.094 kg/hr
FORMWORKS
Foundation 406.92 sq. m 4.5 sq. m/hr
First Floor 434.22 sq. m 4.5 sq. m/hr
Second Floor 347.25 sq. m 4.5 sq. m/hr
Third Floor 299.735 sq. m 4.5 sq. m/hr
CONCRETE WORKS
Foundation 117.3125 cu. m 3.32 cu. m/hr
First Floor 156.7939833 cu. m 3.72 cu. m/hr
Second Floor 132.6629833 cu. m 3.72 cu. m/hr
Third Floor 100.2873333 cu. m 3.72 cu. m/hr
MASONRY
Foundation sq. m 3.18 sq. m/hr
First Floor 419.1384 sq. m 3.18 sq. m/hr
Second Floor 318.7584 sq. m 3.18 sq. m/hr
Third Floor 318.7584 sq. m 3.18 sq. m/hr
STAIRS
Form Works of Slabs (Installation) 86.574 sq.m 4.5 sq.m/hr
Reinforcing Bars of Slabs 86.574 kg 129.094 kg/hr
Concreting of Slabs 16.671 cu.m 3.72 cu.m/hr
Stripping of Formworks 86.574 sq.m 4.5 sq.m/hr
ROOFING
Truss 18183 kg 129.094 kg/hr
G.I. Sheet Roofing 709.2 sq.m 10 sq.m/hr
Ceiling 3768.58 sq.m 30 sq.m/hr
PLUMBING
PVC m m/hr
Sewer Line Works m m/hr
ELECTRICAL
Copper Wire Laying
#2 mm^2 THW wire std. 1204.4 m 25 m/hr
#3.5 mm^2 THW wire std. 1017 m 25 m/hr
#8 mm^2 THW wire std. 300 m 14.286 m/hr
#30 mm^2 THW wire std. 300 m 5.714 m/hr
#14 mm^2 THW wire std. 300 m 14.286 m/hr
#50 mm^2 THW wire std. 300 m 4.615 m/hr
PVC pipe Laying
#20 mm dia. 1291 length 3.5434 length/hr
#32 mm dia. 150 m 3.534 length/hr
#40 mm dia. 150 m 3.534 length/hr
Switches
2 gang and 3 gang switch 12 set 1 set/hr
Lighting Fixtures
Lights and Lamps 161 set 10 set/hr
Convenience Outlet
nience Outlet with grounding, Universal and/ or polarized flat w/105
plate and coverset
* 8 set/hr
Panel Board
Panel Board with Main Breaker 5 set 1 set/hr
FINISHING
Plastering 3333.72 sq.m 7.125 sq.m/hr
Bricks 361.917 sq.m 1.365 sq.m/hr
Railings m m/hr
Windows 147.672 sq.m 0.27 sq.m/hr
Panel Door 56.7 sq.m 0.36 sq.m/hr
Flush Door 10.08 sq.m 0.26 sq.m/hr
Tiles 1418.851 sq.m 1.365 sq.m/hr
Painting 5133.46 sq.m 2.1 sq.m/hr
Workers SETS DURATION
2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19
1 4
3 3
1 6
2 9
2 8
2 8
2 5
2 6
2 7
2 5
2 5
1 5
1 6
1 5
1 4
1 5
1 17
1 13
1 13
1 3
1 1
1 1
1 3
1 18
1 9
1 16
1 #DIV/0!
1 #DIV/0!
1 7
1 6
1 3
1 7
1 3
1 9
8 6
1 6
1 6
1 2
1 3
1 2
1 1
1 59
1 34
1 5
1 69
1 20
1 5
2 10 13
3 20 16
MAY
20 22 23 24 25 26 27 29 30 1 2 3 4 6 7 8 9 10 11 13 14 15 16 17 18 20 21 22
JUNE
23 24 25 27 28 29 30 31 1 3 4 5 6 7 8 10 11 12 13 14 15 17 18 19 20 21 22 24
JULY
25 26 27 28 29 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26
AUGUST
27 29 30 31 1 2 3 5 6 7 8 9 10 12 13 14 15 16 17 19 20 21 22 23 24 26 27 28
29 30 31 2 3 4 5 6 7 9 10 11 12 13 14 16 17 18 19 20 21 23 24 25 26 27 28 30
OCTOBER
1 2 3 4 5 7 8 9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31
TEAM BA: Agbay Cueto Samelo
PROJECT NAME
VIRTUAL PROJECT: 01CP
SITE PREPARATION
Excavation 636 cu. m 20
Gravel Bedding 0.85 cu.m 1.2
FOUNDATION
STEEL WORKS 16787.102 kgs 129.094
INSTALLATION OF FORMWORKS 406.92 sq.m 4.5
CONCRETE WORKS 117.3125 sq.m 3.32
STRIPPING OF FORMWORKS 406.92 cu. m 9
MASONRY WORKS 322 sq.m 3.18
Embankment from Structure Excavatio 395 cu.m 9.84
FIRST FLOOR
STEEL WORKS 16284.3865 kgs 129.094
INSTALLATION OF FORMWORKS 434.22 sq.m 4.5
CONCRETE WORKS 156.7939 sq.m 3.72
STRIPPING OF FORMWORKS 434.22 cu. m 9
MASONRY WORKS 419.1384 sq.m 3.18
SECOND FLOOR
STEEL WORKS 14863.3365 kgs 129.094
INSTALLATION OF FORMWORKS 347.25 sq.m 4.5
CONCRETE WORKS 132.663 sq.m 3.72
STRIPPING OF FORMWORKS 347.25 cu. m 9
MASONRY WORKS 318.7584 sq.m 3.18
THIRD FLOOR
STEEL WORKS 10120.77 kgs 129.094
INSTALLATION OF FORMWORKS 299.735 sq.m 4.5
CONCRETE WORKS 100.2873 sq.m 3.72
STRIPPING OF FORMWORKS 299.735 cu. m 9
MASONRY WORKS 318.7584 sq.m 3.18
ROOFING WORKS
TRUSS 18183 kgs 85
C-PURLINS 3748 kgs 90.45
GI-SHEET 709.2 sq.m 2.769
CEILING WORKS 3768.58 sq.m 30
STAIRS
Form Works of Slabs (Installation) 86.574 sq.m 4.5
Reinforcing Bars of Slabs 86.574 kg 129.094
Concreting of Slabs 16.671 cu.m 3.72
Stripping of Formworks 86.574 sq.m 4.5
PLUMBING
PVC 110 m 5
Sewer Line Works 110 m 5
ELECTRICAL
Copper Wire Laying
#2 mm^2 THW wire std. 1204.4 m 25
#3.5 mm^2 THW wire std. 1017 m 25
#8 mm^2 THW wire std. 300 m 14.286
#30 mm^2 THW wire std. 300 m 5.714
#14 mm^2 THW wire std. 300 m 14.286
#50 mm^2 THW wire std. 300 m 4.615
PVC pipe Laying
#20 mm dia. 1291 length 3.5434
#32 mm dia. 150 m 3.534
#40 mm dia. 150 m 3.534
Switches
2 gang and 3 gang switch 12 set 1
Lighting Fixtures
Lights and Lamps 161 set 10
Convenience Outlet
Duplex Convenience Outlet 105 set 8
Panel Board
Panel Board with Main Breaker 5 set 1
FINISHING
Plastering 3333.72 sq.m 7.125
Bricks 361.917 sq.m 1.365
Railings m
Windows 147.672 sq.m 0.27
Panel Door 56.7 sq.m 0.36
Flush Door 10.08 sq.m 0.26
Tiles 1418.851 sq.m 1.365
Painting 5133.46 sq.m 2.1
Suarez Villanueva
cu.m 1 4
cu.m 1 1
kgs 2 9
sq.m 2 6
sq.m 1 5
cu.m 2 3
sq.m 1 13
cu.m 1 6
kgs 2 8
sq.m 2 7
sq.m 1 6
cu.m 2 4
sq.m 2 9
kgs 2 8
sq.m 2 5
sq.m 1 5
cu.m 2 3
sq.m 2 7
kgs 2 5
sq.m 2 5
sq.m 1 4
cu.m 2 3
sq.m 2 7
kgs 2 14
kgs 2 3
sq.m 5 7
m 2 8
sq.m/hr 1 3
kg/hr 1 1
cu.m/hr 1 1
sq.m/hr 1 3
m/hr 1 3
m/hr 1 3
m/hr 1 7
m/hr 1 6
m/hr 1 3
m/hr 1 7
m/hr 1 3
m/hr 1 9
length/hr 8 6
length/hr 1 6
length/hr 1 6
set/hr 1 2
set/hr 1 3
set/hr 1 2
set/hr 1 1
sq.m/hr 5 12
sq.m/hr 4 9
m/hr 1 12
sq.m/hr 5 14
sq.m/hr 4 5
sq.m/hr 1 5
sq.m/hr 10 13
sq.m/hr 20 16
APRIL MAY
18 19 20 22 23 24 25 26 27 29 30 1 2 3 4 6 7 8 9 10 11 13 14 15 16
CURING
MAY JUNE
17 18 20 21 22 23 24 25 27 28 29 30 31 1 3 4 5 6 7 8 10 11 12 13 14
JUNE JULY
15 17 18 19 20 21 22 24 25 26 27 28 29 1 2 3 4 5 6 8 9 10 11 12 13
CURING
JULY AU
15 16 17 18 19 20 22 23 24 25 26 27 29 30 31 1 2 3 5 6 7 8 9 10 12
CURING
AUGUST
13 14 15 16 17 19 20 21 22 23 24 26 27 28 29 30 31 2 3 4 5 6 7 9 10
CURING
11 12 13 14 16 17 18 19 20 21 23 24 25 26 27 28 30 1 2 3 4 5 7 8 9
OCTOBER NOVEMBER
10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 4 5 6 7 8 9 11
VEMBER
12 13 14
9/18 11/7 12/27
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
12/27 2/15 4/6
4/6 5/26