When airport projects

fly off course.


Anthony Morgan

Executive summary perhaps most significantly, airport


Any major infrastructure project is facilities are being built at a volatile
vulnerable to going over budget, time for air travel when it is difficult
running behind schedule, or to predict accurately an airport’s
experiencing other setbacks. needs 10 years or even five years into
Sometimes the issues can be resolved the future.
through negotiations, but often Unlike other capital projects, airport
they lead to disputes that require developments tend to be more
arbitration or result in litigation. politically sensitive and attract much
Airport projects unfortunately may fly more media attention. The media
off course more often than other types coverage can be primarily local,
of infrastructure construction because but may be international because
they are more complicated and involve an airport is a city’s gateway to the
more uncertainty. world, attracting people from across
the globe. If a project encounters
The stakes can be high: A US$400 serious setbacks, widespread media
million contract for construction of a attention can damage the airport’s
new runway, breakwater, and terminal reputation with potential travellers,
at Beirut-Rafic Hariri International retailers, construction and engineering
Airport ballooned by more than firms, and other interested parties.
US$100 million because of additional The negative coverage may even
costs the contractor claimed due to cost a city’s mayor his job in the
delays that put the project more than next election.
19 months behind schedule.
But airport owners and developers
Airport projects are especially complex can mitigate the risk of disruptions
because they involve a wide variety and disputes by making provisions for
of stakeholders and revenue sources. possible adjustments in their contracts,
Airport developments also are typically incorporating as much flexibility as
very large in scope and have a long possible into their designs, and closely
timeline from planning to completion, monitoring not only the construction
increasing the likelihood of design process, but also changes in the airline
and other changes along the way. And industry and the outlook for air travel.

6 PwC | The “new normal” for airport investment


With any type of project, the For instance, technology allows
passengers now to check their baggage
greater the uncertainty about online, print out their own luggage
demand and other factors, the tags, and load their bags on a conveyor
belt when they arrive at the airport-
greater the risks will be. -all without even interacting with
an airline employee. As a result, an
expansion project may be well under
Multiple stakeholders, was nearing completion when local way before an airport owner sees that
revenue sources, and regulatory authorities said the it needs less physical space for people
smoke alarm and evacuation systems to queue up and check bags than in
regulations
didn’t meet code requirements, the past.
Building a bridge or parking garage
delaying its opening and requiring
is relatively straightforward, with That would then require a terminal
additional work.
only a few key stakeholders and a redesign in the middle of construction
single revenue source. In contrast, an to allocate some of that check-in
airport construction project typically The cloudy skies space to other uses, such as retail
entails a large variety of stakeholders With any type of project, the greater shops. Such modifications can result
and multiple revenue sources. When the uncertainty about demand in differences of opinion and disputes
an airport expands, it affects the and other factors, the greater the between owners and contractors over
operations and revenues of the airlines risks will be. But the volatility of how much the changes increased costs
flying into that facility, operators of air transportation is especially or delayed completion of the project.
the car parking and garages, retail intense today, which can make
shops in the terminals, nearby hotels, Even more costly and disruptive is a
the outlook particularly cloudy
and train lines to the airport, among major change in an airport’s roster
and add uncertainty to an already
others. In fact, a national airline may of airlines. If an airport is being
complex project.
be effectively shut down if its home expanded to serve as a hub with
airport isn’t operating. During the construction phase, many passengers transferring to other
airports may have to adapt to changes flights, it requires a more expensive,
That greater complexity means that in their mix of airlines and the size sophisticated baggage handling
the repercussions can be much more and shape of jet planes, technological system to transfer people’s luggage.
significant when a project runs into advances that can affect an airport’s Should the airline that’s intended to
trouble and the calculation of the exact operations, and an increase or decline transport people to other destinations
impact on the various stakeholders’ in the number of passengers flying in. go bankrupt or be acquired by a
revenue more difficult. When an competitor, the expansion project is
oil pipeline is late, it is relatively Moreover, a particular airport could
no longer appropriate and money was
straightforward to determine the suddenly face political instability and
wasted on such features as the transfer
impact on a refinery’s business. But see a sharp drop in tourism in the
baggage system.
with an airport expansion delay, the midst of a major expansion. We also
financial loss to airlines, retailers, food have seen how a major devastating
caterers, and parking facilities isn’t so event such as the terrorist bombings of Emerging markets:
clear-cut. How do you determine how the World Trade Center and Pentagon opportunities and risks
much revenue a souvenir shop lost in 2001 and the global financial crisis With air travel expected to grow
because of a delayed airport project? in 2008 can sharply change air travel fastest in emerging markets, airport
patterns and affect airport projects. construction will increasingly be
Airports also can encounter
Indeed, by the time an airport project concentrated in the Middle East,
problems if they were designed
is finished, the amount of air travel Asia, and other developing areas of
without taking into account all
and passengers’ needs may have the world. While that bodes well for
of the relevant regulations. In
changed so much that the number engineering and construction firms,
addition to international aviation
of security lines, parking capacity, or it also may mean more complications
standards, project managers need
other features of the new facilities are and disputes. Growth rates in
to be knowledgeable about national
no longer suitable. emerging markets are harder to predict
and local regulations. For example,
the new airport in Berlin, Germany,

When airport projects fly off course. 7


than in mature economies, making it Anticipate change How to avoid disputes
that much more difficult to project air Scope change is the one sure To minimize the number of disputes,
travel demand in five or 10 years and thing to count on with an airport project managers need to look
design an airport of the proper size construction project. So from the outward, not just inward. They are
with the necessary features. outset, airport operators need to plan used to ensuring that the project
Moreover, airport operators and for the likelihood of needing to make comes in on budget, on scope, and on
contractors in emerging markets don’t adjustments to the project. schedule. But with airports, they need
have the experience in dealing with to closely monitor the bigger world of
Project owners and contractors should
risk and the sophisticated knowledge airlines and travel to make certain that
clearly set their expectations and
to figure out solutions to problems the project still matches market needs.
establish communication channels and
that their counterparts in Europe and change procedures. They need to agree Another way to avoid disputes is to
North America enjoy. They also don’t up front that there will most likely be expand in smaller increments. While
have the established relationships changes along the way and that they it might be more economical to design
that can often help the parties in an should be prepared to reassess the an airport expansion to meet expected
airport construction project avoid business case frequently to determine demand for 10 years down the road
problems and resolve disputes more whether the assumptions behind the rather than just five, that longer time
expeditiously. In addition, contractors project still hold true. Such advance horizon increases the risk of making
from developed economies will likely work can go a long way toward inaccurate passenger demand forecasts
find different construction standards preventing major disputes that end up and needing to modify designs during
and a looser legal framework in in arbitration or litigation. the construction process.
emerging countries.
It’s best to detail in contracts the Airport designers also are advised
Cultural differences will also come governance structure processes and to build in as much flexibility as
into play. For instance, project changes information requirements for dealing possible. If they use modular design,
may not be viewed as a normal part with changes and variations. The they can move or knock down walls
of the construction process in some airport owner shouldn’t be required to change configurations. Such a
inexperienced, emerging countries. to carry all the risk and pay for all simple adjustment could provide
As a result, they may not build change design changes. The contractor not more room for baggage claim, for
control procedures into contracts, only would make money from every instance, if passenger traffic suddenly
leading to disputes that can’t be change, but he also would hold the rises that space could be taken away
easily resolved. negotiating power. Instead, owners from another area, such as duty-free
Another potential risk factor in the should consider a “gain share/pain shops. Flexible design also could allow
Middle East is the desire to create a share” approach, which means sharing terminals to more quickly add parking
landmark design for an airport that with contractors both the risks of slots for planes or make modifications
has a sort of “wow” factor. Such unique cost overruns and schedule delays to accommodate larger or smaller
designs may draw attention, but they and the financial benefits of finishing planes.
also are more vulnerable to problems under budget. The project owner also
Project managers also should stay
because they’ve never been done might consider withholding part of
on top of the rapid advances in
before. Contractors may try to price the budget and establishing a capital
technology to avoid being stuck with
that risk into the contract, but if they reserve to cover the expected but
outdated systems when the airport
don’t get it right, they will try to get unknown changes, rather than add
project is completed. That’s made
their money back by contending that new charges later.
the design was flawed from the start
and the problems are the owner’s fault.

From the outset, airport operators


need to plan for the likelihood of
needing to make adjustments to
the project.

8
When airport proyects fly off course PwC | The “new normal” for airport investment
8
It’s wise to include in the
contract the dispute resolution
mechanisms, such as mediation
or arbitration, which will be used
in case there’s a conflict over
changes and increased costs.
even more complex by the extensive It’s also wise to include in the contract Next steps
network of technologies within an the dispute resolution mechanisms, Airport operators and engineering
airport. So much technical change is such as mediation or arbitration, and construction firms will no doubt
possible during an airport construction which will be used in case there’s a face more, not less change in the air
project that the risks can be quite conflict over changes and increased travel business in the coming years.
high and the likelihood of disputes costs. That way, the parties spend any They also will be working increasingly
much greater than with other types expense and time on resolving the in less developed countries, where
of infrastructure projects. While a conflict rather than figuring out the disputes are more likely than in mature
toll road involves some technologies, procedure for settling it. markets. Consequently, they need
it’s much less complicated than to become more flexible and more
Owners and contractors also may want
an airport’s host of technologies, sophisticated to thrive in this volatile
to select in advance an adviser that can
including navigation, radar, baggage climate. Simply put, the better they
do a thorough quantitative analysis
management, communication, can anticipate and plan for changes
in case of a dispute. When a new
reservation, and check-in systems. in air travel demand and shifts within
airport was being built in Hong Kong,
Finally, it’s usually preferable to build it turned out that the specifications the airline industry, the more likely
the kind of airport structures that for the terminal’s roof tiles were they are to avoid major adjustments to
have been done successfully in the extremely tight, causing problems projects and thorny, costly disputes.
past. One-of-a-kind terminals may with the construction tolerances and
About the author: Anthony Morgan leads
be visually exciting and add to an requiring reworking. That resulted in
PwC’s construction dispute resolution practice
airport’s allure, but they also invite a a disruption claim against the owner in EMEA and regularly acts as an independent
multitude of potential problems and in which the contractor retained expert on the project management of large
disputes during construction. an adviser to conduct an extensive complex capital projects. The capital projects
analysis to quantify the impact of the team advises both owners and suppliers on
delivery, control and commercial issues that
tight tolerance on productivity and
Being prepared for costs and presented those findings to a
they face in implementing engineering and
construction projects.
possible disputes mediator for settlement of the claim.
Information is power. That’s why it’s
so important that both airport owners From a cost and time standpoint, Contact: Anthony Morgan (anthony.j.morgan@
it’s clearly better to resolve disputes uk.pwc.com, +44(0) 20 7213 4178)
and contractors invest in top-notch
information technology systems to outside the courtroom. Taking legal
collect data about a project that can action also can raise questions about
be used later to support their case in which nation’s laws apply if the
the event of a dispute. Such thorough, contractors, operators, or financing
easily accessible records can help entities are from outside the airport’s
resolve a conflict more swiftly. home country.

When airport projects fly off course. 9