PILECAP DESIGN

Project : Designed by :
Checked by :
Date :
Sheet No : 1 of 1

Pilecap Design / Quantity Calculation LIFT 3 & 4 (NO CALCULATION DONE, ONLY PROVIDE AS MIN - PRELIM)

Bar Size = 32 mm
Dimension of Column = length,mm width, mm

Dimension of Pilecap = length,mm width, mm


10400 4400
Depth of Pilecap = 3000 mm
Concrete Grade, fcu = 35 N/mm2
High yield Steel Bar, fy = 460 N/mm2
Cover to pilecap = 50 mm
Overhang = 150

Reinforcement Parallel to y-y- axis:

b= 10400 mm

As min = 0.13bh/100
As min = 40560 mm2
As ult = 40560
Provide 51 T 32 205 c/c
As = 41016.64 mm2 OK

Reinforcement Parallel to x-x- axis:

b= 4400 mm

As min = 17160 mm2


As ult = 17160 mm2
Provide 22 T 32 200 c/c
17693.45 mm2 OK

Horizontal Loops

As = 0.13%H^2/4
2925 mm2
Provide 15 T 16 200 c/c
As= 3017.14285714 mm2
PILECAP DESIGN

Project : Designed by :
Checked by :
Date :
Sheet No : 1 of 1

FORMWORK = 88.80 m2

LEAN CONCRETE = 45.76 m2

CONCRETE = 137.28 m3

HORIZONTAL LINKS = 721.58 kg

HIGH TENSILE BAR = 6571.45 kg

EXCAVATION ( < 1.5m) = 68.64 m3

(1.5 ~ 3.0 m) = 68.64 m3


Project: Prolintas Reconfigure - PMU Lobby Date: 3/21/2019

Pilecap Design / Quantity Calculation Shearwall (NO CALCULATION DONE, ONLY PROVIDE AS MIN - PRELIM)

Bar Size = 16 mm
Dimension of Column = length,mm width, mm
3230 230
Dimension of Pilecap = length,mm width, mm
4500 1500
Depth of Pilecap = 850 mm
Concrete Grade, fcu = 35 N/mm2
High yield Steel Bar, fy = 460 N/mm2
Cover to pilecap = 50 mm
Overhang = 150

Reinforcement Parallel to y-y- axis:

b= 4500 mm

As min = 0.13bh/100 As max = 0.04Ac


As min = 4972.5 mm2 As max = 153000 mm2
As ult = 4972.5 As ult = 153000

Provide 30 T 16 150 c/c


= 6031.86 mm2 OK

Reinforcement Parallel to x-x- axis:

b= 1500 mm

As min = 1657.5 mm2 As max = 51000 mm2


As ult = 1657.5 mm2 As ult = 51000
Provide 10 T 16 155 c/c
2010.62 mm2 OK

Horizontal Loops

As = 0.13%H^2/4
234.8125 mm2
Provide 3 T 12 325 c/c
As= 339.42857 mm2
Pilecap Design / Quantity Calculation SHEARWALL

Bar Size = 16 mm
Dimension of Column = length,mm width, mm
4340 300
Dimension of Pilecap = length,mm width, mm
4500 1300
Depth of Pilecap = 650 mm
Concrete Grade, fcu = 30 N/mm2
High yield Steel Bar, fy = 460 N/mm2
Cover to pilecap = 50 mm
Overhang = 200

Reinforcement Parallel to y-y- axis:

b= 4500 mm

As min = 0.13bh/100
As min = 3802.5 mm2
As ult = 3802.5
Provide 30 T 16 150 c/c
As = 6031.86 mm2 OK

Reinforcement Parallel to x-x- axis:

b= 1300 mm

As min = 1098.5 mm2


As ult = 1098.5 mm2 FORMWORK = 7.54 m2
Provide 9 T 16 150 c/c
1809.56 mm2 OK LEAN CONCRETE = 5.85 m2

CONCRETE = 3.80 m3
Horizontal Loops
HORIZONTAL LINKS = 32.39 kg
As = 0.13%H^2/4
137.3125 mm2 HIGH TENSILE BAR = 290.55 kg
Provide 3 T 12 225 c/c
As= 339.42857 mm2 EXCAVATION ( < 1.5m) = 8.78 m3

(1.5 ~ 3.0 m) = 8.78 m3