You are on page 1of 24

Fighting Destruction By Building Consensus

On January 17, 1994, both the San Fernando Despite these complications, or perhaps even
Valley near Los Angeles and much of the build- because of them, what has emerged in these
ing construction industry were shaken by the new FEMA documents is the best, most com-
Northridge earthquake. For those of us involved prehensive set of recommendations compiled
in the technical investigations that followed, the to date to address the discoveries that result-
past seven years have been a whirlwind of dis- ed from the post-Northridge investigations. Yet
covery, analysis, controversy and learning. these guidelines lack one element common to
I had the privilege, responsibility, frustration and U.S. building codes: consensus. These are
professional satisfaction of serving as Director simply guidelines, not codes. By themselves,
of Product Development in the FEMA-sponsored they have no legal authority. FEMA docu-
SAC project, which ultimately became a six- ments cannot be incorporated directly into
year, approximately $12 million effort to better building codes because they have not gone
understand the behavior of the steel moment through the consensus process.
frame connections that fractured during the I am pleased to report that this process is
Northridge earthquake and to develop new practices to avoid underway. The AISC Seismic task committee, under the capable
these problems. I am pleased to announce that the findings of leadership of my SAC colleague Jim Malley of Degenkolb
the SAC project are now available in published form from FEMA. Engineers, continues to work SAC developments into the
See page 10 of this issue for details. Seismic Provisions for Structural Steel Buildings. Welding-relat-
Recently, in an interview for Structural Engineer, I was asked, ed issues from the SAC project are being considered by the
“Did SAC participants 'take sides' on certain issues?” I respond- AWS D1 Seismic Welding subcommittee, led by Duane Miller,
ed that the participants did indeed take sides, based on legiti- Chair, with myself as Vice Chair. Not only are we considering
mate technical opinion and also influenced by four less altruistic the SAC work, but we are following developments from Japan
factors: and New Zealand, as well as the IIW commission chaired by
Hardy Campbell of AWS. Also, we have taken steps to bring the
• Litigation issues. A variety of lawsuits had been filed as a views of some of the strongest critics of the SAC recommenda-
result of damage to buildings. Since the SAC project sought tions to the table for consideration as well.
to gather the best technical experts in the field, and attorneys
on the both sides consulted the same individuals as expert Of course, along with consensus comes the reality of dealing
witnesses, views expressed in the courtroom inevitably with differences of opinion, again. When these are based upon
cropped up during technical sessions. honestly differing points of view, we all must be patient, respect-
ful and try to see each other’s perspectives. This is when the
• Economic issues. These arose because steel suppliers, best of the consensus process emerges. Uneducated opinions,
fabricators, erectors and others had understandable concerns self-serving perspectives and ‘head-in-the-sand’ denials of the
that SAC recommendations might unjustly increase the cost need for change only hinder the process.
of steel construction, and give other materials a market
advantage. As I viewed damage from the recent earthquake in Washington
state, the inevitability of earthquakes and their destructive power
• Job security. For example, some inspectors became con- emphasized to me the need to incorporate into consensus stan-
cerned that SAC recommendations might limit the scope dards the best and most current science for dealing with these
of their involvement on projects. mighty forces of nature. I urge my colleagues to use the consen-
• Proprietary designs. Participants’ knowledge of proprietary sus process in the best manner, for the good of all members of
connection design information complicated the kind of group society whose lives are touched by the standards we help develop.
interaction that has characterized much of the research in the When we do so, ours will be a lasting contribution.
steel construction field.
Ronald O. Hamburger, S.E.
Senior Vice President
EQE International Inc.

INTERNATIONAL SECRETARIES
Australia and New Zealand Croatia Russia
Raymond K. Ryan Prof. Dr. Slobodan Kralj Dr. Vladimir P. Yatsenko
Phone: 61-2-4862-3839 Phone: 385-1-61-68-222 Phone: 077-095-737-62-83
Fax: 61-2-4862-3840 Fax: 385-1-61-56-940 Fax: 077-093-737-62-87
Cover: The Maritime Off-Ramp Bridge in
San Francisco is the first curved welded
steel orthotropic bridge in North America.
See story on page 2. Cover photo by Lynn
Harrison of Caltrans.

Omer W. Blodgett, Sc.D., P.E.


Design Consultant
Features
Volume XVIII
Number 1, 2001
2 North America’s First Curved Welded Steel
Editor Orthotropic Bridge
Duane K. Miller, This project was designed and built in seven separate construction contracts
Sc.D., P.E. to avoid impacting traffic in an important transportation corridor.
Assistant Editor
R. Scott Funderburk 11 Nondestructive Inspection and Responsibility
An American Welding Society engineer explains what engineers need
The James F. Lincoln
Arc Welding Foundation to know about magnetic particle, liquid penetrant, ultrasonic, and
radiographic inspection techniques.

19 Kuparuk River Submersible Bridges


A combination of welded steel submersible bridges and paved low-water
roadways provides a permanent crossing between the Kuparuk Oil Field
The serviceability of a prod-
uct or structure utilizing the
and Prudhoe Bay, Alaska.
type of information present-
ed herein is, and must be,
the sole responsibility of the
builder/user. Many vari-
ables beyond the control of Departments
The James F. Lincoln Arc
Welding Foundation or The

8
Lincoln Electric Company
affect the results obtained Lessons Learned in the Field:
in applying this type of infor-
mation. These variables
Don’t Design with Your Heart
include, but are not limited In this column, Omer Blodgett shares another of the timeless lessons
to, welding procedure, plate he has learned about welded design, and asks Welding Innovation readers
chemistry and temperature,
weldment design, fabrica- to do the same.
tion methods, and service
requirements.
10 Opportunities: SAC Seismic Publications
and New Lincoln Electric Professional Programs

17 Design File: Fillet Welds That Are “Too Long”

THE JAMES F. LINCOLN ARC WELDING FOUNDATION

Dr. Donald N. Zwiep, Chairman John Twyble, Trustee Duane K. Miller, Sc.D., P.E. Roy L. Morrow R. Scott Funderburk
Worcester, Massachusetts Mosman, NSW, Australia Executive Director & Trustee President Secretary

Welding Innovation Vol. XVIII, No. 1, 2001 1


North America’s First Curved
Welded Steel Orthotropic Bridge
by James E. Roberts, Tony Marquez, Carl Huang, Alfred Mangus
California Department of Transportation, (CALTRANS) Sacramento, California
John Williams
ICF Kaiser Engineers, Oakland, California
Michel Benoit
Walnut Creek, California

Introduction
The $22 million, 2,356ft (718 m) long
“Maritime Off-Ramp,” also known as
the Horseshoe Line or “HS” Line
because of its 250 ft (76 m) radius
horseshoe shape, is the first curved
welded steel orthotropic bridge in
North America. It is one of eleven
bridges in a $130 million interchange
located at the intersection of two free-
ways I-80 and I-880 (Figure 1), which

Lynn Harrison, Caltrans


was one construction contract. The
$1.1 billion replacement project was
designed and then built in seven sepa-
rate construction contracts to minimize
impact on traffic in this important
transportation corridor. Figure 1. Morning rush hour traffic under the Maritime Off-Ramp.

There are fewer than 50 orthotropic


bridges in North America and about Bridge Design Criteria ensure adequate toughness (CVN
1,000 in Europe. “Orthotropic” is a • Load factor design was used and Impacts) for improved fatigue perfor-
combination of two words, orthogonal 1983 AASHTO with interims and mance.
and isotropic. When such a bridge is revisions by CALTRANS.
built entirely of steel, the term • ASTM A709 Grade 50 for box gird-
“orthotropic bridge” is used, but if only • Live Loading: HS20-44 and alterna- ers, flat plate stiffeners, bearing
the deck is orthotropic, the term tive and CALTRANS permit design stiffeners and shear keys.
“orthotropic deck” is used to describe load.
the bridge. The jargon “tub” girder is • ASTM A709 Grade 36 for bearing
sometimes used to describe a rein- • Seismic Design: The reconstruction shim plates, manhole door covers
forced concrete deck placed on top of project design package with a site- including stiffeners and hinges and
steel components consisting of two specific response curve. latch components and ladders.
webs and bottom plate. The Maritime
Off-Ramp bridge was more difficult to • Structural Steel: ASTM A709 Grade • ASTM A500 Grade B for structural
fabricate than a tub girder because 50T2 was specified for the tension tubing.
the welders and painters would then components of the orthotropic box
be required to work inside a closed girders. The “T2” is specified to
cellular structure.

2 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


• ASTM A668 Class G with supple- Gate Bridge. Many welding details for Fracture Control Plan
mental Charpy requirement for the trapezoidal rib were repeated for The optimization of the safety and
heavy wall cylindrical forging for the “HS” Line. The transverse flexural performance of the structure under
shear keys. stiffness of the orthotropic steel deck minimal cost is the basic aim of a
is critical for the long-term behavior of rational “fracture control plan.” While
• ASTM A252 Grade 3 (minimum the asphalt overlay. The weight-saving buckling and general yield are consid-
yield strength of 45 ksi) for steel concerns, which guide the seismic ered in the basic design approach,
piles. design, dictate minimal overlay thick- special consideration is given to the
ness. This leads to a compliant deck danger of subcritical crack growth and
• ASTM A-325 for structural steel system, which is very sensitive to tem- unstable crack extension. Special
connections. All bolt heads shall be attention, at the design stage and sub-
located on the exterior face of all “Orthotropic” is a sequently at the fabrication stage, is
exterior steel plates, including the given to the factors affecting these
top deck flange plate, bottom flange combination of two fatigue-induced micro cracks.
plate, exterior inclined web plates words, orthogonal
and end diaphragm plates.
and isotropic The main elements of the fracture
control plan considered are:
• ASTM A-449 for masonry plate
anchor bolts embedded in concrete. perature and to local deflections • the identification of the main tribu-
imposed by concentrated wheel loads. tary factors such as local loads,
• ASTM A-307 for miscellaneous The cyclic nature of this loading only dynamic amplifications, stress risers,
anchor bolts unless noted otherwise. increases the problem of compliance residual stresses, and two-dimen-
between overlay and steel underlay- sional states of “hydrostatic tensile
• Hexagonal shaped reinforced ment. The long-term delamination stresses;”
concrete footings with reinforced danger of the overlay is greatly
concrete columns using the latest reduced by providing a uniform stiffen- • the establishment of the relative
CALTRANS detailing methods. ing pattern with relatively closely importance and contribution of each
spaced components, and a relatively of these tributary factors;
Orthotropic stiff top deck plate.
• the determination of the various
Superstructure Fatigue strategies in design and fabrication
Type Selection The over-all stress ranges under to mitigate the most important “frac-
Steel bridges were selected by CAL- global loads are very low for this type ture-causing” elements; and
TRANS to cross over the busy freeway of multicell box girder. The longitudinal
to minimize travel delays or lane clo- continuity and the 180° in plane • the recommendation of an optimal
sures during bridge erection to com- “curve” further minimize longitudinal design and fabrication procedure,
muters and highway traffic. Kaiser tensile stress ranges. The torsional including choice of materials, quality
Engineers selected an orthotropic stress components are also low for control and inspection methodology.
bridge with trapezoidal ribs. The these large “cell perimeters.” The
unique 180-degree curve or horse- resultant equivalent stress intensity The three primary factors affecting
shoe bend shape of the bridge made values (von Mises yield criterion) are local failure and ensuing major dam-
a closed cell structure the most eco- very low. age, and hence the life span of a
nomical shape to resist the torsional structure undergoing fatigue loading
forces. The bridge utilized reinforced The local orthotropic deck stress are:
concrete “T” bents with a single col- ranges generated by localized dynam-
umn with spiral reinforcing ties. Two ic wheel loading are more critical for • the tensile stress range amplitude;
special bearings connect the super- fatigue, particularly at points of greater
structure to each “T” bent. restraint and stiffness, such as the • the material flaw or discontinuity
intersection of deck plating with the sizes, which relates to quality control
longitudinal webs and the transverse and assurance;
Special Issues diaphragms. Inclusion of the various
Orthotropic Deck Stiffness stress raisers and consideration of the • the material toughness properties
Some of the details used on the “HS” weld types still leads to excellent long which means choice of specific
Line were first utilized on the Golden term fatigue capacities. steel.

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 3


Robert Colin, Caltrans

The cross sectional properties were


derived from local sectional models.
The use of substructuring by means of
the “super-element” technique was
contemplated and subsequently aban-
doned because of the need for live
loads applied on to every span and
the development of envelope curves
for “forces” and “displacements.” The
global dynamic model was developed
with the main requirement of capturing
90 percent of the total modal mass
participation in all three orthogonal
directions.

Special attention was given to the


expansion joints and to the founda-
tions. Upper and lower bounds for
foundation impedance’s were consid-
ered. The pier columns were also
considered under two distinct states,
elastic uncracked and cracked as well.

Figure 2. The unusually large components of the orthotropic box girder sections, The seismic analysis consists of the
shown in the fabricator’s shop. spectral response approach based on
the CQC modal superposition. These
linear analyses are performed for a
site-specific “mud site” spectrum, cor-
The design philosophy consists of Analysis responding to the maximum credible
providing for “minimal” stress raisers Various task-specific programs were earthquake occurring on the closest
through a careful choice of details and used to simulate the static and dynam- fault with an 8.0 M magnitude and,
weld types. Redundancy is used with ic behavior of the bridge structure alternatively, on the nearby fault with
caution to minimize global and local global static analysis. an 8.5 M magnitude.
stress range amplitudes and also to
provide multiple load paths. Crack Kaiser Engineers developed a global The seismic design philosophy is a
arresters are considered in various static model for the complete structure displacement-ductility driven
fracture propagation scenarios. using the computer software “SAP-90”. approach, which permits controlled
Dedicated pre- and post- processors plastic straining to occur at the various
Buckling allowed Kaiser Engineers’ bridge pier foundation bases. Soil-structure
Web and flange local buckling are designers to produce the governing interaction analyses were performed
considered in a “limit load analysis” by means of the GROUP finite-differ-
approach with given transverse imper- ence program. The very deep mud
fections. Indeed, it is essential to The design philosophy layers were simulated under different
include actual fabrication conditions consists of providing material assumptions to detain mean-
simulating imperfect geometry and ingful sensitivity curves, and to verify
welding residual stresses. for “minimal” stress the compliant pile behavior.
raisers…
Shear Lag Dedicated non-linear ABAQUS finite
The web “slenderness” leads to some element models were developed for
shear lag effect which needs to be load combinations for service and for local web and diaphragm buckling
considered in the local fatigue, as well ultimate conditions for service, and for analyses for local wheel loading stud-
as in the local buckling capacity of the ultimate conditions corresponding to ies on the orthotropic deck. The steel
most critical web panels at midspan the standard LRFD approach, in impact barrier was studied by means
and near supports. accordance with AASHTO-NCHRP of a dedicated non-linear ABAQUS
and CALTRANS policies. model as well in order to simulate the

4 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


ultimate energy absorbing capability was further complicated due to the the rib-to-deck welds, welding was per-
and the impact load reaction applied curved configuration of the girders. formed in accordance with the require-
to the main superstructure. The top deck plates with the welded ments of the AWS D1.5-88 Bridge
rib sections proved difficult to handle. Welding Code (Figure 3). Non-destruc-
Seismic Detailing Once all sub-assemblies were fitted tive testing was performed on all critical
together, this required that most weld- weld joints. The contractor fabricated
Features ing be performed in the vertical and thirteen full bridge width orthotropic
The bridge has several unique seismic horizontal positions within the closed sections 7'-0" (2.13 m) deep by 35'-6"
detailing features including the use of box sections. The girder sections (10.7 m) to 37'-6" (11.3 m) wide, with
rubber dock fenders as seismic shock were too large to turn to allow welding
absorbers reducing forces between in the optimum flat and horizontal
completed bridge sections. The rub- welding positions. Both shop and All sections were
ber delta-shaped “dock fenders” were inspection personnel had to work in
used to reduce kinetic energy occur- the interior confinement of the box shipped with a steel
ring during a seismic event at the sections using artificial lighting and uti- orthotropic deck…
hinges in the superstructure. The sys- lizing the various manhole openings
tems were developed for this bridge by for access.
Kaiser Engineers and are unique to lengths varying from 123 to 219 ft (37.5
the CALTRANS. Universal Structural Inc. provided in- to 66.75 m) per section. The sections
house quality control inspection and ranged in weight from 250 tons (227 m
Poly-tetra-fluoro-ethylene (PTFE) testing. This was augmented by the tons) to a maximum of 459 tons (416 m
spherical bearings were used to allow CALTRANS QA shop inspectors who tons). All sections were shipped with a
for rotation and expansion of mem- provided continuous oversight during steel orthotropic deck and with the
bers. These bearings can resist high- the period of fabrication and painting. installed steel barrier rails. The total
er lateral forces including seismic All inspections and tests were per- weight of all fabricated steel equaled
forces. A central shear key pipe was formed in accordance with the require- 5,014 tons (4,548 m tons).
added for additional lateral capacity. ments of CALTRANS standard
specifications and added special provi- All the steel plate for the superstruc-
sion requirements. With the exception ture was manufactured in the USA by
Fabrication of of the added welding requirements for Bethlehem Steel Corporation Burns
Orthotropic Bridge
Sections
The unusually large dimensions and
weight of the orthotropic box girders
would limit their fabrication to only the
largest fabricators (Figure 2). Both
transverse and longitudinal bolted splice
alternatives were included in the design
to allow the fabrication of the girders in
the smallest sections possible. The
complexities of the welding and fit-up of
component pieces required experienced
steel bridge fabricators. Fabrication
was subcontracted to Universal
Structural Inc. of Vancouver, WA, an
established steel bridge fabricator and a
certified AISC category III shop. They
Robert Colin, Caltrans

had previously supplied fabricated steel


components for many bridges owned by
CALTRANS.

The large size and weight of individual


girder components created some diffi- Figure 3. Semi-automatic welding was needed to provide continuity at ends of
cult handling and fit-up problems. This ribs fabricated in 20 ft (6 m) long straight segments tangent to radius.

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 5


Robert Colin, Caltrans

The first three of thirteen bridge sec-


tions were loaded on a 20-line
Scheuerle platform trailer. A transition
ramp was placed between the barge
and the Universal Structural Inc.’s dock
to load the sections onto the barge.
Three barge trips were conducted
using a 400 ft (122 m) long by 100 ft
(30.5 m) wide barge, one of the
largest available in the United States.

A 20-line, two-file Scheuerle hydraulic


trailer with a custom-designed spacer
frame was used to off-load the girders
at the docking facilities near the bridge
site. The frame between the axles dis-
tributed the load over a wider path to
meet structural requirements on the
dock. The Scheuerle hydraulic trailers
have two unique features. First, each
Figure 4. Special heavy-lift hydraulic platforms (SHLHP) pull a 450-ton (408 m pair of tires can be individually
ton) all-steel orthotropic section across freeway lanes. steered. Second, each pair has a
hydraulic cylinder that allows the pair
of tires to move up and down (over
uneven surfaces) to a maximum of 18
Harbor Indiana Division. The combi- tion all the steel sections. Kiewit- in. (457 mm), while maintaining uni-
nation of their 110" and 160" (2,794 Marmolejo’s assignment was to assist form loads across every pair of tires.
mm and 4,064 mm) plate mills were with the jacking, do the traffic control
capable of the full range of plate sizes coordination with the CALTRANS, and The sections were set on temporary
required for this bridge. The bridge perform all of the work associated with cribbing in the staging area. The off-
sections were fabricated by and making the splices and preparing the load sequence and staging locations
barged down in thirteen sections to a bearings. A creative solution for the required careful planning since the
docking area about a mile (1.6 km) installation was conceived using a sections could not pass each other in
from the bridge site. special heavy-lift hydraulic platform the staging area once they were off-
(SHLHP), which consists of two self- loaded. Therefore, each section was
Dramatic Midnight propelled hydraulic platforms braced in moved three times: first from the fabri-
cation facility to the barge; second from
Erection Process the barge to the staging area beside
The bidders were given the option to Closure of 50 percent the freeway; and finally erected.
fabricate and erect the bridge in sec-
tions that would allow the maximum of the freeway lanes Closure of 50 percent of the freeway
number of bidders and fabricators. was required for lanes (at one time) was required for
A minimum section size was specified
on the contract plans. The smaller the
setting three of the setting three of the thirteen sections.
Approximately 500,000 vehicles cross
sections, the more field bolting that thirteen sections below the Maritime Off-Ramp each day.
would be required. The smaller The sections were staged on the east
pieces, however, allowed smaller steel side of the freeway and crossed over
fabricators to bid on the project. The tandem with a strut beam. Universal during night erection. This could only
successful low-bidder was a general Structural Inc. had the capacity to build take place in a ten-hour window begin-
contracting joint venture of Kiewit- the thirteen full bridge width sections ning at midnight on a Saturday night. A
Marmolejo. The steel subcontractor as one welded unit “arc” shaped stiff financial fine was stipulated for
Shaughnessy and Company with pieces. A scale model was built to try each minute that the contractor exceed-
Crowley Maritime Services Inc. was out the various methods to pre-plan ed this time limit. This fine would be
responsible to supply the equipment the most effective use of the SHLHP. paid to CALTRANS. The first section
and trained operators to lift and posi-

6 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


Robert Colin, Caltrans

The final transport vehicle for the sec- were erected, the joint seal assem-
tions, the SHLHP consisted of 24 lines blies were installed and an epoxy
of Scheuerle hydraulic trailers, which asphalt overlay wearing was placed
were assembled into two six-line, four- prior to opening the bridge to traffic.
file platforms (Figure 4). Two hydraulic
support towers on an adjustable frame Lessons Learned
were mounted on hydraulic powered • Pile “load indicator program” eliminat-
sliding turntables. The SHLHP’s ability ed piling driving claims and estab-
to make various motions allowed the lished pile tip elevations for seismic
section to move on six axes. loading. Largest pipe piling used was
42 in. (1067 mm) diameter.
Surveyors called out offsets as the
SHLHP’s six degrees of hydraulic- • Although the orthotropic steel bridge
activated controls aligned the boltholes system is complex, it is a buildable
and set the other end for grade and system. An orthotropic superstruc-
station. Before the first bolt could be ture is under fabrication for the
secured, all holes had to be aligned. Carquinez Suspension Bridge to
The bolting process began less than replace the 1924 Carquinez
two hours from the start of the opera- Cantilever Truss Bridge. The
tion and was completed in another orthotropic superstructure is current-
three hours. The section’s placement ly under final design by the East
Figure 5. Two welders each field-weld and bolting procedure totaled six Spans replacement for San
a top bearing plate to connect the hours, which was well under the ten- Francisco-Oakland Bay Bridge
bottom of the section to the previously hour minimum. Once 25 percent of design team. This self-anchoring
installed bearing. the bolts were installed plus the field bridge will be about a mile (1.6 km)
welding of the section to the bearings west of the Maritime Off-Ramp.
was erected at the west abutment and (Figure 5), then the dead weight of the
allowed the team to practice for the section was transferred to the splice
erection over the freeway. This gave and bearings. Finally the SHLHP was
Kiewit-Marmolejo, CALTRANS and The driven away. The SHLHP have been
California Highway Patrol confidence used to hoist eleven-story structures
that things would go according to plan. into place at oil fields. “This is not a
The hydraulics of the “SHLHP” worked test,” the erector’s manager said. “It’s
smoothly to position the section and actually something we’ve done many
lower it onto the steel bearings times.” The sections were field bolted
anchored to the top of the concrete together. “Some pieces weigh up to
pier. The section over the westbound 500 tons (453 m tons),” said the
lanes was erected about midnight erector’s manager. The remaining ten
on a Saturday. The section over the sections were not located over freeway
eastbound freeway was erected the lanes and were erected during the
following Saturday night. daytime. After the thirteen sections

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 7


Lessons Learned in the Field
by Omer W. Blodgett, Sc.D., P.E.

Don’t Design with Your Heart

Introduction
My introduction to welding and the
field of welded design really began in
my childhood. My grandfather owned
twenty-three wooden ships, steam-
boats and barges on the Great Lakes.
They carried salt and limestone up the 1931 to 1945, the use of welding elec- in the classroom. I do hope that our
lakes, and pulp wood down the lakes trode in the United States increased readers will contribute their own
to the paper mills. In 1917, the year I almost one hundred-fold. “lessons learned in the field.”
was born, my grandfather purchased a
200 amp Lincoln welder. Ten years In 1945, I wrote an article for the In all of the examples I will cite in this
later, I learned to weld using that Globe Shipbuilding Company newslet- column, one cardinal truth overrides
machine. ter in which I predicted “a far greater every other: if the engineer makes the
use of welding than anything which we mistake of considering welding to be
Our last ship burned in 1931, putting can now imagine.” However, the writ- just another type of fastener, alongside
us out of business. It was the Great ers and codes and structural specifica- such fasteners as rivets and bolts, the
Depression, so in our home town of tions were unfortunately not aware of item or structure as designed will fall
Duluth, Minnesota, we started a weld- my predictions! For example, prior to far short of its potential capabilities.
ing shop using that Lincoln welder. My 1953, the AASHTO Specifications for Welding is not a fastener; it is a
brother, my father and I all welded in method of design which, properly
the shop, and my mother kept the used, takes full advantage of the
books. Our work in the shop provided Welding is not versatility of the material.
a variety of experience, and soon I a fastener—it is a
was welding on steel structures. I
method of design Don’t Design
became an iron worker, joining local
No. 563 of the International with Your Heart
Association of Bridge Structure and What do I mean by a statement like
Ornamental Iron Workers in Duluth. Highway Bridges listed only 13 places “Don’t design with your heart?” Well,
Later, I graduated from the University where welding could be used on a all too often, before taking the time to
of Minnesota with the degree Bachelor steel bridge; a welded plate girder was rationally think through a problem,
of Metallurgical Engineering in 1941. not among them. Such oversights— engineers make assumptions based
and there were many more of this on past experiences. These assump-
By the beginning of World War II, I had kind—undermined the true potential of tions may or may not be applicable to
become welding superintendent at the welding technology. a given circumstance. Although my
Globe Shipbuilding Company in illustrations of this lesson are not
Superior, Wisconsin. From 1941 to At Welding Innovation, we decided to structural examples, the basic design
1945, we built and delivered twenty- develop this column as a forum to dis- principles I will discuss can (and
nine all-welded oceangoing vessels for cuss and illuminate key principles of should!) be applied to structural
the U.S. Maritime Commission. From design that are not commonly taught design.

8 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


A salmon canning plant was having
trouble with a cast steel lever that put
the tops on the cans. When the lever
operated rapidly, inertia forces (F =
ma) were created, causing deflection
and putting the lever out of alignment. realize that the modulus also changes maximize “r,” which is the radius of
An engineer (thinking with his heart) to one-third that of steel. Remember gyration. Increasing the radius of
immediately had the idea of making that for structural metals such as steel, gyration can be accomplished one of
the lever out of aluminum, which has stainless steel, aluminum, magnesium two ways: by putting more material out
one-third of the density of steel, in and titanium, the modulus of elasticity away from the neutral axis, or by sub-
order to reduce the mass by one-third, tracting material near the neutral axis.
thus reducing the inertial forces. This The latter can be achieved by drilling
was a good idea, but would not have We can’t pick holes in the lever, as shown in the
alleviated the deflection problem. just the qualities drawing. This simultaneously decreas-
es the area (and subsequently the
To solve the problem the variables that we want and throw mass) and the moment of inertia,
influence deflection must be studied. the rest away while increasing the radius of gyration.
The following equation defines the Even though the moment of inertia is
lever deflection as a function of the reduced, the part will be slightly more
material properties and cross-section. is proportional to the density. So rigid in bending because the rate of
although this solution has reduced the decrease for the moment of inertia is
density by one-third, it has also less that that of the area.
a δ A L4
∆= reduced the stiffness property by one-
3 E I third—in other words, nothing has
been accomplished. The engineer is
right back where he started. The solu-
…where E/δ is the property of the tion will never be found by changing
material, and I/A = r2 is the property of the material, but only by focusing on
the section. the geometry of the cross-section.

When the engineer switches to alu- The design solution to this problem will
minum, he changes the density to be found by maximizing I over A,
one-third that of steel, but he fails to where I = r2A. So the designer must

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 9


Opportunities

SAC Seismic Publications Now Available from FEMA


The results of the six-year research and development effort conducted by SAC following the 1994
Northridge earthquake have been published in four volumes by the Federal Emergency Management
Agency (FEMA). In addition, a CD-ROM to be made available in the future will contain the
Background Reports, which include the results of the various investigations that were conducted in
order to develop the recommendations.
The SAC Joint Venture is a partnership of the Structural Engineers Association of California (SEAOC),
the Applied Technology Council (ATC), and the California Universities for Research in Earthquake
Engineering (CUREe). The following publications are available free of charge by calling the FEMA
hotline at 800/480-2520:
FEMA 350 Recommended Seismic Design Criteria for New Steel Moment-Frame Buildings
FEMA 351 Recommended Post-earthquake Evaluation and Repair Criteria
for Welded Steel Moment-Frame Buildings
FEMA 352 Recommended Seismic Evaluation and Upgrade Criteria
for Existing Welded Steel Moment-Frame Buildings
FEMA 353 Recommended Specifications and Quality Assurance Guidelines
for Steel Moment-Frame Construction for Seismic Applications

Lincoln Electric Professional Programs


Welding of Aluminum Alloys AND CONTINUED FROM PREVIOUS YEARS… PLUS, OTHER LINCOLN ELECTRIC
October 9-12, 2001 2.5 CEUs. For the design professional: TECHNICAL PROGRAMS
Fee: $595.00
Fracture & Fatigue Control in Structures Basics for the Welding Industry
If you are already familiar with basic welding October 16-18, 2001 2.0 CEUs $595.00 October 16-19, 2001
processes, this course will sharpen your knowl-
edge and skills with regard to aluminum alloy Blodgett’s Design of Welded Structures Industrial Processes for the Welding Industry
materials, processes, equipment and techniques. September 11-13, 2001 2.0 CEUs $595.00 October 23-26, 2001 $249.00
Consisting of equal amounts of classroom and
hands-on welding time, this four-day course is Blodgett’s Design of Weldments Advanced Processes for the Welding Industry
designed for engineers, technologists, welding November 13-15, 2001 2.0 CEUs $595.00 September 25-28, 2001 $249.00
technicians and fabricators.
Welding Technology Workshop
July 30-August 3, 2001 $295.00
Welding HPS Bridges
July 25-26, 2001 1.5 CEUs. $595.00 Space for all programs is limited, so register
AWS D1.5 Code Short Course early to avoid disappointment. For full details,
July 24, 2001 0.8 CEUs $295.00 visit our website at www.lincolnelectric.com,
call 216/383-2240, or write to Registrar,
Designed for bridge fabricators, state DOTs, Professional Programs, The Lincoln Electric
consultants and others using or planning to use Company, 22801 Saint Clair Avenue, Cleveland,
High Performance Steel in bridge applications, OH 44117-1199.
Welding HPS Bridges is preceded by a separate
one-day short course on the AWS D1.5 Bridge
Welding Code. Don’t miss this unique opportu-
nity to acquire state-of-the-art knowledge about
HPS and welded bridge fabrication.

10 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


Nondestructive Inspection (NDI)
and Responsibility
By Hardy H. Campbell III
Senior Staff Engineer
American Welding Society
Miami, Florida

This article was published in


Inspection Trends, a publication of
The American Welding Society, and is
reprinted here with permission.

Definition of Terms
Nondestructive Inspection
(NDI)–any technology used to deter-
mine the homogeneity of a weldment
without affecting that weldment’s phys-
ical properties. In this article, the pri-
mary focus will be on magnetic Liquid penetrant inspection
particle (MT), liquid penetrant (PT),
ultrasonic (UT) and radiographic (RT)
inspection techniques.
What Engineers Need acceptable, it would be just as sound if
Engineer—the individual primarily to Know about NDI examined by a subsurface NDI
responsible for the design of a welded Engineers typically graduate from method, such as UT. The problem, of
assembly. In this article, the capital- school with little knowledge of the course, lies with the definition of
ized term “Engineer” will specifically sometimes bewildering science integrity and with the lack of under-
denote the individual acting on behalf involved with NDI, which sometimes standing not only of NDI, but also of
of the project client to make all deci- seems more akin to voodoo magic than the economics and business of fabri-
sions that modify the original design or classical physics. Therefore, they have cating metal.
approve changes proposed by the a limited understanding of the strengths
Fabricator, or accept the Inspector’s and weaknesses associated with each To an engineer, “integrity” means the
report on NDI results. method. All too frequently, engineers ability of a weld to perform its service
use wishful thinking to equate methods, function. But can NDI predict that?
Fabricator—refers to the contracting for example, considering UT and RT to Indeed, how can anyone have confi-
company that performs the welded be essentially identical. dence in that definition unless the
fabrication; the term may used for weld is actually put into service, well
either shop or site welding operations. In addition to their lack of knowledge after fabrication and inspection have
about NDI, engineers without a great been completed?
Inspector—refers to the individual deal of experience in welding may
responsible for supervision of the NDI believe that all welds, if made in accor- So, we must conclude that we can
operations, and who will communicate dance with welding standards, will pro- only use an indirect method to deter-
with the Fabricator and the Engineer vide the same level of integrity. mine “integrity.” NDI provides this by
about the results of the NDI. Therefore, if a weld is inspected only letting us know the extent to which a
by unaided methods and is deemed weld has failed to achieve homogene-

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 11


ity with the base metal being connect- employing experienced welders or The knowledgeable Engineer will know
ed; i.e., the degree to which the weld using small electrodes for the root and that if he or she wants a subsurface
and base metal have failed to form a capping passes, as well as careful quality standard, the contract should
continuous, uninterrupted mass, free grinding and/or the use of GTAW toe call for a subsurface method, at least
of internal (e.g., porosity) and external remelting. for critical connections or some ran-
(e.g., undercut) flaws. domly selected percentage of total
However, the fill passes may not welds. This will ensure that the
Although the achievement of a “per- receive the same degree of cleaning, Fabricator devotes special attention to
fect” weld is ideal, it is not necessary or less experienced welders may be these welds, employing the best
in most circumstances in order to pro- used on the project. This should not welders, and taking extra care in
vide service function. So welding be interpreted to mean that preparing joints prior to welding and in
specifications typically permit a variety Fabricators are trying to hide anything, cleaning the weld while welding is in
of flaw types, sizes and frequencies. progress.
Some, such as porosity, have relatively
little effect on load-resisting adequacy; NDI sometimes Naturally, this extra level of precaution
others, such as lack-of-fusion, can will cost the Engineer’s client more,
have a significant impact. seems more akin but it will provide the added confi-
to voodoo magic dence that the weldment has achieved
Fabricators can control flaws, but the than classical physics the necessary degree of homogeneity.
extent of this control will depend on
the contract requirements. The knowl- All too often, though, the Engineer
edgeable Engineer, familiar with the but simply that they are making opti- specifies a cheaper visual or surface
fabrication business, will realize that mum use of time and available NDI method in the contract docu-
the way a contract is bid will materially resources to comply with the weld ments, but expects a more expensive
affect the way a Fabricator tries to quality standard involved. The use of NDI weld quality. This is sort of like
minimize these internal and external qualified or prequalified weld proce- buying a Volkswagen Beetle and
flaws. If welds are only to be inspect- dures, in addition to the use of quali- expecting it to win a Grand Prix race.
ed with surface inspection methods, fied welders, will minimize the size and Naturally, the consequences of this
whether unaided visual or MT or PT, frequency of subsurface flaws. unrealistic expectation can be nasty
Fabricators will take the measures However, without a method to investi- and expensive.
necessary to ensure that the surface gate the internal volume of a weld,
satisfies these visual or NDI accep- confidence that major flaws have been In the United States, there is a provi-
tance criteria. This may include avoided cannot be high. sion in the AWS D1.1 Structural
Welding Code for Steel that attempts
to address this issue. The provision
states that, if the client wants addition-
al NDI other than the contracted visual
inspection, the client must absorb all
of the subsequent costs, including the
cost of repair for flaws that are outside
the acceptance levels for subsurface
NDI. This appears to be reasonable;
after all, the client should have speci-
fied this NDI in the original bid docu-
ments, which would have allowed the
Fabricator to devoted more stringent
quality control standards to the welds
in question. If these welds fail to live
up to this new, higher standard, the
Fabricator can hardly be blamed.

However, the D1.1 Code adds another


clause, which requires the Fabricator
to absorb all the costs if this new NDI
reveals “an attempt to defraud” or
Magnetic particle inspection

12 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


“gross nonconformance.” This last
clause prompts all kinds of arguments
about what these words mean.
Naturally, the client, who expects
sound work, may argue that any
degree of nonconformance with the
higher NDI flaw acceptance criteria is
“gross” or “an attempt to defraud.”

This may be a disingenuous argu-


ment, if the Engineer acting on the
client’s behalf is truly cognizant of the
differences in NDI capabilities.
However, more often than not, the
Engineer is ignorant of these limita-
tions and is apt to use the following
logic.

“The Code says that if I visually


inspect a weld, it’s acceptable if it
satisfies the visual flaw standard. The Radiographic inspection
Code also says that if I use subsurface
NDI on a weld, it’s acceptable if it
satisfies the NDI flaw standard.
Therefore, both welds being accept- It may be said that such an approach The geometry of a weld will determine
able must mean that both flaw stan- could also invite abuse–why not do the effectiveness and practicality of
this all the time, and make sure that using some NDI methods. Some weld
“X-ray quality” welds are made all the types are thus more conducive to reli-
“Integrity” means the all welds require the same level of
time? Engineers must realize that not able flaw detection than others.

ability of a weld to attention in order to adequately per- Groove welds can be inspected with
perform its service form their intended service function. either UT or RT. However, partial
Trying to make all welds achieve the penetration groove welds will always
function… highest quality standard only unneces- provide flaw-like indications or images
sarily drives up the cost of fabrication. at the unfused weld roots. Unless
Naturally, the Engineer is most con- proper NDI procedures are written,
dards are equivalent. So if I specify a cerned about his or her interests, such such “false” flaws can result in high
visual standard only, I should get an as protection from litigation, but judg- reject rates. Fillet weld geometry cre-
NDI standard too. And if I ask for NDI ment is needed in order to provide ates reflective problems with UT and
and don’t get it, it must mean that the economy as well as integrity for all the image problems with RT. However, the
weld is grossly nonconforming.” interests involved. The central ques- use of partial penetration groove and
tion becomes, “For what weld types fillet welds is usually limited to non-
When I get calls in my office in Miami are the various NDI methods appropri- fatigue, non-tensile or low tensile appli-
on this subject, I suggest that the two ate?” The generic answer is that this cations, so that the need for confidence
disputing parties agree to a mutually depends on both service function and in subsurface quality is not great. The
satisfying settlement, because neither weld geometry. The service function concern is usually restricted to detect-
the Code nor D1 Structural Welding will involve issues such as criticality of ing surface flaws, and so MT or PT are
Committee will ever attempt to define the connection (i.e., consequences of the preferred NDI techniques.
what is “an attempt to defraud” or load-carrying failure), redundancy
“gross nonconformance.” (alternative load paths), loading type Likewise, engineers should specify to
(e.g., cyclic tension, static compres- what extent welds of a particular type
I also suggest that future imbroglios sion), stress level (e.g., sub-yield), and need to be inspected. Logically, welds
can be avoided if some percentage brittle fracture resistance (is toughness that are subject to low stresses, or are
of random subsurface NDI is specified specified?). in compression, or in highly redundant
in the contract, just to keep the structures, could have less coverage
Fabricator vigilant and ensure that
extra care is devoted to critical joints.

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 13


than welds subject to high tensile Additional Comments pose evaluations frequently require
stresses in low redundancy structures. for Engineers fracture-mechanics-based analyses,
It is also important to consider the which, in turn, require information
advantages of automated NDI over This is not to say that either list of about 1.) service stress, 2.) flaw
purely operator-controlled NDI; gener- weld or load types is definitive, but this dimensions, location and orientation,
ally, NDI operated by humans is con- listing serves to highlight typical indus- and 3.) material toughness. For the
sidered less reliable than automated, try practice. Notice that MT or PT purposes of this article, only item 2 is
computerized NDI. would be applied to complete penetra- relevant, highlighting the question,
tion groove welds, even if these would “How confident is the Engineer of the
Recommendations also justify UT or RT. This is because flaw parameters reported by NDI?”
such welds, when subject to high ten-
Weld and Load Types Appropriate sile loads in critical applications, wouldThe use of ultrasonic energy to detect
for MT or PT Inspection need to be checked for potential crack flaws is a tried and true method that
starters on the surface, which UT in does have drawbacks, the biggest
1. Fillet welds. particular can have trouble detecting. being its reliability in flaw detection.
There are many horror stories about
2. Complete or partial penetration Many welding standards will use differ- UT detecting rejectable flaws, only to
groove welds in compression or ent flaw acceptance limits for different
shear. load types, so it is imperative that this
information be conveyed to the Too often, the Engineer
3. Complete or partial penetration Fabricators and Inspectors (the latter specifies a cheaper
groove welds in low static tension or may work for the Fabricator or the
fatigue loads and structures with low Engineer). This can be done in a
visual or surface NDI
criticality and/or high redundancy. number of ways, but probably the most method…but expects
direct method is by indicating on the a more expensive
4. Complete or partial penetration design drawings whether a connection
groove welds in high static tension or is subject to shear, compression or NDI weld quality
fatigue loads and structures with high tension. It must be understood that
criticality and/or low redundancy. this does not refer to the load in the discover upon excavation that the flaw
weld proper, but the load in the attach- was acceptable or nonexistent. This
Recommended Test Frequency – ing members. This is an important may undermine confidence in UT to
Random testing for substantially less distinction to make for fillet welds, some degree, because it is also true
than the total weld length. which are always considered to be that rejectable flaws may also go
loaded in shear. undetected. The reasons for these
Weld and Load Types Appropriate false alarms or missed flaws can vary
for UT or RT Inspection The Engineer’s job doesn’t stop there, from operator error to poor calibration
of course. If an Inspector reports to malfunctioning equipment. But as
1. Complete penetration groove welds unacceptable flaws to the Fabricator, long as we understand that no NDI
in high static tension or fatigue two options exist: method is guaranteed to detect 100%
loads and structures with high criti- of all rejectable flaws, we can appreci-
cality and/or low redundancy. 1. Fix it; or ate the wisdom of requiring safety fac-
tors, redundant designs and specified
2. Complete penetration groove welds 2. Get the Engineer to accept the toughness in critical connections.
in low static tension or fatigue and in-situ flaw. These all assist in bolstering our confi-
structures with high criticality with dence in overall performance.
low redundancy and materials with Most Engineers will opt for A, but often
low or unspecified toughness. conditions will warrant exploring B. Various welding standards use differ-
ent approaches to UT, each with its
Recommended Test Frequency – This will require that the Engineer inherent limitation to accurately size
100% manual inspection of welds or evaluate structural integrity based on a flaws. UT that uses beam reflection
some random percentage for automat- flaw’s existence. Such fitness-for-pur- amplitude only can undersize flaws
ed NDI.

14 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


Fabricators also need to be aware of
how NDI can affect integrity. For
example, using prods for MT can
cause arc strikes on base metal.
While the Fabricator may be diligent in
removing arc strikes caused by weld-
ing, the same concern may not be
shown for prod-induced strikes. Both,
however, can have potentially harmful
hardening effects on steel.

The Fabricator also needs to be aware


Ultrasonic inspection of the NDI complications that can arise
from the selection of certain welding
details. Frequently, Engineers will
allow Fabricators to specify the type of
significantly, while UT that employs What Fabricators Need detail, after indicating the design
beam-boundary techniques is some- to Know about NDI requirement of weld type (typically for
what more reliable, but not foolproof. complete penetration groove welds).
Even more sophisticated techniques, Fabricators fabricate. That statement For example, complete penetration
such as Time-of-Flight-Diffraction may be a tautology, but it emphasizes groove welds made with steel backing
method, do not provide a guarantee of their primary focus, which is not that must be ultrasonically inspected
accuracy, so Engineers must be pru- design or inspection per se. They are will produce a large number of false
dent when using NDI-derived flaw expected to deliver a product that indications arising from the small air
dimensions. meets the standard of quality required gap between the unfused portion of
in their contract with the Engineer’s the backing and the base metal. Too
RT is, of course, an indirect, visual client. If they employ NDI, it is to veri- often, inexperienced UT operators will
method of detecting and sizing flaws, fy that that standard has been report these as rejectable flaws. This
but its weakness is flaw orientation— achieved. Additionally, the client may
planar flaws normal to radiation may have a third party Inspector peering
go undetected. Naturally, planar flaws,
such as lack of fusion or penetration,
over the Fabricator’s shoulder during
fabrication to provide an extra level of
The most important
confidence that the required quality is aspect of Fabricator
Many welding
being achieved. responsibility lies in
standards will use But Fabricators have to be aware of the area of quality
different flaw their obligations vis-à-vis NDI. With control
reference to the situation described
acceptance limits above, should a Fabricator who knows
for different that a critical structure is being bid for can be avoided if removable non-
visual inspection only remain silent at fusible backing is used, or a back-
load types… the bidding stage, and anticipate that gouged two-sided weld is employed,
the client may get wise and require but it behooves all parties to be aware
are the more significant ones from a NDI later? of the potential NDI problems associ-
fracture-mechanics standpoint; for ated with a selected detail.
this reason UT is preferred, since its Such anticipation may require going to
strength is detecting planar flaws nor- the Engineer and pointing out the wis- Other problems associated with NDI
mal to acoustic energy. Additionally, dom of specifying NDI, but Fabricators include the residual magnetism pro-
UT is cheaper than RT and does not may be reluctant to tell Engineers duced by MT, which may affect subse-
involve safety-hazard issues. For what their responsibilities are. It is a quent welding or even the service
these reasons, RT is not generally bit of a conundrum, but one that function of the part. Appropriate
preferred for structural work, though should be addressed at the bid stage, degaussing techniques may have to
many contracts will specify RT in rather than risking a potentially nasty, be implemented.
addition to UT for critical connections. litigious struggle ahead if “gross non-
conformance” is discovered.

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 15


The most important aspect of Inspector or people who report to the for a schedule to be established in
Fabricator responsibility lies in the Inspector, who will need to liaise order to minimize the safety hazards.
area of quality control; i.e., the meth- closely with Engineers and
ods used to ensure conformance with Fabricators. Inspectors should also resist the temp-
a given quality standard in practice. tation to supplant the Engineer in
Quality control adds another layer to As mentioned earlier, fused steel accepting or rejecting detected flaws.
an Engineer’s confidence that, even if backing can become a source of dis- Inspectors are primarily reporters of
some major flaws go undetected, the agreement as the result of the air gap such information, who should of
overall system has been soundly fabri- interface. The good Inspector realizes course provide their assessment of
cated and the consequences of local- the potential for this to happen and acceptability to the Fabricator.
writes a procedure for the NDI person- However, the Fabricator is free to pur-
nel that does not reject these indica- sue Option B as described earlier
Inspectors should tions but instead predicts them. The (persuading the Engineer to accept
resist the temptation Inspector includes this information in the in-situ flaw) and should not feel
the report to the Engineer, who may hamstrung by an Inspector’s opinion.
to supplant the decide to accept these indications as The Engineer should be the final
Engineer in accepting innocuous, or insist on removal of the arbiter of any disputes that arise.
or rejecting backing and re-inspection, or propose

detected flaws
some other alternative. What Do We Get
Similarly, if an Inspector sees that par- Out of NDI?
ized substandard quality are minimal. tial penetration groove welds are to be Can NDI, in and of itself, guarantee
Naturally, this does impose on the subjected to UT, a procedure must be anything about a product? Can it
Engineer the need to verify in some developed that recognizes the reflec- make up for inadequate design? Can
fashion that a quality control system is tors at the not-fully-penetrated weld it even detect all aspects of poor con-
in place and functioning. root so that these are not grounds for struction? The answer to all three
automatic rejection. questions is “No.” What NDI can do is
The use of quality documentation sys- enhance overall confidence in the
tems such as ISO 9001 and its myriad Inspectors must insist on receiving product’s capacity to fulfill its intended
variants may offer some security in information regarding the tensile or function, but it is only part of a process
this regard, but Engineers should be compressive nature of the loads on that involves design and construction
wary of relying exclusively on paper inspected welds when the applicable quality control.
empires. It is the actual implementa- standards require this. Frequently,
tion of written quality systems that Engineers fail to provide this informa- I have used the word “confidence”
determines effectiveness, and for this tion, and the Inspector is tempted to throughout this article, because this
reason, third party inspection teams assume a load-type rather than seek unquantifiable emotion is the very
are frequently used. the Engineer’s input; this should be basis for all the conservative design,
avoided. construction and inspection standards
Inspectors and Their we use. Compliance with all of these
Inspectors should liaise with cannot guarantee performance, but
Responsibilities Fabricators before fabrication or erec- each project phase can add layers of
NDI personnel have education, train- tion even begins in order to determine confidence that the end objective, in-
ing and experience in the esoterica of the accessibility of welds during the situ service performance, can be
their craft. They know the basic construction process. This is particu- achieved. NDI is the last and perhaps
physics and fundamental topics asso- larly true for welds that will be the most visible layer, but cannot stand
ciated with the various methods. They enclosed after final assembly is com- in isolation from design and quality
will work according to procedures plete. Sometimes artificial access, construction. Only when those
established by supervisory personnel such as plate cut-outs, have to be pro- responsible for all three project disci-
to adequately examine the prescribed vided for tight and congested areas. plines cooperate and communicate
weldments. And it is these superviso- For details that are to be radi- effectively can maximum confidence
ry personnel, who will typically be the ographed, it is particularly important be obtained.

16 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


Design File

Fillet Welds That Are “Too Long”


Practical Ideas for the Design Professional by Duane K. Miller, Sc.D., P.E.

When fillet welds exceed a certain leg size to length ratio,


and when such welds are “end loaded,” they can become
“too long.” That is, the added length may not add strength
that is proportional to the increase in length. This situation
rarely occurs, as will be seen, but the designer should be
aware of when it occurs, why the capacity is diminished,
and how to mitigate the effects.

“End loaded” applies to connections where the load is


transferred to the end of a weld. Figure 1 illustrates one
such example. Many lap joints with longitudinal welds
would have end loaded fillet welds, as would bearing stiff-
eners. Welds subject to shear loading due to bending
forces, such as those shown in Figure 2, are not included
in end loaded applications. In addition, transversely loaded Figure 1.
welds are not considered end loaded.

The distribution of stress at the end of welds, such as the


one shown in Figure 1, is far from uniform. The relative
stiffness of the weld versus the two lapped members may
be significantly different. Shear lag further complicates the
stress distribution. Due to these factors, and perhaps oth-
ers as well, the full length of the weld may not be uniformly
loaded. At some length, it becomes unconservative to
assume the full length of the weld is equally effective in
transferring stress. For the purposes of this article, it is at
that point that the weld is considered to be “too long.”

Based on experience and research, a ratio of the weld leg


size to weld length has been determined to be a critical fac-
tor in determining the effective length. When this ratio is 100
or less, the entire length can be considered effective. Thus,
¼ in. (6 mm) welds less than 25 in. (600 mm) long, and 3/8
in. (10 mm) welds less than 37.5 in. (1000 mm) long are no
problem and can be treated in the conventional manner.
Therefore, for many applications, concern about welds that
are “too long” will not occur due to practical considerations. Figure 2.

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 17


For longer welds, however, the additional length may not cross sectional area of the connected material that can be
be proportionally stronger. To address this, the AISC joined by one fillet weld of 100w length. Column 7 provides
LRFD 2000 Specification has added an equation to calcu- the same data for a pair of such fillet welds.
late a β (beta) factor, which reduces the effective weld
length as follows: Careful examination of the data in this table demonstrates
that the need to consider an adjustment on the weld length
β = 1.2 - 0.002 (L/w) < 1.0
will not arise often. The 300w ratio will only occur in very
Leff = β x L unique circumstances. Nevertheless, the designer should
be aware of the situations where the weld is “too long” and
where, adjust the effective length in accordance with the equation
β = length reduction factor shown above.
L = actual length of end-loaded weld, in. (mm)
w = weld leg size, in. (mm)
ENGLISH
Leff = effective length, in. (mm).
Weld Size, w Critical Length, in. Capacity, kips Member Size, in2
When the length of the weld exceeds 300 times the leg in. 100w 300w 1 weld 2 welds 1 weld 2 welds
size, the value of β shall be taken as 0.60. 1/16 6.3 18.8 5.8 11.6 0.2 0.4
1/8 12.5 37.5 23.2 46.4 0.8 1.5
Consider a weld with a w/L ratio of 200: a ¼ in. (6 mm) fillet
weld that is 50 in. (1200 mm) long. Beta is 0.8 in this exam- 3/16 18.8 56.3 52.2 104.3 1.7 3.5
ple, and the effective length is reduced to 40 in. (960 mm). 1/4 25.0 75.0 92.8 185.5 3.1 6.2
5/16 31.3 93.8 144.9 289.8 4.8 9.7
Note for w/L less than 100, the equation would generate
an invalid value of β that is greater than 1.0. 3/8 37.5 112.5 208.7 417.4 7.0 13.9
1/2 50.0 150.0 371.0 742.0 12.4 24.7
Once w/L is greater than 300, β remains fixed at 0.6, 5/8 62.5 187.5 579.7 1,159.4 19.3 38.7
according to the above equation. 3/4 75.0 225.0 834.8 1,669.5 27.8 55.7
7/8 87.5 262.5 1,136.2 2,272.4 37.9 75.8
Table 1 summarizes key issues surrounding the leg size to
weld length ratio. Columns 2 and 3 simply show the 100w 1 100.0 300.0 1,484.0 2,968.0 49.5 99.0
and 300w values for the different weld sizes. Welds less
than 100w are never “too long” and β = 1.0. Welds that are METRIC
longer than 300w will have their length adjusted by β = 0.6.
Between these two values, the simple equation shown Weld Size, w Critical Length, mm Capacity, kN Member Size, mm2
above must be used. mm 100w 300w 1 weld 2 welds 1 weld 2 welds
2 200 600 40.7 81.4 0.2 0.4
In the design process, before the weld size or length is 4 400 1,200 162.8 325.6 0.8 1.6
determined, the load transferred through the connection is
calculated. Then, the corresponding weld length and size 6 600 1,800 366.3 732.7 1.7 3.5
is determined for the electrode strength classification that 8 800 2,400 651.3 1,302.5 3.1 6.2
will be used. Columns 4 and 5 show the maximum load 10 1,000 3,000 1,017.6 2,035.2 4.8 9.7
that can be end loaded on a fillet weld of length 100w,
assuming the use of an E70 (E48) electrode. Column 4 12 1,200 3,600 1,465.3 2,930.7 7.0 14.0
assumes the unusual case where only one fillet weld is 14 1,400 4,200 1,994.5 3,989.0 9.5 19.0
involved, while Column 5 considers the more typical situa- 16 1,600 4,800 2,605.1 5,210.1 12.4 24.8
tion where a pair of welds is involved.
18 1,800 5,400 3,297.0 6,594.0 15.7 31.4
Columns 6 and 7 examine the applications of the equation 20 2,000 6,000 4,070.4 8,140.8 19.4 38.8
described above in yet another manner; that is, by consid- 22 2,200 6,600 4,925.2 9,850.4 23.5 46.9
ering the size of the connected materials. Assuming the
use of a 50 ksi (350 MPa) steel, and a maximum allowable 24 2,400 7,200 5,861.4 11,722.8 27.9 55.8
stress of 60% of yield, Column 6 provides the maximum 26 2,600 7,800 6,879.0 13,758.0 32.8 65.5

18 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


Kuparuk River Submersible Bridges
By Kenton W. Braun
Alan B. Christopherson
Dempsey S. Thieman
Peratrovich, Nottingham &
Drage, Inc.
Anchorage, AK

Introduction
The strength, resiliency and construc-
tion flexibility of welded steel were
keys to the design and construction of
innovative submersible bridges on the
North Slope of Alaska. Representing
a $10 million investment, they cost
about 50 percent less than elevated
bridges to cross two river channels in
a flood plain nearly two miles (3.2 km)
wide. Design challenges included:

• extreme environmental conditions


Figure 1. Aerial view of the completed East Channel Bridge during spring
• design vehicle weights approaching ice breakup.
4 million lbs (1.8 million kg)

• impact from river ice 5 ft (1.5 m)


thick week per year, and eliminate the need Spine Road by using a combination of
to reconstruct the road annually. The welded steel submersible bridges and
• discontinuous permafrost soil project’s completion is expected to paved low-water roadways. Traditional
conditions save the owner and other Alaska elevated bridges serving the same
North Slope contractors more than $3 function would have cost about twice
Background million per year in oil field operational as much as the submersible solution,
and advanced material purchase even though the submersible struc-
Concerns for fish habitat as well as tures are subject to substantially
further industry expansion beyond the The piece is a woven greater environmental forces. The
Kuparuk Oil Field were the major fac- short-span, stout, welded steel struc-
tors driving the Kuparuk River East shell, in which the tures proved to be the most practical
and West Channel Crossings project. inside is outside, and and cost-effective answer to perma-
For the previous nineteen years, these
crossings had consisted of gravel
the outside is inside nently crossing the dynamic arctic
coastal plain rivers.
roads and large multi-plate culverts.
The crossings were breached and costs. The submersible bridges pro- Design and
allowed to wash out during annual vide a permanent crossing between
spring ice breakup, eliminating all road the Kuparuk Field and infrastructure at Construction
access to the Kuparuk Field for six to Prudhoe Bay, Alaska (Figure 1). The owner requested that the bridges
eight weeks per year. The new be designed to support any oil field
Kuparuk River submersible bridges, The crossings pass the peak spring vehicle currently in operation on the
with a total length of 360 ft (110 m), breakup flows (typically more than North Slope. The largest of these
reduce the closure period of this criti- seven times greater than summer vehicles weighs about 3.8 million lbs
cal road link to a maximum of one flows) through and across the existing (1.7 million kg). The entire load carry-

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 19


ing capacity of each bridge is provided Required capacity (design load) of The submersible bridge design utilizes
by the welded steel structure. The each pile was 750 kips (375 tons) 30 ft (9 m) spans that allow an
concrete deck is used only to provide which was easily achieved using a extremely shallow, high-capacity deck
the driving surface, lateral buckling Delmag D-62 diesel impact hammer, and girder system. The superstructure
support, and ensure composite action rated at 165,000 ft-lbs (223,700 joules) consists of eleven welded 22-1/2 in.
for horizontal loads. of energy. (6,858 mm) deep steel plate girders at
3 ft (0.9 m) spacing in cast-in-place
Environmental loads for the bridges The pipe piles were slotted at cut-off structural concrete. The steel struc-
consisted of wind, seismic, river cur- to receive the 36 in. deep x 20 in. ture served as formwork for the super-
rent, buoyant and river ice loading. (900 mm x 500 mm) wide welded steel structure, eliminating the need for
For this design, ice loading was by far box pile cap (Figure 2). The welded falsework and minimizing on-site con-
the most significant consideration. connection between the piles and pile struction time and costs. A 26 in.
cap provided both a full moment con- (7,925 mm) diameter fabricated steel
nection for lateral load resistance and half-pipe deck nose was welded to the
The entire load flexibility in the field critical to success- edge of the upstream girder to provide
carrying capacity ful fit-up of the girder splices. The a round surface that further limits the
of each bridge slotted pile-to-pile cap connection also ice load to the deck (Figure 3). The
provided the load transfer for vertical deck nose is fitted with guardrail sup-
is provided by the loads, again eliminating the need for port pipes that are welded to the out-
welded steel structure bearing stiffeners. All of the welded side girders. A rolled plate welded to
joint designs were AWS pre-qualified, the downstream girder provided the
an instrumental point in reducing cost, concrete formwork on the other side of
Design ice thickness was 52 in. (1300 saving time and providing construction the bridge. Steel plate placed on the
mm) of hard structural ice capable of flexibility in the field. bottom flange of the plate girders and
imposing tremendous loads on the
bridge deck and ice breakers. Each in-stream pile bent has a welded
steel ice breaking pipe on the The unique design
The substructure of each bridge con-
sists of large-diameter, heavy wall,
upstream side. The ice breaker is a
fabricated 36 in. (900 mm) diameter,
saved time and
welded steel pipe piles. Each pile 1 in. (25.4 mm) wall API 5LX-52 pipe expense by reducing
bent, spaced at 30 ft (9 m), consists of installed at 45 degrees. It was field- the ice loads to the
four vertical 36 in. (900 mm) diameter, welded to the pile cap with fillet welds
1 in. (25.4 mm) wall API 5LX-52 pipe to the cap webs only, which provides a structure…
piles driven to 80 ft (24 m) penetration pinned connection. The base was
to support the heavy vehicle loads and welded to a vertical pile using a 7/8 in.
provide lateral support for ice loads. (22 mm) partial joint penetration attached with intermittent fillet welds
groove weld with a 5/16 in. (8 mm) served as the underside concrete form
The piles were spliced near the site to fillet cover pass. When impacted by for the bridge.
100 ft (30 m) lengths with complete an ice floe, this design will fail the ice
joint penetration groove welds in order sheet in bending rather than crushing, The bridge design required an easily
to eliminate expensive and time-con- substantially reducing the lateral force removable guardrail for the crossing of
suming splices in the field. The driven on a single ice breaker from approxi- ultra-wide oilfield vehicles (up to 60 ft
piles required welded cutting shoe tips mately 750 kips to 320 kips (3.34 mil- [18 m] wide). Welded steel pipe
for anticipated hard driving through lion newtons to 1.4 million newtons). sleeves at the edges of the deck pro-
permafrost at refusal. Because stan- This unique design saved time and vide support for the removable
dard pile driving techniques cannot be expense by reducing the ice loads to guardrails. The identical sections of
used in permafrost conditions, a full the structure, providing reasonable tol- guardrail are easily removed and
depth pilot hole was drilled and erances for field fit-up, and utilizing a replaced as the pipe legs slide into the
steamed to thermally modify the per- vertical pile in lieu of more expensive pipe supports in the bridge deck.
mafrost prior to driving each pile. and impractical batter piles.

20 Welding Innovation Vol. XVIII, No. 1, 2001 Return to TOC


Fabrication
All of the components of the bridge
were shop-fabricated into sections that
were easily transported to the site to
minimize costs. Inspections by the
engineer were performed throughout
the fabrication process, and all welds
were 100% visually inspected per
AWS D1.1. In addition, 20% of all
welds and all critical joints and plates
were UT examined. The ends of gird-
ers were beveled in the shop for the
1-1/2 in. (460 mm) complete joint pen-
etration groove field welds. This accel-
erated the project schedule and held
costs down by minimizing the amount
of preparation and weld that had to be
performed in extreme weather condi-
tions. Careful match marking of each
fabricated member allowed the struc-
ture to be erected without field modifi-
cations even given windy and Figure 2. Fabrication of the pile cap. Angle braces were welded to the base
extremely cold conditions. of the webs to minimize distortion/warpage and to support the bottom flange
during fabrication.

Conclusion
This unique and innovative design per-
mitted the creation of permanent
structures across the Kuparuk River
East and West Channels in a very
challenging natural environment. The
combination of durable, submersible
bridges and paved low water roadways
kept the total expense of the project to
about half of what traditional, elevated
bridge designs would have cost. This
successful design promises to serve
as a model for future expansion of the
infrastructure of the North Slope of
Alaska and that of other similarly chal-
lenging environments.

Figure 3. Five-ft (1.5 m) thick fresh water ice impacting the bridge. The thin
superstructure with rounded upstream nose and the sloped ice breaking pipes
were all designed to minimize the ice loading on the submersible bridge, and
to provide ice passage over or under the bridge.

Return to TOC Welding Innovation Vol. XVIII, No. 1, 2001 21


P.O. Box 17188
NON-PROFIT ORG.
Cleveland, OH 44117-1199
U.S. POSTAGE
The PAID
James F. Lincoln JAMES F. LINCOLN
Arc Welding ARC WELDING FND.
Foundation

Cross-section conceptual drawing of a submersible bridge designed and fabricated for the North Slope
of Alaska. See story on page 19.

Return to TOC

You might also like