You are on page 1of 6

Bar Bending Schedule [BBS] Estimate of Steel in Building Construction

Introduction to Bar Bending Schedule [BBS]:-


“BBS” The word BBS Plays a significant role in any construction of High rise buildings. BBS refers to Bar Bending
Schedule. Well, What’s the use of BBS? Why we use BBS? What is BBS?
First of all, Bar is any type of rebar which is used as a reinforcement in RCC. The bar may be a Mild Steel bar or HYSD
bar or TMT Bar.
Bar Bending Schedule is termed as “Calculation of the total Steel required for the construction of a building” We use
steel to make concrete to be reinforced and for tension requirements. But how much steel required for constructing
15 floors building? How much Steel I have to order? All these questions are answered in BBS

In Bar bending schedule, the bars are organized for each structural units (Beams or columns or slabs or footings etc)
and detailed list is prepared which specifies the Bar location (Bar in footings, slabs, beams or columns), Bar Marking
(to identify the bar in accordance with the drawing), Bar Size (length of the bar used), Quantity (No. of Bars used),
Cutting length, Type of Bend and Shape of the bar in reinforcement drawings.

How BBS Changed from 1950-2019:-


Bar Bending
From 1950 to 2019 lots of modifications and enhancements Percentage
Member
happening in our world. In 1950, three-storeyed buildings are
high rise buildings now we are constructing a building with 200 Slab 1% of total volume of concrete
floors+. There is a massive growth in the construction industry.
Due to the vast increase in world population demands Beam 2% of of total volume of concrete
increased facilities, more need for space and more
construction. Column 2.5% of total volume of concrete

Father of Estimation B.N. Datta has given certain Footings 0.8% of total volume of concrete
recommendations for the usage of steel in different
components of buildings. But, he didn’t mention any values if we use more bars in a single structural member.

At that time we’ve used only four bars in S.No. Particulars Result
columns; now we are using 12+ bars in
columns based on load analysis. So, the Standard Length of the Steel Bar
percentage of steel is increased in a 1. 12m or 40'
(Bars are sold at standard Length)
column which reveals that the above-
cited values are outdated. ( They are D2/162
outdated “not wrong”) He wrote that Weight of Bar
2. (were D =
book in 1950. Now we are in 2019. He for length = 1m
Dia of Bar)
gave recommendations according to the
potentiality of construction at that time. If length of bar is 12m with 10mm Dia then ,
Now we are constructing 200 + floors in Weight of bar = D2/162
the small area. Ex: Therefore for length 1m = 1m x D2/162 7.40Kgs
= 1 x 102/162 = 0.61 Kgs
Bar Bending Schedule [BBS]:- For length 12m = 12 x 102/162 = 7.40Kgs
Before dealing with the BBS, it’s very
important to learn the basics of Bar 3. Density of Steel 7850Kg/m3
bending schedule. The below-
mentioned table is a kick-start guide for learning Bar bending schedule from scratch.

Below I am discussing the different concepts of Bar Bending schedule which are very useful while working with BBS.
All these concepts are used in BBS design calculation of any structural member. So be familiar with the below concepts.
To keep it clear, firstly the concepts are discussed and in the end, this post is closed with an example of BBS calculation
of a member.
1. Hook Length or Cutting length of Stirrups:-
The hook length is commonly provided for stirrups in beams and
ties in columns. In general, Hooks are added at the two ends of
the rebar in stirrups or ties.
Hook Length = 9d (d is dia of the bar)
Below image makes you clear why the Hook length = 9d

From above fig, length of hook = [(Curved Portion) + 4d] =


[(4d+d)+4d] = 9d

Hook Length = 9d [d is Diameter of the Bar]

Example Calculation considering stirrup with the hooks at ends:


For clear understanding, look at the below image for calculation of the total length of stirrup the with two hooks at
ends.

Total Cutting Length of stirrup or tie = Total length of Bar + 2 x Hook Length (Two hooks)
Total Cutting Length = L+2(9d)
Therefore Total Cutting length = L+18d (d is the Diameter of a bar)
Hope, now you are clear with the Hook length calculation.

2. Bend Length:-
The Bend length calculation is different for Cranked bars (bent up bars) and bends at corners.
The bars are usually cranked in Slabs and bars are bent at corners in Stirrups or ties.

(i) Bend Length calculation in Cranked Bars:-


As Shear stress is maximum at supports in Slab. To resist these stresses we usually crank the bars at the ends of
supports in the slab. The below figure depicts the bent up bar in Slab. To calculate the bend length the below procedure
is followed.
From the above figure as the bar is bent at an
angle θ0 the additional length (la) is
introduced.

Where, la = l1 – l2–(i)

Tanθ = D/l2 ; Sinθ = D/l1

Hence l1 = D/Sinθ and l2 = D/tanθ

Therefore from (i) :- la = D/Sinθ – D/tanθ

Giving different θ values as 300 , 450, 600 results different additional length la values as below.

The additional length is added to the total length of the bar if the bars are θ0 D
/Sinθ D
/tanθ la =D/Sinθ – D/tanθ
cranked at a certain angle.
300 D/0.500 D/0.573 0.27D
Example Calculation considering Bent up bar in Slab (Cranked bar):-
To keep the crank bar in position, an extra bar of length (L/4) is provided 450 D/0.707 D/1.000 0.42D
below the crank bar as shown in the below figure.
Therefore, the total length of bar = L+0.42D+0.42D+(L/4)+(L/4) = 600 D/0.866 D/1.732 0.58D
1.5L+0.84D
900 D/1 0 1D

1350 D/0.707 D/-1 2.42D


Remember D = Depth of Slab-Top Cover-Bottom cover

(ii) Bend Length calculation when bars are bent at corners:-


The important standards used while calculating the bend length at
corners
1. 45° Bend length = 1d
2. 90° Bend length = 2d
3. 135° Bend length = 3d
Here, ‘d’ = Diameter of bar

Example Calculation considering stirrup with the bends at corners:


From above fig, There are 3 bends which are bent at an angle of
900 and two bends are bent at an angle of 1350
Total bend length = 3 x 900 Bend length + 2 x 1350 Bend length = 3 x
2d + 2 x 3d = 12d = 12 x 8 = 96mm
Below table represents the total length of bar calculation for different types of bar shapes.
(If you are viewing the below table through mobile, scroll horizontally for a clear view)

Total Length of Total Bend


Bar Shapes Total Length of Bar
Hooks Length

Straight Bar
Two Hooks
= 9d + 9d No bend l + 18D
= 18d

Bent Up at one End only

One bend
Two Hooks
bent at an
= 9d + 9d l + 18D + 0.42D
angle 45
= 18d
= 0.42D

Double Bent up Bar

Two Hooks Two bends l + 18D + 0.42D +


= 9d + 9d bent at an 0.42D
= 18d angle 450 =l+18D+0.84D

Overlap of bars
Two Hooks
Overlap Length
= 9d + 9d No bends
=(40d to 45d)+18d
= 18d

3. Overlap Length / Lap Length in Reinforcement:-


The standard length of Rebar is 12m. Suppose the height of the column is 20 m. To purvey this requirement, two bars
of length 12m and 8m are overlapped (joined) with overlap length.

Overlap Length for compression members (columns) = 40d


The Overlap Length for tension members (beams) = 50d
[d is the Diameter of the bar]
Have You seen the below picture on your top
floor of the building? We generally project some
length of Bar on the last floor i.e., 50D. It is used
for further construction purpose. (Constructing
a new floor)

How to Prepare Bar Bending Schedule:


To understand clear, Here I am considering the below structural member RCC Column and preparing a BBS for it.

Calculation part of above table:


No. of Bars calculation:
Main bars = 4
To calculate the No. of longitudinal bars adopt
spacing between bars is 0.1m
No. of Longitudinal bars = Length of column /
Spacing = 3/0.1 = 30bars
Longitudinal bars = 30

Cutting length calculation:


Main bars = 3m + 50d + 50d = 3 + 50×0.016 +
50×0.016 = 4.6m
Stirrups:
Hook length = 9d + 9d = 18d = 18×0.08=1.44m
Bend length =3 x 900 Bend length + 2 x 1350 Bend length
= 3 x 2d + 2 x 3d = 12d = 12 x 8 =0.096m
= l +hook length + bend length = 0.3+0.3+0.3+0.3 +0.144+0.096=1.44m
Hence for Main Bars = 4.6m ; Longitudinal bars = 1.44m

Total Length of Bars:


Total length of Main bars = No. of Main bars x length of one bar
= 4 x 4.6 = 18.4m
Total length of Longitudinal bars=No. of longitudinal bars x length of one bar
=30×1.44=43.2m
Weight of steel bar: BBS of Column
Weight of steel bar for 1m = 1m x D2/162 Column
Total weight of Main bars = 18.4 x 162/162 = 29Kgs Structural Member
(3mx0.3mx0.3m)
Total weight of longitudinal bars = 43.2 x 82/162 =17Kgs
1. Main Bars
Total weight of steel bar required to do BBS of above column = Bar Marking
2. Stirrups (Longitudinal bars)
46Kgs
1. Main Bars = 16mm ;
Important rules while preparing Bar Bending Schedule:- Dia of Bar 2. Stirrups
(Longitudinal bars) = 8mm
 The bars used in building should be grouped together for
each structural unit and listed separately for each floor. 1. Main bars = 4
No. of Bars used
 Bars are listed in numerical order. 2. Stirrups = 30
 To identify the bar in the bundle of bars, each bar is
uniquely labelled with reference details (Length of the 1. Main bars = 3.16m
Cutting length
bar, size of the bar, Shape of the bar) 2. Stirrups = 2.64m
 The type of bar and shape of the bar should be in
accordance with B8666. 1. Main bars = 18.4m
Total Length of bar
 It is essential that the bar mark reference on the label 2. Stirrups = 43.2m
attached to a bundle of bars refers uniquely to a
particular group or set of bars of defined length, size, 1. Main bars = 29Kgs
Weight of Steel bar
shape and type used on the job. 2. Stirrups =17Kgs
 The cutting length and bending length calculations are
separately calculated and not included in the detailed list. Like I have listed the Bar Bending details in a table
and calculations are done separately.

Use of Bar Bending Schedule:

 BBS helps to estimate the total quantity of steel required for the construction of building or structure. It helps
to quote for tender the cost incurred by steel.
 Finding the cutting length and bending length in reinforcement detailing improves the quality of construction
and minimize the wastage of steel, makes an economic construction
 With the help of reinforcement drawings, cutting and bending can be done at the factory and transported to
the site. This increases faster construction and reduces the total construction cost.
 For site engineers, It becomes easy to verify the cutting length and bending length of the reinforcement before
placing the concrete.

You might also like