You are on page 1of 2

Long lead item

Definition
Long lead item refers to the equipment, product or system that is identified at the earliest stage of
a project to have a delivery time long enough to affect directly the overall lead time of the project.
Comments
The long lead items are common in the oil & gas and petrochemicalindustry because of the
complexity of the supply chain used by the end users to design and execute their projects.
In the oil & gas and petrochemical sector, the end user outsource the procurement of the
equipment, product and system to the engineering, procurement and construction
(EPC) contractors.
These EPC contractors have been involved in the project at the last stage for execution, after the
project conceptual study, feasibility study and the front end engineering and design (FEED).
When the end user goes to execution it expects the awarded EPC contractors to execute the
construction of the project as fast as possible.
That is where the conflict comes with the long lead items.
Some equipment, product or system have a normal delivery time which is too long to be outsourced
through the EPC contractors.
Typically large compressors, turbines, generators, control systems may have 12 to 24 months
delivery times for a project to be executed in 36 months.
Even if the delivery time of these equipment may be shorter than the whole project, it must be
considered the additional time for the EPC to organize the tenders and selection of
the vendors which may take 6 to 12 months, plus the time to install these equipment when
delivered on site.
In the best case if these equipment would be bought by the EPC contractors they should add at
least 12 months to the overall project schedule.
To avoid this delay, these equipment are treated as long lead items meaning that they will not
follow the same supply chain as the other equipment.
These long lead items shall be defined at the detailed design stage, or FEED, and the end user will
conduct the bidding process in parallel of the EPC contracts tenders.
The engineering company in charge of the FEED or the Project Management Consultant (PMC) is
normally supporting the end user in this process.
The goal is to synchronize the final decision to select the vendors of the long lead items previously
the choice of the EPC contractors.
To do so the end user places a letter of intent (LOI) to selected vendor of the long lead item and
inform the leading EPC contractor that in case of being awarded it will have to endorse
this LOI and convert it into a formal order.
The benefit is for the end user and its long lead item vendor to work in parallel of
the EPC contractors, so that the long lead item shall be delivered and installed in line with
the EPC overall schedule.

You might also like