WEEKLY ACTIVITY REPORT

3 -STOREY TOWN HOUSE WITH ROOF DECK ( 6 UNITS)


525 Protacio Street, Pasay City, Metro Manila

Contractor : KLK Construction Services Date : 14-19 January 2019


Contract Duration : 183 Calendar Days Day No. : 63
Date Started : 19 Nov. 2018 % of Time Elapsed : 34.43%
Completion Date : 5 May 2019 Weather AM : Fair
PM : Fair

ITEM ACTIVITIES REMARKS

1.0 Dismantling of scaffolds at sidings of concreted beams at Roof Deck On-going


2.0 Plastering works at second floor at wiindow openings and at stairs On-going
3.0 Rebars installation for the other half of the Roof Deck slab/beams On-going
4.0 Chipping works for the stub-out of T&B water closet (Plumbing) On-going
Chipping works for the re-allignment of sewerline at Ground Floor
5.0 On-going
(Plumbing)
6.0 Electrical roughing-ins On-going
7.0 Installation of pipe scaffolds for the other half of roof deck Slab. On-going

ITEM PROBLEMS ENCOUNTERED DURING THE EXECUTION OF WORK REMARKS

Wrong stub-out for Water Closet at 2nd Floor T&B which will cause a
1.0
time consuming in chipping a new stub-out.
Insufficient raw materials which will delayed the execution of works like
2.0
materials needed for CHB laying and beam stirrups.

MANPOWER Number EQUIPMENT Type Model Qty. Status


Project Manager 1 Chipping Gun 1 Operational
Project Engineer 1
General Foreman 1
Working Foreman 1
Steelman 5
Carpenter 4
Mason/Carpenter 2
Labor 1
Personnel/Timekeeper 1
TOTAL 17

Prepared by: Noted by:


ALVIN N. DELIRO LESTER J. REYES
KLK - Project Engineer KLK - Project Manager
PROGRESS PHOTOS ( as of 19 January 2019)

Fig.1. Showing installation of rebars for beams at other half of the roof deck slab
PROGRESS PHOTOS ( as of 19 January 2019)

Fig.2. Showing dismantling of pipe scaffolds at beam sidings

Fig.3. Showing the on-going CHB laying at 3rd Floor Units


PROGRESS PHOTOS ( as of 19 January 2019)

Fig.4. Showing the on-going plastering works at 2nd Floor Units


PROGRESS PHOTOS ( as of 19 January 2019)

Fig.5. Showing the on-going chipping works at Ground Floor Units for sewerline (Plumbing)