Professional Documents
Culture Documents
TECHNICAL SPECIFICATIONS
FOR BMC – ICOMC BUILDING
1 Excavation
The Contractor shall provide all labour, equipment, materials and any incidentals necessary to complete
all aspects of work included in the drawings and specifications.
b. Applicable Standards:
The following standards shall be followed:
a. IS: 3764-Safety Code for Excavation Work.
b. IS: 1498- Classification and identification of soils for general engineering purposes.
c. British Standard 1377-Methods of test for Soils for Civil Engineering Purposes.
d. British Standard 5930- Code of Practice for Site Investigations.
e. SP27 Handbook of method of measurement of building works.
f. Local Building Regulations and Statutory Regulations.
c. Definitions
Clear: The removal of trees, scrub and artificial obstructions including fences, concrete slabs,
kerb and channel, remains of old buildings and the like.
Grub: The removal of tree stumps and roots.
Top soil: Topsoil is all surface soils, which have sufficient humus to support plant growth without
resort to artificial fertilization.
Cut: A general term for ‘in place’ material removed by digging from the ground. The term
‘excavation’ or derivatives thereof may be used interchangeably.
Fill: A general term for material spread and compacted over the ground to make up finished
levels or levels to sub-grade. The term ‘Embankment’ or derivatives thereof may be used
interchangeably.
Sub-Grade: The finished, trimmed and prepared surface of the earth works after completion of
all cut and fills operations. The term ‘formation level’ or derivatives thereof may be used
interchangeably.
Sub-Base: A selected filling layer spread and compacted over the sub-grade to make up levels to
the underside of the base course or floor slab.
Should the Contractor excavate to a greater depth or width than shown on the drawings, as directed by
the employers representatives he shall at his own expense fill the extra depth or width in cement
concrete in proportion as directed by the Project Manager/Client but in no case with concrete of mix
leaner than 1:4:8 cement concrete.
The Contractor shall report to the Project Manager/Client when the excavations are ready to receive
concrete. No concrete shall be placed in foundations until the Contractor has obtained Project
Manager/Client approval in case, the excavation is done through different strata of soil and if the same is
payable as per provision in the Schedule of Quantities the Contractor shall get the dimensions of the
strata decided by the Project Manager/Client for payment. If no specific provisions are made in the
Schedule of Quantities it will be presumed that excavation shall be in all types of soil and other material
and the Contractor's rate shall cover for the same.
The Contractor is responsible for finding suitable dumping yard and for the removal of all sub grade
obstructions, whether indicated or not, wherever it is likely to interfere with execution and completion of
the Project is deemed to be included in its rates. Project document to be maintained as per Client/Project
Manager instructions.
All surplus and unusable earth shall be carted out and disposed off outside the Site but at a location
approved by local authority and confirming to their specifications. The Contractor shall quote its rate for
disposing off or carting away the item considering requirements and standards of the local authority with
whose permission surplus and unusable earth shall have to be disposed off.
1.12 Dewatering:
Rate for excavation shall include bailing or pumping out water which may accumulate in the excavation
during the progress of work either from seepage, rain water or any other cause and for diverting surface
flow, if any by bunds or other means. Pumping out water shall be done in such approved manner as to
preclude the possibility of any damage to the foundation trench, concrete or masonry or any adjacent
structure inside or outside the wall front. When water is met in foundation trenches or in tank excavation,
pumping out water shall be from auxiliary pit of adequate size dug slightly outside the building
excavations. The depth of auxiliary pit shall be more than the working foundation trenches / levels. The
auxiliary pit shall be refilled with approved excavated materials after the dewatering is over.
The Contractor shall adopt an appropriate method of dewatering work and shall submit its proposal for
carrying out the dewatering work for the approval of the Project Manager/Client. The water shall be
Adequate number of pumps shall be deployed to ensure a continuous dewatering process. Power / Fuel
required for the operation of pumps etc shall be provided and paid for by the Contractor. Electrically
operated pumps are to be used to control sound pollution.
Softening of the bottom of excavation will not be allowed. If softening occurs due to weather or any
other source, the Contractor shall remove the affected area and replace as specified and directed by the
Project Manager/Client at no extra cost.
Necessary grading, trenching and temporary sumps shall be made around excavations as required to
prevent water runoff into excavation and to ensure proper protection to slopes from erosion.
1.14 Protection
The excavated area shall be surrounded by strong barricaded safety barriers made of wooden posts three
to four (3 to 4) inches in diameter and cross planks/ runners/corrugated sheets shall be erected to a
height of 1.2m all around the excavation with reflective tapes and necessary lighting at night all as shown
on drawings. The Contractor shall take all necessary measures for the safety of the excavation, persons
working, tools and plants working in and near the excavation pits, property and people in the vicinity.
Protection and maintenance of all bench marks axis points and other similar reference points if disturbed
and/ or damaged, to be replaced by the Contractor at no extra cost to the Client.
All the temporary roads, constructions etc shall be made and maintained according to the provisions of
this Contract and as per the instructions of the Project Manager/Client upon the completion of this
Contract, the Contractor shall remove after getting the approval from the Project Manager/Client all such
temporary roads, structures, etc. and restore the area in its original condition without any extra cost.
Sufficient safety signs /board to be placed in the site premises and all the safety precautions should be
strictly maintained.
General Fill:
One test for each 3000 sqm. placed.
One test whenever there is a change of gradation or placement conditions.
Execute site density tests for compaction at a minimum depth of 100 mm below compacted
surface.
Execute a full compaction test or a one-point compaction test in conjunction with each site
density determination.
Execute a gradation test with each site density test and whenever there is an apparent change in
material being placed.
Execute the following site density tests and laboratory moisture density tests to evaluate
compaction achieved
(i) One test for every 200-400 sqm of backfill in trenches or surrounding structures.
(ii) One test for every full shift of compaction operations on mass earthwork.
1.15.6 General and Structural Fill:
To conform to gradation of well graded soil.
To be free from plastic fines and weakly elemented lumps of sand.
To be homogeneous and at the optimum moisture content for compaction purposes when placed.
1.15.8 Water
Water used for compacting fill or for washing crushed stone shall be clean and free from oil, grease,
organic matter, suspended sediments and other deleterious substances.
1.15.9 Adjacent excavations:
Where an excavation encroaches below a line drawn at an angle of 60 Deg. from the horizontal from the
nearest formation level of another higher excavation, the lower excavation, all work within it and
backfilling thereto shall be completed before the higher excavation is done.
Excavated formations:
1. In made up ground excavate foundations down to a natural bearing formation of undisturbed
subsoil, unless otherwise instructed.
1. Vibratory roller of either double or single vibrating drum of not more than 3.2 tonne mass per
meter of roll width having a vibration frequency of not less than 37 Hz. Vibrating roller not
exceeding the above weight limit but of frequency less than 37 Hz are approved providing the
nominal amplitude does not exceed that shown relative to the weight in tones per meter roll width
in figure1 any other vibrating roller specifically approved by the Project manager. Vibrating rollers
of less than 1 tonne per meter of roll width shall not be used to compact any layer of fill of more
than 175mm of un-compacted thickness.
2. Three wheel steel- tired rollers having rear rolls each at least 0.50m wide and having not less than
4.5 tonne per meter of roll width.
3. Pneumatic tyred roller having a minimum weight when operating of not less than seven tonne,
spread over at least seven pneumatic tyred wheels.
For filling in inaccessible places or against structures, hand tamping or small vibratory compaction
equipment may be used with the approval of the Project Manager/Client.
Care must be taken during compaction to ensure that no gaps are formed between adjacent
layers.
Fill material shall be compacted to attain the densities as called for in the specifications.
As filling proceeds, test to verify the compaction being achieved shall be conducted. Tests shall
be done at a minimum frequency no less than one test per 150 cum. of fill volume. Testing
locations shall be distributed evenly throughout the fill volume and each layer area. The
locations shall be to the satisfaction of the Project Manager/Client and copies of the results of
all tests shall be submitted to them whether successful or not.
In the event that tests do not verify the minimum compaction requirements, the whole of the
area for which the test is representative shall be reworked and retested, unless otherwise
directed by the Project Manager/Client.
Compact filling after grading and leveling surfaces. Compact filling in layers, adding any necessary extra
fill and water, to attain the minimum dry densities as tabulated in the table appended at the end of this
Section.
Backfilling and compaction shall be undertaken under full-time presence of the Contractor’s Supervisor,
and each layer shall be got checked by the Project Manager/Client. Further layers are not to be placed
without the approval of the Project Manager/Client.
Compact filling using vibratory plate, roller or other approved (mechanical) equipment, making the
required number of passes with the equipment to obtain specified densities. Each trip of equipment
shall overlap the previous trip by 500mm.
If selected earth kept aside as per the provisions is not sufficient for the back filling, the Contractor,
with its own cost, shall bring in good quality earth, murrum etc. from borrow pits, either approved at
the site and/ or elsewhere by the Project Manager/Client. The cost of developing and reinstating the
same after use as per the directions of the Project Manager/Client and/or local laws prevailing for such
borrow pits, loading, transporting and re-handling of earth/ murrum etc. deemed to have been
included in its rates by the Contractor.
The Contractor at its own cost rectify and / or restore the damage (s) occurred due to improper backfill
and compaction done by it.
If any settlement occurs due to improper backfill and compaction and/ or cracks developing in the sub-
structure/ super structure works due to the same, the Contractor shall make good its damages/ defects
at no extra cost to the Client.
The Contractor at its own cost protect by bracing the basement walls till the proper back filling and
compaction are completed with the satisfaction of the Project Manager/Client and complying with the
conditions of the Contract and Technical Specifications. The Contractor shall also undertake and
execute the patching of the basement wall after removal of such bracing at no extra cost.
The stones for soling shall be of a height equal to the required thickness of soling. Their length or
breadth shall not be greater than twice the soling thickness. This means that the stones would pass
through a ring 180mm in diameter but not a ring 100mm in diameter.
Soling stone shall be hand packed as close as possible with their broadest side downward and greatest
length across the road. Gauge pegs shall be driven at close intervals to indicate the required thickness
of the soling. The joints between stones shall be placed at the edges of the area to be covered. All
interstices between stones shall be wedged in with smaller stones, well driven into achieve tight
packing and complete filling of the interstices.
Vibratory compactors may be used, if approved by the Consultants / Project Manager/Client instead of
mechanical rollers. For areas where access is difficult or restricted heavy hand rammers and hand
rollers may be used if approval for this has been obtained from the Consultants / Project
Manager/Client.
IS - 3558 Code of practice for use of immersion vibrators for consolidating concrete
IS - 3414 Code of practice for design and installation of joints in buildings
IS - 2571 Code of practice for laying in-situ cement concrete flooring
IS - 1904 Code of practice for design and construction of foundations in soils
IS - 2950 Code of practice for design and construction of Raft foundations
IS - 13920 Code of practice for ductile detailing of reinforcement concrete structure subjected to
seismic forces.
Definitions
a. Water / Cement Ratio:
The ratio by weight of water to cement in a mix expressed as a decimal fraction. Water being that
which is free to combine with cement, including free water in aggregate but excluding that.
b. Hot Weather:
o
Shade air temperature of 37 C and higher.
Quality
All materials used in the works shall be of best quality of their respective kind as specified herein,
obtained from suppliers and sources approved by the Structural Consultant and shall comply strictly to
tests instructed by the Structural Consultant / Project Manager/Client, and where tests are not laid out,
with the requirements of the latest issue of the relevant Indian Standard.
Test Certificate
All manufacturer’s test certificates, proof sheets, etc showing that the materials have been tested in
accordance with the requirements of the specification and of the approved Indian Standard(s) are to be
supplied free of charge on request to the Project Manager/Client.
Cement
Cement shall be of Portland type /PPC and shall comply of IS: 269. The cement used shall be of approved
manufacture and the sources of supply shall not be changed without approval of the Consultants / Project
Manager/Client.
It shall be received in bags of 50 kg each confirming to IS 2580,IS 11652, or IS-11633- or IS-12174. The
bags shall be marked with the manufacturer’s name or its registered trademark, if any, type of cement
and grade legibly and each batch shall be accompanied by a Test Certificate from the factory.
Samples shall be taken immediately on receipt of cement at about one sample per 1000 bags. Tests shall
be carried out on fineness, initial and final setting time and compressive strength as per IS:4031 and result
verified by the Project Manager/Client before use in the permanent works. Samples shall be taken
immediately on receipt of cement at site. Sampling shall be as per IS 3535.
For extra safety during monsoon, or when cement is expected to be stored for an unusually long period,
each stack shall be completely enclosed by a waterproofing membrane, such as polyethylene which shall
cover the top of the stack. Care shall be taken to see that the stored cement is not damaged at any time
during the use.
Storage of the cement at the Site shall be at the Contractor’s expense and risk. Any damage occurring to
cement due to faulty storage in the cement godown or on account of negligence on its part, shall be the
liability of the Contractor.
Aggregate
a. To be crushed naturally occurring materials conforming to IS: 383-All physical properties and
grading parameters must conform to this code.
b. Aggregate, 95% of which shall be retained on 4.75 mm test sieve.
c. Aggregate shall be from crush granite, quartzite, trap, and basalt quarries.
d. Free from soft friable thin porous laminated or flaky pieces.
e. Free and clean from dust and foreign matters, namely injurious amounts of disintegrated pieces,
alkali, vegetable matters and other deleterious substances.
f. Shall be chemically inert when mixed with cement.
g. The aggregate shall not contain any material that will attack the reinforcement. The maximum
quantities of deleterious materials in coarse aggregates shall not exceed the limits laid down as per
IS:2386 (Part I & II)
h. Shall be angular in shape
i. Maximum size of the aggregate shall be 20mm.
j. Shall have a minimum Specific gravity of 2.6(Standard surface dry basis)
k. When stone aggregate or gravel is brought to the site single sized (ungraded), it shall be mixed with
single sized aggregates of different sizes in the proportion to be determined by the field tests to
obtain graded aggregate or specified nominal size. The Contractor is deemed to have included the
cost for above in its rates.
Course aggregates shall be measured in stacks and adjustment shall be made by deducting seven and half
(7.5) per cent of gross measurements of stacks in respect of aggregate of nominal size 40 mm and above.
No deduction from the gross measurements of the stacks is to be made in respect of aggregates of
nominal size below 40 mm.
Course aggregates brought to site shall be washed clean if required and as directed by the Project
Manager/Client.
Fine Aggregate
a. Shall be washed dry sand and shall confirm to IS: 383 between Grading Zone I and II for structural
concrete.
b. Shall pass through IS sieve 4.75mm test sieve leaving a residue not more than 5%
Miscellaneous
a. Chemical curing compound of approved make to form a membrane or surface which will
disintegrate and flake from that surface over a period of days commencing at least 7 days after
application.
b. Vapour barrier and separation layer to underside of concrete slab, as and when necessary, and
grade 10 mil (.25 mm) thick polyethylene sheets with laps 100mm on sides and ends.
Ordinary Concrete
a. Ordinary cement concrete where specified shall be used
b. Proportions 1:3:6, 1:2:4, 1:1.5:3, etc., in the specification refers to the quantity of cement by
volume, dry coarse sand by volume, quantity of coarse aggregate by volume.
c. Cement shall be weighed based on 1 cum. of cement weighs 1440 kgs or 1 full bag of cement 50 kgs
corresponding to 35 lts. by volume.
d. Correction factors to be applied for bulking of sand when the sand is either wet or moist
e. Water cement ratio used shall be just sufficient for the workability of concrete.
f. Minimum strength of concrete shall be obtained as below:
Bill of Quantities shall specify various types of concrete aimed to be used in the Project. It shall be the
Contractor’s responsibility to carry out Design mixes and approval of the same from the Clients
Representative well in advance of the actual pouring of concrete at the Site in the permanent works.
The basic aim of Mix Design shall be to find the most economic proportion of cement, aggregate and
water which will give the desired target mean strength of concrete, workability and durability for
specified grade of concrete. Also it is important that the Mix should be easily worked with the help of
equipment available at the Site. The operations involved are measurement of materials, their mixing,
placing, compacting, finishing required and curing. The design shall be carried out strictly to IS
Specifications and IS Codes of Practice, namely IS: 456- and S P –23-
On receipt of the above, the Project Manager/Client may immediately order to carry out work or site test
before the final approval. This shall be done with the mixer, weigh batches, etc. and materials actually
used in the Project.
This shall give the Contractor additional chance to check for itself actual workability and make sure that
the mix proposed by it will be satisfactory with regards to slump, water-cement ratio and workability.
Test cubes shall be of size 150mm x 150mm x 150mm. These are to be legibly marked with location and
date of concreting. Where concrete (in works) is to be vibrated or not vibrated, the cubes are to be cast
as per IS Standards.
Where the concrete in the works is un-compacted, pour the concrete into the mould in three layers and
compact each layer with a 16mm dia tamping rod.
Six (6) cubes shall be taken from each of the three batches to test the mix. Cube shall be cast, stored,
cured, transported and tested as per IS:516-1959. The test may be carried out at the Site or at laboratory
as approved by the Project Manager/Client.
Trial mix
a. Within 7 days of signing the Contract and before commencing work on site, prepare trial mixes
for each type of concrete and submit 6 preliminary test cubes from each mix to the testing
authority.
b. The testing authority shall test three test cubes at 7 days and three at 28 days for each type of
mix where the difference between the higher and the lowest test results from any one trial mix
at 7 days exceeds 15% of the average and any cube weaker than the minimum requirement,
make a further trial mix, increasing the proportion of cement if necessary to obtain the required
strength.
c. If any test results from any one-trail mix fail to exceed the minimum strength at 28 days:
i. Remove from site materials from which the trial mix was prepared.
ii. Provide new materials and prepare and test further trial mixes until specified requirements are
achieved.
The Design Mix shall hold good so long as the materials continue to be of the same quality and from the
same source. Minor adjustments are to be done daily based on the tests of materials used.
Compression strength on 150mm. Cubes
Control concrete shall be proportioned to obtain the required strength by conducting lab tests using the
coarse aggregate, sand and cement based on the design mix.
Control concrete shall have suitable workability for proper consolidation.
At places having heavy reinforcement when compacting concrete is a problem, the control concrete shall
be designed with special care to the required strength and workability at no extra cost.
Testing facilities to access the moisture content of aggregate at frequent intervals, testing of concrete
cubes and testing of aggregate shall be done at the site by establishing testing laboratories.
Concrete shall be weighed batched. The dials of weigh-batching units shall be checked with standard
weights periodically.
Under special circumstances the conversion of weights to volumes will be allowed by the Consultants /
Project Manager/Client.
The minimum cement content to be used for the job is as per IS:456
Further the Contractor has to provide and maintain all the equipment and stock at the Site throughout to
carry out the following tests in a small Site laboratory or get these tests done from approved laboratories
without extra cost to the Contract.
Grading of aggregate
Silt content of sand
Moisture content of aggregate
Slump test of concrete mix
Concrete cube test
The Contractor shall maintain full records for all above tests in a register. The format of the records shall
be prepared in consultation with the Project Manager/Client. It shall have full access to the Contractor’s
site laboratory. The Contractor shall include charges for these in its rates and no extra whatsoever shall
be payable on this account of designing, testing, maintaining laboratory, etc.
However, when adequate post records for a similar grade exists and justify to the designer a value of
standard deviation different from the shown in table above, it shall be permissible to use that value.
i. Number of test results - Total number of test results required to constitute an acceptable record
for calculation of standard deviation shall be not less than 30. Attempts should be made to
obtain the 30 test results, as early as possible, when a mix is used for the first time.
ii. Standard deviation to be brought up to date -The calculation of the standard deviation shall be
brought up to date after every change of mix design and at least once a month.
Consistency
The concrete which will flow freely into the forms and around the reinforcement without any segregation
of coarse aggregates shall be used. The consistency shall depend upon the type of vibrator etc. to be
used. The controlling factor for the same is the Slump Test.
When considered necessary by the Project Manager/Client, the workability of the concrete shall be
ascertained by compacting factor test and VEE BEE consistometer method as per IS:1199-1959. The
computing of values of workability of concrete by above two methods, IS:456-2000 have to be referred to.
Temperature of Concrete
The placing temperature of concrete shall not be more than 38 degrees Celsius. If it is more, the Project
Manager/Client may order addition of ice or chilled water to the concrete. Also the Contractor shall take
following precautions:
Mixer and Weigh Batcher shall be painted white color.
Aggregate storing bin shall not be exposed to the sun.
Water shall be sprinkled on aggregate well before concreting to keep the temperature low.
Similarly, during the cold weather, concreting shall not be done when the temperature falls below 4.5
Degrees Celsius. The concrete placed shall be protected against by suitable covering. The concrete
damaged by frost shall be removed and work redone with no extra cost.
Shrinkage Cracks
Concreting shall be avoided in very warm weather. Under such circumstances, the placed concrete shall
be covered with damp hessian cloth within two hours of placing of concrete.
To achieve good result the concrete shall be immediately covered with a plastic sheet and not allowed to
any direct wind contact to eliminate shrinkage cracks.
Workmanship
All works shall be true to level, plumb and square and all corners and edges in all cases shall be unbroken
and neat.
Any work not to the satisfaction of the Project Manager/Client or the Design Consultant will be rejected
and the same should be rectified or removed and replaced with work of the required standard of
workmanship at no extra cost.
Transportation
Concrete shall be transported with the help of pumps of sufficient capacity to achieve necessary heights
wherever required from the mixer to the place of laying as rapidly as possible by methods which will
Placing of Concrete
Placing of concrete shall be done using pumps only at all levels. The pumps shall be of sufficient capacity
to achieve necessary heights wherever required.
The slump of concrete placed with the help of pumps shall not be more than 120mm unless otherwise
instructed by the Project Manager/Client. Concreting shall commence only after formwork is approved
reinforcement is recorded and permission to proceed with concreting has been approved in writing from
the Project Manager/Client.
Formwork should be clean, free from dust, pieces of wood or any other foreign material. It should be
treated by form releasing agent prior to the laying of reinforcement and concrete, based on sample
approved by the Project Manager/Client prior to start of construction at Site. Concrete shall be as gently
deposited as is practically possible, in its final position to avoid re handling and shall be so deposited that
segregation of aggregates do not occur. In case of deep trenches and footings, it may be done with the
help of chutes. Concrete from wheelbarrows shall not be dumped away from the face of concrete already
been placed. It shall be dumped into the face of concrete already in place. Concrete shall be laid during
normal working hours. Concreting at night or on holidays shall be permitted only on the written approval
of the Project Manager/Client. No concreting shall be done within half an hour of the closing time of the
day, unless permitted by the Project Manager/Client.
For concreting of slabs and beams wooden plant or catwalks of chequered MS plates or bamboo mats or
any other suitable materials supported directly on the centering by means of wooden blocks or lugs shall
be provided to convey the concrete to the place of final deposition without disturbing the reinforcement
in anyway. In no case labour or any other persons are allowed to walk over the reinforcement.
In case of columns and walls, it is desirable to place concrete without any construction joints. The
progress of concreting in the vertical direction, shall be restricted to one meter per hour.
Concrete pouring shall be done by using appropriate methods like funnel system/chutes for vertical
elements, flexible hoses for horizontal elements etc.
Compaction of Concrete
Concrete shall be thoroughly compacted into a dense mass as depositing shall proceed by means of
suitable vibrators. The vibrator shall maintain the entire concrete under treatment in an adequate state of
agitation and shall continue during whole period occupied by placing of concrete. Care should be taken
not to over-vibrate the concrete. While vibrating no holes should be visible in concreting. Compaction
should be completed before the initial setting time. Compaction shall be done till air bubbles cease to
appear. Concrete already set shall not be disturbed by successive vibration.
The layers of concrete shall be so placed that the bottom layer does not finally set before the top layers
are placed. The vibrators are so applied so that the centre of mass being compacted at the time of placing
of concrete.
Vibrator shall be of immersion type with frequency of 100 Hz minimum when operating in concrete, or
the exterior with a frequency of 50 Hz minimum.
Care shall be taken to ensure that at no time the vibrators and /or vibration action is used to push the
concrete ahead. Vibrators shall be applied systematically to overlap zones of influence.
It shall be ensured that the needle vibrators are not applied directly on the reinforcement on the
formwork which may destroy the bond between concrete and reinforcement.
When electric vibrators are in use the standby petrol, diesel or kerosene vibrator should always be
available at the concreting point.
Construction Joints
Construction joint shall be avoided as far as possible. If provided, concreting shall be carried out
continuously up to the construction joints as directed by the Project Manager/Client and/or at the
location and arrangement shown in the structural drawings. However, the number of such joints shall be
kept to a minimum and they shall be as straight as possible. Swelling bars or per formed plastic adhesive
water stops shall be used for construction joints at water retaining members
Proposed location of construction joints shall be submitted by the Contractor well in advance for approval
of Project Manager/Client/Structural Consultant. The joints shall be at places where shear force is nil or at
a minimum (normally at 1/3rd to 1/4th point of a span) and these shall be straight and at right angles to
the direction of the main reinforcement. Stop ends provided shall be with necessary slots for
reinforcement bars to pass freely without bending or other obstructions. They should be supported firmly
so that the concrete can be properly vibrated and compacted at these points.
Before commencement of concreting after a break, adjacent concrete stopper and surfaces shall be
cleaned, chipped free of any loose mortar and roughened to expose the aggregate and than brushed and
cleaned. The concrete surface shall be sprayed with water for 24 hours before casting and kept wet until
casting.
All construction joints in concrete shall be treated with bonding agent prior to pour next layer of approved
makes at no extra cost. Water swelling bars at construction joints in basement works shall be paid extra.
No construction joints are allowed in casting footings including stepped foundation .Starters shall be of
min 100mm high with necessary frame work and steels.
Curing
Curing of concrete is most important. There shall be no compromise on this activity as it is for the
Contractor to arrange for everything necessary to make sure that the concrete is cured to the complete
satisfaction of the Project Manager/Client. As said above after concrete has begun to harden, i.e. about 1
to 2 hours after laying. It shall be protected from quick drying with moist or damp hessian cloth or any
other material approved by the Project Manager/Client. After 24 hours of laying of concrete, the surface
shall be cured by flooding with water or covering with moist hessian cloth for period of 7 days to keep it
moist. For the next seven days surface shall be kept wet all the time by sprinkling water continuously.
On finishing standards and quality / workmanship, the decision of the Project Manager/Client shall be
final and binding on all parties.
Inspection and Corrective Measures
Immediately on removal of formwork, the RCC surface shall be examined by the Project Manager/Client.
Till such time, no remedial measures shall be carried out by the Contractor. All remedial actions including
breaking, if any, shall be on the instructions of the Project Manager/Client. In case of any violation of this
rule, the concrete poured stands rejected. The decision of the Project Manager/Client in this regard shall
be final and binding to all parties.
Sagged, bulged, patched, honeycombed work to an extent detrimental to structural safety or architectural
concept shall stand to be rejected and Contractor shall rectify by breaking or redoing, if required, as
directed by the Project Manager/Client/Structural Consultant and all expenses incurred due to this shall
be to the Contractor’s account.
Surface defects minor in nature may be accepted as a special case by the Project
Manager/Client/Structural Consultants whose decision in this matter is final and binding on the
Contractor. Once accepted, the defects shall be rectified as follows and all expenses incurred due to the
rectification process, shall be to the Contractor’s account.
(a) Surface defects which require repair when forms are removed, usually consist of bulges due to the
movement of forms, ridges at form joint, honey combed areas, damage, resulting from the stripping
of forms and bolt holes, bulges and ridges are removed by careful chipping or tooling and the surface
is then rubbed with a grinding stone. Honey combed and other defective areas must be clipped out,
the edges being cut as straight as possible and perpendicularly to the surface, or preferably slightly
undercut to provide a key at the edge of the patch.
(b) If permitted in writing by the Client’ Representative/ Structural Consultant, shallow patches are first
to be treated with a coat of thin grout composed of one part of cement and one part of fine sand
added with polymer modified cementitious material as per manufacturer’s specification, and then
filled with mortar (mixed with non-shrink additives) similar to that used in concrete. The mortar is
placed in layers not more than 10 mm thick and each layer is given scratch finish to secure a bond
with the succeeding layer. The laid layer is finished to match with the surrounding concrete by
floating, rubbing or tooling on formed surfaces by pressing the form material against the patch while
the mortar is still plastic.
Cracks
Cracks observed shall be examined. It shall be kept under observation and a record shall be maintained
for a period of 45 days. It shall be shown to the Project Manager/Client/the Structural Consultant and the
following procedure shall be followed:
Cracks not propagating/developing further and according to the Structural Consultant not
detrimental to the strength of the construction shall be grouted with non-shrinking epoxy based
cement slurry or as directed by the Project Manager/Client/Structural Consultant.
Cracks developing further and felt detrimental to the strength of construction shall be tested as per
the relevant Indian Standards.
Based on results, the structural Consultant in consultation with the Project Manager/Client shall
order remedial measures or order the Contractor to dismantle construction, cart away the debris,
replace the construction and carry out all the consequent works thereto as directed/specified.
Cost of above shall be borne by the Contractor if the failure is on its part unless it is due to a design
fault, decided at the discretion of the Project Manager/Client.
Decision of the Project Manager/Client in the matter shall be final and binding on all parties. This decision
shall not be open for arbitration.
Quantum of Cube Testing
The minimum frequency of cube testing shall be as follows. Each set of sample shall consist of 6 cubes.
Concrete Quantity Number of Sample sets
Up to 5 cum a day 1
5 cum to 15 cum a day 2
Acceptance of Work
It shall be in accordance with in IS:456-2000, SP-23 and SP-24. The guidance brief is elaborated below.
Part or element of work shall be deemed to be accepted, provided the results of the 28th day cube testing
confirm to the criteria stated as under:
The average of the three consecutive cubes strength shall not be less than specified strength.
No individual cube strength shall be less than 90% of the specified strength.
If the individual cube strength exhibit more than 133% of the specified strength such a cube shall be
specified as freak and the criteria in above two points shall be applied to remaining two cubes and
their acceptability determined.
If cubes fail at 7 days, defective concrete can be dismantled, removed and replaced without awaiting
28 day test results.
If the concrete tests fail to meet the acceptance strength required for respective grades of concrete,
the Project Manager/Client may take one of the following actions:
Instruct Contractor to carry out such additional tests (e.g. Core tests, load tests, ultrasound, etc.)
and/or remedial measures to ensure the soundness of the structure at the Contractor’s expense
The work will be rejected and any consequential action as needed shall be taken at the Contractor’s
expense, including cutting out and replacing a part or whole of work.
Precast Concrete
Ready Mix Concrete
Reference - IS 4926-1976 or amended
Terminology
Ready Mixed Concrete - Concrete delivered at site or into the purchaser's vehicle in a plastic
condition and requiring no further treatment before being placed in the position in which it is to
set and harden. All provisions for good workmanship, quality control and treatment, as stated in
previous clauses shall be applicable.
Agitation - The process of continuing the mixing of concrete at a reduced speed during
transportation to prevent segregation.
Agitator - Truck mounted equipment designed to agitate concrete during transportation to the
site of delivery.
Truck mixer - A mixer generally mounted on a self-propelled chassis capable of mixing the
ingredients of concrete and of agitating the mixed concrete during transportation.
Basis of Supply
The ready mixed concrete shall be manufactured and supplied on the following basis. Specified strength
based on 28-day compressive strength of 15-cm cubes tested in accordance with IS: 456
When the concrete is manufactured and supplied on the basis of specified strength, the responsibility for
the design of mix shall be that of the manufacturer.
General Requirement
In addition to the requirements specified in this standard and subject to such modifications as
may be agreed to between the purchaser and the manufacturer at the time of placing order, the
ready-mixed concrete shall generally comply with the requirements of IS: 456
The minimum quantity of cement and the details regarding proportioning and works control shall
be as per Clauses above.
When a truck mixer or agitator is used for mixing a transportation of concrete, no water from the
truck-water system or from elsewhere shall be added after the initial introduction of the mixing
water for the batch, except when on arrival at the site of the work, the slump of the concrete is
less than that specified; such additional water to bring the slump within required limits shall be
injected into the mixer under such pressure and direction of floor that the requirements for
uniformity specified in Appendix A are met.
Unless otherwise agreed to between the purchaser and the supplier, when a truck mixer of
agitator is used for transporting concrete, the concrete shall be delivered to the site of the work
and discharge shall be complete within 1.5 hours (when the prevailing atmospheric temperature
is above 20°C) and within 2 hours (when the prevailing atmospheric temperature is at or below
20°C) of adding the mixing water to the dry mix of cement and aggregate or of adding the
cement to the aggregate, whichever is earlier.
The concrete quality shall meet all requirements and Specifications of concrete as stated hereof. Contractor shall
be allowed to use own Batching Plant or procure concrete, but Quality Tests will be the responsibility of the
Contractor and off-site Batching Plants shall be open for inspection to the Project Manager/Client throughout the
Project.
Admixtures
General
Admixtures may be used in concrete only with the approval of Consultant / Project Manager/Client based
upon evidence that, with the passage of time, neither the compressive strength not its durability get
reduced. Calcium chloride shall not be used for accelerating set of the cement for any concrete
Retarding Admixtures
Where specified and approved by Consultants / Project Manager/Client retarding agents shall be added to
the concrete mix in quantities specified by Consultants / Project Manager/Client.
Measurement
Formwork and reinforcement shall be paid separately. Volume of concrete measured shall include that
occupied by:
The price of concrete shall include all labour, material, equipment, mixing, pumping, gangways, tools,
transporting, hoisting to any height and lowering to any depth, pouring or laying, consolidating, leaving
pockets, holes, disconnecting them till the next operation or completion of work, hacking the surface, to
provide key for providing further work including cleaning wetting surfaces, etc preparing construction
joints as described, and all other activities required as per good construction practice.
Unit rates shall allow for chamfers, grooves, lines etc. in reinforced concrete members as well as
necessary slope, drops, drip models etc.
Minimum cement content per cubic meter of cement concrete has been specified in each item of cement
concrete work; however, if cement is required to be used so as to obtain the minimum strength specified
for the grade of cement concrete, the Contractor will not be paid for extra cement used.
The supply, maintenance and removal of all temporary rungs, and ramping as necessary on the
site
Placing of concrete will be pumps only or as approved by the Project Manager/Client.
All finishes and to the concrete work as shown or specified.
Allowed for the removal of constructions encountered.
The excavation and concrete construction of all sump pits, manholes, drains under slabs, etc as
described in the specifications and shown on the drawings.
Formwork, reinforcing, embedded items and layout for concrete tank cradles.
All roof mechanical and other building services equipment pads and kerbs at the HVAC and
Electrical openings, concrete including dowels, formwork and roughing of concrete
All fire grading and removal of standing water before the placing of concrete.
Included for all below slab, surface water and drainage, including brickfill, within the Tender.
Points and in steel below slabs lightening protection systems as detailed. The Contractor, in the
preparation of his Tender, is to allow for watertight construction.
Allow for keeping the works clear and tidy at all times and for the removal of debris arising from
the works, and to be disposed off at locations designated by the Project Manager/Client, and
frequent removed off the site. Any surplus concrete deposited at the workfront of on the site
(concrete droppings) must be removed by the Contractor at its own expense.
Provisions, hoisting, distribution and fixing of all embedded items required.
Leaving all necessary holes and pockets for steel work beams for lifts and for making good after
installation by other Contractors. Casting in all slots and inserts for fixings to guides and runners
to lift shafts.
All trench drain box-cut with necessary recesses and casting in all anchor bolts and providing and
installing trench drains and other embedded items as shown on the drawings.
Include design mix weight and storage box for samples and test cylinders.
Levelling of the floors to proper elevations as shown on the drawings to the tolerances and
cambers and slopes specified including all changes of slab elevation.
All means of transportation of concrete.
Providing and casting into concrete slots to receive masonry or blockwork ties to support all such
walls as shown on the drawings or as directed by the Project Manager/Client.
Forming holes to riser ducts.
Forming necessary cutouts at pipe locations to accommodate electrical, plumbing, sprinkler and
electrical services.
Forming in the concrete members chases for any asphalt "track-in" and/or flashing and the like.
Provide grout for lift saddle and floor closures prior to setting (setting by others).
Grout pumps and other mechanical equipment as required.
3 Reinforcement
3.1 Related Works
A. Concrete Formwork
B. Cast in-situ Concrete
Steel Grades
Reinforcements for concrete from “grade” of steel indicated below, conforming to the relevant Indian
Standard and their latest amendments mentioned:
BIS Certification
Material received at the Site shall have BIS Certification mark. Such bundle or coil containing the bars
shall be suitably marked with BIS Certification mark. Bars shall also be marked to identify categories. This
shall be done as per IS: 1387.
In case bars are without BIS Certification mark, the manufacturer shall give a certificate stating the
process of manufacture, chemical composition and mechanical properties. Each certificate shall indicate
the number or identification mark of the cart to which it applies, corresponding to the number or
identification mark to be found on the material.
Each batch of steel brought to the Site shall be tested prior to use. Cost of all tests shall be borne by the
Contractor.
Material acceptable as per IS Specifications will be allowed into the Project. All rejected material shall be
removed from the Site by the Contractor within 30 days of its rejection. If the same is not done, the
Project Manager/Client can get work done by third party at the Contractor’s risk and cost shall impose a
penalty of Rs 500 (Rupees Five Hundred only) per metric ton per day. This will be without any appeal and
shall not be subjected to arbitration.
Storage
Reinforcement bars received at the Site shall be stored on hard, concreted platform and clear of the
ground to a minimum of 200 mm with the use of timber sleepers or any other means. Reinforcements
shall be kept covered by tarpaulins or plastic to avoid excessive corrosion or any other contamination. It
is advised to follow storage methods as described in IS: 4082.
Reinforcement steel shall be stored in such a manner as to avoid distortion and to prevent deterioration
and corrosion. Prior to assembly of reinforcement on no account any oily substance shall be used for
removing the rust.
Quality Assurance
a. Supervisory staff shall have qualification and experience in the above field.
b. Welders qualified and having approved certificates for welding shall be employed.
Handling
a. Bend test requirements shall conform to the following and shall be based on 1800 bends of full
size bars around pins.
Bar diameter (mm) Pin diameter for test bend
10, 12,16 3.5 x bar dia
20, 22, 25 5.0 x bar dia
28, 30, 32 7.0 x bar dia
b. Spacers shall be of any of the following:
i. Wire
ii. Precast concrete
iii. Moulded plastic
Spacer material shall be of durable quality and shall not lead to corrosion of reinforcement or
spilling of concrete. Precast concrete spacers shall be of the same mix as that of surrounding
concrete.
c. Tying wire shall be of 18 G black annealed mild steel wire or other approved type double fold to
tie the reinforcements confirming to is 280.
Unit Weights: Unit weights payable per meter shall be as per IS:456
Execution
Cutting and Bending
a. Flame cut and hot bending is absolutely forbidden.
b. Cut and bend reinforcement to approved shop drawings and details shall be used.
c. Bars to be cold-bend, either mechanically or by hand, but to correct radius using proper tools,
machine and platform and confirming to IS 2502-
d. Do not rebend without approval. In case of re bending, care shall be taken that the rating of
bend is not less than 4 x bar dia at construction joints for plain steel bars and 6 x bar dia for high
strength bars.
e. Reinforcement projecting from concrete shall not be bent without approval.
Bar bending schedule to be submitted for approval of the Structural Consultant to the Project
Manager/Client prior to commencement of any cutting, bending and binding of steel at site.
f. Cracked end of bars shall not be used on this Project.
g. Bars should be inspected for visible defects such as cracks, brittleness, excessive rust, loose mills
scale, etc.
Welding
a. Do not weld reinforcement unless authorized by the Consultants / Project Manager/Client and
recommended by the manufacturers.
b. Site welding shall be done with suitable safeguards and techniques.
c. Welding, if approved, may be used for:
i. Lapping reinforcement in position
ii. Fixing reinforcement to other steel members.
d. The length of run deposited in a single pass shall not exceed 5 x bar diameters. If a longer welded
length is required divide into sections with the space between runs not less than 5 x bar
diameters.
e. Welded joints:
i. Shall not be made at bends in reinforcement.
ii. Stagger joints in parallel bars of principal reinforcement unless otherwise approved.
iii. The distance between staggered joints shall not be less than the end anchorage length joints.
Mechanical Splicing
a. To comply with ISI 456-. ACI 318- and ACI 439-3R-83
Inspection
a. Ensure that the reinforcement placing is checked by Project Manager/Client.
b. Ensure that the Formwork to receive the reinforcement is clean and free from debris.
c. Cracked end of bars to be cut out.
Anchoring
Anchoring of bars and stirrups shall be provided exactly as detailed in the structural drawings or as
directed by Project Manager/Client/Structural Consultant.
In case of reinforcement steel in tension, deformed bars may be used without end anchorage provided
the development length requirement is satisfied. Hocks shall normally be provided for plain bars in
tension. Development length of the bars shall be determined as per relevant clauses of IS: 456 -
The anchorage length of straight bar in compression shall be equal to the Development length of the bars
in compression as specified in relevant clause of IS: 456 -
Lapping of Bars
Laps shall be strictly as per the structural drawing or as directed by the Project Manager/Client/Structural
Consultant. For general guidance the following principles shall be followed as given in IS: 456 -
Securing Reinforcement
a. Adequately secure with tying wire or approved steel clips.
b. Bend the tying wires well back clear of forms.
Concrete Cover
a. Shall be in accordance with ISI: 456- and as per the instructions in structural drawings.
Precautionary Measures
a. Do not insert bars into placed concrete.
b. Do not damage forms and form linings, if any when fixing reinforcement.
Measurements
Reinforcement shall be measured as follows:
Length of different diameters of bars actually used including laps shall be measured nearest to a
centimeter and their weights calculated as shown on the drawings or as instructed by the
Structural Consultant
Weights per meter shall be as mentioned
Rolling margin to be considered in quoted rates.
The Contractor shall account for all these in its quoted rate.
Rate build-up shall include, in addition to cost of material (ie will not be measured and paid for
separately):
- PVC Cover blocks of required thickness for keeping reinforcement bars in position
- Unauthorized overlaps (allowed for Contractor’s convenience), spacer bars, chairs and
ties.
- Cutting, bending, placing and fixing in position in any size and shape and placing in
position as per detailed drawings
Approved Makes
Reinforcement bars shall be procured from one of the following manufacturers only unless the
same is approved by Consultants. (Reinforcement bars from other sources will not be approved)
4.0 Formwork
4.1 Related Work
Concrete
Reinforcement
4.5 Formwork
Related Work
Concrete Form Work
Concrete Reinforcement
Cast - in situ Concrete
Formwork shall start only after written approval from the Project Manager/Client & Structural Consultant
has been received. Approval of the proposal in submitted form an acceptance of modification does not
relieve the Contractor of its obligation to achieve its required line finish within accepted tolerance limits in
terms of quality of works completed and safety. Neither will it diminish the Contractor’s responsibility for
the satisfactory performance of formwork.
a) Erected Form work shall be watertight, shall conform to shape, lines, dimensions, verticality, rigid during
placing, vibrating and configuring the concrete
b) Formwork system shall be of 12mm thick water resistant Ply board, and shall be continuous, straight and
without any warping.
c) Design of formwork shall take into account:
Height of pour
Thickness of member
Rate of pour
Concrete slump
Texture of finish
Placing temperature
Concrete density
Construction joints
Wind load
Method of Discharge
d) Form work design shall have
Dimensional tolerance
De mountable without shock, disturbance or damage to concrete
e) All construction joints in beams and slabs shall be provided as shown in drawings.
f) Ties shall be provided where required
g) Cambers shall be provided where shown.
h) Props / supports of extra ceiling height shall be specially designed.
g) Form coating compound that will not bond with, stain, not adversely effect concrete for required
bond or adhesion not hamper the wetting of surface to be covered with water or curing compound.
h) Shuttering scheme for retaining wall, shear walls etc shall be of Doka or equivalent.
All propping and centering shall be of adjustable steel supports (built-up sections of rolled steel) and
tubular props to full height without joints, and with sufficient bracing to take into account the
construction loads, namely full load of concrete with any live load and impact load likely to occur during
concreting.
4.9 Workmanship
Formwork shall be classified based on the ultimate finishes required of the concrete surface as:
Textured or decorative finish
Fair-faced finish
Rough finish
The Contractor shall account for all material and labour to achieve the above finishes to the satisfaction of
the Project Manager/Client in his quoted price.
Joints of formwork shall be watertight. It is easy to check from the bottom and make sure no light
is visible
Props shall be on solid base, plumbed, in straight line, braced horizontally and cross
Tie-bars, bracing and spacers in beams, walls and columns shall be at correct place/location and
fully tight
Wedges shall be fully secured and nailed with heads left out for easy removal
All saw dust, dirt, shavings and any other unwanted material shall be cleaned and hosed out
Provision shall be made for watching formwork while concreting and any other platform needed
for movement of workers without any disturbance to the reinforcement
Provision is made for traffic on formwork: not to bear directly on reinforcing steel.
Number of reuses shall be decided by the Project Manager/Client on examining the condition of
formwork after each use. If during concreting any weakness develops or formwork shows any
distress, the work shall be stopped and remedial action taken.
4.11 Measurements
Formwork shall be measured as the area (in square meters) of shuttering in contact with the concrete
including covers, angles, splays, mitres, bevels, etc. for which no special rate shall be allowed.
It shall be measured to the nearest centimeter and the area worked out correct to two decimal
places
No deduction shall be made for openings up to 0.4 square meter in plan
Area of voids shall be deducted from the face area of shuttering.
No deductions shall be made from formwork of main beams where a secondary beam intersects
it. Formwork for secondary beams shall be measured up to sides of the main beams.
No deduction shall be made from the formwork to column casings at intersection of beams.
Lapping of formwork with previously laid out concrete will not be measured and will not be paid
for.
The quoted rate shall be applicable for all working conditions and at all heights and depths or lifts
specified in the drawings. The rate shall include the cost of materials and labour for various
operations involved including, but not limited to the following:
Provision of formwork, its erection and treatment of the concrete surface immediately after
removal of the formwork
Holes to be made in the formwork for inserting electrical conduits, piping for plumbing works, etc
Centering, bracing, tightening with bolts and nuts, staging, etc.
Splayed edges, notchings, allowance for overlaps, centering, shuttering, strutting, bolting, nailing,
welding, casing striking and removal.
Filling to form stop chamfered edges or splayed external angles to footings, beams, columns and
the like.
Temporary openings in the forms for pouring concrete and removing rubbish.
Dressing with oil/approved emulsion to prevent adhesion of concrete with shuttering.
Raking or cutting.
Fixing inserts and openings at the correct line and level and at any stage to support the same at
the directed height and place.
Platforms if any to check forms while concreting is in progress.
Filling and making joints watertight to the satisfaction of the Project Manager/Client.
Cleaning of the shuttering.
Cleaning the complete floor immediately on deshuttering complete to enable the start of next
activity.
Cleaning and washing of the complete floor during and after concreting to avoid any damage to
finished surface. It will be responsibility of the Contractor to protect and retain all finished
surfaces.
Should there be any laitance due to concreting of upper floors or other construction activities within the
said floor the Contractor shall be responsible to do all that is required to bring the finish back to the
original or as specified in the Technical Specification/ directed by the Project Manager/Client.
4.12 Tolerances
Tolerance is a specified permissible variation from lines, grades or dimensions given in drawings. No
tolerances are specified for horizontal or vertical encroachments beyond the legal boundaries. Unless
otherwise specified, tolerances given in the following sections shall be permitted.
In the lines and surface of columns, walls, and other vertical members, viz inside face of lift shaft, etc.
3 mm per 3.0 meter but not exceeding 10mm for the full height of the building.
For exposed corner column and other conspicuous lines
In any bay up to 5 m maximum 3 mm
In 10 m or more bays 5 mm
Soffits of slabs, ceilings and beams
2.5 m bays 3 mm
5.0 m bays 3 mm
10.0 m or more 10 mm
Lintels, sills, parapets, grooves and other conspicuous lines
In any bay up to 5 m maximum 3 mm
In 10 m or more 5 mm
Variation of the linear building lines from established positions in plan and related position of
columns, wall and partitions
In bay up to 5 m maximum 5 mm
In 10 m or more 10 mm
Variation in sizes and location of sleeves, opening in walls and floors to be 5 mm (except for anchor
bolts)
Variation in cross-sectional dimension of columns and beams and thickness of slabs and walls -5 mm,
+10 mm
Variation in steps
In a flight of stairs Risers Treads
Formwork shall be removed carefully without jarring the concrete and curing of the concrete shall
commence immediately. Sudden shocks / vibrations during removal of wedges shall be avoided.
Where finished edges have re-entrant angles, remove formwork as early as possible to avoid
shrinkage cracks.
Concrete surfaces to be exposed shall where required by the Project Manager/Client, be rubbed
with carborandum stone to give a smooth and even finish.
Where concrete requires plastering or other finish later, the concrete surface shall be hacked as
directed.
No extra charge will be allowed to the Contractor for such work.
The surface of the forms to be in contact with the concrete shall be coated with a reliable coating that will
effectively prevent the adherence of concrete and will not stain the concrete surfaces. After each use, the
surfaces of forms which have been in contact with concrete shall be cleaned of mortar and any other
material sticking to them, then well wetted and treated with form oil approved by the Project
Manager/Client.
The Contractor shall provide commercial form release agent that will not bond with, stain or adversely
affect concrete surfaces and will not impair subsequent treatment of concrete surfaces.
5. Structural Steel
General
Description
Extent and Intent
The Contractor shall furnish all materials, labour operation, equipment, tools and plant and incidentals
necessary and required for the completion of all metal work in connection items of metal work as called
for in the drawings. The drawings and specifications cover the major requirements only. The supplying of
additional fastenings, accessory features and other items not mentioned specifically herein but which are
necessary to make a complete installation shall be a part of the Contract. Works Include anchorages in
cast-in-situ concrete.
Related Work
i. Grouting base plates and bearing plates
ii. Metal fabricators
iii. Roofing sheets
Products
Materials
a. Structural steel members.
b. Structural tubing.
c. Bolts, nuts and washers.
d. Welding materials.
e. Primer.
f. Shear studs.
g. Electrodes
All metal materials shall be free from defects impairing strength, durability and appearance and they shall
have structural properties that comply fully with the standards set. All ferrous metal shall be free from
rust, scale and other defects. All non-ferrous metal shall have uniform finished surfaces, machined and
buffed, free from defects. All sections shall conform accurately to sizes and shapes required.
Fabrication
a. Fabricate structural steel members in accordance with IS Specifications 800 Section V and approved
shop drawings.
b. Defective material used shall be replaced by the Contractor.
Finish
Clean, prepare and shop rime structural steel members. Do not prime surfaces to be field welded or
bolted or in contact with concrete.
Execution
a. Erect structural steel in accordance with IS Specifications.
b. Make provision for erection loads and for sufficient temporary bracing to maintain the structure in
proper plumb and in true alignment until completion of erection and installation of permanent
bracing.
c. Do not field cut or alter structural members without approval of Project Manager/Client.
d. After erection, prime welds, abrasions and surfaces not shop primed, except surfaces to be in contact
with concrete.
e. Members shall be cut mechanically by saw or shear or by oxy acetylene flame and not by electric
metal arc.
f. Cut edges shall be ground as per IS 823.
g. Cutting tolerances shall be
Members connected at bolt ends: + or - 1 mm.
Other members: + or - 3 mm.
h. All bolt holes shall be drilled and to the sizes specified in drawings.
Tolerance for spacing between two holes: + or - 1 mm.
Tolerance between two perpendiculars of any oval hole: + or - 1 mm.
Bolt holes for field joints shall be drilled in the shop to the required diameters and tested.
i. Drilling holes for standard sizes if varies can be reamed to next higher sizes. The tolerance for hole
reaming shall not exceed 15% of the total number of holes for one joint.
Welding
Personnel:
a. Welders shall be fully trained, experienced and certified by the recognized welding institutes.
b. Welders’ qualification tests shall be as per ASME SEC IX and approved by Project Manager/Client.
Execution:
a. Welding shall be done in accordance with IS 823.
Approval:
a. Welded parts shall not have any deformations.
b. Welded joints should compensate for Contractions due to welding.
c. Defective welds must be rectified.
d. Weld seams shall correspond to design shapes and dimensions.
e. Weld seams shall not have cracks, fusion, under cuts, rough surfaces, burns, blowholes, and
incomplete penetration.
f. Approval of finished elements, inspections and tests shall be as per Annexure
Bolting
Material
a. Bolts, nuts shall be in accordance with IS 1367 and tested as per IS 1608.
b. Washers shall be as per IS 2016.
Preparation
a. Members shall be assembled for bolting with proper jigs and fixtures to sustain the assemblies
without deformation and bending.
b. All sharp edges, shavings, rust, dirt, etc. shall be removed before assembly.
c. Before assembly the contacting surfaces of the members shall be cleaned and given a coat of primer.
d. Temporarily the assembly shall be done and checked for co-axiality of the holes after which the
assembly shall be finally bolted.
Execution
Bolts shall be fixed after all the defects have been rectified and approved by Project Manager/Client.
Bolts shall be tightened from the centre of joint towards the edge.
Identification
Structural members prior to dispatch for erection shall be marked with weather proof light coloured
paint. The size and thickness of members shall be so chosen as to facilitate easy identification.
Structural members small in size shall be bundled or crated and shall be marked with metal tags for
bundles and painted on crates for identification with particulars of the bundle / crate size, weight,
etc.
Shop - approvals
Pre Assembly
Inspection
a. Contractor to provide facilities for Project Manager/Client to inspect the steel assembly, welding,
bolting, painting etc. at any time during fabrication of members.
b. Project Manager/Client shall have the access to the fabrication shop at all times for satisfying himself
regarding the fabrication of steel items to the drawings and specifications.
c. Shop approval by the Consultants / Project Manager/Client is only mandatory.
d. Contractor to bear all the expenses for testing required by the Consultants / Project Manager/Client
for satisfying regarding the quality of workmanship.
e. Contractor to furnish necessary tools, gauges, instruments, technical and non-technical personnel for
shop tests at his own cost.
Approvals
Intermediate approvals
a. For part of the work that cannot be inspected later.
b. For part of the work that will be difficult to perform inspection and even if done results are not
satisfactory.
Partial approvals
a. To the structural steel members and assemblies before the primer coat is applied.
b. of materials used for fabrication.
c. of test erection.
d. of markings.
e. of fillet joints.
f. of plain surfaces.
g. of special features such as rollers, etc.
Final approval
a. To all elements and assemblies of steel structures after having a shop primer coat and ready for
delivery.
b. Includes partial approval
c. Of shop primer coat.
d. Of mode of loading and transport.
e. Of storage of materials.
Approved Fabricators
All metal work fabricated shall be approved by the Structural Consultant / Project Manager/Client. The
entire work shall be carried out by workmen skilled in this kind of work in a shop fully equipped to carry
out all phases of fabrication in accordance with the best-accepted trade practices.
Painting
c. To verify the quality of material obtained at site and for workmanship to the specifications and
drawings.
d. To verify whether the parts obtained at site is free from defects due to loading, unloading
transportation.
e. To avoid warping of members during unloading by taking sufficient precautionary measures.
f. To store the members as per the symbol and markings and in order of erection.
g. To place the steel members at least 150mm above the platform on wooden or steel locks for
protection against direct contact with ground and to permit drainage of water.
h. To equip for rectification of members like straightening at site and to provide sufficient space for
the same.
i. To see that the parts are clean before erection.
Field Erection
a. To get approvals of foundation, columns, column pedestals or other related structure on which the
structural steel members are to be erected.
b. To get approvals of the members receiving structural steel members regarding their levels,
dimensions, alignments and verticality well in advance.
c. To carry out any minor discrepancies at no additional cost.
d. To get approvals of pockets, bolt locations, levels of base plates before erection.
e. Erection to commence after satisfying the above conditions.
f. Erection to be done in an organised way so that any individual member is not subjected to instability
during the erection time.
g. Precautionary measures to be taken during erection of trusses, purlins and other steel members by
providing proper bracing.
h. Faulty erections done without caring for safety of members and of personal shall be made good at no
additional cost.
i. Contractor is not relieved of his responsibilities, guarantees even after the Project Manager/Client
approves the fabrication, erection, etc., at any stage of work.
j. Contractor is solely responsible for the correctness accuracy and quality of the fabrication, erection
and final approvals to be obtained by the Project Manager/Client.
Measurements
a. Payment of structural steel members including bolts, nuts, washers, gusset plates, etc., will be done
on weight basis.
b. The weight of members will be assessed from the final fabricated and approved drawings and the
respective Bill of Materials prepared by the Contractor and approved the Structural Consultant /
Project Manager/Client.
c. The weight of members shall be as per IS handbook.
d. Sections different than mentioned in IS handbook shall be taken as per manufacturers’ information.
e. No rolling tolerance will be allowed.
f. Built up of members will be paid as per the actual weight of the members.
g. Gusset plates shall be paid to the nearest rectangle enclosing the shape and no deduction shall be
made for any skew cuts.
h. Welds, bolts, anchors, washers, etc will not be measured and paid for separately.
Grouting
a. To level, align and plumb the structural steel work and the base of stanchions by providing steel
shim plates.
b. To align anchor bolts in foundation to the required level, location and orientation by using
templates.
c. To clean the underside of base plates, pockets to receive grout by using compressed air.
d. To use cement mortar 1:2, 1 of cement and 2 of sand, non-shrink grout under base plates.
e. To use grade M 30 concrete to fill up the grout pockets left for fixing anchor bolts.
f. To pour the grout under a sufficient head and tam until the voids are thoroughly filled and the grout
overflows.
Tolerances
a. Steel work for line and level ± 3mm
b. For structural steel for plumb 3.5mm for 10M and not more than 7mm for 30M
c. To follow any tolerance criteria provided on the drawings.
d. To provide tolerances for all structural steel members as per IS code other than what is mentioned
in a, b and c.
ANNEXURE - A
Checking of Sizes At least one Ordinary measuring Should faulty weld be found all
for each Weld instruments (rule, welds shall be checked & all
templates) defects shall be rectified.
Mechanical tests for As per
welding procedure ASME SEC IX
Performance &
electrodes
6.1 INTRODUCTION
Post – tensioning of the slabs /beams be carried out in accordance with Below . – flat holded post –
tensioning system shall be adopted the processing shall consist of stands of 12.7 mm ( 0.5 “) dia and
contained in a flat sheet metal duct. Each strand is anchored by means of a barrel and wedge and
individually stressed by means of a nonstrand jack, which occupies limited space. The pre – stressing force is
transferred to the concrete by a flat anchor plate casting . By use of flat duct the static depth of slab is
more efficiently utilized compared to a round duct for same number of strands.
6.2 Sheathing
The sheathing ducts shall be of the spiral - corrugated type. Unless otherwise specified , the material shall
be Cold Rolled Cold Annealed (CRCA) Mild Steel conforming to IS 513 intended for mechanical treatment
and surface refining but not for quench hardening or tempering. The material shall be bright finished. The
thickness of sheathing shall be shown on the drawing, but shall not be less than 0.3 mm.
The sheathing ducts shall be manufactured at the project site using appropriate machines or in the
factory and dispatched to site as per suitable programme so as to minimize period of site storage. Where
sheathing duct joints are unavoidable, such joints shall be made slurry tight by the use of corrugated
threaded sleeve couplers, which may be lightly screwed onto the outer side of the ducts.
The length of the coupler shall not be less than 150 mm but should be increased up to 200 mm wherever
practicable. The joints between the ends of the coupler and the duct shall be sealed with adhesive
sealing tape to present penetration of cement slurry during concreting. The couplers of adjacent ducts
should be staggered wherever practicable . As far as possible, couplers should not be located in curved
zones.
The finished duct shall be flattered to form an oblong section out of the round pipes by a suitable
machine . The size of the flat duct shall be 70 mm x 26.2 mm for 405 size anchorages (4 nos. of 0.5” strand )
The sheathing duct of round pipes shall be periodically tested as per the recommendations of the SRC 18
– 1995 for acceptance.
All bearing surfaces of the anchorage shall be cleaned prior to concreting and tensioning . Anchor cone
shall be securely positioned and maintained during concreting such that the centerline of the duct passes
axially through the anchorage assembly. The anchorages shall be recessed from the concrete surface by
minimum cover of 100 mm or as per construction drawings which ever is higher.
At the fixed end of tendon, Cona – flat loop anchorage for 405 shall be supplied as per system supplier’s
detail.
Un –tensioned steel reinforcement , and anchorage shall conform to details of pro-stressing system and as
shown on the drawing.
6.4 Strand
12.7 mm ( 0.5”) dia HT strand shall conform to class 2 of IS : 6006. The normal cross – sectional area of
the 7 ply 12.7 mm dia strand shall be 98.7 mm2 with minimum breaking load of 183.7 KN rest certificate
of manufacturer shall be supplied along with each lot dispatched to site.
6.5 Cleaning
Tendon shall be free from loose rust, oil, grease, tar, paint , mud or any other deleterious substance.
6.6 Straightening.
High tensile steel strand shall be supplied in coils of sufficiently larger diameter such that tendon shall
retain their physical properties and shall be straight as it unwinds from the coil. Tendons of any type
that are damaged , kinked or bent shall not be used.
The packing of pre- stressing strand shall be removed fast prior to marking of cable for placement in
ducts. Proper platform shall be provided to facilitate uncoiling of strand without damage to steel. Care shall
be taken to avoid the possibility of the such coming into contact with the ground.
Sheathing shall be placed in correct position and profiles suitable ladders / spacers made from 4 or 5 mm
dia rod may be provided at intervals of approximately 1.0 m. Sheathing shall be tied rigidly with such ladders
/ spacers bars so that they do not get disturbed during concreting. The method of supporting and fixing
shall be such that profile of cables is not disturbed during vibrations, by pressure of wet concrete, by
6. 8 Cutting of strands
Cutting and trimming of strands shall be done by suitable mechanical or flame cutters. When a flame
cutter is used, care shall be taken to ensure that the flame does not come in contact with other stressed
steel. The location of flame cutting of wire or strand shall be kept beyond 100 mm of where the tendon
will be gripped by the anchorage or jacks. The ends of pre-stressing steel projecting beyond the anchorage
shall be cut after the grout has set.
Additional Precautions
It is proposed that the strands are permanently anchored in concrete during casting.
The post tensioning force (actual) must be limited in such a way that accidental breaking of strand is
catered for.
Additional stresses during concreting of upper slab shall be considered to enable no back propping of
second or subsequent lower levels slabs beneath concreting slab.
Approvals:
Design mix of concrete
Approval of strands-Testing to be done by independent agency to confirm codal norms.
Methodology of pre-stressing, construction sequence, minimum and maximum concrete pour
Designs to be submitted to consultants for their approval and perusal much before actual
commencement of works at site.
Designs to be wetted by consultants and if need be modified as per consultants requirements.
Design in soft /hard copy to be submitted to consultants and if required to forward and support to
the local authorities for approval.
A copy of the stress details done at site shall be submitted to consultants for their perusal.
Safety measures at site to be spelled and incorporated in work order.
Co-ordination with consultants, architects, project managers, civil contractor and PMC team is
required at all times.
Local technical representative should be available for any clarifications
Final as built drawings to be submitted to consultant’s incl .soft and hard copies.
The treatment shall be carried out generally in accordance with the stipulation laid down by IS 6313 - Part
II latest edition (Code of practice for anti termite measures in buildings and part II re constructional
chemical treatment measures) subject to the min. Requirement given in this specification.
6.4. Application
The chemical solution shall be prepared by mixing the chemical with the appropriate quantity of water to
obtain a chemical emulsion of the correct concentration as stipulated above. The prepared emulsion shall
be applied as described below.
1.13 Grouts
1.13.1 Grouting
Grouting shall be done in 1:2 cement mortar (one part cement and two parts coarse sand) of
thickness 3’’ (75mm) or less, or as directed. Where the thickness is more than 3’’ (75 mm) thick
grouting shall be done in plain or reinforced cement with coarse aggregate 3/8” and down gauge.
The mix of concrete will be as shown in the relevant drawings as directed.
The base plate shall be temporarily supported on steel wedges and properly aligned before
grouting. Forms shall be built around the base and wet mortar shall be placed under pressure
around and under the base. To ensure that no air pockets are left after grouting additions holes
may have to be cut if directed in the base plate so that pressure grouting can be carried out
thorough these holes also and proper inspection of the grout can be ascertained. The wedges shall
be removed after the grouting has set and recess shall be properly pointed.
Grouting of machine foundations shall be done only after taking the written instructions form the
Consultants / Project Manager/Client.
The grouting work is included in the respective item of concrete and the rate for these items and
inclusive of proper pressure grouting after preparations of surfaces to be grouted, necessary form
work providing and removing necessary wedges, cutting holes in the base plate to ensure that the
air pockets are left etc. No extra rate will be paid for grouting or any work that will be necessary to
carry out and ensure proper grouting entirely to the satisfaction of the Consultants / Project
Manager/Client. If however a concrete mix richer than the foundation is specified for grouting, only
Exposed precast surfaces shall be finished as called for on the drawing or as directed by the Consultants
/ Project Manager/Client. All surfaces coming in contact with in situ concrete shall be wire brushed and
hosed down until the aggregate is free from cement slurry. Castellation shall be provided wherever
called for. Leaving grouting holes, grooves, inserts, projections reinforcements, lifting hooks etc., to
conform to the erection procedure. All edges and delicate projection likely to be damaged during
erection shall be protected by means of wooden cover fillets, until placed in position.
1.15 Waterproofing
Alternatives
1. Cement Based Waterproofing
2. Membrane Type
Execution
Box Method
A. Basement
a First layer shall be laid after cleaning, brushing the PCC layer/ blinding concrete.
b. First coat of waterproof plaster is done with CM 1:3 & approved waterproofing admixture as per
manufacturer’s specification to be used with cement and 20mm size aggregates are embedded
over the surface evenly. Weight of aggregates shall be 20kgs/Sqm.
c. Second layer of waterproof admixture mixed mortar shall be applied a day after the first coat to
the thickness of the aggregate.
d. Grouting shall be done at selected points with cement slurry mixed with waterproof admixture
e. Third layer or finishing coat is done with waterproof admixture mixed cement mortar and surface
is finished smooth. Curing shall be carried out for a minimum period of 7 days.
f. Total thickness of water proofing layers shall be not less than 50mm.
B. Retaining Wall
a. Shall be done in two layers of waterproof plastering leaving 2 hours gap between each coat.
b. Total thickness shall not exceed 35mm or 1.5” thick.
c. Water proof admixture to be used as per manufacturer’s specification with CM 1:3.
d. Grouting wherever necessary and at construction joints shall be carried out.
e. Curing shall be done till 7 days.
f. Back filling shall be done carefully with specified material. Care to take not to puncture the layer.
C. Roof
Surface Method
Part - 1
Part - 2
a. RCC surface to be cleaned brushed and watered.
b. Cement slurry with waterproof compound shall be provided over the cleaned surface.
c. Brick coba shall be laid for necessary gradient for easy flow of rain- water (joints shall be
filled with CM 1:1 with water proof compound)
or
d. Metal coba shall be laid for specified thickness and necessary gradient for easy flow of rain-
water with CM 1:1 with waterproof compound
e. Coba to be covered with joint less water proof plaster with CM 1:2 with water proof
compound as per manufacturer’s specification finish shall be smooth.
f. Impression markings of 300mm x 300mm square to be done with 3mm rod.
g. Parapet to be treated for a height of 600mm in shape of round water.
h. Curing shall be carried for 7 days.
QUALITY ASSURANCE
Manufacturer:
Provide products of manufacturers with not less than 10 years of successful experience in supplying
the principal materials for the required work.
The manufacturer shall preferable holder of the ISO 9001:2000 quality certificate with a validity
period of at least two years.
Installation Company:
Before starting the installation the contractor shall deliver a certificate, recognizing the installation
company as an approved applicator.
Before awarding the works, the contractor must present all necessary certificates that allow the
company to perform waterproofing works.
SUBMITTALS
Product Data:
Prior to delivering any waterproofing material the contractor shall submit two copies of specifications,
installation instructions and general recommendations by the manufacturer of waterproofing materials.
Sample Installations:
Construct sample installations of waterproofing before proceeding with the work. Size of samples shall
be adequate to represent completed work and be retained for the duration of the waterproofing work
as minimum standards.
QA/QC-procedure
All parties concerned will check materials prior to installation.
The QA/QC-procedure of the manufacturer is implemented and where necessary adapted to the
requirements of the project.
During the works a QA/QC engineer of the manufacturer will control the works and carry out
inspections.
All materials need to be certified compatible by the manufacturer.
All materials are delivered with a certificate of origin.
All related waterproofing materials need to be delivered by the same manufacturer.
The applicator needs to provide the proof of its certification by the manufacturer.
Completion
The contractor shall deliver a clean site and wastage will be dumped at an authorized location.
At the delivery of the works, the owner will receive an original and signed 10 year, insurance-
backed warranty for waterproofing and root resistance
A final quality inspection will take place and hand-over documents signed by all responsible parties
Primer:
Bituminous, solvent based primer, modified with elastomers.
The primer will be used at all vertical areas and details.
Specific gravity : +/- 0,95 kg/l (at 20 C)
Kinematic viscosity : 46 mm²/s (at 40°C)
Drying time : 3 to 5 hours (depending on weather conditions)
The technical properties of the membrane shall have or exceed the following characteristics:
INSTALLATION
Preparation
Ground water level needs to be kept under raft concrete level by the contractor.
The raft/lean concrete surface has to be free of standing water, debris and mud.
All rough construction-joints or other rough particles need to be made smooth.
All honeycomb-areas of the concrete wall must be repaired according to specification.
Tie-rod holes need to be filled according to specification.
All formwork and nails need to be removed.
Details
The details of the waterproofing comprises of material specifications, installation procedures.
Waterproofing of details is in conformity with the instructions and detail drawings issued
Application
The works need to be done according to the rules of good craftsmanship.
The vertical areas of beam, pile-cap and wall, receive the primer.
The primer must be dry before waterproofing application can start.
The membrane is either loose laid on the raft/lean concrete. Only the prefabricated overlaps are
torched or fully torched and bonded
The membrane is torched fully bonded to all vertical areas of beams and pile-caps.
Side-overlaps have a width of 100mm.
The overlap of the head joint is 150mm. Head-overlaps cannot be next to each other.
If required, a protection screed neds be applied on top of the membrane.
Primer:
Bituminous, solvent based primer, modified with elastomers.
The primer will be used at all vertical areas and details.
Specific gravity : +/- 0,95 kg/l (at 20 C)
Kinematic viscosity : 46 mm²/s (at 40°C)
Drying time : 3 to 5 hours (depending on weather conditions)
The technical properties of the membrane shall have or exceed the following characteristics:
Warranty
The roof waterproofing is covered by an international, insurance backed warranty, issued to the
owner.
The warranty certificate has to mention the insurance policy number and project data.
The warranty covers product defaults and includes the following elements:
o Removal of the default waterproofing.
o Hiring of necessary labour to perform the reparation
o Hiring of necessary equipment to perform the works (e.g.: scaffolding)
o New product installation
The approved applicator issues an installation warranty.
Warranty period is Ten (10) years.
INSTALLATION
Preparation
The roof needs a minimum slope of 1%. The slope is achieved prior to the waterproofing works. In
case of a screed to fall, the minimum thickness of the screed must be 25mm.
Verify that the roof surface is clean, dry, smooth and free of oil and grease.
Treat honeycomb areas prior to the start of the waterproofing works.
All complementary items like roof drains, pipes, ducts and vents are solidly set.
Primer
Apply primer at a rate of 300 g/m².
Allow the primer to dry for at least 4 hours.
Add an additional layer of primer if first layer got stained.
Application
The works need to be done according to the rules of good craftsmanship.
Inclusion of humidity must at all times be avoided.
The roof receives the primer and is allowed to dry.
The membrane is torched fully bonded to the concrete roof slab.
Overlaps will follow the slope of the roof to prevent water stagnation.
Side-overlaps have a width of min 70mm.
Head-overlaps cannot be next to each other. The overlap of the head joint is 100mm.
Primer
Bituminous, solvent based primer, modified with elastomers.
Specific gravity : +/- 0,95 kg/l (at 20 C)
Kinematic viscosity : 46 mm²/s (at 40°C)
Drying time : 3 to 5 hours (depending on weather conditions)
F TECHNICAL SPECIFICATIONS
Packing Details
Roll Length Nominal m 25
Roll Diameter Nominal m 0.850
H. Application
Preparation
The planter area needs a minimum slope of 1%. The slope is achieved prior to the
waterproofing works. In case of a screed to fall, the minimum thickness of the screed must
be 25mm.
Verify that the concrete surface is clean, dry, smooth and free of oil and grease.
Treat honeycomb areas prior to the start of the waterproofing works.
All complementary items like floor drains and scupper drains are solidly set.
Primer
Apply primer at a rate of 300 g/m².
Allow the primer to dry for at least 4 hours.
Add an additional layer of primer if first layer got stained.
Waterproofing
The works need to be done according to the rules of good craftsmanship.
Inclusion of humidity must at all times be avoided.
The concrete receives the primer and is allowed to dry.
The membrane is torched fully bonded to the concrete roof slab.
Side-overlaps shall be min 70mm. Head overlaps are 100mm
Head joints cannot be next to each other.
I. Completion
The contractor shall deliver a clean site and wastage will be dumped at an authorized
location.
At the delivery of the works, the owner will receive an original and signed 10 year,
insurance-backed warranty for waterproofing and root resistance.
Optional Method
RCC surface to be cleaned, brushed and watered. Water stagnation test shall be done for terrace slabs.
RCC surface shall be Coated with compatible Multiplas primer / Cold sticker / Multiplas blown bitumen
of grade 85/25 or 90/15. Waterproofing treatment with polymeric standard waterproofing membrane
of 4kg/Sqm or 4mm thick (Multiplas standard) shall be provided as per the manufacturer's specification
approved by Clients with an overlap of 10cms.Then membrane shall be bound by torch application with
Option - 2
Expansion joints shall be provided with 20 gauge copper strips/m.s. hot dip galvanized strips of 250
mm width at locations shown on drawings or as approved by Consultants / Project Manager/Client.
The strips shall be bent to the shape indicated on the drawing and embedded properly in masonry.
The joint width shall be uniform throughout and special care shall be taken to ensure proper bonding
at expansion joints. Expansion joints shall be continuous and where two or more strips meet, they
shall be lapped to the extent of 75 mm and joints properly soldered. The expansion joints shall be
filled with pre moulded joint fillers and sealed with mastic compound. For purposes of measurement,
the laps provided will be neglected. Wherever an expansion joint between the existing part and new
part is proposed the rate quoted shall be inclusive of making necessary connections with existing
part.
1.15.6.4 Flashings
Metal or tar felt flashing shall be fixed as directed by the Consultants / Project Manager/Client. Metal
flashing where provided shall be welded/ soldered to obtain continuity. Tar felt flashing shall be
lapped for a minimum length of 150 mm. Flashing shall be measured and paid for in linear meters for
the specified width disregarding laps or joints.
1.15.7.1 Material
Chloroprene shall only be used in the manufacture of bearing.
Grades of raw elastomer of proven use in elastomeric bearings, with low crystallization rates and
adequate shelf life (e.g. Neoprene, WRT, Bayprene 110 or equivalent) shall be used. No reclaimed
rubber or vulcanized wastes shall be used.
The raw elastomer content of the compound shall not be lower than 60%. The ash content shall not
exceed 5% (as per test conducted in accordance with ASTM D-297)
Properties of Elastomer
The elastomer shall conform to all properties specified in the following table.
Sl Property Unit Test method I.S Value of the
No specification reference characteristic
specified.
Duration Temperature
(h) (C)
C.R. (+0 to 100 ± 1 35
24-2)
3.0 Maximum compression set IS : 3400 (Part IV)
%
C.R. (70) 100 ± 1
3.1 Maximum change in hardness
IRHD + 15
Shear modules of the elastomer bearing shall not be less than 0.8Mpa nor greater than 1.20Mpa.
The adhesive strength of elastomer to steel plates (determined as per IS 3400: Part XIV method A)
shall not be less than 7 kN/m
1.15.7.3 Fabrication
o Bearing with steel laminates shall be cast as a single unit in a mould and vulcanized under heat
and pressure. Casting of elements in separate units and subsequent bonding is not permitted
nor shall cutting from large size cast be permitted.
o Bearings of similar size shall be produced by identical process and in one lot as for as practicable.
o The moulds used shall have standard surface finish adequate to produce bearings free from any
surface blemishes.
o Steel plates for laminates shall be sand blasted, clean of all mill scales and shall be free from all
contaminates prior to bonding by vulcanization. Rusted plates with pitting shall not be used. All
edges of plates shall be rounded.
o Spacers used in mould to ensure cover and location of laminates shall be of minimum size and
number practicable. Any hole at surface or in edge cover shall be filled in subsequently.
o Care shall be taken to ensure uniform vulcanizing conditions and homogeneity of elostomer
through the surface and body of the bearing.
Sl No Items Tolerances
1. Overall plan dimensions -0, +6mm
2. Total bearing thickness -0, +5%
3. Parallelism
a. Of top surface of bearing with respect to the 1 in 200
bottom surface as datum.
b. Of one side surface with respect o the other as 1 in 100
datum
4. a. Thickness of individual internal layer of ± 20% (max of 2 mm)
elastomer
b. Thickness of individual outer layer - 0, + 1mm
5. a. Plan dimensions of laminates -3mm, +0
b. Thickness of laminate ± 10%
c. Parallelism of laminate with respect to bearing 1 to 100
base as datum
The vulcanizing equipment press should be such that between the platens of the press the pressure
and temperature are uniform and capable of being maintained at constant values as required for
effecting an uniform vulcanization of the bearing.
The moulding dies utilized for manufacturing the bearings should be so set inside the platen of the
press so that the pressure development during vulcanization of the product is evenly distributed and
the thickness maintained at all places is within acceptable tolerance limits taking into consideration,
the shrinkage allowance of vulcanization.
The raw compound which has been introduced inside the metal dies for vulcanization should be
accurately weighed each time and it must be ensured that sufficient quantity has been put inside the
die for proper flow of material at every place so that a homogeneous and compact bearing is
produced without any sign of sponginess or deficiency of material at any place.
Before any vulcanization of any batch of production is used for producing vulcanized bearings, test
pieces in the form of standard slab and buttons should be prepared in accordance with prescribed
standards and salient properties tested and recorded regularly against each batch of production to
monitor the quality of the products.
Classification
Bricks shall be classified on the basis of their minimum compressive strength as given below:
Class designation Average compressive strength
Not less than Less than
N/mm2 (Kgf/cm2) N/mm2 (Kgf/cm2)
7.5(75) 7.5 (75) 10 100
The brick shall have smooth rectangular faces with sharp corner and shall be uniform in colour and emit clear
ringing sound when stuck.
Water Absorption:
The average water absorption of bricks when tested in accordance with the procedure laid down shall not be more
than 20% by weight.
Soaking of Bricks:
Bricks shall be soaked in water before use for a period for the water to just penetrate the whole depth of the
bricks. Alternatively bricks may be adequately soaked in stacks by profusely spraying with clean water at regular
intervals for a period not less than six hours. When the brick are soaked they shall be removed from the tank
sufficiently early so that at the time of laying they are skin-dry. Such soaked bricks shall be stacked on a clean place
where they are not again spolled by dirt earth etc.
Laying:
Bricks shall be laid in English bond unless otherwise specified for brickwork in half brick wall, brick shall be laid in
stretcher bond. Half or cut bricks shall not be used except as closer where necessary to complete the bond .Closer
in such cases shall be cut to required size and used near the ends of the wall .Header bond shall be used
preferably in all courses in all courses
Bricks shall be laid with frog (where provided) up. However, when top course is exposed, bricks shall be laid with
frog down. For the bricks to be laid with frog down, the frog shall be filled with mortar before placing the brick in
position.
Finishing of Joints:
The face of brick work may be finished flush or by pointing. In flush finishing either the face joints of the mortar
shall be worked out while still green to give a finished surface flush with the face of the brick work or the joints
shall be squarely raked out to a depth of 1 cm while the mortar is still green for subsequently plastering. The faces
of brick work shall be cleaned with wire brush so as to remove any splashes of mortar during the course of raising
the brick work. In pointing, the joints shall be squarely raked out to a depth of 1.5 cm while the mortar is still green
and raked joints shall be brushed to remove dust and loose particles and well wetted, and shall be later refilled
with mortar to give ruled finish. Some such finishes are ‘flush’, ‘weathered’, ruled, etc.
Curing
The brick work shall be constantly kept moist on all faces for a minimum period of seven days. Brick work done
during the day shall be suitably marked indicating the date on which the work is done so as to keep a watch on the
curing period.
Scaffolding
Scaffolding shall be strong to withstand all dead, live and impact loads which are likely to come on them.
Scaffolding shall be provided to allow easy approach to every part of the work.
Single Scaffolding:
Where plastering, pointing or any other finishing has been indicated for brick work, single scaffolding may be
provided, unless otherwise specified. In single scaffolding, one end of the put-logs/pole shall rest in the hole
provided in the header course of brick masonry. Not more than one header for each put-log/pole shall be left out.
Such holes shall not be allowed in the case of pillars, brick work less than one metre in length between the
openings or near the skew backs of arches or immediately under or near the structural member supported by the
walls. The holes for putlogs/poles shall be made good with brick work and wall finishing as specified.
Double Scaffolding:
Where the brick work or tile work is to be exposed and not to be finished with plastering etc. double scaffolding
having two independent supports, clear of the work, shall be provided.
Measurements
Brick work shall be measured in cubic metres unless otherwise specified. Any extra work over the specified
dimensions shall be ignored. Brick work shall be measured separately in the following stages:
(a) From foundation to Plinth level
(b) Plinth (floor one) level to floor two level
Note : (i) Brick work in parapet walls, mumty, lift machine room and water tanks constructed on the roof upto 1.2
m height above roof shall be measured together with the corresponding work of the floor next below.
7.1. SCOPE
This specification covers the general requirements for the materials and construction of soling, water bound
macadam course and bituminous surface treatment of roads.
Soling Stone
It shall be clean, sound, dense, hard, tough, durable stone of uniform quality free from unsound material cracks,
decay and weathering. Water absorption shall not be more than 5 percent. The stone shall be in the smallest
dimension equal to thickness of the soling course specified with a tolerance of 25 mm. Soling stone shall be
sufficiently flat bedded. The height of the soling stone shall be equal to the specified thickness of soling. The
length and breadth shall not exceed twice the specified thickness. Contractor to note that available laterite stone
of specified strength at site shall be used as sling material in co-ordination with Project Manager
Stone Aggregate/Metal
Coarse aggregate, stone chippings shall consist of natural or crushed stone, clean, hard tough, durable and free
from excess of flat, elongated, soft and disintegrated particles, dirt, salt, alkali, vegetable matter, adherent
coatings, organic and other objectionable matter, and shall conform to the physical requirements given in Tables 1
or 2 hereunder, as applicable. Aggregate for bituminous wearing courses shall in addition have good hydrophobic
properties i.e. capacity of retaining the film of bituminous material applied to the stone in all weather conditions
and especially in wet conditions. Basalt, dolerites are good in this respect; granite, quartzite are comparatively
poor.
TABLE – 1
PHYSICAL REQUIREMENTS OF COARSE AGGREGATE FOR WATER BOUND MACADAM (SUB BASE / BASE COURSE)
TABLE – 2
PHYSICAL REQUIREMENTS OF AGGREGATES FOR BITUMINOUS WEARING COURSE
TABLE – 3
GRADING REQUIREMENTS OF COARSE AGGREGATES FOR WATER BOUND MACADAM
Grading Size Range Sieve Designation Percent by Weight
no. Passing the sieve
1 90 mm to 45 mm 125 mm 100
90 mm 90 – 100
63 mm 25 – 60
40 mm 0 – 15
22.4 mm 0–5
2 63 mm to 45 mm 40 mm 100
63 mm 90 – 100
53 mm 25 – 60
45 mm 0 – 15
22.4 mm 0–5
3 53 mm to 22.4 mm 63 mm 100
53 mm 95 – 100
45 mm 65 – 90
22.4 mm 0 – 10
11.2 mm 0–5
The use of screening shall be omitted in the case of soft aggregates such as brick metal, kankar, laterites
etc. as they are likely to get crushed to a certain extent under rollers.
Binding Material
Binding material shall comprise of a suitable material, approved by Project Manager, having plasticity
index value of less than 6 as determined in accordance with IS:2720 (part V)
Application of binding material may not be necessary when the screenings used are of crushable type
such as moorum or gravel.
EARTHWORK
9.12.1 Earthwork in Excavation
9.12.2.1 In general the excavation shall be in accordance to specifications mentioned herein “Excavation”
9.4 SOLING
9.14.1 Soling shall not be constructed on a wet sub-grade with available approved Laterite stones at site /
Approved soling material brought from outside.
9.14.2 Unless otherwise specified, the width of the soling shall be 200mm more on either side than that of the
water bound macadam wearing course and the finished thickness of the soling course shall be 200mm.
9.14.3 The soling stones shall be laid with the largest face downwards and in contact with each other. The stones
shall break the joint as far as possible. The height of the soling stone shall be equal to specified thickness
of soling.
9.14.4 As the laying of rubble advances the soling shall be hand packed by wedging and packing with 80 mm
metal in the joints of the soling and driving them by hammer in place so as to fill the voids as completely
as possible. This operation of hand packing shall be laid and had packed true to grade and section and
these shall be often checked by boning rods, template boards and fish line etc. The grades, sections etc.
of the soling shall correspond to those of the surfacing coming on it. The soling thus laid shall be finished
by knocking out projecting stones and filing depressions by chips to come up to the grade and camber.
9.14.5 The quality of the 80mm metal shall be same as specified for the soling and the longest dimension shall
not be more than 100mm and the shortest dimension not less than 50mm.
9.14.6 The soling after it is properly laid and hand packed including filling of voids with 80mm metal shall be
rolled dry with 12T power roller to refusal i.e. till the stones in the soling course cease to move under the
roller and no more compaction can be achieved. Rolling shall start at the edges and work towards the
centre. The roller shall run over the same surface of rolling for at least 8 times still the soling course is
well consolidated. The surface shall be checked by templates and in case of unevenness high spots shall
be knocked our and depressions filled by spalls and re-compacted fully. Bunds shall be laid along the
edges and compacted before starting rolling on soling to prevent spreading of stones.
9.14.7 Gravel shall be spread in thin layers over the above prepared soling surface, swept into the interstices
with brooms, watered lightly to assist the filling of voids. Spreading of gravel, sweeping and watering
shall continue till the interstices are completely filled. At all times only enough water shall be sprinkled to
force the gravel into the voids and never so much as to soften the sub grade. The process of gravel filling
shall be accompanied by rolling as for dry rolling and soling with a power roller weighing not less than 12
tonnes starting at edge and working towards the centre. The roller shall run over the same surface for at
least eight times. Each pass of the roller shall uniformly overlap not less than one third of the track made
9.15.5 W.B.M. Base Course: The coarse aggregate for this shall normally conform to requirements for Base in
Table-1 and its grading shall confirm to Grading 3 of Table 3 and screening to type B of Table 4. The total
consolidated thickness of the base course shall be as specified.
9.15.7 Rolling
9.15.7.1 Following the spreading of the coarse aggregate, rolling shall be started with three wheeled power
rollers of not less than 12 tonne capacity or tandem or vibratory roller of approved type. Rolling
shall begin from the edges and gradually progress towards the centre. First the edges/edge shall
be compacted with roller running forward and backward and then move inwards parallel to the
centre line of the road, in successive passes uniformly lapping preceding tracks by at least one half
The Contractor shall intimate to the Project Manager in writing, well in advance of the start of
work, the job-mix-formula proposed to be used by him for the work and shall give following details
to the Project Manager for his approval.
i. Source and location of all materials
ii. Proportions of all materials expressed as follows where each is applicable:
iii. A single definite percentage passing each sieve for the mixed aggregate.
iv. The results of the best enumerated in Table-6 as obtained by the Contractor.
v. Test results of physical characteristics of aggregates to be used.
Should a change in the source of material be proposed, a new job mix formula shall be established
and got approved from the Project Manager before actual using the materials.
i. Coarse aggregate and screenings conforming to clauses and compacted with heavy hadn
rammer or approved mechanical tempers or
ii. Premix chippings binders (bitumen grade 80/100) content of 3 percent by weight of total mix,
after painting the sides and bottom of the holes with a thin application of bitumen, or a
combination of both as directed by Project Manager. The surface shall be thoroughly swept
and scraped clean and free of dust and other foreign matter.
Provided, however, that the negative tolerance for wearing course shall not be permitted in
conjunction with the positive tolerance for base course if the thickness of the former is thereby
reduced by more than 6mm.
9.18.3 Surface Regularity
The surface regularity of completed subgrade, sub-bases, base course and wearing surfaces in the
longitudinal and transverse directions shall be within the tolerances indicated in Table-7.
The longitudinal profile shall be checked with a 3 meter long straight edge, at the middle of each
traffic lane along a line parallel to the centre line of the road. The transverse profile shall be
checked with a set of three camber boards at intervals of 10 meters.
9.18.4 Rectification
Where the surface irregularity of subgrade and the various courses fall outside the specified
tolerances, the Contractor shall be liable to rectify these in the manner described below and to the
satisfaction of the Project Manager.
i. Subgrade
Where the surface is high, it shall be trimmed and suitably compacted. Where the same is low,
the deficiency shall be corrected by adding fresh material. The degree of compaction and the
type of material to be used shall conform to the clauses.
ii. Water Bound Macadam
Where the surface is high or low, the top 75mm shall be scarified, reshaped with added material
as necessary re-compacted to clauses. The area treated at a place shall not be less than 5 meter
long and 2 meters wide.
iii. Bituminous constructions
For bituminous construction other than wearing course, where the surface is low, the deficiency
shall be corrected by adding fresh material and re-compacting to specifications. Where the
surface is high, the full depth of the layer shall be removed and replaced with fresh material and
compacted to specifications.
For wearing course, where the surface is high or low, the full depth of the layer shall be removed
and replaced with fresh material and compacted to specifications. In all cases where the removal
and replacement of a bituminous layer is involved, the areas treated shall not be less than 5
meter lon and not less than 1 lane wide.
TABLE – 7
PERMITTED TOLERANCES OF SURFACE REGULARITY FOR SUBGRADE AND PAVEMENT COURSE
Sl. Type of construction Longitudinal profile with 3 cross profile meter straight
No. edge
Notes:
1 ** These are for machine laid surfaces. If laid manually due to unavoidable reasons,
tolerance up to 50 percent above these values in this column may be permitted at the
discretion of the Project Manager. However, this relaxation does not apply to the values
of maximum undulation for longitudinal and cross profiles mentioned in columns 3 and
8 on the table.
Surface evenness requirements in respect of both the longitudinal and cross profiles
should be simultaneously satisfied.
9.19 TESTS
9.19.1 General
For ensuring the requisite quality of construction, the materials and works shall be subjected to quality control
tests, as described hereinafter. The testing frequencies set forth are the desirable minimum and the Project
Manager shall have the full authority to increase the frequencies of tests as he may deem necessary to satisfy
himself that the materials and works comply with the appropriate specifications.
Test procedures for the various quality control tests are indicated in the respective sections of these specifications
or for certain tests within this section. Where no specific testing procedure is mentioned, the tests shall be carried
out as per the prevalent accepted engineering practice to the directions of the Project Manager
9.19.2 Tests on earthwork for embankment and sub grade construction
A. Borrow material
a. Sand content {IS:2720 (part IV)}: 1-2 tests per 8000 cum. of soil
b. Plasticity Test {IS:1270 (Part V)}: Each type to be tested, 1-2 tests per 8000 cum. of soil
B. Compaction control
Control shall be exercised by taking at least one measurement of density for each 100 square meters of compacted
area, or closer as required to yield the minimum number of test results for evaluation a day’s work on statistical
basis. The determination of density shall be in accordance with IS: 2720 (part XXVIII). Tests locations shall be
chosen only through random sampling techniques. Control shall not be based on the results of any one test but on
the mean value of a set of 5-10 density determinations. The number of tests in one test in one set of
measurements shall be 5 as long as it is felt that sufficient control over borrow material and the method of
compaction is being exercised. If considerable variations are observed between individual density results, the
minimum number of tests in one set of measurement shall be increased to 10. The acceptance of work shall be
subject to the condition that the mean dry density equals or exceeds the specified density and the standard
deviation for any set of results in below 0.08 gm/cc.
However, for earthwork in shoulders (earthen) and in top 500mm portion of the embankment below the sub
grade, at least one density measurement shall be taken for every 50 square meters of the compacted area
provided further that the number of tests in each set of measurements shall be at least 10. In order respects, the
control shall be similar to that described earlier.
TABLE – 9
CONTROL TESTS AND THEIR FREQUENCY FOR BITUMINOUS WORKS
10 .1 QU A LI TY C ON TR OL T E ST S:
1 Cement:
a) Recommended tests:
i) Fineness
ii) Soundness
iii) Consistency
iv) Setting time
v) Compressive strength and
vi) Chemical analysis
2 Fine aggregate:
a) Recommended tests:
i) Particle size and shape
ii) Estimation of deleterious materials and organic impurities.
iii) Specific gravity and density
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 383- Specification for coarse and fine aggregate from natural sources for concrete.
IS:2430- Method of sampling of aggregates for concrete.
IS:2386- Methods of tests for aggregates for concrete
3 Concrete workers
Guide – 1992 by Research and Consultancy directorate, A.C.C. Ltd., Mumbai
4 Coarse aggregate:
a) Recommended tests:
i) Sieve analysis
ii) Flakiness index
iii) Specific gravity and density
iv) Soundness
v) Alkali aggregate reaction
vi) Mechanical properties
vii) Petrographic examination
5 Water
a) Recommended tests:
i) P-Alkalinity
ii) M-Alkalinity
iii) Inorganic solids
iv) Sulfates
v) Chlorides
vi) Suspended solids
vii) pH Value
6 Admixtures:
(Accelerating, retarding, water reducing/workability improvement and air entraining admixtures)
a) Recommended tests:
i) Water content of concrete with and without admixture
ii) Setting time of concrete with and without admixture
iii) Compressive strength of concrete with and without admixture
iv) Change in length of concrete with and without admixture
v) Bleeding of concrete with and without admixture
vi) Workability of concrete with and without admixture
vii) Air content of concrete with and without admixture
viii) Heat of hydration of concrete with and without admixture
ix) Chloride content
8 Hardened concrete:
a) Recommended tests:
i) Compressive strength
a) Accelerated curing
b) Normal curing
ii) Permeability test
b) Sampling and frequency of sampling:
As pe guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS : 456 – Code of practice for plain and reinforced concrete
IS: 516 – Methods of tests for strength of concrete
IS: 9013 – Method of testing of accelerated cured concrete
IS: 3085 – Method of tests for permeability of cement mortar and concrete.
9 Reinforcing Steel:
a) Recommended tests:
i) Tensile test on bars welded or otherwise.
ii) Bend and re-bend test
iii) Bond test
iv) Chemical analysis
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian standards.
d) Relevant references:
IS:1786 –Specification of high strength deformed steel bars for concrete reinforcement.
IS: 1608 –Method of tensile testing of steel products.
IS: 228 –Method of chemical analysis of steel.
Part 1 : Determination of carbon by volumetric method.
Part 3 : Determination of phosphorous by alkali metric method
Part 9 : Determination of sulphur
12 Door Shutters:
a) Recommended tests:
i) Dimensions and defects of square ness test
ii) General flatness test
iii) Local plane ness test
iv) Impact indentation test
v) Edge loading test
vi) Shock resistance test
14 Tiles (Concrete):
a) Recommended tests:
i) Dimensional tolerance
ii) Flatness
iii) Perpendicularity
16 Marble:
Recommended tests:
Moisture absorption
Hardness
Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards
Acceptance criteria:
As per guidelines in relevant Indian Standards
Relevant references:
IS: 1237 –Specification for marbles (Blocks, slabs & tiles)
IS: 1124 –Methods of tests for determination of water absorption, apparent specific
gravity and porosity of natural building stone.
17 Non-destructive Testing of Concrete:
a) Recommended tests:
i) Ultrasonic pulse velocity test
ii) Rebound hammer test
b) Frequency of test:
Core to be taken from walls, slabs and footings whenever in doubt.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 516 –Method of tests for strength of concrete
IS: 456 –Code of practice for plain and reinforced concrete
19 Load Test:
a) Recommended test:
Load testing of selected in-situ panels/pre-cast components (service load test)
b) Frequency of test:
On representative in-situ panels in each type of housing whenever in doubt about 0.5%
of the total precast floor roof components.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 456-Code of practice for plain and reinforced concrete.
IS: 6441 (part 7 & 8) Method of test for autoclaved cellular concrete products subject to
load test.
20 Earth-filling in Building:
a) Recommended tests:
i) Grain size distribution for material selection
ii) Proctor compaction test
iii) Field density by core extraction
b) Frequency of test:
i) One sample from each borrow pit
21 Mix design:
a) Recommended method:
Method outlined in SP-23-– Hand book on concrete mixes.
b) Frequency of design:
On every source of type of the following:
i) Aggregates
ii) Cement
iii) Admixtures and for different grades of workability.
c) Acceptance criteria of mix:
As per guidelines in relevant Indian Standards.
d) Relevant references:
SP:23- Hand book on concrete mixes
SP: 10262 – 1982 Recommended guidelines for concrete mix design.
SP: 456-1978 Code of practice for plain and reinforced concrete.
GENERAL REFERENCES:
1 Properties of concrete by A.M>Neville, ELBS Publication 1981
2 (a) Elements of concrete making,
(b) Concrete workers guide,
(c) Control tests for quality user,
(d) Notes for the cement user, by Research and Consultancy directorate, ACC Ltd.,
Mumbai.
3 SP: 24-Explanatory handbook on Indian Standard Code of practice for plain and
reinforced concrete.
4 Workshop on testing of fresh and hardened concrete Indian Concrete Institute,.
5 SP:21 –Summaries of Indian Standard for building materials.
6 National building code,.
7 Non-destructive testing by Barry Hall, Macmillan Education,.
TOLERANCES:
1) Cement Concrete
A VOLUMETRIC MIX
a cum 1:1.5:3 8.000 400.000
b cum 1:2:4 6.400 320.000
e cum 1:3:6 4.400 220.000
f cum 1:4:8 3.400 170.000
g cum 1:5:10 2.600 130.000
DESIGN MIX
a cum M7.5 3.000 150.000
b cum M10 4.400 220.000
C cum M15 5.600 280.000
d cum M20 6.000 300.000
e cum M25 6.400 320.000
f cum M30 6.800 340.000
g cum M35 7.500 375.000
h cum M40 8.200 410.000
i cum M45 9.000 450.000
j cum M50 9.000 450.000
2) Mortars
a cum 1:1 28.800 1440.000
b cum 1:2 14.400 720.000
c cum 1:3 9.600 480.000
d cum 1:4 7.200 360.000
e cum 1:5 5.760 288.000
f cum 1:6 4.800 240.000
g cum 1:8 3.600 180.000
3) Brick work - 230mm Thick
a cum 1:3 2.880 144.000
b cum 1:4 2.160 108.000
c cum 1:5 1.728 86.400
d cum 1:6 1.440 72.000
e cum 1:8 1.080 54.000
4) Half Brick work - 115mm Thick
13) Aerocon Block work - 150mm Thick sqm 1:6 0.080 4.000
14) Aerocon Block work - 100mm Thick sqm 1:6 0.053 2.650
15) Stone masonry Rubble
a cum 1:4 2.520 126.000
b cum 1:5 2.016 100.800
c cum 1:6 1.680 84.000
d cum 1:8 1.260 63.000
16) Coursed roubbled masonry
a cum 1:4 2.376 118.800
b cum 1:6 1.584 79.200
c cum 1:8 1.188 59.400
Conformance by Deviations if
S.No Materials Approved Makes
vendor Yes / No any by vendor
1
Chlorpyriphios De-Nocil// Cynamide/Tricel
Expanded Polystyrene
13 Beardshell / Toshiba
(Thermocole)
Fosroc/ EMALITE OF
20 Non Metallic Floor
Structural/CICO technologies / STP
Acrylic/polymer modified
22 BASF / FOSROC / SIKA
coatings
28
PT Strands Tata / DP wires / Usha Martin
Note: In the List of recommendation above, out of makes mentioned in the list, only 1st make shall be quoted for
and used. However if due to non-availability or any other technical reasons, the alternative make is allowed, it
shall be subject to prior approval of the Project Manager and price adjustment.
1. The contractor shall produce all samples including natural stones, before procurement of the materials, for
approval of the Architects/Project Managers.
2. Where more than one manufacturer is listed, the names are given in the order of preference. The contractor
shall quote the rates for the various items of work based on the materials of first preference after ascertaining
the availability, delivery schedule of the same. Unless the contractor stipulates in this tender, it shall be
presumed that the rates quoted are for material of first preference only.
3. In the event, the contractor is permitted to use the material of lower preference because of valid reasons,
then the contract rates for the relevant items of work shall be suitably adjusted on the basis of variation in
prices of the materials of first preference and those actually used. If the prices of the materials used are higher
than the material of the first preference, the owner shall not be liable to make any enhanced payment for the
affected items of work on this account.
4. In respect of materials for which approved makes are not specified above, these will be makes to be decided
by the Architects/Project Managers and as per samples getting approved.
The Building is designed for an Energy Efficient Structure and hence all products have to be green rated
and wherever not mentioned clarifications should be sought from the Project Manager.
CEMENT PLASTER
The cement plaster shall be 6mm, 12 mm, 15 mm or 20 mm thick as specified in the item.
Scaffolding:- For all exposed brick work or tile work double scaffolding independent of the work having
two sets of vertical supports shall be provided. The supports shall be sound and strong, tied together with
horizontal pieces over which scaffolding planks shall be fixed.
For all other work in buildings, single scaffolding shall be permitted. In such cases the inner end of the
horizontal scaffolding pole shall rest in a hole provided only in the header course for the purpose. Only
one header for each pole shall be left out. Such holes for scaffolding shall, however, will not be allowed in
pillars/columns less than one metre in width or immediately near the skew backs of arches. The holes left
in masonry works for scaffolding purposes shall be filled and made good before plastering.
Note : In case of special type of brick work, scaffolding shall be got approved from Authority’s Engineer in
advance.
Preparation of Surface:
The joints shall be raked out properly. Dust and loose mortar shall be brushed out. Efflorescence if any
shall be removed by brushing and scrapping. The surface shall then be thoroughly washed with water,
cleaned and kept wet before plastering is commenced.
In case of concrete surface if a chemical retarder has been applied to the form work, the surface shall be
roughened by wire brushing and all the resulting dust and loose particles cleaned off and care shall be
taken that none of the retarders is left on the surface.
Mortar:
The mortar of the specified mix using the type of sand described in the item shall be used. It shall be as
specified in Subhead 3.0. For external work and under coat work, the fine aggregate shall conform to
grading IV. For finishing coat work the fine aggregate conforming to grading zone V shall be used.
Application of Plaster:
Ceiling plaster shall be completed before commencement of wall plaster. Plastering shall be started from
the top and worked down towards the floor. All putlog holes shall be properly filled in advance of the
plastering as the scaffolding is being taken down. To ensure even thickness and a true surface, plaster
about 15 × 15 cm shall be first applied, horizontally and vertically, at not more than 2 metres intervals
over the entire surface to serve as gauges. The surfaces of these gauged areas shall be truly in the plane of
the finished plaster surface. The mortar shall then be laid on the wall, between the gauges with trowel.
The mortar shall be applied in a uniform surface slightly more than the specified thickness. This shall be
brought to a true surface, by working a wooden straight edge reaching across the gauges, with small
upward and sideways movements at a time. Finally the surface shall be finished off true with trowel or
All corners, arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall be
carefully finished. Rounding or chamfering corners, arises, provision of grooves at junctions etc. where
required shall be done without any extra payment. Such rounding, chamfering or grooving shall be carried
out with proper templates or battens to the sizes required.
When suspending work at the end of the day, the plaster shall be left, cut clean to line both horizontally
and vertically. When recommencing the plastering, the edge of the old work shall be scrapped cleaned
and wetted with cement slurry before plaster is applied to the adjacent areas, to enable the two to
properly join together. Plastering work shall be closed at the end of the day on the body of wall and not
nearer than 15 cm to any corners or arises. It shall not be closed on the body of the features such as
plasters, bands and cornices, nor at the corners of arises. Horizontal joints in plaster work shall not also
occur on parapet tops and copings as these invariably lead to leakages. The plastering and finishing shall
be completed within half an hour of adding water to the dry mortar.
No portion of the surface shall be left out initially to be patched up later on. The plastering and finishing
shall be completed within half an hour of adding water to the dry mortar.
POINTING
All exposed joints shall be pointed with mortar as specified. The pointing when finished shall be sunk from
stone face by 5 mm or as specified. The depth of mortar in pointing work shall not be less than 15 mm.
Curing
Masonry work in cement or composite mortar shall be kept constantly moist on all faces for a minimum
period of seven days. In case of masonry with fat lime mortar, curing shall commence two days after
laying of masonry and shall continue for at least seven days thereafter.
Scaffolding:
Double scaffolding having two sets of vertical supports shall be provided. The supports shall be sound and
strong, tied together with horizontal pieces over which scaffolding planks shall be fixed.
Rate: The rate shall include the cost of materials and labour required for all the operations described
above
Before laying the first course, the alignment of the wall shall be marked on the damp-proof course. The
blocks for this course shall first be laid dry, that is, without mortar along a string stretched between
properly located corners of the wall in order to determine the correct position of the blocks including
those of the cross walls jointing it and also adjust their spacing. When the blocks are set in proper
position, the two corner blocks shall be removed, a mortar bed spread and these blocks laid back in place
truly level and plumb. The string shall then be stretched tightly along the faces of two corner blocks and
the faces of the intermediate ones adjusted to coincide with the line. Thereafter, each block shall be
removed and re-laid over a bed of mortar. After every three or four blocks have been laid, their correct
alignment, level and verticality shall be carefully checked.
The construction of walls may be started either at the corners first or started from one end proceeding in
the other direction. If the corners of the wall are built first, they shall be built four or five courses higher
than the centre of the wall. As each course is laid at the corner, it shall be checked for alignment and level
and for being plumb. Each block shall be carefully checked with a level or straight-edge to make certain
that the faces of the blocks are all in the same plane. This precaution is necessary to ensure truly straight
and vertical walls.
The use of a storey rod or course pole which is simply a board with markings 200 mm apart,
provides an accurate method of finding the top of the masonry for each course. Each course, in
building the corners, shall be stepped back by a half-block and the horizontal spacing of the block
shall be checked by placing a mason’s level diagonally across the corners of the blocks.
When filling in the wall between the corners, a mason’s line shall be stretched from corner to
corner for each course and the top outside edge of each block shall be laid to this line. The
manner of handling or gripping the block shall be such as to position the block properly with
minimum adjustment.
To assure satisfactory bond, mortar shall not be spread too far ahead of actual laying of the block
or it will stiffen and loose its plasticity. As each block is laid, excess mortar extruding from the
joints shall be cut off with the trowel and thrown back on the mortar board to be reworked into
the fresh mortar. If the work is progressing rapidly, the extruded mortar cut from the joints may
be applied to the vertical face shells of the blocks just laid. If there be any delay long enough for
the mortar to stiffen on the block, the mortar shall be removed to the mortar board and
reworked. Dead mortar that has been picked up from the scaffold or from the floor shall not be
used.
FLOORING /SKIRTING
Vitrified tiles flooring
The tiles shall be of approved make and shall generally conform to IS 15622. They shall be flat, and true to
shape and free from blisters crazing, chips, welts, crawling or other imperfections detracting from their
appearance. The tiles shall be Group BI b and thickness 9 - 10mm.
Over this mortar bedding neat grey cement slurry of honey like consistency shall be spread at the rate of
3.3 kg of cement per square meter over an area upto one square meter. Tiles shall be soaked in water
washed clean and shall be fixed in this grout one after another, each tile gently being tapped with a
wooden mallet till it is properly bedded and in level with the adjoining tiles. The joints shall be kept as thin
as possible and in straight lines or to suit the required pattern.
The surface of the flooring during laying shall be frequently checked with a straight edge about 2 m long,
so as to obtain a true surface with the required slope. In bath, toilet W.C. kitchen and balcony/verandah
flooring, suitable tile drop or as shown in drawing will be given in addition to required slope to avoid
spread of water. Further tile drop will also be provided near floor trap.
Where full size tiles cannot be fixed these shall be cut (sawn) to the required size, and their edge rubbed
smooth to ensure straight and true joints. Tiles which are fixed in the floor adjoining the wall shall enter
not less than 10 mm under the plaster, skirting or dado. After tiles have been laid surplus cement slurry
shall be cleaned off.
Preparation of Surfaces
The joints shall be raked out to a depth of at least 15 mm in masonry walls. In case of concrete walls, the
surface shall be hacked and roughened with wire brushes. The surface shall be cleaned thoroughly,
washed with water and kept wet before skirting is commenced.
Laying
12 mm thick plaster of cement mortar 1:3 (1 cement: 3 coarse sand) mix of as specified shall be applied
and allowed to harden. The plaster shall be roughened with wire brushes or by scratching diagonal at
closed intervals.
The tiles should be soaked in water, washed clean, and a coat of cement slurry applied liberally at the
back of tiles and set in the bedding mortar. The tiles shall be tamped and corrected to proper plane and
lines. The tiles shall be set in the required pattern and jointed. The joints shall be as fine as possible. Top
of skirting or dado shall be truly horizontal and joints truly vertical except where otherwise indicated. Odd
size/cut size of tile shall be adjusted at bottom to take care of slope of the flooring.Skirting and dado shall
rest on the top of the flooring. Where full size tiles cannot be fixed these shall be cut (sawn) to the
required size and their edges rubbed smooth. Skirting /dado shall not project from the finished “surface
of wall” by more than the tile thickness; undulations if any shall be adjusted in wall.
i) Mortar Bedding:
Cement mortar shall be prepared in a mortar mill or pan. The amount of water added shall be the
minimum necessary to give just sufficient plasticity for laying and satisfactory bedding. Care shall be taken
in preparing the mortar to ensure that there are no hard lumps that would interfere with the even
bedding of the stone slabs. Before spreading the mortar the sub floor or base cleaned of all dirt, scum,
loose materials and laitance if any by scrubbing with coir or steel wire brush or by hacking if necessary,
and then well wetted without forming any pools of water on the surface. Before laying the mortar, the
Measurement
Marble stone flooring with different kind of marble shall be measured separately and in square metre
correct to two places of decimal. Length and breadth shall be measured correct to a cm before laying
skirting, dado or wall plaster. No deduction shall be made nor extra paid for voids not exceeding 0.20
square metre. Deductions for ends of dissimilar materials or other articles embedded shall not be made
for areas not exceeding 0.10 square metre. Nothing extra shall be paid for laying the floor at different
levels in the same room. Steps and treads of stairs paved with marble stone slabs shall also be measured
under the item of Marble Stone flooring. Extra shall, however, be paid for such areas where the width of
treads does not exceed 30 cm. The width of treads shall be measured from the outer edge of the nosing,
as laid, before providing the riser
Rate
The rate shall include the cost of all materials and labour involved in all the operations described above.
However, extra shall be paid for making special type of pattern/design/flowers as per drawings.
Laying
Base concrete or the RCC slab on which the slabs are to be laid shall be cleaned, wetted and mopped. The
bedding for the slabs shall be with cement mortar 1:4 (1 cement: 4 coarse sand) or as given in the
description of the item. The average thickness of the bedding mortar under the slab shall be 20 mm and
the thickness at any place under the slab shall be not less than 12 mm.
The slab to be paved shall then be lowered gently back in position and tapped with wooden mallet till it is
properly bedded in level with and close to the adjoining slabs with as fine a joint as possible. Subsequent
slabs shall be laid in the same manner. After each slab has been laid, surplus cement on the surface of the
slabs shall be cleaned off. The flooring shall be cured for a minimum period of seven days. The surface of
the flooring as laid shall be true to levels, and, slopes as instructed by the Client/Project manager. Joint
thickness shall not be more than 1 mm. The slabs shall be matched as shown in drawings or as instructed
by the Client/Project manager
Supporting Joists: Main beams and joists of the class of wood sections specified in the description of the
item for beams and joists, or as instructed by the Authority’s Engineer shall be fixed in position to dead
levels. The width of the joints shall not be less than 50 mm. The arrangement and spacing of beams joists
etc. shall be as per design furnished.
Fixing
The joists on which the planks shall be fixed shall be checked and corrected to levels. The end boards shall
be accurately fixed with the sides parallel and close to the walls. Each adjoining board shall be carefully
jointed and shall be tightened in position and screwed. For fixing the boards to the joists, two screws shall
be used at each end of the boards and one screw at each of the intermediate joists in a zig-zag manner.
The screws shall be countersunk and screw holes filled with approved stopping.
The junction between timber flooring and adjacent flooring shall be formed by inserting a metal
strip (brass or aluminium) at the junction. The metal strip shall be fixed to the end of the planks
by screws. The strips shall be paid for extra.
The flooring shall be truly level and plane. The joints shall be truly parallel and or perpendicular
to the walls, unless otherwise specified.
The floor shall be plane in both directions and made perfectly even, true and smooth.
The boards shall be planed true on the top face only unless otherwise specified in the description
of the item. Where the bottom face is exposed and it is also required to be planed, then such
planning shall be paid for extra.
Unless otherwise described in the item, the longitudinal joints of planks shall be tongued and
grooved to a minimum depth of 12 mm while the heading joints shall be of the square butt type
and shall occur over the centre line of the supporting joists. Heading joists in adjacent boards
shall be placed over the same joists.
Rate: The rate shall include the cost of the labour and materials involved in all the operations described
above, with the exceptions noted in the relevant sub-paras
All timber for carpentry and joinery in touch with masonry or concrete shall be painted with wood
preservative before fixing.
Doors, Frames:
The specification for frames of doors, are described here. The frames shall wrought, framed and fixed in
position as per detailed drawing and as directed by the engineer in charge. Specified timber shall be used,
and it shall be sawn in the direction of the grains. Sawing shall be truly straight and square. The scanting
shall be planed smooth and accurate to the full dimensions, rebates, rounding and mouldings as shown in
the drawings made, before assembling. Patching or plugging of any kind shall not be permitted except as
provided. A tolerance of 2 / 3 mm shall be allowed in the finished cross section dimensions of door and
windows frames.
Joints:
These shall be of mortise and tenon type, simple, neat and strong. Mortise and tendon joints shall fit in
fully and accurately without wedging or filling. The joints shall be glued, framed, put together and planned
with hard wood or bamboo pins not less than 10 mm diameter after the frames are put together in
position by means of a press.
Gluing of joints:
The contact surface of tendon and mortise joints shall be treated before putting together with synthetic
resin adhesive of make, approved by the engineer.
Fixing in Position:
Before the frames are fixed in position, these shall be inspected and passed by the engineer. The frame
shall be placed in proper position and secured to walls or columns as the case maybe with metallic
fastener, iron hold fasts as per direction of the Authority’s Engineer.
In case of door frames without sills the vertical members shall be embedded in the flooring to its full
depth. When sills are provided, these sills shall be embedded and sunk in the floor to its full depth. The
door frames without sills while being placed in position shall be suitably strutted and wedged in order to
prevent warping during construction. The frames shall also be protected from damage, during
construction.
Measurement:
Wood work wrought and framed shall be measured for finished dimensions. No allowance shall be made
for wastage and for dimensions supplied beyond those specified. Length of each peace shall be measured
Rate:
The rate is to include the cost of all materials required and labour involved in all the operations, described
above.
Core
The core of the flush door shutters shall be a block board having wooden strips held in a frame
constructed of stiles and rails. Each stile and rail shall be a single piece without any joint. The width of the
stiles and rails including lipping, where provided shall not be less than 45 mm and not more than 75 mm.
The width of each wooden strip shall not exceed 30 mm. Stiles, rails and wooden strips forming the core
of a shutter shall be of equal and uniform thickness. Wooden strips shall be parallel to the stiles.
End joints of the pieces of wooden strips of small lengths shall be staggered. In a shutter, stiles and rails
shall be of one species of timber. Wooden strips shall also be of one species only but it may or may not be
of the same species as that of the stiles and rails. Any species of timber may be used for core of flush
door. However, any non-coniferous (Hard wood) timber shall be used for stiles, rails and lipping.
Face Panel
The face panel shall be formed by gluing, by the hot-press process on both faces of the core, either
laminate or cross-bands and face veneers. The thickness of the cross bands as such or in laminate shall be
between 1.0 mm and 3.0 mm.
Lipping
Lipping, where specified, shall be provided internally on all edges of the shutters. Lipping shall be done
with battens of first class hardwood or as specified of depth not less than 25 mm. For double leaved
shutters, depth of the lipping at meeting of stiles shall be not less than 35 mm. Joints shall not be
permitted in the lipping.
Adhesive
Adhesive used for bonding various components of flush door shutters namely, core, core frame, lipping,
cross-bands, face veneers, plywood etc. and for bonding plywood shall conform to BWP type, phenol
formaldehyde synthetic resin adhesive conforming to IS 848.
Rates
The rate includes the cost of material and labour and all hardware fitting & fixtures involved in all the
operations.
MS SHEET DOOR
Door shall be made of 1 mm thick MS Sheet door with 40x40x6 mm angle iron frame and 3 mm MS gusset
plates using flats 30x6 mm for diagonal braces and central cross piece. All the steel surfaces to be
thoroughly cleaned, free from rust, mill scales, dirt, oil etc by mechanical means, than applying a coat of
red oxide zinc chromate primer and finally finished with minimum two coats of synthetic enamel paint of
approved brand.
Door frame shall be double rebate profile of minimum size 154mm x 77mm made out of minimum 1.5
mm thick GPSP sheet. NDRF 154mm x 77mm frames shall be butt jointed and field assembled with self
bolted .All provision should be mortised, drilled and tapped for receiving appropriate hardware ,Frames
should be provided with back plate bracket and anchor fasteners for installations on a finished plastered
masonry wall opening.
Door leaf shall be minimum 49mm thick fully flush double skin door with or without vision lite. Door leaf
shall be manufactured from 1.0 mm minimum thick GPSP sheet. The internal construction of the door
should be rigid reinforcement pads for receiving appropriate hardware. The infill material shall be
Rockwool treated with Viper FRS 881 LH. All doors NSD 12049 shall be factory prepped for receiving
appropriate hardware and provided with necessary reinforcement for hinges, lockand door closers. The
edges should be interlocked with a bending radius of 1.44mm.For pairs of doors astragals has to be
provided on the meeting stile for both active and inactive leaf. Vision lite wherever applicable should be
provided as per manufacturers recommendation with a beeding and screw from inside.
o Preparation of Surface:- For new work, the surface shall be thoroughly cleaned off all mortar dropping,
dirt dust, algae, fungus or moth, grease and other foreign matter of brushing and washing, pitting in
plaster shall make good, surface imperfections such as cracks, holes etc. should be repaired using white
cement. The prepared surface shall have received the approval of the Engineer in charge after inspection
before painting is commenced.
PAINTING
i. Materials:
Paints, oil, varnishes etc. of approved brand and manufacturer shall be used ready mixed paint as
received from the manufacturer without any admixture shall be used. All materials shall be low VOC
levels. If for any reason thinning is necessary in case of ready mixed paint, the brand of thinner
recommended by the manufacturer or as instructed by the Authority’s Engineer shall be used.
Approved, paints, oil or varnishes shall be brought to the site of work by the Contractor in their
original containers in sealed condition. The material shall be brought in at a time in adequate
quantities to suffice for the whole work or at least a fortnight’s work. The materials shall be kept in
the joint custody of the contractor and the Authority’s Engineer. The empties shall not be removed
from the site work, till the relevant item of work has been completed and permission obtained from
the Authority’s Engineer.
ii. Commencing Work:
Painting shall not be started until the Authority’s Engineer has inspected the items of work to be
painted, satisfied himself about their proper quality and given his approval to commence the
painting work. Painting of external surface should not be done in adverse weather condition like hail
storm and dust storm.
Painting, except the priming coat, shall generally be taken in hand after practically finishing all other
builder’s work. The rooms should be thoroughly swept out and the entire building cleaned up, at
least one day in advance of the paint work being started.
iii. Preparation of Surface:
The surface shall be thoroughly cleaned from dust & other foreign materials... All rust, dirt scales,
smoke and grease shall be thoroughly removed before painting is started. The prepared surface shall
have received the approval of the Authority’s Engineer after inspection, before painting is
commenced.
iv. Application:
v. Measurements:
The length and breadth shall be measured correct to a cm. The area shall be calculated in sq. meters
(correct to two places of decimal), except otherwise stated, small articles not exceeding 10 sq.
decimeters (0.1 Sqm.) of painted surfaces where not in conjunction with similar painted work shall
be enumerated. Painting up to15 cm in width or in girth and not in conjunction with similar painted
work shall be given in running meters.
Laying Out:
A figure of the steel structure to be fabricated shall be drawn on a level platform to full scale. This
may be done in full or in parts, as shown on drawings or as directed by the Authority’s Engineer.
Steel tape shall be used for measurements.
Fabrication:-
Welding: Welding shall generally be done by electric arc process as per IS 816 and IS 823. The
electric arc method is usually adopted and is economical. Where electricity for public is not available
generators shall be arranged by the contractor at his own cost unless otherwise specified. Gas
welding shall only by resorted to using oxyacetylene flame with specific approval of the Authority’s
Engineer. Gas welding shall not be permitted for structural steel work Gas welding required eating
of the members to be welded along with the welding rod and is likely to create temperature stresses
in the welded members. Precautions shall therefore be taken to avoid distortion of the members
due to these temperature stresses.
The work shall be done as shown in the shop drawings which should clearly indicate various details
of the joint to be welded, type of welds, shop and site welds as well as the types of electrodes to be
used. Symbol for welding on plans and shops drawings shall be according to IS 813.
As far as possible every effort shall be made to limit the welding that must be done after the
structure is erected so as to avoid the improper welding that is likely to be done due to heights and
difficult positions on scaffolding etc. apart from the aspect of economy. The maximum dia of
electrodes for welding work shall be as per IS 814. Joint surfaces which are to be welded together
shall be free from loose mill scale, rust, paint, grease or other foreign matter, which adversely affect
the quality of weld and workmanship.
Precautions: All operation connected with welding and cutting equipment shall conform to the
safety requirements given in IS 818 for safety requirements and Health provision in Electric and gas
welding and cutting operations.
Assembly: Before welding is commenced, the members to be welded shall first be brought together
and firmly clamped or tack welded to be held in position. This temporary connection has to be
strong enough to hold the parts accurately in place without any disturbance. Tack welds located in
places where final welds will be made later shall conform to the final weld in quality and shall be
cleaned off slag before final weld is made.
Erection: The specification shall be as described in 10.3.3 except that while erecting a welded
structure adequate means shall be employed for temporary fastening the members together and
bracing the frame work until the joints are welded. Such means shall consists of applying of erection
bolts, tack welding or other positive devices imparting sufficient strength and stiffness to resist all
temporary loads and lateral forces including wind. Owing to the small number of bolts ordinarily
employed for joints which are to be welded, the temporary support of heavy girders carrying
columns shall be specially attended. Different members which shall be fillet welded, shall be brought
into as close contact as possible. The gap due to faulty workmanship or incorrect fit if any shall not
exceed. 1.5 mm if gap exceeds 1.5 mm or more occurs locally the size of fillet weld shall be
increased at such position by an amount equal to the width of the gap.
Synthetic Enamel Paint (conforming to IS 2933) of approved brand and manufacture and of the
required colour shall be used for the top coat and an undercoat of ordinary Paint of shade to match
the top coat as recommended by the same manufacturer as far the top coat shall be used.
Painting on new surface:-
Wooden Surface : The wood work to be painted shall be dry and free from moisture. The surface shall
be thoroughly cleaned. All unevenness shall be rubbed down smooth with sand paper and shall be
well dusted. Knots, if any shall be covered with preparation of red lead made by grinding red lead in
water and mixing with strong glue sized and used hot. Appropriate filler material conforming to IS
345 with same shade as Paint shall be used where specified. The surface treated for knotting shall be
dry before Paint is applied. After obtaining approval of Authority’s Engineer for wood work, the
priming coat shall be applied before the wood work is fixed in position. After the priming coat is
applied, the holes and indentation on the surface shall be stopped with glazier’s putty or wood putty.
Stopping shall not be done before the priming coat is applied as the wood will absorb the oil in
stopping and the latter is therefore liable to crack.
Iron & Steel Surface : All rust and scales shall be removed by scrapping or by brushing with steel wire
brushes. Hard skin of oxide formed on the surface of wrought iron during rolling which becomes
loose by rusting, shall be removed.
All dust and dirt shall be thoroughly wiped away from the surface.If the surface is wet, it shall be
dried before priming coat is undertaken.
Application: The number of coats including the undercoat shall be as stipulated in the item.
Under Coat: One coat of the specified ordinary Paint of shade suited to the shade of the top coat,
shall be applied and allowed to dry overnight. It shall be rubbed next day with the finest grade of wet
abrasive paper to ensure a smooth and even surface, free from brush marks and all loose particles
dusted off.
Top Coat : Top coats of synthetic enamel Paint of desired shade shall be applied after the undercoat is
thoroughly dry. Additional finishing coats shall be applied if found necessary to ensureproperly
uniform glossy surface.
Base
Interlocking paver block to be fixed on the bed 50 mm or specified otherwise thick of coarse sand of
approved specification and filling the joints with the sand of approved type and quality or as specified
and as directed by Authority’s Engineer.
KERB STONE(PRECAST):-`
Laying:-
Trenches shall first be made along the edge of the wearing course of the road to receive the kerb
stones of cement concrete of specified grade. The bed of the trenches shall be compacted manually
with steel rammers to a firm and even surface and then the stones shall be set in cement mortar of
specified proportion.
The kerb stones with top 20 cm. wide shall be laid with their length running parallel to the road edge,
true in line and gradient at a distance of 30 cm. from the road edge to allow for the channel and shall
project about 12.5 cm. above the latter. The channel stones with top 30 cm. wide shall be laid in
position in chamber with finished road surface and with sufficient slope towards the road gully
chamber. The joints of kerb and channel stones shall be staggered and shall be not more than 10 mm.
Wherever specified all joints shall be filled with mortar 1:3 (1 cement : 3 coarse sand) and pointed
with mortar 1:2 (1 cement: 2 fine sand) which shall be cured for 7 days.
The necessary drainage openings of specified sizes shall be made through the kerb as per drawings or
as directed by the Authority’s Engineer for connecting to storm water drains.
Finishing:- Berms and road edges shall be restored and all surplus earth including rubbish etc.
disposed off as directed by the Authority’s Engineer. Nothing extra shall be paid for this.
Measurements:-It shall be measured in cubic meters with Length of the finished work (for specified
width and height of stone) shall be measured in running metre along the edge of the road correct to a
cm.
Note : An effective means shall be provided for maintaining the reinforcement in position and for
ensuring correct cover during manufacture of the unit. Spacers for this purpose shall be of rust proof
material or of steel protected against corrosion.
Laying and Jointing Cement Concrete Pipes and Specials:
(i) Trenches: Trenches shall be as described in 18.4.4.(CPWD specs) Where the pipes are to be
bedded directly on soil, the bed shall be suitably rounded to fit the lower part of the pipe, the cost for
this operation being included in the rate for laying the pipe itself.
(ii) Loading, transporting and unloading of concrete pipes shall be done with care. Handling shall be
such as to avoid impact. Gradual unloading by inclined plane or by chain pulley block is
recommended. All pipe sections and connections shall be inspected carefully before being laid.
Broken or defective pipes or connections shall not be used. Pipes shall be lowered into the trenches
carefully. Mechanical appliances may be used. Pipes shall be laid true to line and grade as specified.
Laying of pipes shall proceed upgrade of a slope.
(iii) If the pipes have spigot and socket joints, the socket ends shall face upstream. In the case of
pipes with joints to be made with loose collars, the collars shall be slipped on before the next pipe is
laid. Adequate and proper expansion joints shall be provided where directed.
(iv) In case where foundation conditions are unusual such as in the proximity of trees or holes, under
existing or proposed tracks manholes etc. the pipe shall be encased all-around in 15 cm thick cement
concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) or
compacted sand or gravel.
(v) In cases where the natural foundation is inadequate the pipes shall be laid either in concrete
cradle supported on proper foundations or on any other suitably designed structure. If a concrete
th
cradle bedding is used the depth of concrete below the bottom of the pipe shall be at least 1/4 of
the internal dia of the pipe subject to the min. of 10 cm and a maximum of 30 cm. The concrete shall
extend up the sides of the pipe at least to a distance of 1/4th of the outside diameter of
pipes 300 mm and over in dia. The pipe shall be laid in this concrete bedding before the concrete has
set. Pipes laid in trenches in earth shall be bedded evenly and firmly and as far up the haunches of
the pipe as to safely transmit the load expected from the backfill through the pipe to the bed. This
shall be done either by excavating the bottom of the trench to fit the curve of the pipe or by
compacting the earth under around the curve of the pipe to form an even bed. Necessary provision
shall be made for joints wherever required.
(x) In all pressure pipe lines the recess at the end of the pipe line shall be filled with jute braiding
dipped in hot bitumen or other suitable approved compound. Pipes shall be so jointed that the
bitumen ring of one pipe shall set into the recess of the next pipe. The ring shall be thoroughly
compressed by jacking or by any other suitable method.
The number of pipes that shall be jacked together at a time shall depend on the diameter of the pipes
and the bearing capacity of the soil, for small pipes up to 25 cm diameter, six pipes can be jacked
together at a time. The quantity of jute and bitumen in the ring shall be just sufficient to fill the recess
in the pipe when pressed hard by jacking or by any other suitable method. Before and during jacking
care shall be taken to see that there is no offset at the joint.
(xi) Testing: For pressure pipes, the completed pipeline shall be tested for pressure (Known as site
test pressure) which shall not be less than the maximum pipeline operating pressure plus the
calculated surge pressure, but in no case shall it exceed the hydrostatic test pressure. For
nonpressure pipes the joints shall be tested as per procedure laid down under CPWD specs19.2.1.2.
(xii) Refilling of Trenches: The specification described in CPWD specs19.2.1.2 (v) shall apply. In case
where pipes are not bedded on concrete special care shall be taken in refilling, trenches to prevent
the displacement and subsequent settlement at the surface resulting in uneven street surfaces and
dangers to foundations etc. The backfilling materials shall be packed by hand under and around the
pipe and rammed with a shovel and light tamper. This method of filling will be continued up to the
top of pipe. The refilling shall rise evenly on both sides of the pipe and continued up to 60 cm above
the top of pipe so as not to disturb the pipe. No tamping shall be done within 15 cm of the top of
pipe. The tamping shall become progressively heavier as the depth of the backfill increases.
Design, supply and install semi unitized structural glazing system/curtain wall designed to withstand
the design wind pressure of 1.8 kPa confirming to IS -875 part III. The system is with microwave cured
EPDM gaskets in exposed and unexposed area, structural and weather sealants of GE or approved
make, Norton spacer tape, backer rod, Bracketing system with MS hot dip galvanized brackets
designed to accommodate three dimensional movements, SS 316 grade fasteners and anchor bolts of
approved make, nylon separators to prevent bi-metallic corrosion, all complete required to perform
as per specification and drawing in conjunction with BOQ.
The system designed include pressure equalization with barrier gaskets for improved thermal
performance and weather performance, drainage at ground floor level thru bottom, spandrel panel
shall have pressure release & condensation drainage provisions, to accommodate building
movements, thermal expansions and the seismic movements. All metal joints in the wet area shall be
small joint sealant applied to ensure water tightness.
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to DIN standard
from approved extruder. All the internal and external visible surfaces shall have average 65 microns
Powder Coating finish. Glazing shall be with double layer of 6mm toughened glass one reflective and
one clear with a 12 gap filled with argon gas for energy efficiency and thermal insulation.
The window system shall have a u value of 0.31, SHGC(g value)- 0.3 and VLT 50% with high acoustics
level. The vendor is to provide execution drawings and get the same approved before construction.
The rates shall be inclusive of drawings, design for requisite wind load, getting the design approved,
supply, installation inclusive of all taxes, T&P etc. complete including all support structural members
necessary hardwares, sealants, tapes etc. complete and all inclusive.
The system designed include pressure equalization with barrier gaskets for improved thermal
performance and weather performance, drainage at ground floor level thru bottom, spandrel panel
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to DIN standard
from approved extruder. All the internal and external visible surfaces shall have average 65 microns
Powder Coating finish. Glazing shall be with double layers of 6mm toughened translucent glass with a
12 gap filled with argon gas for energy efficiency and thermal insulation.
The glazing system shall have a u value of 0.31, SHGC(g value)- 0.3 and VLT 50% with high acoustics
level. The vendor is to provide execution drawings and get the same approved before construction.
The rates shall be inclusive of supply, installation inclusive drawings, design for requisite wind load,
getting the design approved, of all taxes, T&P etc. complete including all support structural members
necessary hardwares, sealants, tapes etc. complete and all inclusive.
CANOPYUSING LAMINATEDGLASS
Providing and fixing and finishing of Canopy glass with 12.5mm (5mm clear H.S glass+1.52mm(4layer
of PVB)+6mm clear toughened )Laminated Glass with spider fitting including 4way, 2way spiders 1
way spiders and Routels bolt(316 grade) for 12 mm fixed glass fixed at 100x50x2.5 & 75x50x2.5 mm
square tube M.S Structure etc. complete as per the direction of Authority’s Engineer
CLADDING
Providing and fixing of Cladding with external wall with solid exterior grade compact high pressure
laminates as per EN 438-6 type EDS and EGS manufactured using specially treated acrylic resin under
high pressure and temperature and hardened with electron beam curing providing weather
resistance and UV resistance. The cost is inclusive of Aluminum framework for the same, fixing details
with Aluminum/MS cleats and all necessary arrangement inclusive cost of adhesive, all hardware,
materials, labour & T&P etc. complete as per the direction of Authority’s Engineer.
POLYCARBONATE SHEET:
Providing and fixing of 12 mm thick (minimum) co-extruded UV Protected Multicell Polycarbonate
panels with 3 cells - 4 walls structure with panel width of 700 - 900mm and having vertical standing
seam at both sides of the panel minimum protruded 15-20mm height for better connector
engagement. Panels shall be fixed on Purlin with the Z-type stainless steel fastener and snap on
STRUCTURAL GLAZING
Design, supply and install semi unitized structural glazing system/curtain wall designed to
withstand the design wind pressure of 1.8 kPa confirming to IS -875 part III. The system is
with microwave cured EPDM gaskets in exposed and unexposed area, structural and
weather sealants of GE or approved make, Norton spacer tape, backer rod, Bracketing
system with MS hot dip galvanized brackets designed to accommodate three dimensional
movements, SS 316 grade fasteners and anchor bolts of approved make, nylon separators to
prevent bi-metallic corrosion, all complete required to perform as per specification and
drawing in conjunction with BOQ.
The system designed include pressure equalization with barrier gaskets for improved
thermal performance and weather performance, drainage at ground floor level thru bottom,
spandrel panel shall have pressure release & condensation drainage provisions, to
accommodate building movements, thermal expansions and the seismic movements. All
metal joints in the wet area shall be small joint sealant applied to ensure water tightness.
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to DIN
standard from approved extruder. All the internal and external visible surfaces shall have
average 65 microns Powder Coating finish. Glazing shall be with double layers of 6mm
toughened translucent glass with a 12 gap filled with argon gas for energy efficiency and
thermal insulation.
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to DIN
standard from approved extruder. All the internal and external visible surfaces shall have
average 65 microns Powder Coating finish. Glazing shall be with double layers of 6mm
toughened translucent glass with a 12 gap filled with argon gas for energy efficiency and
thermal insulation.
PLINTH PROTECTION:
Min 750mm wide plinth protection by providing 50mm thick of cement concrete 1:3:6 (1 cement :3
coarse sand : 6 graded stone aggregate 20 mm nominal size) over 75mm thick bed of dry brick ballast
40 mm nominal size, well rammed and consolidated and grouted with fine sand shall be provided
around all buildings.
CORE CUTTING
Core cutting of RCC Slab of required diameter and depth of the slab with the help of required
machineries as specified and direction of CLIENT/Project Manager specified as per BOQ.
Rates: The rate includes the cost of material and labour and involved in all the operations
Note: In the List of recommended above, out of makes mentioned in the list, only 1st make shall be quoted for and
used. However if due to non-availability or any other technical reasons, the alternative make is allowed, it
shall be subject to prior approval of the Project Manager and price adjustment.
1. The contractor shall produce all samples including natural stones, before procurement of the materials, for
approval of the Architects/Project Managers.
2. Where more than one manufacturer is listed, the names are given in the order of preference. The contractor
shall quote the rates for the various items of work based on the materials of first preference after ascertaining
3. In the event, the contractor is permitted to use the material of lower preference because of valid reasons,
then the contract rates for the relevant items of work shall be suitably adjusted on the basis of variation in
prices of the materials of first preference and those actually used. If the prices of the materials used are higher
than the material of the first preference, the owner shall not be liable to make any enhanced payment for the
affected items of work on this account.
4. In respect of materials for which approved makes are not specified above, these will be makes to be decided
by the Architects/Project Managers and as per samples getting approved.
1. INTRODUCTION
The proposed Office site is located at Bhubaneswar
2. SCOPE
The scope of Public Health Engineering Services though not limited can be classified as follows
Domestic & Flushing water supply system.
Soil & Waste water drainage system.
Water treatment plant
Sewage Treatment Plant.
Rain/storm water management system
Solid waste management.
1.1 Scope
The General character and the scope of work to be carried out under this section as illustrated in the drawings,
specifications and scope of work attached herewith. The contractor shall carry out and complete the said work
under this contract in every respect in conformity with the rules and regulations of the local authority. The
Contractor shall furnish all labour, materials, appliances, tools and equipment necessary for the work for plumbing
services installation including testing and commissioning as specified herein, and as per the relevant Bureau of
Indian Standards (BIS), British Standards codes, and as shown on the drawings. This also includes any material,
appliances and equipment not specifically mentioned here in or noted on the drawings as being furnished or
The installation shall be in conformity with the bylaws and requirements of the local authority in so far as these
become applicable to the installation. Wherever this specification calls for, a higher standard of materials and /or
workmanship than those required by any of the above regulations and standards, then this specification shall take
precedence over the said regulations and standards.
1.9 Guarantee
The contractor shall guarantee both the material and workmanship of first class quality corresponding to
standard engineering practice. Any defective materials / workmanship shall be rejected, the contractor has to
rectify / replace at his own cost. Guarantee certificate of the materials supplied shall be handed over to the
owner.
SECTION – II: SOIL, WASTE AND VENT PIPES AND RAIN WATER PIPES
Soil, Waste & Vent Pipes shall be PVC pipes & fittings.
PVC (SWR) class pipes conforming to IS 13592 of dia 63mm up to 250mm dia of Type A are used in rain water &
ventilation and Type B for soil and waste discharging system shall be used. The pipes shall be supplied in nominal
lengths of 2, 3, and 4 or 6 meters, tolerance on specified lengths shall be +10mm and – 0mm. Any physical test
requirements shall be as per IS 13592. And Pipe of higher Dia i.e. 160mm Dia. and above shall be agricultural series
(6kg / sq. cm pressure rated) made as per IS 4985.
1.2.1 HANDLING
Because of their light weight, there may be a tendency for the PVC pipes to be thrown much more. Reasonable
care should be taken in handling and storage to prevent damage to the pipes. Contractor should hold the fullest
responsibility in this case. On no account the pipes should be dragged on the ground. Pipes should be given
adequate supports at all times.
1.2.2 LAYING
1.2.3 JOINTING
The jointing of pipes to fittings shall be done as per the manufacturer’s instructions / recommendations. The UPVC
pipes and fittings shall be joined with Solvent Cement and jointing shall be carried out as follows:
1. Cut the spigot end of the pipe square.
2. All burrs from the internal and external surfaces should be removed.
3. The spigot should be marked with a pencil line and a distance equivalent to the socket depth. Clean the
surface within the marked area.
4. Apply uniform coat of solvent cement on the external surface to the pipe and a lighter coat on the internal
surface of the fitting.
5. Insert the pipe end into the socket of the fitting and push it in up to the mark.
6. Remove the excess solvent cement and hold the joint firmly in position for 30seconds to dry. Gluing should
be avoided in a rainy or foggy weather.
The other method of jointing shall be rubber rings. The material of rubber ring should conform to IS 5382-1969.The
ring is housed in groove formed in a plastic or metallic housing. The rubber is compressed and makes a seal
between the pipe and housing. Lubricating paste should be applied before compressing the rubber. Where natural
rubber rings are used, mineral oil or petrol or grease should be used. Joining of UPVC pipes shall be made means of
solvent cement for horizontal lines and by rubber ring for vertical lines.
1.2.4 TESTING
PVC pipes and fittings shall be tested for water tightness in accordance with IS 13592. The openings of the pipes
shall be sealed for the section to be tested. The water pressure of 1mtr water column to be applied for a period of
15 minutes. The Authority’s Engineer shall examine carefully all the joints for leakage.
1.3.2 TESTING
The method which is commonly in use is filling the pipe with water, taking care to evacuate any entrapped air and
slowly raising the system to the test pressure. The water pressure of 1mtr water column to be applied for a period
of 15 minutes.
inches mm mm kg. mm mm
2 50 3.5 8.5 73 25
3 75 3.5 12.7 99 25
4 100 4.0 19.2 126 25
6 150 5.0 35.5 178 38
TOLERANCES
Tolerances on the external diameter of the barrel as mentioned below. The internal diameter of the socket and
the depth of socket shall be as follows:
Dimension Nominal diameter mm Tolerance mm
External 50, 57 + 3.0
Diameter in barrel 100 + 3.5
150 + 4.0
Closing the Ends of Pipe to Prevent Entry of Foreign Materials While Laying Pipe
Every precaution shall be taken to prevent foreign material entering the pipe while it is being placed in the line. If
the pipe laying team cannot put the pipe into the trench and in place without getting earth into it, the Engineer in
charge may order a heavy tightly woven canvas bag of suitable size be placed over each end and left there until the
connection is to be made to the adjacent pipe that before lowering the pipe into the trench. During laying
operations, no debris, tools, clothing or any other material shall be placed in the pipe. After laying and jointing of a
reach is completed the two free ends shall be kept closed to prevent entry of foreign materials, rodents and other
animals.
Cutting of Pipe
The cutting of pipe for inserting fittings or closure pieces shall be done in a neat and good workmanship without
any damage to the pipe so as to leave a smooth end at right angles to the axis of the pipe. For this purpose use of a
pipe cutter is recommended. Pipe cutting machines are recommended for large dia of pipes. When pipe-cutting
machines are not available for cutting pipes of large diameters, the electric arc cutting method may be permitted
using carbon or steel rods.
Only qualified and experienced workmen shall be employed on this work. When the pipe-cutting machine is not
available and the site conditions do not permit pipe cutting by machine, the pipe can be cut using a chisel. Flame
cutting of pipes by means of ox-acetylene torches shall not be allowed.
1.4.2 Testing
The method which is commonly in use is filling the pipe with water, taking care to evacuate any entrapped air and
slowly raising the system to the test pressure. The pressure of 1mtr water column to be applied for a period of 60
minutes.
b. Gully trap and Chamber: Shall be recorded between socket pipe near gully trap and inside of chamber.
The pipes covered in this standard are not meant for potable water applications. The dimensions are grouped into
two sections Section A & B. Section A covers dimensions of straight pipes and all such fittings which normally from
part of pipeline and which are subjected to same conditions. Section B includes dimensions of fittings, which are
commonly used but do not form part of the normal pipeline.
1.8.2 Laying
The pipes shall be carefully laid to the levels and gradients shown in the plans and sections by making use of sight
rails and boning rod and socket up the gradient. The pipes crossing the road shall be encased in Plain Cement
Concrete of 1:3:6 to the required depth as per the drawings and bill of quantities. The pipes laid in the soil shall be
enclosed with selected sand filling as per the bill of quantities.
1.8.3 Jointing
Hemp rope socked in neat cement slurry shall be passed round the joint and inserted in it by means of caulking
tool. More skins of yarn shall be added and well rammed. Cement mortar with one part of cement and one part of
sand with minimum water content, but on no account soft or sloppy, shall be carefully inserted by hand into the
1.8.4 Curing
The joint shall be cured at least for seven days.
1.8.5 Testing
As per IS 4127 – 1983 – code of practice for laying of glazed stoneware pipes, the pipelines and fittings shall be
subjected to a test pressure of at least 2.5 m head of water at the highest point of section under test. This pressure
shall be maintained for not less than 30 minutes. The contractor shall also carry out the smoke test for the drains
and sewers. Any leakage will be visible & the defective part should be cut out and made good.
1.1 General
All fixtures shall be fixed in a neat workman like manner true to line and as recommended by the manufacturer or
shown in the drawings. Care shall be taken to fix all fixtures, brackets and accessories by proper wooden cleats, rawl
plugs, bolts and nuts.
Care shall be taken in fixing all approved chromium plated (CP) single lever fixtures and accessories so as not to leave
any tool marks or damages on the finish. All such fixtures shall be tightened with fixed spanners. Use of `Stiltson' type
pipe wrenches with toothed jaws shall not be allowed.
All fixtures shall be thoroughly tested after connecting the drainage and water supply system. All fixtures shall be
thoroughly finished and any leakage in piping valves and waste fittings corrected to the complete satisfaction of the
Consultant/Engineer.
Upon completion of the work, all labels, stickers, plasters, etc. shall be removed from the fixtures and all fixtures shall
be cleaned with soap and water so as to present a neat and clean toilet.
1. 2 Eu r op e an T yp e Wa t er C lo s et
The closet shall be white or colored as per BOQ and made of vitreous China and shall be of the best quality
manufactured by an approved firm, and fixed by approved means. It shall have 100 mm dia `P` or `S` trap depending
on the location of water closets and soil stacks with effective seal. The water volume shall be 3 and 6 litres per flush
or 2 and 4 litres per flush. Each closet shall be provided with the following accessories:
a. Double flapped heavy urea formaldehyde seat cover of approved make quality and color with rubber buffers
and C.P. brass screws fixed to the pan.
b. Exposed ceramic cistern of approved design.
c. Cast-iron chair or rag bolt for wall hung type with C.P bolt & nut.
1. 3 Wa sh B as in s
They shall be white or colored as per BOQ and of vitreous China with best quality manufactured by an approved firm
and size as specified. Oval/circular wash basins shall be supported on a RC counter with necessary steel
reinforcement and rectangular wash basins with or without pedestals shall be supported by a pair of rag bolts of
approved design. The washbasin shall be circular or oval shape below or above counter or rectangular with or without
pedestal type as specified in Schedule of Quantities. The basin shall be provided with waste coupling, bottle trap,
angle cocks, pillar cock/ basin mixer, connecting pipes and other accessories. The flow rate of pillar cock or basin
mixer shall be less than 2 liters per minute at 60 psi pressure.
1. 4 Sin k
They shall be Stainless steel of AISI 304 -18/8 grade and shall be supported on counter. Each sink shall be provided
with 40 mm CP waste coupling, CP bottle trap, Table/wall mounted sink cock/mixer, angle cock and other accessories.
1. 5 He al th F au ce t
These shall be of brass CP .The make and model shall be as specified in the BOQ. These shall be fixed by means of
stainless steel counter sunk screws to wooden/ plastic cleats firmly embedded in the wall.
15 mm CP health faucet with 1.0m long flexible tube with end nuts & Hook.
1 No 15mm CP brass angular stop cock with wall flange
Hook with CP brass counter sunk screws.
2.1 Urinal
Urinal shall be back inlet type, white colored and of vitreous China with best quality manufactured by an approved
firm. The urinal shall be fixed with hangers and brackets. The urinal shall be provided with auto flush system with
sensor, solenoid valve / pneumatic push cock / angle valve etc., complete. Make and model shall be as specified in
the BOQ. The complete set shall comprise of the following.
Urinal with auto flush system along with battery / electrically operated solenoid valve / with push cock.
Fixing brackets,
32mm CP Bottle Trap, dome type grating, spreader etc., if the specified model is not having in-built units
as indicated above the same shall be part of the scope of work.
CP wall flanges (if required).
2. 3 B id et
The bidet shall be white or colored as per BOQ and made of vitreous China and shall be of the best quality
manufactured by an approved firm, and fixed by approved means. It shall have 100 mm dia `P` or `S` trap depending
on the location of bidet and soil stacks with effective seal. Bidet shall be provided with its fittings, seat cover, CI
bracket/rack bolt for support,15mm CP bidet cock with connection to spray outlet,15mm CP angle cock , CP bolts and
nuts with all the arrangements of approved make.
1.1 General
1.1.1 In brief scope of work involves following
Tapping of water from existing lines
Puddles, piping for Sump and OHT
Water lines within toilet, pantry, shaft, terrace etc
Isolation valves, Pressure regulating valves, brackets and other accessories
1.1.2 Manuals
Three sets of all manuals for the systems shall be submitted to the client. This shall include instruction and
maintenance manuals.
1.1.3 As-built Drawing
As built drawings as specified in the contract shall be submitted to the client on completion of work.
Drawing shall clearly show pipe routes, component details including
1.1.4 Training
It is the responsibility of the Contractor to train the Owner’s personnel in the operation and maintenance
of the system.
The covers and frames shall be coated with a black bituminous composition. The coating shall be smooth
and tenacious. It shall not flow when exposed to a temperature of 63° C and shall not brittle as to chip off
at a temperature of 0° C.
Approx. nos. of joints which can be 200 180 150 Nos 130 Nos 100 Nos 70
made per litre of solvent cement. Nos Nos
1.6.1 General
This section deals with different type of valves like butterfly valves, gate valves, ball valves, check valves, balancing
valves and Strainers and pressure gauges. The contractor shall refer to the approved make of materials specified
in the document & relevant drawings.
Valves shall be provided on branch pipe connections to mains and at connection to equipment where indicated.
All valves are to be located for easy access. All valves shall be supported wherever necessary with MS brackets.
Valves shall comply with IS 780 (Class I) for C.I sluice valves and IS 778 for G.M valves and tested.
Pressure gauges shall have outer diameter not less than 115mm with 10mm BSP full thread, brass body siphon
and gauge cock of size10mm. Dia l ga u g e s sh al l h a v e adequate response for the pressures encountered
within the specified (Range 0-15Kg/sq.cm).
1. 6. 2 Va l ve s
All valves (gate, ball, check, safety) shall be of brass suitable for the particular service as specified. All valves shall
be of the particular duty and design as specified. Valves shall either be of screwed type or flanged type, as
specified, with suitable flanges and non-corrosive bolts and gaskets. Tail pieces as required shall be supplied along
with valves. Gate, ball and check valves shall conform to Indian Standard IS: 776 and non-return valves and swing
check type reflux to IS: 5312.
d. Flap Type – Non return valve 40 mm and above Cast Iron Flanged
1. 6. 3 Fl an ge s an d Un io n s
Sufficient number of flanges and unions shall be provided as required to facilitate maintenance work after the
piping is installed. Mild steel flanges shall be used for pipes. The flanges shall be connected to the pipeline by
screwing or welding depending on the requirement. The flanges shall conform to the relevant ASTM standard for
the particular material used for its manufacture. The flanges shall also conform to IS 5211.
1. 6. 4 R el i ef Ven ts
Drainage systems, especially those in tall buildings, are frequently found to develop extremely high and
objectionable pneumatic effects in several specific portions of such piping. Special air pressure relief vents are
recommended to control, within tolerable limits.
The air pressure relief vent ,at least one-half the diameter of the building drain , should be provided at the top of
vertical offset so as to supply such additional air to the drain as may be required by the sudden increase in liquid
velocity in the vertical offset Where a building trap or other sharp change in flow direction is provided in the
building drain downstream from the vertical offset ,an air pressure relief vent should be provided at the base of,
The recommended provision for soil and waste stacks more than ten stories in height is to provide a yoke relief
vent at each tenth story of the drainage stack, counting downward from the top story. The lower end of the yoke
relief vent should connect to the drainage stack by means of a Y located below the horizontal branch drain serving
fixtures in that story, and the upper end should connect to the vent stack by means of a T or inverted Y located at
least 3 ft (0.900m) above the floor level as shown in the drawing.
1. 6. 5 In st a l lat io n o f V al ve s
Valves should be installed in true tolerance of +/-5mm with respect to the center line of the pipe. Where threaded
joints are encountered the threads should be initially sealed with PVC tape to avoid leakage due to improper
tightening and leakage from threading.
Proper care has to be taken in welded installation so that the centreline of valve should not deviate from the pipe
causing uneven load on the pipe and further stress during its operation. The welding should be done only after
proper inspection of the joint by the Authority’s Engineer in the tacked position of the joint.
Before putting the line in operative mode the valves should be checked for free and easy operation of the hand
wheel. Any burrs or foreign materials should be removed by flushing before final operation so that no choking in
the valves should occur which might damage the valve seat.
1.7 PUMPS
1.7.1 Submersible- Mono block Pump
Supply, testing & commissioning of Horizontal Single/ Multi- stage submersible pump suitable for pumping clean,
less viscous, non-aggressive liquids without solid particles or fibre. Pumps are fitted with standard & approved
motor. Impeller & other parts of pump are made of SS304 with 3-phase motor, sand shield, liquid-lubricated
bearings and pressure equalizing diaphragm. Pump Enclosure class (IEC 34-5):IP58. Pumps should contain integral
suction strainer & fitted with priming mechanism. Motor parts are CED coated, fitted with carbon bushes. Double
lip Seal back to back to arrangement to ensure no water leakage inside the motor. Motor should be fitted with
mechanical seal & withstand upto 6 kN having 4 SS segments and carbon thrust pads. Pumps are provided with
stop ring. Motors should be locally rewindable. Motor should capable of good starting torque and low starting
current. Pumps shall be of NEMA with Standard AISI 416 Stainless steel shaft Rubber O-ring for all fasteners. All
bearing should be water lubricated and square shape to enabling sand particular from the pump. At the delivery of
the pump each pump shall be fitted with a NRV & a valve of appropriate size & make of components shall be as per
approved list. The pump shall be placed in a pump pit of adequate size such that the minimum submergence level
is maintained at all times. Dry run protection, overload trip, shall be provided for each pump system. The pump
shall be provided with a chain/ guide rope to lift the same. The pump shall be placed such that dust particles, etc
do not enter the pump impeller & damage the same. A min clear ht of 100 mm shall be provided at the base of the
pump to avoid dust particles entering the pump. The pump shall work with a min motor efficiency of 55-80%.
Motor should be suitable for horizontal installation. Operating voltage 220 + 10% -15% for single phase and 415+
10% -15% for three phases.
1.7.5 Pump
The pumps shall be of the vertical multi-stage centrifugal design. The pump suction/discharge chamber
(base) shall be in CI or SS as per requirement. Motors tool and pump shaft coupling shall be constructed of
cast iron. The impellers, pump shaft, diffuser chambers, outer discharge sleeve, impeller seal rings, and seal
ring retainers shall be constructed of stainless steel. Optional materials for the suction/discharge chamber
and motor stool liner shall be stainless steel.
The pump impellers shall be secured directly to the pump shaft by means of a spine shaft arrangement for
model of the lower sizes, and the pump impellers shall be secured to the shaft by a split cone and nut for
higher sizes. The shaft journal and chamber bearings shall be Tungsten Carbide and Ceramic/ Bronze. All
pumps shall be equipped with a high temperature cartridge mechanical seal assembly with Tungsten
Carbide/ Carbon or Tungsten Carbide seal faces mounted in stainless steel components. The shaft seal shall
be of the cartridge design; the larger pumps (with 7.5 Kw and above motors) shall be designed so that the
cartridge seal may be replaced without removing the motors.
The entire packaged pumping system shall be mounted on a Hot Dipped Galvanized MS or SS fabricated skid. The
control cabinet shall be mounted in one of the following ways depending on the size of the cabinet.
1. On a Hot Dipped GI or MS fabricated with powder coated control cabinet stand attached to the system
skid
2. On a Hot Dipped GI or MS fabricated with powder coated skid, separate from the main system skid
3. Floor mounted control cabinet with plinth.
1.7.10 Plumbing
The suction and discharge manifolds shall be fabricated of Hot Dipped Galvanized MS or SS. Both
manifolds shall be designed to attach to the system piping at either end of the manifold. Delivery
manifold shall include a pressure gauge. The suction manifold shall have as standard a pressure switch or
pressure sensor to detect low suction pressure or a float switch to prevent dry running. The discharge
manifold shall include a pressure transducer with a 4-20mA output. The pressure transducer shall be
factory installed and wired.
Isolation valves shall be installed on the suction and discharge of each pump. A check valve shall be
installed on the discharge of each pump (optional on the suction side for suction lift applications).
The system shall include a diaphragm type pressure tank sized by the system manufacturer. All systems
shall be factory tested for performance and hydrostatic tested to at least 1.5 times the system working
1.7.11 Hydro pneumatic System Specification for Pressurised Water Boosting System Using Variable Speed Drive
Supply of booster set consisting upto a maximum of six identical vertical multistage in - line pumps in cast
iron GG20 pump head & base c/w cataphoresis coating, cartridge type mechanical seal, all internals in AISI
304 stainless steel, mounted on common galvanized steel base frame and controlled by variable
frequency drives & a logic controller, which have features like application optimized software, regular
optimization of operating conditions and read-out of operating data, Bus Communication possibility,
Digital remote-control functions, pump & system monitoring functions, Display, Alarm & signal functions
and clock programs. Panel to have 2x24 character LCD display, green & red LED’s for operating & fault
indication, potential free contacts for remote interfacing, and an inbuilt lifetime battery backup for all
clock functions.
Booster set should include non return valves, isolating valves, pressure transmitter on discharge side, non-
return valve, and pressure gauge. Booster set should ensure constant pressure on discharge side through
continuously variable adjustment of speed of one of the pumps, while the remaining pumps in operation
are running on mains operating at full speed to bring about pump performance to meet consumption
levels. Also provision should be made for alternate change over between pumps in operation once every
24 hours & frequency converter operation of pumps by rotation - all should be built in, cyclically, in the
controls to ensure equal wear and tear of all pumps in the booster set. Means should be provided for
friction loss compensation for increased consumption rate.
Booster set should incorporate following “Power saving features” as standard.
Selection of 3 basis set points for pressure relative to time.
Pipe compensation i.e. Change of set point depending on water consumption.
Compulsory change of staring of sequence, i.e. Equal operating time for pump, both for frequency control
and ON/OFF regulation.
Inputs and outputs for external communication.
A small sized pressure tank, (accumulator) to provide for reducing impact of water hammer and minimize
short cycling of the pumps. The accumulators are piped to allow for in service maintenance.
Valves of an approved make shall be provided as near to the tank as practicable on every outlet pipe from
the storage tank except the overflow pipe. Overflow and vent pipes shall terminate with mosquito proof
grating.
The overflow pipe shall be so placed to allow the discharge of water being readily seen, except for flushing
water tank, in-case of which the overflow should be connected to waste pipe. The overflow pipe shall be of
size as indicated. A stop valve shall also be provided in the inlet water connection to the tank.
SCOPE
This specification covers requirements, test methods, and methods of marking for chlorinated poly (vinyl chloride)
plastic hot-and cold-water distribution system components made in one standard dimension ratio and intended
0 0
for water service up to and including 180 F (82 C). These components comprise pipe and tubing, socket-type
fittings, street fittings, plastic-to-metal transition fittings, solvent cements, and adhesives. Requirements and
methods of test are included for materials, workmanship, dimensions and tolerances, hydrostatic sustained
pressure strength, and thermo-cycling resistance. The components covered by this specification are intended for
use in residential and commercial, hot and cold, potable water distribution systems.
The values stated in either inch-pound or SI units are to be regarded separately as standard. Within the text, SI
units are shown in brackets. The values stated in each system are not exact equivalents therefore each system
shall be used independently of the other. Combining values from the two systems may result in non-conformance
with the specification.
Materials
Basic Materials Description—Chlorinated poly (vinyl chloride) plastics used to make pipe, tubing, and
fittings meeting the requirements of this specification are categorized by two criteria; namely, basic short-
term properties, and long-term hydrostatic strength.
Basic Short-Term Properties—This specification covers CPVC 41 pipe, tubing, and fittings made from
plastic materials meeting the mechanical strength, heat resistance, flammability, and chemical resistance
requirements for CPVC 23447-B in Specification D 1784.
CPVC 23447-B was formerly designated as CPVC Type IV Grade 1, and is herein designated as CPVC 41.
This is also used in marking pipe, tubing, or fittings.
Long-Term Hydrostatic Strength—This specification covers CPVC 41 pipe, tubing, and fittings which are
further defined by hydrostatic design stress as CPVC 4120. Pipe and tubing are so defined on the basis of
0
long-term hydrostatic strength tests and are made from compounds having an established 180°F [82 C]
hydrostatic design stress of 500 psi [3.45 MPa] or greater in accordance with Appendix XI and Test
Method D 2837. Fittings are so defined by hydrostatic sustained pressure tests on fitting assemblies,
required by this specification and based on the hydrostatic strength of the corresponding pipe or tubing.
No hydrostatic design stress, as such, exists for finings until such time as long-term hydrostatic strength
test methods for fittings are developed.
Classification
Pipe, Tubing, and Fittings—This specification classifies CPVC 4120 pipe, tubing, and fittings by a single standard
0
dimension ratio which shall be SDR II, by a maximum continuous use temperature which shall be 1800F [82 C] and
by nominal pipe or tubing diameters from 3/8 in.[9.5 mm] through 2 in. [50 mm].
Plastic-to-Metal Transition Finings—This specification classifies CPVC plastic-to-metal transition fittings intended
0
for use up to and including 1800F [82 C] as CPVC-I800F on the basis of resistance to failure by thermo-cycling.
Solvent Cements and Adhesives— this specification classifies solvent cements and adhesives meeting the require-
ments contained herein as CPVC Solvent Cement or CPVC Adhesive.
General
Wall Minimums—Table 1 and Table 2 show wall thickness minimums. Calculated SDR 11 tubing wall thick-
nesses that fall below 0.068 in. [1.73 mm] shall be arbitrarily increased to that value. Calculated SDR 11
fitting wall thicknesses that fall below 0.102 in. [2.59 mm] for the fitting socket bottom, or 0.I28 in. [3.25
mm] for the fitting body, shall be arbitrarily increased to these values.
Interference Fit—the diameters and tolerances in Table I and Table 2 provide for socket-type joints having
an interference fit based on the major diameter of pipe and tubing having a degree of out-of-roundness.
This does not necessarily imply interference based on the minor diameter of the pipe or tubing.
Out-of Roundness—the maximum out-of-roundness requirements shown in Table 1 and Table 2 for pipe,
tubing, and finings apply to the average measured diameter.
General—CPVC solvent cements, for use in CPVC 41, plastic-to-plastic, socket-type joints shall meet the re-
quirements set forth in Specification F 493.
Hydrostatic Burst Strength—2-in. [50-mm] CPVC solvent cement joints shall exceed the minimum hydrostatic burst
strength requirements given in Table 6 after a maximum drying interval of 2 h when tested in accordance with
10.1.3, Failure to pass the burst requirement at either temperature is cause for rejection.
CPVC SCHEDULE 40 PRESSURE PIPES AND FITTINGS FOR WATER SUPPLY AS PER ASTM F- 441
Outside Diameters and Wall Thicknesses For CPVC 4120, SDR 11 Plastic Pipe As Per ASTM D-2846
Handling
The pipe should be handled with reasonable care. Thermoplastic pipe is much lighter weight than the metal pipe.
There is sometimes a tendency to throw it around. This should be avoided. The pipe should never be dragged or
pushed from a truck bed. Pallets for pipe should be removed with a fork lift. Loose pipe can be rolled down
timbers, as long as the pieces do not fall on each other or on any hard or uneven surface. In all cases, severe
contact with any sharp objects (rocks, angle irons, forks on forklifts, etc.) should be avoided.
Storing
If possible, pipe should be stored inside. When this is not possible, the pipe should be stored on level ground,
which is dry and free from sharp objects. If different schedules of pipe are stacked together, the pipe with the
thickest walls should be at the bottom.
The pipe should be protected from the sun and be in an area with proper ventilation. This will lessen the effects of
ultraviolet rays and help prevent heat build-up. If the pipe is stored in racks, it should be continuously supported
along its length. If this is not possible, the spacing of the supports should not exceed three feet (3').
When storage temperatures are below 32°F, extra care should be taken when handling the pipe. This will help
prevent any problems, which could be caused by the slightly lower impact strength of PVC and CPVC pipe at
temperatures below freezing.
The sealed chamber type shall be installed upstream of flush valves or quick closing valves. The size to be as
recommended by manufacturer’s recommendation submitted for approval.
Body : CI
Pressure rating : PN 10
Type : Screwed end
Strainer : Inbuilt
Gasket : Synthetic rubber as per IS 638 type B
Ball : Rubber coated wooden valve
Air release : Automatic
Bolt & nut : Caron steel BS 916.
1. 1. 1 LO C AT IO N AN D SI ZE S
The size indicated in the drawings shall be the internal size of chamber. Unless otherwise specified, manholes and
inspection chambers are provided at all changes of direction of drains and where branch drain meets the main
drain. Chambers shall be of such size as to allow necessary examination and clearance of drains. The minimum
internal sizes shall be taken as per detail drawings; standards specified and local bye laws if any. In the absence
of local byelaws, the requirements stipulated in IS 4111 (Part I) Code of Practice for Ancillary Structures on
Sewage System shall be followed. The work shall be done strictly as per standard drawings and the following
specifications:
1. 1. 2 B E D CO NCR E T E
Bed concrete shall be in 1:4:8 cement concrete 150 mm thick for inspection chambers, 200 mm for depths upto 2
m and 250 mm for greater depths in case of manholes.
1. 1. 3 B R IC K M A S ONR Y
Brick work shall be with best quality table moulded bricks in 1:5 cement mortar as per specification for brick masonry.
The thickness of masonry shall be as per Bill of Quantities.
1. 1. 4 PL A S TE R
Inside walls of chambers/manholes shall be plastered with 15mm thick cement plaster 1:3 and finished smooth with a
floating coat of neat cement. External walls shall be plastered in CM 1:3 mixed with waterproofing material and
sponge finished.
1. 1. 5 B EN C HIN G
Channels and benching shall be done in cement concrete 1:3:6 rendered smooth with neat cement. The following
sizes of channels for the bench shall be adopted:
1. 1. 6 CH AM B E R/M AN H OL E C OV ER S
Covers shall be of heavy duty cast iron or fiber reinforced cement concrete as per material specification with lifting
hooks as per IS 1726 - 1974 and as per the details given in the drawings and fixed on CI frame or cement concrete
embedded in concrete. Covers placed on the frames shall be airtight. The weight of frame and cover shall be as per
bill of quantities.
1. 1. 7 ST E P S
PVC steps shall be provided wherever the depth of the manhole/chamber is more than 1.2M. Steps shall be arranged
in a staggered manner as per drawings.
1. 1. 8 DR O P C ONN E CT I O NS
In case the difference in invert levels between the main drain and the branch line requires a drop more than 600 mm,
a drop connection should be provided with a PVC fourway junction, fixed at right angles to the drop pipe at the level
where the branch pipe enters the manhole. Access for cleaning the bend should be provided at finished ground level
1. 1. 9 GU LL Y TR A P C H A M B ER S
14 Manhole frame & cover in Fiber reinforced Southern Concrete Industries / Approved Equivalent
concrete
15 Manhole PVC steps Southern Concrete Industries / Approved Equivalent
NOTE : 1) Quote should be for the first preference make only, if not available then second preference can be quoted
same has to be mentioned in the BOQ.
2) All bought-out items shall be of makes approved by Architect, Consultants & Equivalent makes to
be got approved by Architect / Consultant / Owner prior to placement of order.
1. All items of work mentioned in the Schedule of Quantities shall be read and executed strictly in accordance
with the description of the item in the Schedule of Quantities & read in conjunction with the appropriate IS
and conditions of Contract.
IN D EX
B A SI C EL E CT RI CA L R E Q U IR EM EN T S
S WI TC H B O AR D S
PO W ER F A CT OR CO RR EC TI ON
M E D IUM V O LT AG E C AB L E S
WI RIN G D E VI C ES
B U SB A R T RU N KIN G
LUM IN A IR E S
INV E RT OR U P S S Y ST E M
E AR T HIN G
LI GH TN IN G P RO T EC T ION
RE CO M M EN D E D M A K E OF M A T ER I AL S
1.0 General
1.1 Scope
The scope of work covers complete electrical installation system for all buildings including but not limited
to:
Supply, storage, installation, testing and commissioning of all equipment, components,
accessories, labour, tools and tackles required for the operation of the buildings to the extent
specified and detailed on the drawings and specifications.
All Civil works in connection with the Electrical Installation including supply, laying and fixing of
necessary inserts, hooks, brackets and sleeves etc.
Any work which can be reasonably inferred as necessary for the safe, satisfactory operation
whether such work is specified or shown on the drawings or not.
Arranging permanent supply including necessary submissions of drawings as required to the
supply authorities and arranging inspections and obtaining necessary approvals of all the
concerned authorities.
In general, the materials, equipment and workmanship not covered by the above shall conform to the
latest Indian Standards. All bolts and nuts used shall be metric size with corrosion protection suitable for
the location.
1.4 Documentation
The indication and/or description of an item on the drawings or in the Specifications, unless
otherwise specifically stated, implies an instruction to supply and fix such items.
Notes on drawings referring to individual items of work generally take precedence over
specifications, however all discrepancies shall be referred to the Consultant / Developer before
ordering materials or commencing work.
Drawings show general run of cables, approximate locations of outlets and equipment, utility
symbols and schematic diagrams of no dimensional significance. Refer to the Architectural
drawings for locations and also obtain approval from the Consultant / Developer wherever
2.0 Submissions
2.1 Shop Drawings
Shop drawings shall be provided of the Main and Sub-Main Switchboards, Distribution Boards, Cable
Trays, Reactive Power Compensation Panel, and any other switchboards and panels, wherever applicable
and approval shall be obtained from the Consultant / Developer before commencing fabrication or
procurement.
Any equipment or switchboard manufactured without the written consent of the Consultant / Developer
prior to the approval drawings shall be liable for rejection.
3.0 Foreman/Supervisor
3.1 Qualifications
The Electrical Contractor shall employ a competent, licensed qualified full time electrical
foreman/supervisor to direct the work of electrical installations in accordance with the Drawings and
Specifications. Required 5 years of documented experience at least.
3.2 Responsibility
The foreman/supervisor shall be available at all times on the site to receive instructions from the
Consultant / Developer in the day to day activities throughout the duration of the work. The foreman/
supervisor shall correlate the progress of the work in conjunction with all the relevant requirements of
the Supply Authority. The skilled workers employed for the work shall have the requisite qualifications
and shall possess competency certificates from the Electrical Inspectorate of Local Administration.
4.4 Tests
The Consultant / Developer shall have full powers to require the materials or works to be tested
by an independent agency at the Contractor's expense in order to establish their soundness and
adequacy.
The Contractor shall notify the Consultant / Developer at least 7 working days before testing of
each system. The Consultant / Developer reserve the right to be present when such tests are
being made.
If the Electrical Inspectorate requires manufacturer's test reports for HT cables, HT switch gear,
transformers or any other equipment used in the project, the Contractor shall obtain such
approvals at no extra cost to the Developer. Such approved reports shall be handed over to the
Consultant / Developer.
Calibration certificates shall be obtained from the Meter and Relay Testing Department of the
Electricity Board for all relays and meters used in the project at no extra cost to the Developer.
S WI TC H B O AR D S
1.2 General
Distribution boards shall be suitable for 433 volts, 3 phase AC supply and 240 volts single phase AC supply,
as required. Distribution boards shall generally conform to IS:2675 or BS:214.
1.10 Terminals
Distribution Boards shall be provided with an approved make terminal block of adequate size to receive
mains and outgoing circuits. The location of the terminal block shall be so located that crowding of wires
in the proximity of live parts is avoided. A neutral link having a rating equal to that of phase bus shall also
be provided.
1.11 Directory
Distribution boards shall be provided with a directory indicating the area or loads served by each circuit
breaker, the rating of breakers, size of conductors and other components as determined necessary for
clear identification of the function and operation of the distribution board.
Indication labels shall be machine engraved on laminated plastic and attached with approved adhesive or
mechanical fasteners. The font shall be ARIAL and sized to suit the application. The minimum font size
shall be 3.5mm. Hand painted directory or text is not acceptable.
The equipment shall be designed for operation in high ambient temperature and high humidity tropical
atmospheric conditions. Means shall be provided to facilitate ease of inspection, cleaning and repairs for
use in installations where continuity of operation is of prime importance.
2.2 Standards
The equipment listed below shall conform to tie requirements shown:
The height of the panel shall not be more than 2200 mm unless otherwise specified and maximum height
of switch operating handle shall not be more than 1800mm from FFL. The total depth of the panel shall be
adequate to cater for proper cabling space.
Doors shall be of minimum 14 gauge sheet steel and covers and partitions of 160 sheet steel. All sheet
steel work forming the exterior of switchboards shall be smoothly finished, levelled and free from flaws.
The corners shall be rounded.
The Components in the switchboards shall be so arranged as to facilitate ease of operation and
maintenance and at the same time to ensure necessary degree of safety.
Components forming part of the switchboards shall have the following minimum clearances:
a. Between phases 25 mm
b. Between phases and neutral 25 mm
c. Between phases and earth 25 mm
d. Between neutral and earth 19 mm
When, for any reason, the above clearances are not available, suitable insulation barrier/shielding shall be
provided. Clearances shall be maintained during normal service conditions.
Creepage distances shall comply to those specified in relevant standards. All insulating material used in
the construction of the equipment shall be of non-hygroscopic material treated to withstand the effects
of high humidity, high temperature and tropical ambient service conditions.
Functional units such as circuit breakers, MCCBs, etc. shall be arranged in multi-tier formation except that
not more than two air circuit breakers shall be housed in a single vertical section.
Metallic and/or insulated shrouding shall be provided within vertical sections and between adjacent
sections to ensure prevention of accidental contact with:
All covers providing access to live power equipment or circuits shall be provided with tool operated
fasteners to prevent unauthorized access. Provision shall be made for permanently earthing the frames
and other metal parts of the switch gear by two independent distinct connections. Only CRCA steel sheets
shall be used for fabricating the cubicle. Thickness tolerance for sheets shall be as applicable in relevant
IS.
3.2 CONSTRUCTION
The Breaker shall be suitable for rear and vertical mounting and line load reversibility without duration.
The operating mechanism shall be designed such that the handle can only be in `OFF' position if the Main
contacts are actually separated and vice versa. It shall confirm to Isolation as per standard.
The Control Unit shall be suitable to provide short circuit, overload and earth fault protection (wherever
specified). The Control Unit shall not be a peak sensing device and shall measure the true RMS values to
make the measurement free from the influence of harmonics. It shall have thermal memory.
3.4 PROTECTIONS
The overload settings shall be adjustable from 0.4 to 1.0 times the nominal rating (In) and shall have time
delay. Short circuit protection shall be from 3 to 9 times the rated current (Ir) with time delay.
Instantaneous protection shall be settable upto 15 times nominal rating. Earth fault Protection (wherever
specified) from 0.2 to 0.7 time’s nominal current (In) with time delay.
All breakers shall have segregated Led fault Indications & mP failure indication.
3.5 ACCESSORIES
All ACB feeders shall have metering and local display features viz. Ammeter, Voltmeter,
frequency, KVA, KW, KWAh, p.f, maximum demand. It shall be possible via COM (485 port) to
transmit the protection & metering settings to PC.
ACB shall be provided with following accessories, in addition to the item specified in Bill of
Quantities. Further these devices shall be fit-table at site accessible from the top and front and
shall be common for all ratings.
The connection for the auxiliary shall be accessible from the front.
All ACBs shall have Under Voltage trip, shunt trip, auxiliary switches with NO. + NC. In EDO type,
closing coil shall be provided.
3.6 INTERLOCKING
ACBs shall be provided with the following interlocking devices for interlocking the door of a
switchboard:
Handle interlock to prevent unnecessary manipulations of the breaker.
Door interlock to prevent door being opened when breaker is ON position.
Defeat interlocking device to open the door even if the breaker is in ON position.
All Breakers shall have adjustable overload and short circuit settings.
Overload – adjustable 0.4 to 1 times nominal rating(In)
Short-circuit – adjustable fro 2 – 9 times rated current(Ir)
Earthfault (wherever specified) – adjustable setting with time delay.
All MCCB feeders shall have monitoring & display feature viz. Ammeter, Voltmeter, frequency, KVA, KW,
KWAh, p.f, THD with COMM port.
4.2 Accessories
MCCB shall be designed to have following accessories and it shall be fittable at site.
a. Under voltage trip
b. Shunt trip
c. Alarm switch
d. Auxiliary switch
e. Remote operation using motor mechanism with facility of using the same in auto / manual mode.
4.3 Interlocking
MCCB shall be provided with following interlocking devices for interlocking the door of a switchboard.
a. Handle interlock to prevent unnecessary manipulations of the breaker.
b. Door interlock to prevent door being opened when breaker is in ON position.
In addition to the above, and other features indicated elsewhere shall also be provided.
Typical Features for MCCB ABB Schneider Siemens
Upto 160A rating T2N MG-compact NS VL-160X
Service Breaking Capacity(KA) 35kA 35kA 40kA
Type of Release TM TM TM
Overload protection Adjustable Yes Yes Yes
Short circuit protection Fixed Yes Yes Yes
Instantaneous - - - -
Earth fault protection (add on
Adjustable Yes Yes Yes
module)
The Contactors shall be capable of withstanding breaking and making capacities per following:
--------------------------------------------------------------------------------------
AC3 Category AC4 category
--------------------------------------------------------------------------------------
Making Current 10 x Rated Current 12 x Rated Current
Breaking Current 08 x Rated Current 10 x Rated Current
---------------------------------------------------------------------------------------
o Contactors shall be capable of withstanding an impulse voltage of 8kV and have an insulation
voltage of 1000V.
o Contactors shall be suitable for copper termination with a maximum permissible temperature
rise of 65 Deg; C at the terminals with an ambient temperature of 50 Deg; C.
o The coils shall have three terminals and the insulation shall be of class H type.
o The auxiliary contact block shall have a switching capacity of 240V at 2A. Contactors shall have
one auxiliary in built and it shall be possible to have additional normally opened, normally closed
contacts in steps of two.
Line supply may be connected to either top or bottom terminals i.e. there shall be no line-load restriction.
Degree of protection, when the MCB is flush mounted, shall be IP40. MCB shall be supplied with clamping
terminals fully open. Contact closing shall be independent of the speed of the operator. The breaking
capacity of the MCB shall be 10kA. The MCB shall be capable of being used as Incomer Circuit Breaker and
shall be suitable for use as an isolator. In case of multiple MCBs in a single location (DB), it shall be
possible to remove any MCB without having to disturb other MCB's in the vicinity.
RCCB shall comply with IS 12640-1988/IEC 1008. The short circuit withstand of the RCCB without the
associated short circuit/overhead protection shall not be less than 3 kA. It shall be operationally
independent of line voltage. The sensitivity thresholds (30mA, 100mA, 300mA) shall be of non-user
adjustable type by construction.
Provide RCCB per 6 branch circuits for General Purpose (Normal Power) or when indicated.
No RCCB will be provided at UPS Boards.
All the Potential Transformers shall comply with the requirements of IS 3156 latest edition. All
PT's shall be resin cast type and shall have Voltage ratios, output and accuracy class as Specified
in Data Sheer.
All PT's shall be single phase, dry type suitable for mounting inside the panel or cubicles. Clamps,
brackets and supports required for the mounting shall be supplied along with PT.
Polarities and Terminal markings shall be clearly marked in all PT's. Name plate indicating,
voltage ratio, burden, accuracy class, type, serial number, make and model plus other related
data, shall be provided.
A common earth terminal for earthing of core, bolts, clamps (non current carrying metal parts)
etc., shall be provided.
All instruments and meters shall be enclosed in dust proof, moisture resistant black finished cases and
shall be suitable for tropical use. They shall be calibrated to read directly the primary quantities. They
shall be accurately adjusted and calibrated at Works and shall have means of calibration, check and
adjustment at site. Definition of various meters as follows:-
a. Power Qulaity meters needs Complete Electrical Data that includes Analyzer Harmonics, Voltage
Sags,Swells, Current Peaks, Vectorial Information on V and I etc.
b. Load Manager: It is derived from managerial terms that to have effective Control (Manual or
Automatic ) over electrical loads need to have comprehensive information.
c. Multi Function meter: A meter that Can Monitor Control and Communicate meter and expand to
Interface with External Environment like PC/PLC/DCS SCADA etc.
d. Load Monitor or Energy Analyzer: Like EYES is to human body , Digital meters is for Electrical Panels ,
here look at Individual Paramaters
e. Power & Energy meter is an Indication of Consumption it also needs to meter Show Work Done ,
need to Have Power and Energy
f. Multi Data Meter A single Instrument will Display Many Electrical Parameters
b. VAF POWER METER ( Used on Main outgoing Panels Located within Sub station) ( Equvalent
to New Horizon make model mdm)
1. METER TO DISPLAY SIMULTENOUSLY VOLTAGE CURRENT KILO WATT POWER FACTOR
AND FREQUENCY PHASE WISE.
2. high luminosity red led displays RMS measurement up to the 16th harmonic
3. Inputs: Voltage: 3 x 200 - 240 VAC Phase neutral ± 10% 50 / 60 Hz
4. Current from external CT 0 - 5 A Field Programmable CT ratio thru Dip Switches
5. Accuracy: 0.5% of reading on V and I. 1% of the reading on P.Auto Scale Change for
Linearity of accuracy (Number of scales: 1 voltage scale , 2 current scales)
6. Protection level: Front panel = IP40
7. Temperature range: -10°C +50°C Relative Humidity: max 90%. Condensation not
permitted.
8. Isolation: In accordance with group B VDE 0110 standards for 250 VAC rms operating
voltages
5.9.2 Energy meters with Power ( used in all panels where Loads are running 30 % of the utility Time of the
factory /Building ) (Equivalent to New Horizxon make model mico 3 )
A. Must Indicate kw and Kwh through Selectable Display Switch on LCD display
B. Inputs: Voltage: 250V from 20 to 800 Hz
C. Current: 5 A from 20 to 800 Hz with Field programmable Ct ratios
D. Input overload: Voltage: max.264 Vrms phase to neutral Current: max 20 Arms,
E. Automatic Scale Change on V and I for linearity of reading min scales: 2 current scales 1 voltage scale
and Auto offsetting of Errors for Consistent reading
F. Accuracy: Class 1 according to IEC1036 standards
G. IP rating : Instrument = IP20 Front panel = IP40
H. Temperature range: from -10°C to +40°C Relative humidity: R.H. max 90% Condensation: not
permitted
I. Isolation: in accordance with group B VDE 0110 standards for 250 VACrms operating voltages.
J. Output through RS 485 confirming to J MODBUS MODICON communication Protocol
5.9.3 Dual Energy meter (Used in Multi tenant Billing or Multi product Energy Accounting) - Equivalent to New
Horizon make model mico 3 2 T
A. Must Indicate kw and KWH of EB and Dg selectable through Separate Display Switch
B. Tariff Change to be imitated through Volt Free Contacts ( NO Aux or DG power will be available
C. Inputs: Voltage: 250V from 20 to 800 Hz
5.9.4 Energy Analyzer Used in Electrical Panels (Equivalent to New Horizxon make model PLUS 96)
1. To Display Voltage Current Frequency Active Power factor and kWh
2. LCD Display with Separate switch for Selecting the Required parameters
3. Inputs: Voltmetric: 500VAC 20-800 Hz Input impedance: 2 Mohm
4. Current 0-5 A from external CTs with Field Programmable CT ratio
5. Overload: V: max. 800 Vrms, A: max. 7 Arms
6. Connection: Three phase delta networks (3 phases without neutral wire) Three phase STAR
connection (3 phase + neutral )
7. Accuracy: ≤0,5% of the reading x V and I, 1% of the reading x P. as per IEC 1036
8. Automatic Scale Change on V and I for linearity of reading min scales: 2 current scales 1 voltage scale
and Auto offsetting of Errors for Consistent reading
9. Protection class: Front= IP40
10. Temperature range: -10°C + 50°C Relative humidity: RH: max. 90%. Condensation: not allowed.
11. Insulation: according VDE 0110, group C for rated voltages of 500 VAC rms.
12. Output through RS 485 confirming to J MODBUS MODICON communication Protocol
5.9.5 Load Manager /Multi Function meter used on All Transformer and Outgoing Panels (Equivalent to New
Horizxon make model FLASH NH )
1. To Display All Electrical parameter V,I,Hz,kw,kVA,kVAr , Energy (kwh kVAh,kVArh), Max Demand,
and Neutral Current
2. To Display Individual harmonics from 0 to 31 on V , I and KW with Indication of Direction of Harmonic
from load to Source or Vice versa
3. Accuracy Class 1 on energy complying with IEC EN 61036. Quadrants ........ 2 and 4 quadrant
measurement (programmable) with Auto Automatic Scale Change on V and I for linearity of reading
min scales: 2 current scales 1 voltage scale and Auto offsetting of Errors for Consistent reading
4. Standards - Safety: .....IEC EN 61010 class 2 – E.M.C.: ......IEC EN 61326-1A
5. Protection degree .......... IP51 on front panel.
6. OUTPUT through RS 485 confirming to J MODBUS MODICON communication Protocol or Output
thru RS 4*20mA
7. 2 Set Points as 2 digital outputs rated 27Vdc-27mA (DIN43864) with programmable functionality
(pulse output or alarm)
8. Galvanic Isolation on all inputs and outputs to Attunate RFI Disturbance
a) To Display All Electrical parameter V,I,Hz,kw,kVA,kVAr, Energy (kwh kVAh,kVArh), Max Demand and
Neutral Current
b) To Display Individual harmonics from 0 to 31 on V , I and KW with Indication of Direction of Harmonic
from load to Source or Vice versa
c) POWER QUALITY EVENTS (EN 50160 standards) Meter should detect and stores, with individual date-
time stamp several events giving an accurate monitoring of the power supply quality according to the
EN 50160 standards. It should store on 2 MB Flash memory
d) Voltage sags/dips , Temporary over voltage/swell and Temporary current peak and direction of flow
i.e. short duration events (1 cycle resolution) with registration of date-time, event type, phase
involved, duration in number of cycles and min/max parameter value attained during each event.
e) Under voltage/voltage interruption Over voltage and Over current and direction of flow i.e. medium
and long duration events with registration of event start-end date/time, event type, phase involved
and parameter min/max value attained during each event.
f) MIN. AND MAX. VALUE per Phase of V A KW and PF
g) LOAD PROFILES AND CONSUMPTION DATA on all Energy and MD parameters
h) HARMONICS SURVEYS to Cover Individual harmonics with the direction of Harmonic recorded with
date/time stamped sample of 42 default readings is automatically saved to the instruments'built-in
memory on a circular buffer (FIFO) covering a 10-day survey period with samples taken every 2
minutes and data organized in daily files.
i) Accuracy Class 1 on energy complying with IEC EN 61036. Quadrants ........ 2 and 4 quadrant
measurement (programmable) with Auto Automatic Scale Change on V and I for linearity of reading
min scales: 2 current scales 1 voltage scale and Auto offsetting of Errors for Consistent reading
j) Standards - Safety: ...............IEC EN 61010 class 2 – E.M.C.....................IEC EN 61326-1A
k) Protection degree .......... IP51 on front panel.
l) OUTPUT through RS 485 confirming to J MODBUS MODICON communication Protocol or Output
thru RS 4*20mA
m) 2 Set Points as 2 digital outputs rated 27Vdc-27mA (DIN43864) with programmable functionality
(pulse output or alarm)
n) Galvanic Isolation on all inputs and outputs to Attunate RFI Disturbance
5.9.7. TVSS
1.1 GENERAL
TVSS shall be as per IEEE standards & UL listed. The current rating of TVSS for different panels
shall be as specified below.
The TVSS shall be mounted in a separate chamber away from control components. The cable
length between bus & TVSS shall be less as much as possible.
Irrespective of TVSS rating a minimum of 10Sq.mm copper wire shall be used.
3.0 OPERATION
3.1 Controller Display and Keypad
A. A four line, 20 character LCD display and keypad shall be an integral part of the controller for viewing
all available data and setting desired operational parameters. Operational parameters shall also be
available for viewing and limited control through the serial communications input port. The following
parameters shall only be adjustable via DIP switches on the controller:
1. Nominal line voltage and frequency
2. Single or three phase sensing
3. Operating parameter protection
4. Transfer operating mode configuration (Open transition, Closed transition, or Delayed transition)
All instructions and controller settings shall be easily accessible, readable and accomplished without
the use of codes, calculations, or instruction manuals.
B. Repetitive accuracy of all settings shall be within ± 0.5% over an operating temperature range of -
20°C to 60°C.
C. Voltage and frequency settings shall be field adjustable in 1% increments either locally with the
display and keypad or remotely via serial communications port access.
D. The controller shall be capable (when activated by the keypad or through the serial port) of sensing
the phase rotation of both the normal and emergency sources. The source shall be considered
unacceptable if the phase rotation is not the preferred rotation selected (ABC or CBA).
The following features shall be built-in to the controller, but capable of being activated through
keypad programming or the serial port only when required by the user:
O. Communications Module - A full duplex RS485 interface shall be installed in the ATS controller to
enable serial communications. The serial communications shall be capable of a direct connect
or multi-drop configured network. This module shall allow for the seamless integration of existing or
new communication transfer devices. The serial communication interface shall be equal to ASCO
Accessory 72.
P. External DC Power Supply - An optional provision shall be available to connect an external 24 VDC
power supply to allow the LCD and the door mounted control indicators to remain functional when
both power sources are dead. This option shall be equivalent to ASCO accessory 1G.
Open contacts comprising rivets of pure silver. The contacts shall be able to make and carry 5 A and break
up one amp inductive loads at 250V DC.
5.14 Relays
All Relays shall conform to the requirement of IS : 3231/IS 8686 or other applicable approved standards
Relays
All AC Relays shall be suitable for operation at 50Hz. AC Voltage operated relays shall be suitable for 110v
3 Volts PT secondary and Current operated relays for 5Amp CT secondaries, as specified in this
specification. Voltage operated relays shall have adequate thermal capacity for continuous operation.
Auxiliary Relays and Timers shall have pairs of contacts as required to complete the scheme. Contacts
shall be silver faced with spring action.
All Protective Relays, Auxiliary Relays and Timers except the lockout relays and Interlocking relays
specified, shall be provided with self reset type contacts. All Trip relays and Timers shall be provided with
externally hand reset positive action provided with inscription subject to Consultant/Developer approval.
Timers shall be of the electromagnetic or solid state type.
Wherever solid state relays are used the following requirement shall be met:
(a). All Relays shall be designed for operating under an ambient temperature 55 Deg; C and 100%
relative humidity.
(b) All accessories required for correct operation of each relay shall be supported by the Contractor
without any extra cost.
(c) The solid state relays shall be stable and suitably protected against transient or induced over
voltages. The Bidder shall state clearly in his list special requirements, if any, for DC input
arrangement or cabling considered necessary for satisfactory operation of solid state relays
quoted by him.
6.0 Labelling
6.1 General
Every switchboard, switchboard control contactor, time switch, relay, indicator lamp, meter. motor
starter, link and any control or protection equipment within or on a switchboard shall be clearly and
accurately labelled.
A switchboard designation label shall be provided. For other than main switchboards, the designation
label shall also state the source of electrical supply. Separate sections of enclosures shall be identified.
The label for any section or enclosure containing Supply Authority equipment shall be to the satisfaction
of the Consultant / Developer and the Supply Authority.
(a) Circuit designation for all main switches, main controls and submain controls.
(b) Details of the consumer's mains and all submains.
(c) Incoming busbar or cable rating to the first tee-off.
For identification of final sub circuits, a typed schedule, cross-referenced to the lighting and power layout
plans shall be provided. The schedule shall be protected by a plastic sheet and fixed in a suitable frame
mounted on the inside of the relevant switchboard door or, if the switchboard has no door, on the wall
immediately adjacent to the switchboard.
WARNING
PAINTED COATING ON BUSBARS OR TERMINATIONS IS NOT INSULATION.
If a stand-by power supply is installed, an appropriate warning label shall be fixed at the main switch or
local main switch. An example of a typical label is:
WARNING
IN THE EVENT OF LOSS OF NORMAL SUPPLY GENERATOR SET WILL AUTOMATICALLY START AND BE
CONNECTED TO THIS SWITCHBOARD
When anti-condensation heaters are fitted, a label shall be provided at each heater reading
WARNING
THERMOSTATICALLY CONTROLLED ANTI-CONDENSATION HEATER-DO NOT SWITCH OFF
7.0 Tests
7.1 General
The routine tests shall be conducted as per IS standards on each Power Control Center and shall comprise:
Inspection of the Switchboards including inspection of wiring and electrical operational and functional
tests where necessary.
Checking of protective measures and electrical continuity of the protective circuits.
8.2 Erection
Switchboards shall be installed over trench/floor as required. Suitable grouping holes shall be provided in
the flooring. Suitable MS base channel shall be embedded in the flooring on which the panel can directly
be installed The switchboards shall be properly aligned and bolted to the flooring by at least four bolts.
Cables shall be terminated on the bottom plate or top plate as the case may be, by using brass
compression glands. The individual cables as shall then be led through the panel to the required feeder
compartments for necessary terminations. The cables shall be clamped to the supporting arrangement.
Either side, the switchboard earth bus shall be connected to the local earth grid.
The base channel used for erection of panels shall form part of the cost of the panel and shall not be
measured or paid separately.
(a) All main and auxiliary bus bar connections shall be checked and tightened.
(b) All wiring terminations and bus bar joints shall be checked and tightened.
(c) Wiring shall be checked to ensure that it is according to the approved drawing.
(d) ll wiring shall be tested for insulation resistance by a 500 volt megger
(e) Phase rotation tests shall be conducted.
(f) Suitable injection tests shall be applied to all the measuring instruments to establish the
correctness and accuracy of calibration and working order if required by the Developer.
(g) All relays and protective devices shall be tested for correctness of settings and operation by
introducing a current generator and an ammeter in the circuit or shall produce calibration or test
certificate as required by the inspectorate or Consultant / Developer.
(h) Functional tests on all feeders.
(i) Make, type and ratings of all components shall be checked and verified as per the approved
drawings.
All steel work used in this Contract shall in general, undergo the following process of treatment and finish.
(a) Degreasing: by hot alkaline degreasing solution followed by cold water rinsing to remove
traces of alkaline solution.
(b) Phosphating: by a recognised phosphating process to facilitate durable coating of the paint on
the metal surfaces and also to prevent the spread of rust in the event of the paint film being
mechanically damaged. This again shall be followed by hot water rinsing to remove traces of
phosphate solution.
Manufacturer's guarantees and warranties shall be obtained in accordance with Clause 9.11 of the
Preliminaries. The warranty period shall be for eighteen months commencing from the date of installation
or twelve months from the date of practical completion, whichever is the first to occur.
1.2 Rating
The cable shall be rated for a voltage of 1100 Volts.
a) The trays are ladder type and shall have suitable strength and rigidity to provide adequate
support for all contained cables.
b) It shall not present sharp edges, burrs of projections injurious to the insulation of the
wiring/cables.
c) If made of Sheet metal, it shall be adequately strength protected against corrosion or shall be
made of corrosion resistant material.
d) It shall have side rails or equivalent structural members.
e) It shall include fittings such as horizontal, vertical bends, tie rods, hooks etc., or other suitable
means for changes in direction and elevation of runs, fishplates and hard ware.
2.6 Installation
a) Cable trays shall be installed as a complete system. Trays shall be supported properly from the
building structure. The entire cable tray system shall be rigid.
b) Each run of the cable tray shall be completed before the installation of cables.
c) In-portions where additional protection is required, non-combustible covers/enclosure shall be
used.
d) Cable trays shall be exposed and accessible.
e) Where cables of different system are installed on the same cable tray, non-combustible solid
barriers shall be used for segregating the cables.
f) Cable trays shall be grounded by two nos. earth continuity wires. Cable trays shall not be used as
equipment grounding conductors.
2.8 Testing
Cables shall be tested at factory as per the requirements of IS 1554 Part I. The tests shall incorporate
routine tests, type tests and acceptance tests. Copy of such test certificates shall be furnished to the
Developer prior to dispatch.
For all aluminium cables, the oxide shall be removed by thoroughly wire-brushing the bare end of the
cable. After brushing, a liberal coating of approved oxide-inhibiting, moisture-excluding thermally stable
grease shall be applied, and the cable shall be wire-brushed again through the grease. Cable strands shall
not be separated before brushing.
Bare aluminium lugs, ferrules and other connectors, unless factory-tinned or factory pre-filled with
inhibiting grease, shall be wire-brushed and grease coated in the same way as cables.
Before making any joints or terminations in aluminium cables, the Contractor shall submit the proposed
method for the Consultant / Developer approval. Notice of at least three working days shall be given
before making any joints or terminations, to enable the Consultant / Developer to witness the work.
Tinned copper ferrules shall be terminated using the compression method. For compression connections
on stranded cables, a hexagonal die shall be used, on solid conductor cables, indent type dies shall be
used, with at least two indentations per cable connection. Lugs of ferrules shall be selected to suit the size
and shape of the conductor. Compression dies shall be selected to suit the particular lug or ferrule.
Aluminium crimp lugs shall be filled with oxide inhibiting grease.
Joints by the fusion welding method shall be made by jointers experienced in this method. Particular care
shall be taken to protect the cable insulation from heat by fixing substantial heat sinks to the cable near
Bi-metal connections shall consist of lugs or pin type connectors having a cast copper palm or pin, friction-
welded to an aluminium barrel section which is subsequently factory filled with oxide-inhibiting grease.
The aluminium cable shall be inserted in the barrel section and fixed using the compression method as
detailed above. The copper pin or palm section shall be fixed to copper or brass connectors or bus-bars in
the conventional manner.
Where electro-tinned aluminium lugs are used, they shall be fixed to the cable using the compression
method. The palm of the lug shall be bolted to the copper bus-bar or terminal using a stainless steel bolt
and nut, with one large diameter stainless steel flat washer and two "Belleville" spring cup washers.
All nuts shall be adequately torque tightened to manufacturer's recommended levels. Identification
tags for feeder designation shall be by using `Phoenix' plastic cable markers, tied to either end of each
cable.
4.3 Refilling:
The filling shall be done in layers not exceeding 15mm in depth. Each layer shall be watered, rammed and
compacted. Ramming shall be done with iron rammers where possible and with blunt end of the crow
bars where rammers cannot be used. Special care shall be taken to ensure that no damage is caused to
the pipes, drains, masonry or concrete in the trenches.
4.5 Testing
Cables shall be tested at the factory as per the requirements of 1S 1554 Part 1. The tests shall incorporate
routine tests, type tests and acceptance tests. A copy of such test certificates shall be furnished to the
Consultant / Developer prior to dispatch.
All sockets 6A and 16 A ratings shall be of flush mounting type (unless otherwise indicated with control
switches of plate type design of the same rating as that of the sockets. All socket outlets shall be of 3 pin
type with PVC boxes. UPS sockets should not contain switch, need to be different consistent color from
others.
1.4 Installation
All switch connections shall be made only after ensuring the continuity of wires and terminations. Tapping
of wires shall be done only at the terminals of switches, sockets and ceiling roofs and terminal blocks.
Under joining and extension of wires in pipes and conduits shall not be carried out under any
circumstances.
The arrangement of switches and sockets shall be neat, systematic, and aesthetic. The Contractor shall
obtain approval from the Consultant / Developer with regard to the proper location of switches and all
outlets.
The enclosures of sockets and pin of the sockets shall be connected to the ground through a proper size
insulated earth continuity wire. Metal or hylam phase barriers shall be interposed between switches
located in a common enclosure, when wired on different phases.
Sub-main shall include Ms or PVC draw-boxes, sized as required to be located at every floor for easy
drawing of wires.
Wiring of light points and 6A switched socket outlets by providing PVC or 16G rigid MS Box with
accessories, and 2.5 sqmm 660V/1100V grade PVC flexible multi strand copper wires, SP MCB 6A modular
plate switch, and other point wiring accessories and carrying out surface/concealed conduit point wiring.
All light points, 5A sockets shall be earthed using the third core of green colour insulated copper wires.
1.7 Labeling
The Contractor shall provide labelling for all light control switches, industrial-type sockets, socket outlets,
permanently connected devices, etc, identifying the distribution board and circuit breaker number, in an
approved manner, acceptable to the Consultant / Developer, to provide ready identification.
General
There are no devices or methods capable of modifying the natural weather phenomena to the extent that they can
prevent lightning discharges. Lightning flashes to, or nearby, structures (or lines connected to the structures) are
hazardous to the structures, their contents and installations as well as to lines. This is why lightning protection
measures are essential
Lightning Protection System shall be in accordance with IS IEC 62305-3 & NBC-2016. Lightning Protection consists of
external Protection for the building with Air termination, Down Conductors and Earthing and Internal protection for
power lines with Surge Protective devices.
Generally lightning between cloud and ground creates failures. However inter-cloud and intra-could lightning also can
create potential differences and failures in electronic installation. More than 95 % of Lightning strikes are of Negative
impulse and less than 5 % are of positive impulse. Positive impulses are mainly due to dry lightning in cold areas.
Current parameters as per IS/IEC 62305 and the effects of lightning are as below
Damages from lightning strike are due to Peak Current (I), Charge (C), Specific Energy (W/R) & Rate of change of
current (di/dt). Lightning protection is designed to take care of these effects of lightning and hence the following
parameters shall be strictly followed.
Effect of Lightning on External LPS (Air termination, Down Conductor and Earthing)
Effects on air-termination systems arise from both mechanical and thermal effects. Effects on down-conductors are
thermal effects due to resistive heating & mechanical effects in parallel conductors and in Bends. The real problems
with earth-termination electrodes are linked with chemical corrosion and mechanical damage caused by forces other
than electro dynamic forces.
Effect of Lightning on Internal LPS (SPD’s for POWER, DATA lines etc)
Effect on internal LPS is mainly due to coupling and the rate of change of current. Due to Very high d i/dt of the first
negative stroke. The expected problem is the response time of SPD and the voltage drop in the connecting wires. SPD’s
at the incoming panels shall have a response time less than 1 nano sec & shall be of BUSBAR Mounted type to avoid
connecting wire length.
70
0
a 60
50
40
30
IV
I II III
20
10
0
10 20 30 40 50 60
H m
Aluminium accessories if connection is between Aluminium materials are necessary. SS accessories if connections are
between aluminium and copper / copper coated materials.
Earth Termination Conductor: 10 mm solid copper coated steel conductor (100 microns min coating)
Earth Termination Joints in soil: Exothermic welding
GI material for earthing shall not be used as per the recommendation in IS/IEC62305 as well as Kerala electrical
inspectorate guideline.
If the structure height is more than 60 meters, top 20% of the height of the structure shall be protected with a lateral
air termination system. This is needed because the probability of flashes to the side is generally more for structures
more than 60 meters in height. More importance need to be provided to Corners, Edges and significant protrusions
such as balconies. Metallic handrails/ Aluminium frame of wall cladding if used in balconies shall be conned to air
termination / down conductors.
In PEB / Steel buildings where GI sheet roofing, air termination mesh / Rod shall be directly mounted on the sheet.
Fixing materials used shall be in good electrical contact with the sheet, shall not create water leakage.
No drilling is allowed in the terrace for fixing the air terminal, if the roof is made of concrete. Parapet wall is
exception to this.
Concrete Roof structure: Conductors shall be securely fixed on the terrace by means of concrete air terminal holders
with suitable fixing materials which is fixed on the roof by adhesive or cement mortar taking care of varying weather
conditions. Plastic air termination conductor holder is not allowed. The minimum height of this air terminal holder shall
be 50 mm to avoid the contact of conductor with water
Metal Roof structure: Conductors shall be securely fixed on the terrace by means of air terminal holder which is fixed
on the roof by metal conductor holder made of Stainless steel. As metal roof structures are normally tapered at an
angle, there are no min height criteria for metal conductor holder.
If antenna, Chillers or any other roof top electrical equipment is present in terrace, the same have to be protected by
using vertical air terminal after calculating the safety or separation distance. The vertical air terminal has to have
suitable supports to hold it. Wind speed need to be taken into account. Vertical air terminal must be connected to
horizontal air terminal by using suitable connectors.
At the crossings of the horizontal air terminals, suitable Cross connector has to be used.
Safety or Separation distance: (not required for LPS using structural natural components)
To avoid flash over to electrical/electronic apparatus, this equipment shall be kept at a distance away from LPS
components more than the safety distance as per the following calculation.
Expansion piece
In order to take care the expansion of the metal in summer and contraction of the metal in winter, expansion piece
with suitable connectors have to be used at every 20m distance of horizontal air termination mesh.
Test joints:
At the connection to the earth conductor, a test joint should be fitted on each down conductor at a height of 1 m from
the ground, except in the case of natural down conductors combined with foundation earth electrode. The purpose of
test joint is to measure the earth resistance value. The remaining portion of down conductor (i.e., after the test joint
should be mounted inside a plastic pipe of minimum 3 mm thickness.)
Earth Terminations
For earth termination system, 2 basic types of earth electrode arrangements are applicable. Type A & Type B
arrangement.
Type A arrangement: Comprises of horizontal or vertical earth electrode installed outside the structure to be protected
connected to each down conductor. Minimum Length of vertical earth electrode shall be as below
Class of Typical Length of each vertical earth electrode based on Soil resistivity
LPS Up to 500 Ω M 1000 Ω M 2000 Ω M 3000 Ω M
1 2.5 meter 10 meters 25 meters 40 meter
2 2.5 meter 5 meter 15 meters 22 meter
3 2.5 meter 2.5 meter 2.5 meter 2.5 meter
4 2.5 meter 2.5 meter 2.5 meter 2.5 meter
If horizontal electrodes are used, the length shall be double. In type A arrangement, the total number of earth
electrodes shall not be less than two. Type A arrangement is suitable in places where electronic equipment are not
located.
Type B arrangement: This type of arrangement comprises either a ring conductor external to the structure to be
protected, in contact with the soil for at least 80% of its total length or a foundation earth electrode. Ring earthing
must be 1 meter away from the building and 0.5m below the ground as a closed loop. Such earth electrodes can also be
meshed. For structures with extensive electronic systems or with high risk of fire, type B earthing is most preferable
method. There is no limit in the resistance of Ring Earthing if the ring radius of the ring is larger than 50 meters or 80
meters for LPL 1 and 2. For LPL 3 and 4 this radius is about 5 meters. The overall resistance of earthing system shall not
exceed 10 ohms.
References:
IS/IEC62305 – PROTECTION AGAINST LIGHTNING:
Part 1: General Principles
Part 2: Risk Management
Part 3: Protection of structures
Part 4: Protection of Electrical & Electronic equipment within structure
NBC-2016: National Building Code of India – 2016
IS3043: 1987: Code of practice for earthing.
UP S – IN V ER T ER TY P E
1.0 General
1.1 Scope
Supply, install and commission RATED KVA / 230V (single phase) UPS systems with necessary batteries for
a battery back up time of 90 minutes. For lighting & general power applications.
1.4 Submissions
Full details of the systems, including technical specifications and shop drawing showing precise layout of
UPS and batteries, shall be provided to the Development Manager.
Once the warranty expires the Developer may at his discretion enter in to an annual maintenance
contract (AMC) or ask, the Specialist Agency to support the maintenance of the system on a per call basis
with the same commitment as in the case of AMC.
2.2 Batteries
All batteries shall be sealed maintenance-free batteries of appropriate rating to provide 90 minutes back
up at full load. Battery mounting racks shall also be supplied with batteries.
3.0 Execution
3.1 Installation
The UPS System and batteries shall be installed as per the approved drawing. All cable shall run through
the cable turn provided
3.2 Commissioning
The Contractor shall be responsible for the testing and satisfactory performance of the complete UPS
system which shall include as a minimum:
(a) Switch off all the output breakers that are connected to the load. Run the UPS in no load
condition at least for 15 minutes.
(b) Measure and confirm output voltage. Phase difference, frequency and all other specified
parameter are within the allowed range.
(c) Conduct the load test of the UPS system by connecting the UPS to a dummy load like water load
Contractor shall arrange for test facility.
d) Measure and confirm at full load, voltage, frequency, phase difference, Battery backup time,
battery charging current, DC ripple, parallel redundancy operation, and all other necessary
and/or specified parameters are within the approved range.
e) Once the result of the load test is satisfactory, and approval is received for connecting the power
to the electric circuit; connect the UPS output to the actual computer load.
f) Check for any malfunctioning with the computers and UPS system. Observe for 15 minutes.
g) Repeat step
3.3 Manuals
Two sets of all manuals for the systems, including instruction, administration and maintenance manuals,
shall be submitted to the Consultant / Developer.
E AR T HIN G
Scope of work
o Supply and installation of all Earth Electrodes as enumerated in earthing schematic.
o Supply installation of earthing conductors for the electrical works covered under this scope of
work.
o Supply and installation of Rigid PVC pipes up to the nearest shaft or cut in building or the cable
trench in the vicinity to enable laying of earthing strips by other agencies at a later date.
o Earthing electrodes shall be designed as per the requirements of clause 17.2 of IS:3043. The
number and size of earth electrodes shall be calculated so that under fault conditions no
electrode is loaded above its maximum permissible current density. The resistance of earth
electrodes shall not exceed one Ohm.
o The number of earth electrodes shown in the drawing is indicative. The Contractor shall provide
required additional earth electrodes to contain the ohmic value at no extra cost.
o Earthing electrodes of plate type shall be used. The choice of pipe or plate electrode shall be
decided according to the anticipated fault level of the network and local soil conditions.
o All grounding electrodes shall be tested with earth meggers and grounding resistances are
recorded.
Characteristics
Shall have good Electrical conductivity.
Shall high Corrosion Resistance.
Shall be mechanically robust and reliable.
Maintenance free Earthing System shall consist
1. Copper bonded Earth Rod at a depth of minimum 3 meters (3 rod per pit)
2. Ground Enhancing Material (GEM).
3. Earth Rod Clamps.
Precautions
Earthing system shall be mechanically robust and the joints shall be capable of retaining low resistance,
even after passage of fault currents.
Joints shall be welded, bolted or double-riveted. All welded joints are painted with cold zinc galvanizing
paint. All the joints shall be mechanically and electrically, continuous and effective. Joints shall be
protected against corrosion.
Testing
On the completion of the entire installation, tests on the earth resistance of the electrodes shall be
conducted using an earth-testing Megger.
All meters, instruments and labour required for the tests shall be provided by the Contractor. The test
results shall be submitted in triplicate to the AE / Owner for approval. Tests shall be conducted in the
presence of AE / Owner.
Ground resistance test shall be conducted to verify impedance of the electrical ground systems. For sizes
of conductors of earthing refer to earthing schematic.
Luminaires
1.0 Supply and Installation
1.1 General
Luminaries shall be installed in an approved manner and shall be complete with incandescent lamps,
fluorescent tubes, discharge lamps and accessories necessary for their proper functioning and shall be in
accordance with the provisions indicated herein.
All discharge luminaries shall be power factor corrected to a minimum of 0.8 lagging. Lead lag circuits or
blocking Inductors shall be incorporated where indicated.
Supply of Luminaries
Luminaries shall be purchased from a reputable supplier and shall be manufactured in accordance with
relevant standards.
The catalogue numbers or trade designations for luminaries used in the schedule of equipment are
intended to indicate the required quality, style and performance of the luminaries. Where alternative
luminaries are offered all performance data shall be submitted to the Consultant / Developer for
approval. If requested, by the Consultant / Developer, a sample shall be submitted for approval.
(a) Fixing to timber: steel wood screw No.10 x 25, round head, cadmium plated.
(b) Fixing to concrete: approved screw expanding bolts M5 x 40.
(c) Fixing to hollow blocks: M5 electro-galvanized, round head screws with spring loaded butterfly
toggles. Where a deep cast iron junction box is provided in the centre, M5 metal screws shall be
used with approved expanding fixings at each end.
(d) Fixing to suspended ceilings shall be as indicated.
All fixings shall be fitted with large diameter (minimum 3 mm screw dia.) cadmium plated washers under
the heads of each screw.
The scope briefly shall include supply, erection, testing and commissioning of External Water Supply
Distribution Network , containing various requirements of piping, valves, supports, specialities etc.
The water requirement for building shall be calculated as per Plumbing section of IS: SP: 7-2005.
The pipe shall be concealed and painted with anti-corrosive bituminous paint (as per IS:158) wherever
required as per requirement and direction of Authority’s Engineer /Client
The total water requirement shall be met with underground source by providing deep tube wells or by any
other nearby water source.
Construction of Borewells with adequate capacity of submersible pumps(Including complete set as per
requirement) shall be in scope of Work as per requirement and direction of Authority’s Engineer /Client..
Water source shall be tested for potable water quality and suitable water treatment shall be provided as per
WHO standards.
The contractor shall have to maintain the plant for a period of 12 months including all the materials etc. at their own
cost after satisfactory commissioning of the plant. The contractor shall provide training to the operators of the owner
for a minimum period of three months during the maintenance of the plant. The responsibility for any defect due to
design, construction, performance lies solely with the contractor.
The scope shall cover the following activities and services in respect of all the works of WTP:
Basic Engineering
Detailed design of all the civil structures,
Providing engineering drawings, data, Operation & Maintenance/ instruction manuals, as built drawings and
other information,
Compliance with statutory requirements and obtaining clearances from statutory authorities, wherever
required,
Finalisation of sub-vendors, manufacturing quality plans and Field quality plans,
Complete manufacturing including conducting all shop / routine tests.
Packing and transportation from the manufacturer’s works to the site including customs clearance & port
clearance, port charges (if any),
Receipt, storage of manufactured items, at the site,
Erection, testing and putting into satisfactory operation all manufactured items
Satisfactory completion of the contract.
The contractor shall be responsible for making all connections at terminal points, and for supplying any
necessary jointing material, connectors, nuts, bolts etc.,
PUMPS
Suitable capacity of Drinking water Pumps along with drive motor (Vertical turbine wet pit type) (as per
requirement including all) to be provided at underground water tank.
UNDERGROUND TANKS
Earth pressure for all underground structures shall be calculated using coefficient of earth pressure at rest or
co-efficient of active earth pressure, whichever is applicable, depending upon the structural configuration
Minimum 100 mm thick PCC of grade M-10 as per IS:456 shall be provided as mud mat below the bottom slab
/ raft. The PCC shall extend 100 mm beyond the outer edge of the structural concrete. A layer of bitumen
paper or craft paper shall be provided over the blinding layer (lean concrete) to destroy the bond between
structural concrete and blinding layer.
Water proofing cum plasticizer compound shall be mixed with the concrete.
For the design of substructure of pump houses, earth pressure at rest shall be considered. Co-efficient of
passive earth pressure shall be used only in design of shear keys for stability against sliding.
The design of all liquid retaining structures shall be carried out by working stress method of IS 3370 (All parts)
STP
Design, drawing, supply, erection, testing and commissioning of Sewage Treatment Plant as per the Schematic,
Flow Scheme, Specification consisting of :
Bar Screen Chamber ( Bucket Screen )
Equalisation Tank
FRP treatment plant comprising of pre-aeration in contact media, aeration treatment, sedimentation
and disinfection. System is equipped with settling and anaerobic filtration as an integral part of the FRP
module.
Semi Treated Effluent sump
Treated Effluent sump
Screen Filter
Diffusers
Raw Effluent pump, Filter feed Pumps, Alum dozing system & Blowers.
Pump House
Note:
All works to be carried out to the relevant IS Specifications whether so mentioned in the description of
works or not.
Including all Electrical, mechanical and piping works complete in all respects. Rate quoted shall also
include for obtaining necessary approvals from the Pollution Control Board & other statutory bodies as
applicable, for trial run & commissioning of the plant with performance Guarantee for 12 months from
the date of commissioning for trouble free performance. The Total plant is to be above ground with
only Equalisation tank, Semi Treated water tank & Final treated water tank located below ground level.
Galvalume sheet roof with pump room in masonry to be provided above ground.
The cost inclusive of all civil structure.
SC O P E O F W OR K
Work under this section consists of furnishing all labor, materials, equipment and appliances
necessary and required to completely install drainage system as re quired by the drawings,
specified herein after and given in the schedule of quantities.
Without restricting to the generality of the foregoing, the drainage system shall include the following: -
a) RCC Hume pipes (light duty pressure pipes)
b) Connection of all pipes to Catch Basins as shown on the drawings.
c) Testing of all pipes lines.
LA Y ING AN D J O IN TIN G
The concrete pipe should be carefully loaded, transported and unloaded without impact, the
laying of pipes shall be done by using tripod stand and chain pulley blocks.
Joints shall be of collar joint and the caulking space shall be filled with CM. 1:1 mixture of
cement & sand. The caulking shall be employed on both the ends and finished neatly outside the
socket at an angle of 450. Wooden caulking tool shall be used for forc ing the mortar home into
the collar.
All the joints shall be kept moist by means of wet gunny cloth to protect them from quick drying. The
joints sh a l l be cured at least for seven days.
T ES TI NG
Testing of non-pressure pipes shall be subject to a test for 2.5 meters head of water at the
highest point of the section under test for 10 minutes. The leakage or quantity of water supplied
during testing shall not exceed 0.2 lt./mm dia of pipes per Km length per day.
PR OC E D UR E FO R L E A K A GE T E S T – I S 31 11 4
A leakage test shall be conducted currently with the pressure test. Leakage is defined as the
quantity of water to be supplied into the newly laid pipe, or any valve section thereof within
0,035 N/Sq.mm /0.35 Kgf/Sq.cm, of the specified leakage test pressure after the air in the
pipeline has been expelled and the pipe has been filled with water (in case of test pressure is 10
Kgf/Sq.cm the leakage test pressure will be 3.5 Kgf/Sq.cm.)
No pipe installation shall be accepted until the leakage is less than the n umber of cu.cm/h as
determined by the formula:
VA RI A TI ON FR OM P ERM IS S IB L E L E A KA G E
The leakage or quantity of water supplied during testing shall not exceed 0.2 lts/mm diameter of
pipe per kilometer of length per day.
PL A IN CE M ENT C ONC R E T E O V ER P IP E S
When pipes are laid under roads and payments subjected to heavy traffic loads the trenches
may be covered with plain cement concrete slabs of suitable dimension, supported on edges to
relieve the load on pipes to the adjoining earth.
CON TR AC T OR S H AL L R E ST OR E S E TT L EM EN T AN D D AM AG E S
The Contractor shall at his own cost make good promptly, during the whole period that the works are
in hand, any settlement that may occur on the surfaces of roads, berms, footpaths, gardens,
open spaces, etc. whether public or private caused by trenches or his other excavations and he shall be
liable for any accidents caused thereby. He shall also, at his own expense, repair and make good any
damage done to the buildings and other properties.
GENERAL SPECIFICATIONS
SITE CLEARANCE, EXCAVATION, SITE LEVELLING AND GRADING
The term Grading, Grading Plan, Site Grading shall mean the following in singular and collectively:
Surface dressing: Trimming of natural ground and / or excavated surface / filled up area to remove
vegetation and undulations not exceeding 150 mm deep shall be described as surface dressing. Measured
in sq Mts.
Rough excavation: Excavation not requiring surface dressing. Measured in Sq mts.
Surface Excavation: Excavation exceeding 1.5m width and 10 sq mts in plan but not exceeding 300 mm in
depth.Measured in sq Mts.
Area Excavation: Excavation exceeding 1.5m width and 10 sq mts in plan and exceeding 300 mm in depth.
Measured in Cu M.
1. Each dimension shall be measured to the nearest 0.01 m. for dimensions exceeding 25 mts, the accuracy
shall be 0.1 m
2. Areas shall be worked out to the nearest 0.01 sq mts.
3. Cubic content shall be worked out to nearest 0.1 Cu m.
Measurement of Cut: Where the ground is not uniform, levels shall be taken before the commencement of works
and after completion of works and the quantity of cutting calculated from this measurement.
Measurement of Fill: Where the ground is not uniform, levels shall be taken before the commencement of works.
Works shall be measured during compaction of fills at suitable intervals, and the final measurement taken after
achieving and after completion of neat surface dressing.
The following works shall not be measured seperately and allowance for the same shall be deemed to have been
made in the description of the main item.
1. Setting out
2. Profiles
3. Site clearance
4. Informal Battering or benching of excavation
5. Pumping out water from excavated areas and sub soil.
6. Slinging or supporting pipes and cables encountered during work.
All plantations shall be done in the refilled pits or trenches containing a well mixed composition of the
following ingredients:
Stacked top soil/ Garden earth (2 parts)
Cocopeat (1/2 part)
Sieved sand (1 part) (grade as specified for construction) – to increase aeration and reduce termite
and other insect attack.
Organic sterilized manures like vermicompost granules (without mud), or any refined manure or
Amrut compost (1/2 part)
Conventional methods of using FYM in the soil mix, in the pre and post planting stage are avoided
since it heats up the soil, increases methane production, thus affecting plant roots, it also increases
weed, pest and disease incidence. This also reduces the cost of maintenance.
The soil mixture shall have a pH of 6.5 to 7.
The soil used shall be properly screened into coarse texture and fine texture to suit the type of plant
(coarser for trees and shrubs and finer for lawns) containing adequate amount of humus, friable and
free from perennial weeds, stones and pebbles, foreign materials, plastic bags, roots, half decayed
leaves, debris etc. It shall be fine textured soil that breaks into clods and lumps when crushed. All the
soil should be of the same structure and composition throughout. The soil shall not be delivered,
handled or placed in a muddy condition.
(3) Stakes
Each tree shall be secured to a stout straight stake of average diameter of 2”. These stakes of soft wood or
bamboo should have a clear height of 6’-0” above the ground and 2’-0” below ground. They shall be driven
into the hole before the tree is planted and the trees shall be secured to them immediately below the bottom
branch. The second tie is to be staked as practicable.
(H) WORKMANSHIP
(A) Trees
(a) Tree pits: After making out the positions for planting the trees, pits shall be made minimum 1 cum or at
least 150mm wider and deeper than the space the roots will occupy when they are spread out in their
natural positions.
(b) Handling: The container of the trees shall be removed before planting the trees. The tree shall be handled
by the soil ball. The trunk of the tree shall not be used as a handle as this may injure the tree by breaking
of fragile roots or loosening the whole root system, while planting a small hole shall be made in the centre
of the pit slightly larger than the ball of earth holding the roots.
(c) Placing/ Protection: If the plant is tall and likely to sway by the wind, it shall be supported by a stick to
which it is tied. For a young tree under 2.5” to 3” dia., support of 2” x 3” wooden stake 4’ long shall be
used. The end of the stake shall go into the ground. The tree shall be tied to the stake with coir tie (sutli).
The stakes and ties shall be removed after they have done their job between one year to three years.
(d) Planting: The pits shall now be filled with the prepared mixture of manure and earth, working the soil
between the roots. The soil shall be pressed down firmly by treading on it, leaving a shallow depression all
around for watering. When the tree has lawn around it, the surface of the lawn shall have a slight slope
around the tree.
(e) Watering: The tree shall be watered heavily soon after planting in the absence of rain, the trees shall be
watered every three days for smaller trees and once a week for larger trees. The interval between
watering shall gradually be increased to twice a month, once in a month to once in six months in the case
of large trees only.
(D) Lawns
Ground preparation: Thorough and adequate ground preparation shall be carried out as mentioned
earlier. In absence of rain, the surface shall be watered heavily. Any weeds that come up shall be removed
thoroughly. As soon as the surface is dry enough, the levels shall be rechecked, slight surface settling that
occurs shall be filled in before grass planting is commenced for turfing. Turf (minimum 1’ wide) shall be
spread on the ground without any gaps. Any cavities shall be filled with fine soil. The entire area shall be
watered liberally. Any soil settling/ turf settling should be corrected by removing the turf at this stage and
refilling with soil mix, and re-turfing. After six months, all levels should be resurfaced to required grade by
top dressing the turf with soil mix, and washing it down.
Growing and shaping: When the growth of the grass has progressed sufficiently to require mowing, hand
weeding shall be done. After each mowing, sieved soil mix shall be spread, watered and smoothed down.
Planks of wood shall be used for this purpose. Besides mowing, weeding, and watering of lawn, lawn shall
be treated with organic manures and fertilizers as mentioned earlier. The edges of the lawn where it
meets shrub areas, walkways, or structures shall be clipped by hand and well maintained.
(I) INSPECTION
The site will be inspected by the Architects, Clients, Landscape Architect and Horticulturist from time to time
at different stages of work. All the stages of work will be under continuous supervision and observation by the
horticultural supervisors appointed by the Landscape Architect. Security measures will have to be provided by
the Clients during the entire period of planting and maintenance.
All the trees/ shrubs/ creepers will have free maintenance period of 6 months, during which the contractor is
supposed to maintain all these items in all respects such as watering, pruning, spraying of pesticides,
fungicides, insecticides, adding fertilisers, removing of weeds etc. The maintenance of the horticultural work
includes employment of required malis and others continuously for period as per contract agreement.
All plant materials furnished or relocated shall be warranted for a period of six months from the date of pre-
maintenance inspection against defective, unsound, or diseased condition that may appear. Any damaged
plant material shall be promptly replaced with new material of the same size and condition and installed
according to the specifications. The expense of replacement shall be borne by the contractor. The contractor
shall not be held liable for the loss of plants due to accidents, severe storms or inclement weather or theft.
Final acceptance shall be based upon a visual inspection operation by the Architect/ Landscape Architect at
the completion of the maintenance period.
Scope the section death with technical requirement of lift installation. Its components safety devices various type of
controls and methods of operation will be guided by the requirements in individual case such as nature of building,
usage occupancy, traffic pattern etc. and has to be decided in individual cases.
4.2 General illumination of lift well. : Suitable light points shall be provided in the lift well at a spacing of not
more than 10meters in suitable light at the ground floor. All the points should be group controlled from the M/C
room. The wiring shall be carried out in surface conduit as per CPWD General Specification. One socket outlet shall
be provided in the shaft for use by maintenance personnel at a level slightly above the ground floor landing.
The guide rails shall be supported by brackets secured to the hoistway frame at each floor. The rails shall be
securely fastened to the brackets or other supports by approved heavy rail clamps. Ali necessary guide rails
packing or additional supports shall be provided to prevent guide rail deflection and stresses exceeding the
prescribed limits. The stresses on the guide rail due to the horizontal forces imposed on it during loading.
Unloading and running calculated without impact. Shall not exceed 1100 kg/sq cm based upon the class fastenings
and supports shall be capable of resisting the horizontal forces mentioned above. With the total deflection at the
point of support not in exceed of 3mm.
Guide rails shall extend from pit floor to the underside of concrete slabs or grafing at top of the lift well. They shall
be erected in plumb and parallel with a maximum deviation of 3mm. all shimming required shall be of metal
securely held in place. Jointing plates shall be so located as not to interfere with supporting clamps and brackets.
The bolts shall be used with spring lock washers. The guide rail anchorage at pit floor must be made without
puncturing the water proofing. The expansion joints in the guide rails shall be so designed as to avoid jerks in the
left car. Machined guide rails shall be maintained till the commissioning of the installation. Before the car is a
placed in operation, the preventive coaling shall be removed and the guide rails thoroughly cleaned and
smoothened.
6.7 Clearance
The clearance between the top of the car and the soffit of the lift shall roof. Bottom of the car and the pit floor, the
buffers etc. and the clearance between the car and the lift well, between the car and the landing sill, between two
lift cars in the same shaft etc. shall be provided as per IS 14665(Part 1.2&4)and relevant lift rules mentioned in
appendix-1.
6.9.2. The device used for emergency signals should incorporate a feature that gives immediate feedback to the
car passengers that the device has worked properly and the signal has been passed on to the intended agency. This
shall be achieved by pressing of button from control room which shall give audio signal to the passengers in the
car.
6.9.3 Provision of group indicator panel in the control room shall be made to indicate working of lifts.
The car door shall be centre opening horizontal sliding stainless steel scratch proof(moon rock finish) for office.
Residential and goods lift applications whereas telescopic horizontal sliding stainless scratch proof surface(moon
rock finish) for hospitals.
7.1.3 In order to avoid accidental closure of doors while boarding or alighting the car, a temper proof infrared
curtain covering almost the entire height of the door should be provided in the lift doors.
7.2.2 A hand rail not less than 600mm long at 900mm above floor level shall be fixed adjacent to the control panel.
7.2.3 The time of an automatically closing door should be minimum 5 seconds and the closing speed should not
exceed 0.25 m/sec. The interior of the cage shall be provided with a device that audible indicate the floor the cage
has reached and indicate that the door of the cage for entrance/exit I either open or closed.
8. Landing doors
Each landing door shall be complete with locks. Headers, skill frames rims hanger supports with cover plates etc.
the finished work shall be strong, rigid and neat in appearance plain surfaces shall be smooth and free from warp
or buckle. Moulded surfaces shall be clean out,straight and true. Fastenings shall be concealed from the face side
of the material. Steel sills shall be provided with a suitable noising of approximately 25mm depth on the shaft side.
The opening for the landing gates or doors shall not be wider than that of the lift car. In the case of bi- parting type
steel doors, the locking of the two leafs locking of the doors should be positive.
Car landings
All the lift car landings shall be well lit to an illumination level of 150 lux and shall be free from obstructions. The
control for landing lights and the sign lights shall be temper proof. Wherever standby power supply is available,
these lights shall be connected to standby circuits also.
For the purpose of identification, the lift number should be displayed outside the landing door, inside the car and
in the machine room. This numbering may be used as reference for the purpose of routine/ preventive
maintenance, for operating from machine rooms and reporting of any incidental etc.
Leveling
All lift (s) shall be incorporated with suitable floor leveling devices. In case of lifts automatic power operated doors
and with A.C VVVF controller a separate level device for automatic leveling with leveling accuracy of 5mm shall
be incorporated.
9. Counter weight
The counter weight for lift cars shall be in accordance with clause 6 of IS14665 (part4/sec-3)2001 and shall be
designed to balance the weight of empty lift car plus approximately 50percent of the rated load. If shall consist of
cast sections firmly secured in relative movement by at least two numbers steel tie rods having lock nuts/split pins
at each end and passing through each section and housed in a rigid steel frame work. Cracked and broken sub
weights shall not be accepted.
12.2.1 The governor shall be of “v” groove wheel design and only wheel is stopped to actuate the car safety upon a
pre- determined over speed downward without damaging the rope.
12.3 The governor, rope and sheave shall be so located so as to minimize danger of accidental injury to the
equipment.
The pressing of an up down landing call shall illuminate appropriate direction indicator in the car panel, which is to
answer that call and if the doors open shall also sound buzzers as a signal to the attendant. If both car ore parked
at the lower landing the above signals shall be given to the car which has been at the floor for longest time.
a. Up peak programme:- The group supervisory control responds to the increasing influx of passengers at the main
landing in the morning hours. At the start of work, by automatically switching on the up peak programme. The car
are dispatched from the main landing automatically ot a pre- determined interval after the previous dispatched
car. The leaves first signal is transferred instantaneously from the car dispatched to another car at the main
landing. The car answers the registered calls in the natural sequence of the floors and returns directly to the main
b. Down peak programme.:- An intense traffic flow from the upper floors towards main landing will automatically
switch on the down peak programme. The cars when fully loaded at upper floors travel directly to the main landing
and after discharging the passenger. Immediately start up to answer further down landing calls. The down landing
call which has been by passed gets a priority over other down calls which ensure equal service to all floors.
c. Up down interfloor programme. :- A steady traffic between main floor and upper floor and between floor to
floor causes automatic switching on of the interfloor programme. Specific cars are assigned to answer specific calls
by traffic analyzer so that the calls are handled most efficiently. The cars are so well distributed that every call gets
equal service with short waiting intervals.
As soon as the number of calls drops to occasional calls only such as at night, the cars get automatically parked in
their assigned zones to give personalized service with minimum lift travel. If no calls are registered for some time
the motor generator sets are automatically switched off.
d. Night programme: - When the traffic ceases to occasional calls only, the supervisory control automatically
switches over to night programme. All cars remain at the main landing with doors close,but are at all times ready
for operation. One of the lifts has its leave first signal lighted. On pressing of call button at the main landing the
doors of this particular lift open and the passenger can travel with the lift. The same lift also responds to landing
calls from above. The moment this car leaves the main landing the leave first signal is transferred to a second lift.
This second lift also responds to landing calls from above if one lift can no longer cope with the demand. After
these lifts have answered their calls, the one reaching the main landing last will retain the leave first signal.
Thereby, the service is practically confined to one lift alone and motor generator sets of the remaining lifts remain
switched off. If no calls are registered for sometime, the major generator of the stand by lift also automatically be
switched off. The motor generator will start up again. The moment the call is received. The number of lifts going in
to action in automatically regulated to just so many as are necessary to cope with the occasional traffic surge.
In case where more than 3lifts installed in a bank, a better utilization of these lifts can be obtained by two
additional programmes to deal with heavier traffic in each direction in difficult time. These are (I) heaver up
programme (II) heaver (DOWN programme)
I. Heaver UP programme :- This shall require the cars to make more stops in the up direction, necessitating more
time for the up travel. For this purpose the automatic – traffic analyzer shall dispatch cars from both terminal at
automatically adjusted time intervals so that the cars are equally spaced. Thus reducing passenger waiting interval
(this programme caters for the traffic which is likely to be in both directions but predominantly in the up direction
e.g. immediately after the morning peak or after lunch.
II. Heaver DOWN programme :- This shall require the cars to make more stops in the down direction and the
dispatch times shall be adjusted accordingly by the traffic analyzer.
If any of the cars in the group develops any defect it shall be automatically disconnected from the group control
until it is rectified.
In the event of failure of automatic dispatch system the lifts shall function by auxiliary means to avoid any
disruption of service.
Audio visual indication shall be provided to bring such failures to notice.
The lifts shall be designed for attendant operation as described under single (simplex) selective
collective operation car except as follow.
C. There shall be a master isolating switch fuse associated with the controller heavy duty load break. Quick
make quick break type. TP&N preferably interlocked with controller cabinet door isolator handle shall have
provision for external locking in off position.
All relay shall be suitable for lift service and shall incorporate adequate contact wipe for reliable operation. Relay
shall operate satisfactorily between 80 percent to 110 percent of their voltage.Main motor contactors shall be
suitable for A.C duty. Tenderer shall be required to furnish full details of make, Type applicable standard. Voltage
and current rating duty class, type and routine tests done etc. on contactors and relays. Copies of type test
certificates and other lest certificates shall also be furnished by the successful tenderer. All cables shall be with
copper conductors and flame retardant or PVC insulated of appropriate size. The cables feeding motor and in
heavy current flow paths shall be so selected that the size matches the protecting fuses and will not result in more
than 2percent voltage drop from the main board in the terminals of motor. Control cables shall not be less than 0.5
sq mm or equivalent of stranded. Where installation of heavy gauge conduits present difficulties Short lengths of
flexible conduits will be permitted but effective electrical continued by earth bonding shall be ensured. Ferrules
shall be slipped at the ends of all cables as per standard control wiring practice. All terminal blocks shall be suitable
marked.
14.4.2 Trailing cables.
A single trailing cable for lighting control and signal circuit is permitted. If all the conductors of this trailing cable
are insulated for maximum voltage running through any one conductor of this cable. The lengths of the cables shall
be adequate to prevent any strain due to movement of the car. All cables shall properly tagged by metallic/ plastic
tags for identification.
Trailing cable shall run from a junction box on the top of the car to a junction box located in the shall near
midpoint of travel and from those junction boxes conductors shall be run to the various locations.
Trailing cables exceeding 30metres in length shall have steel supporting fillers and shall be suspended directly by
then without rubbing over other supports.
16.1. ARD should move the elevator to the nearest landing in case of power failure during normal operation of
elevator.
16.2. ARD should monitor the normal power supply in the main controller and shall activate rescue operation
within 10 seconds of normal power supply failure. It should bring the elevator to the nearest floor at a slower
speed than the normal run. While proceeding to the nearest floor the elevator will detect the zone and stop. After
the elevator has stopped, it automatically opens the doors and parks with door open. After the operation is
completed by the ARD the elevator is automatically switched over to normal operation as soon as normal power
supply resumes.
16.3. In case the normal supply resumes during ARD in operation the elevator the elevator will continue to run in
ARD mode until it reaches the nearest landing and the doors are fully opened. If normal power supply resumes
when the elevator is at the landing, it will automatically be switched to normal power operation.
16.4. All the lift safeties shall remain active during the ARD mode of operation.
16.5 The battery capacity should be adequate so as to operate the ARD at least seven times a day provided the
duration between usage is at least 30 minutes.
CONTENTS
SECTION CLAUSE DESCRIPTION
1 INTENT OF SPECIFICATION
2 DESIGN PHILOSOPHY
3 APPLICABLE CODES AND STANDARDS
4 SCOPE OF WORK
5 EQUIPMENT SPECIFICATIONS
A FIRE HYDRANT SYSTEM
2.0 PIPING
2.1.1 ABOVE GROUND PIPES
2.1.2 UNDER GROUND PIPES
2.2 EXCAVATION OF TRENCHES
2.3 THRUST BLOCKS
3.0 VALVES
4.0 EXTERNAL HYDRANTS
5.0 HOSE REEL
6.0 LANDING VALVES AND HOSE PIPES
7.0 FIRE HOSES
8.0 BRANCH PIPES
9.0 HOSE CABINETS
10.0 SHUTTER FOR FIRE HOSE SHAFT
11.0 FIRE BRIGADE INLET CONNECTION
12.0 AIR RELEASE VALVE
13.0 DRAIN VALVE
14.0 VALVE CHAMBERS
15.0 TESTS AT SITE
15.1 PIPING
15.2 PUMPS
16.0 PUMPS AND ACCESSORIES
17.0 DIESEL ENGINE
B AUTOMATIC SPRINKLER SYSTEM
C ELECTRICAL WORKS
D FIRE ETECTION SYSTEM
I ADDRESSABLE FIRE DETECTION SYSTEM
II CONVENTIONAL FIRE DETECTION & ALARM SYSTEM
E PUBLIC ADDRESS SYSTEM
F FIRE EXTINGUISHERS
G SIGNAGE
6 MAKE OF EQUIPMENT
This specification is intended to cover design, residual, engineering, manufacture, test and
inspection at works, delivery to site properly packed for transportation, erection, testing,
commissioning, performance demonstration at site and handing over to purchaser of Fire
Protection System as indicated in the schedule of Requirement and scope of work and as
required for reliable and effective fire protection
1.1 This specification also includes complete earthwork, i.e. excavation and back filling for the entire
buried piping for hydrant and Sprinkler System.
1.2 The specification also includes the supply of erection and commissioning of spares as specified
and special tools and tackles.
1.3 This specification also makes it obligatory for the contractor for arranging and obtaining
necessary clearance / approval from all Local / statutory authorities.
1.4 It is not the intent to completely specify all the details of design and construction herein. Never
the less the equipment and installation shall confirm to high standard of engineering, design, and
workmanship in all respect and shall be capable of performing continuous satisfactory operation
and acceptable to the purchaser as well as to the various statutory authorities. In case of any
violation of the above contract, the purchaser reserves the right to change / reject / modify the
equipment / system during detail engineering.
1.5 Wherever material or article is specified or described by the name of particular brand,
manufacturer or vendor, the specific item mentioned shall be understood as established type
function and quality desired. Other manufacturer’s product will be considered provided
sufficient information is furnished to allow the purchaser to determine that the product
proposed is equivalent to those brands.
1.6 The entire system shall be designed and engineered by the Bidder based on the guidelines
furnished in the specification, various codes / standards. Bidder’s experience and also good
engineering practice. Items and quantities, which have been furnished in this specification, are
tentative and indicative only. During quoting, the Bidder shall vet the above Bill of Material and
may furnish additional items necessary for satisfactory operation of the system.
1.7 Supplies and services to be covered under this tender specification and the conditions thereof
are detailed in the subsequent sections of the specifications. In case of conflict among various
sections, subsections, documents, drawings the same shall be referred to purchaser whose
decision shall be final and binding to the Bidder. In all cases, the best advantages will go to the
purchaser.
1.8 Bidder to note that no technical deviation shall be permitted for the system
Electrically driven common Jockey pump multi out let type (two out lets) for both systems
th
(One outlet shall feed up to 14th floor at 120 MWC and other outlet shall feed from 15
onwards at 215MWC)
2.6 FIRE HYDRANT SYSTEM
A ring main at ceiling of Basement floor-1 with isolation valves.
Wet risers cum down comers for all Blocks
Landing Hydrants on all floors near Staircases inside the dedicated Shaft.
Fire Brigade Inlet connection for filling the Firewater tank as well as wet riser system.
2.7 WET RISER CUM DOWN COMER SYSTEM
Wet riser cum down comer for every 1000 sq.mts floor area for all buildings, there shall be
th th
two risers one shall feed up to 14 floor at 120MWCand other shall feed from 15 floor
onwards. at 215MWC for each Block (Tower – 7)
Wet riser cum down comer for every 1000 sq.mts floor area for all buildings.
This is to reduce the constant pressure on the equipment and same is ease to operate. All
wet risers are interconnected with Terrace level water tank with Booster pump to increase
the pressure in case of emergency.
The contractor shall guarantee both the material and workmanship of first class quality corresponding to standard
engineering practice. Any defective materials/workmanship shall be rejected, the contractor has to rectify/ replace at
his own cost. Guarantee certificate of the materials supplied shall be handed over to the clients.
SECTION - 5
EQUIPMENT SPECIFICATIONS
2.0 PIPING
All pipes inside the building and where specified, outside the building shall be M.S. tubes conforming to IS:
1239 - heavy duty up to 150 mm dia. Fittings for pipes shall be as per IS: 1239, Part II (heavy grade) up to
150mm dia,. and pipes 200mm dia & above shall be M.S. as per IS: 3589 with minimum 6 mm wall thick &
fittings shall be fabricated from pipes confirming to IS 3589.
Pipes shall be carefully laid to the alignment, levels and gradients shown on the plan and sections and great
care shall be taken to prevent any sand, earth or other matter from entering the pipes during laying. Pipes
shall be kept thoroughly clean during the course of laying. The ends of pipes shall be blocked with wooden
plugs wedged home, at the end of each days work to prevent dirt and rodents, insects etc., entering the
pipe.
Pipes up to 50mm dia, tapered screwed / Socket welded / Butt welded type jointing shall be adopted, while
for pipes above 50mm dia welded or flanged connections shall be used. Flanged joints shall be made with 3
mm thick insertion rubber washer / Gaskets. All boltholes in flanges shall be drilled & making hole by using
gas cutting is not acceptable. The drilling of each flange shall be in accordance with relevant Bureau of Indian
Standards.
Flanged joints shall be used for connections to vessel equipment, flanged valves and also on suitable straight
lengths of pipeline at strategic points to facilitate erection and subsequent maintenance work.
The Bolts /Nuts / Washers used in the system shall be Galvanised as per IS 1367 and suitable length & not
more than 15mm beyond the Nut.
17.6 ACCESSORIES
The engine shall be mounted on a base plate of fabricated steel construction. Adequate access shall be provided
for the big end and main bearings, camshaft and governor drives, water jackets etc., The engine shall have a base
plate made from MS sections. There shall be reasonable space at the big end, camshaft, water jackets, governor
drives and main bearings. The engine shall be provided with intake and discharge ductwork, inlet filter and
silencer, outlet muffler, expansion joints, dampers etc., as necessary for efficient operation. Intake air should be
taken from inside the building in which the engine is located, but the exhaust should be discharged outside the
building and exhaust duct shall be adequately sized for minimum pressure drop as per relevant code/standard, and
shall be housed clearing man height. The flywheel shall have graduated marking around the periphery to facilitate
checking of valve and fuel pump timings. Full set of diesel engine spares as per Standard requirement to be
provided along with tool kit.
Sprinkler main, branch and internal piping complete with valves, alarms and supporting arrangements, sprinkler
heads with spare sprinklers, connections to risers etc., all material shall be of the best quality conforming to
specifications and subject to the approval of the Authority’s Engineer. Pipes and fittings shall be fixed truly
vertical/horizontal or on slopes required in a neat manner. Pipes shall be fixed in such a manner so as to provide
easy accessibility for repair and maintenance and shall not cause obstruction in shafts, passages etc., Pipes shall be
securely fixed to walls and ceilings by suitable clamps at intervals specified. Only approved types of anchor
fasteners shall be used for RCC ceilings and walls. Valves and other equipment shall be so located that they are
easily accessible for operation, repairs and maintenance.
th
Sprinkler risers shall be of two pressure levels, one can feed up to 14 floor at 120mwc and other shall feed
th
from 15 floor onwards at 215mwc with necessary valves etc,-
C. ELECTRICAL WORKS
1.0 ELECTRICAL WORKS
1.1 General
The CONTRACTOR shall supply and install the electrical equipment and services necessary for the efficient
and safe operation of the fire protection systems detailed elsewhere in the specification, including :-
(a) Motors for Fire water pumps.
(b) MCC cum control panel housing the starters for all motors and complete with the switches, relays, push
buttons, indicating lamps, etc. necessary for the control of the fire protection system
(c) Power and control cabling between the MCC, motors, pressure switches, etc. including
accessories like conduits, cable trays ,etc.,
(d) To carry out the electrical installation works in accordance with specifications and as required by the local
statutory departments.
(e) To include the preparation of shop drawings and construction drawings for submission to the Consulting
Engineers to review prior to construction. Final as-built drawings after commissioning of the Fire Protection
System.
The enclosure shall be designed to provide an effective sealing between the primary and secondary air circuits.
Motor winding shall be vacuum impregnated with heat and moisture resistant varnish glass fiber insulated. Two
independent earthing points shall be provided in accordance with IS:3043 on opposite sides of the motor for
bolted connection. The cable boxes and termination shall be designed to enable easy disconnection and
replacement of cables.
The switch board shall be metal clad, totally enclosed, rigid, compartmentalized design, floor mounting, air
insulated, extensible cubicle type for use on medium voltage power, 3 phase 4 wire 50 cycles system. The degree
of protection shall be of IP55 in case of outdoor application as detailed in BOQ. The equipment shall be designed
for operation in high ambient temperature and high humidity tropical atmospheric conditions. Means shall be
provided to facilitate ease of inspection, cleaning and repairs for use in installations where continuity of operation
is of prime importance.
The entire logic of the fire protection system shall be built in this panel. It shall have necessary relays/contactors
for accepting contacts from Pressure/limit switches and for switching ON/OFF motors accordingly. It shall have
ammeter, voltmeter, start / stop push buttons, manual and automatic selector switches, pumps on, off, trip
indicating lamps, relays and other control equipment necessary for the efficient indication and operation of the
system. A visual and audio alarm shall also be provided to raise an alarm when any of the pumps is tripped. It
shall have provision for annunciating the water tank water level high / low / overflow conditions.
Provision shall be made for interfacing with the Building Automation system. Potential free contacts for motors
ON / OFF / TRIP, MCC trouble and fire water tanks level LOW/HIGH/OVERFLOW conditions be provided in the
control panel for BAS. Also provision shall be made for receiving signals from BAS.
2.2 STANDARDS
Following equipment shall conform to the requirements of :
Air Circuit Breaker (ACB) - IS 13947 - 1,2 / IEC 947 - 1,2
Moulded Case Circuit Breaker (MCCB) - IS 13947 - 1,2/ IEC 947 - 1&2
Contactors - IS 13947 - 1,4
Miniature Circuit Breaker (MCB) - IS 8828 - 1996/ IEC 898 - 1995
Residual Current Circuit Breaker (RCCB) - IS 12640 - 1988 / IEC 1008
HRC fuse link - IS 9224 and BS 8 :8
Current Transformer - IS 2705 and IEC 185
Potential Transformer - IS 3156
Relay - IS 3231 & IS 8686 (For Static Relays)
Indicating Instrument - IS 1248
2.3 CONSTRUCTION
The switch board shall be:
Sheet steel enclosed, indoor floor mounted free standing cubicle type. Made up of the requisite vertical
sections modular type which when coupled together shall form continuous dead front switchboards. Dust, vermin
and damp proof and enclosure protection not less than IP 52. Each feeder/instrument compartment shall be
provided with a hinged door interlocked with MCCB/SFU inside the compartment such that door can only be
opened when MCCB/SFU in off position. Readily extendable as required by the addition of vertical sections
after removal of the end covers. Switch boards shall have access to the feeders, bus bars, cable termination,
cable alley, etc. as required
Components forming part of the switchboards shall have the following minimum clearances:
Between phases - 25mm
Between phases and neutral - 25mm
Between phases and earth - 25mm
Between neutral and earth - 19mm
When, for any reason, the above clearances are not available, suitable insulation barrier/shielding shall
be provided. Clearances shall be maintained during normal service conditions. Creep age distances shall
comply with those specified in relevant standards. All insulating material used in the construction of the
equipment shall be of non-hygroscopic material treated to withstand the effects of high humidity, high
temperature and tropical ambient service conditions. Functional units such as circuit breakers, fuse switches,
MCCBs, etc. shall be arranged in multitier formation except that not more than two air circuit breakers shall be
housed in a single vertical section. Metallic/insulated shrouding shall be provided within vertical sections and
between adjacent sections to ensure prevention of accidental contact with: Main bus-bars and vertical risers
during operation, inspection or maintenance of functional units and front mounted accessories. Cable
terminations of one functional unit, when working on those of adjacent unit/units. All covers providing access
to live parts/circuits shall be provided with tool operated fasteners to prevent unauthorized access. Provision
shall be made for permanently earthing the frames and other metal parts of the switchgear by two independent
distinct connections. Only CRCA steel sheets shall be used for fabricating the cubicle. Thickness tolerance for
sheets shall be as applicable in relevant IS.
2.11 CONTACTORS
Contactor shall comply with IS 13947-1 for general rules and IS 13947 - 4.1 for Standards pertaining to Contactor
and Motor Starter. The Contactors shall be capable of withstanding breaking and making capacities per following
:
AC3 category AC4 category
Making Current 10 x Rated Current 12 x Rated Current
Breaking Current 08 x Rated Current 10 x Rated Current
Contactor shall be capable of withstanding an impulse voltage of 8KV and have an insulation voltage of 1000V.
Contactor shall be suitable for aluminum termination with a maximum permissible temperature rise of 650 C at
the terminals with an ambient temperature of 500 C. The coils shall have three terminals and the insulation
should be of class H type. The auxiliary contact block shall have a switching capacity of 220V, 2A. Contactor shall
have one auxiliary in built and it should be possible to have additional NO/NC contacts in steps of two. Miniature
Circuit Breakers [MCB] :
MCB shall be in 1,2,3,4, pole versions. MCB casing shall be made of self extinguishing, tropicalised material. MCB
shall comply with IS 8828-1996/IEC 898-1995. It shall be suitable for use in frequency range 40Hz to 60Hz and
shall accommodate AC/DC supply according to requirements. It shall have a trip-free mechanism and toggle shall
give a positive contact indication. It shall be suitable for mounting on 35mm DIN rail/surface mounting. It may be
installed horizontally, vertically on the ceiling in any place without any change in electrical performance. Line
supply may be connected to either top or bottom terminals i.e. There should be no line-load restriction. Degree of
protection when the MCB is flush mounted, shall be IP40. MCB shall be supplied with clamping terminals fully
open. Contact closing shall be independent of the speed of operator. The breaking capacity of the MCB shall be
9KA/10KA. The MCB shall be capable of being used as Incomer Circuit Breaker and shall be suitable for use as
isolator. In case of multiple MCBs in a single location (DB), it should be possible to remove any MCB without
having to disturb other MCB in the vicinity.
The FRLS outer sheath material shall meet the following requirements ( if used),
i) The oxygen index value shall be minimum 29 when tested at 27 2 C as per ASTM-D-
2863-77 and temperature index value shall be minimum 250 C when tested as per
NES 715.
ii) The maximum total acid gas generation as determined by titration shall be less than 20
% by weight. The test shall be conducted as per IEC-754-1 (1994).
iii) The smoke density shall be 60 % maximum, when tested as per ASTM-D-2843-77
(1988).
iv) The finished cable shall pass the flammability test as per IEC-332-1 (1993), In addition,
it shall also pass flammability test as per Class F3 of Swedish Standard SS-424-1475
(1978).
The sizes of cables shall be selected to limit the voltage drop during running and voltage dip during starting to 5%
and 10% respectively. Adequate derating factors shall be considered
3.2 RATING
The cable shall be rated for a voltage of 1100 Volts.
3.3 CORE IDENTIFICATIONS
Cores shall be provided with the following colour scheme of PVC insulation:
1 core : Red/Black/Yellow/Blue
2 core : Red and Black
3 core : Red, Yellow and Blue
3 1/2 / 4 core : Red, Yellow, Blue & Black
4.0 STORING, LAYING, JOINTING AND TERMINATIONS
4.1 STORING
On receipt of cables at site the cables shall be inspected and stored in a safe place.
4.2 LAYING
Cables shall be laid as per the specifications given below.
5.0 CABLES IN OUTDOOR TRENCHES
Cables shall be laid in outdoor trenches wherever called for. The depth of the trenches shall not be less
than 75 cm from the final ground level. The width of the trenches shall suit easy laying of cable. Where more
than one cable has to be laid in the same trench, all attempts shall be made to keep the axial distance between
successive cables to be at least 1d where 'd' is the diameter of the bigger cable. The trenches shall be cut square
with vertical side walls and with uniform depth. Wherever cables are bent, the minimum bending radius shall not
be less than 12 times the diameter of the cable. After the cable is laid and straightened, it shall be covered with
sand cushion. Over this a course of cable protection tiles or burnt brick shall be provided on either sides and
above. Trench shall be back filled with earth and consolidated. Cables shall be laid in hume pipes/stoneware
1.3. SUBMITTALS
A. GENERAL
1. Six copies of all submittals shall be submitted to the Architect/Engineer for review.
2. All references to manufacturer's model numbers and other pertinent information herein is intended to
establish minimum standards of performance, function and quality. Equivalent compatible equipment from other
manufacturers may be substituted for the specified equipment as long as the minimum standards are met.
3. All substitute equipment proposed as equal to the equipment specified herein, shall meet or exceed the
following standards. For equipment other than that specified, the contractor shall supply proof that such
1.7. APPROVALS
A. The design, supply, installation, testing and commissioning of the entire fire detection and alarm system
shall conform to EN 54,or BS: 5839. The Detectors shall conform to relevant codes for Fire Alarm System.
The system installed shall comply with the following codes/publications:
a) LPCB for addressable detector, fire panel.
b) EN 54
c) BS 5839
2.0 PRODUCTS
2.1. EQUIPMENT AND MATERIAL, GENERAL
A. All equipment and components shall be brand new, and the manufacturer's current model. The materials,
appliances, equipment and devices shall be tested and listed by a nationally recognized approvals agency for use as
part of a protected premises protective signaling (fire alarm) system. The authorized representative of the
manufacturer of the major equipment, such as control panels, shall be responsible for the satisfactory installation
of the complete system.
B. All equipment and components shall be installed in strict compliance with each manufacturer's
recommendations. Consult the manufacturer's installation manuals for all wiring diagrams, schematics, physical
equipment sizes, etc. before beginning system installation. Refer to the riser/connection diagram for all specific
system installation/termination/wiring data.
C. All equipment shall be attached to walls and ceiling/floor assemblies and shall be held firmly in place (e.g.,
detectors shall not be supported solely by suspended ceilings). Fasteners and supports shall be adequate to
support the required load.
2.2. CONDUIT AND WIRE
A. CONDUIT
1. Conduit shall be in accordance with The National Electrical Code (NEC), local and state requirements.
The panel shall also have automatic dialer with speech processor for transmit fire message to select
telephone numbers in case of fire.
The fire alarm control panel shall meet the modular listing requirements of Underwriters Laboratories
Inc. The control panel shall be capable of expansion via Loop cards. Each Loop shall support a minimum
of 100 analog addressable detectors/devices. The System shall be fail safe and adequate safe guards
should be under taken that in the event of a failure of a part of the System, say a loop card or CPU; it shall
not handicap the complete System. The Loop Control Module shall contain its own microprocessor and
shall be capable of operating in a local/degrade mode (any addressable device input shall be capable of
activating any or all addressable device outputs in that loop) in the unlikely event of a failure in the main
CPU.
The logic circuitry shall be based on high noise immunity solid state hardware.
All addressable units shall be connected to the FACP through the Loop Cards and shall be addressed
through individual numbers. The FACP shall be able to obtain analogue value for all detectors in the
circuit through a pulsed digitalized current data. The FACP shall be able to analyse all analogue inputs
from all addressable units, and through its own software and ambient level screening the FACP shall be
able to identify fire, possible fire or fault conditions. The unit supervision shall be dynamic and
continuous.
The FACP shall also give adequate warning signal whenever there is dust accumulation in detectors, and
up to the point of its replacement it should be possible to change the level of ambient alarm calibration
condition either by the use of software program operable by the owner or by resetting the detector.
Short / Open circuit units shall also be reported at the FACP In such cases, the system through the use of
fault isolators shall be able to isolate that segment between the two fault isolators. The missing
Detectors/Devices shall also be reported at the FACP with identification of the location.
The Bidder shall also undertake to trip the AHUs from the Fire Alarm Panel through the use of
Addressable Output Modules and necessary AC/DC relays, activated by the fire signal of specified
detectors and Input Modules for monitoring contacts from Fire exit doors.
The FACP shall also be able to discriminate between false alarms and fire conditions, as well as priority
selection of alarm in case alarm activates in two or more remotely located units simultaneously. In such
cases, the Manual Call Points shall have the highest priority.
It shall be able to withstand temperature variations from 00 centigrade to 500 centigrade. Further,
Relative Humidity (non-condensing type) up to 95% shall not hamper its performance. The voltage rating
shall be from 17V DC to 31V DC, though the voltage may be change depending upon the working voltages
of a proprietary FACP.
The FACP shall also capable of repeating all the events & messages to a Passive Repeater Panel.
The Fire Alarm Control Panel shall include a full featured operator interface control for the field
programming and control of the fire alarm system. All programming or editing of the existing program in
the system shall be achieved without special equipment and without interrupting the alarm monitoring
functions of the fire alarm control panel
Display & Indication : The backlit LCD display shall atleast be of 168 characters that indicate all
information associated with the fire alarm condition, including the type of alarm point and its location
within the protected premises. It shall also provide Light-Emitting-Diodes (LEDs), that indicate the status
of the following minimum system parameters: POWER STATUS, TEST STATUS, FIRE ALARM, FAULT, CPU
FAILURE, POINTS DISABLED etc.,
Alarm Acknowledge: Activation of the control panel acknowledges function in response to new alarms
and/or troubles shall silence the local panel piezo electric signal and the associated LED on the panel shall
be turned ON.
Signal Silence: Signal Silence function shall cause all programmed alarm notification appliances and relays
to return to the normal condition. The selection of notification circuits and relays that are silence able by
this switch shall be fully field programmable within the confines of all applicable standards.
System Reset: Depression of System Reset switch shall cause all electronically latched initiating devices to
return to their normal condition. And the system reset operation starts. The associated Yellow LED shall
flash during this operation to inform the user of the progress status of the reset cycle. The LED shall flash
fast during the smoke detector power down sequence, then it shall flash slowly during the restart phase,
and shall illuminate steadily for the restoral phase. The LED shall go out completely when the system is
back to normal mode.
Evacuation/ Fire drill: Depression of the Drill switch shall activate all programmed notification appliance
circuits. The drill function shall latch until the panel is silenced or reset.
System Programming: Advanced Windows based software shall be used to configure the system during
system start-up or system commissioning. Time and Date Stamps of all modifications made to the
program must be included to allow full retention of all previous program version data. All System
The panel shall provide means for all SLC devices on any SLC loop to be auto programmed into the system
by specific address. The system shall recognize specific device type ID's and associate that ID with the
corresponding address of the device.
Event Buffer: The panel shall maintain a history file of at least the last 1000 events, each with a time and
date stamp. History events shall include all alarms, troubles, operator actions, and programming entries.
Early warning capability: To obtain early warning of incipient or potential fire conditions, the system shall
support a programmable option to determine system response to real-time detector sensing values
above the programmed setting.
It shall be possible to set individual smoke detectors for pre-programmed pre-alarm thresholds. If the
individual threshold is reached, the pre-alarm condition shall be activated and an alert displayed on the
panel.
When the detector reaches a level exceeding the pre-programmed level, the control panel shall indicate
an action condition. Sounder bases installed with either heat or smoke detectors shall automatically
activate on action Pre-Alarm level, with general evacuation on alarm level.
Alarm verification delay: The FACP shall provide means to cause alarm signals to only sound in specific
areas with a delay of the alarm after start of alarm processing. If the alarm is not acknowledged within
programmed delay, all local and remote outputs shall automatically activate immediately. The control
panel shall ignore the alarm verification timer if another alarm is detected during the verification period.
Enable/ Disable points: The FACP shall allow the operator to restore a disabled point (device) in the
system, allowing that point (device) to operate as originally intended by the application program of the
system. Additionally, the system shall allow the operator to restore any group function, function, Panel,
system module, “software - defined zone”, operator control, or time control function.
The FACP shall allow the operator to disable any point (device) in the system, inhibiting that point
(device) from operating as originally intended by the application program of the system. Additionally, the
system shall allow the operator to disable any group function, function, Panel, system module, “software
- defined zone”, operator control, or time control function within the system.
Check/Alter parameters: The system shall allow the operator to manually turn on any system output
point, or system function. Alter Smoke Detector sensitivity, message routing within the system shall be
modifiable with this simple command from the control panel.
The system shall allow the operator to restore the primary (application program defined) operation to
the Smoke Detector sensitivity and the message routing functions with this simple command from the
control panel.
AHU Shutdown: The panel shall be capable of shutting down the AHUs in the event of Fire Alarm. It shall
be possible to program the shut on zone basis
Sensitivity Adjust: The system shall provide Automatic Detector Sensitivity Adjust based on Day/Night
schedules.
Environment Drift Compensation: The system shall automatically compensate for the drift in the sensitivity that
can occur due to dust & environment changes. Environmental compensation shall mean that the sensing element
adapts to long-term changes caused by dirt, humidity, aging etc. It shall even compensate for small amounts of
normal ambient smoke. The detector shall periodically adjust and updates the sensitivity (% obscuration) baseline
for its photoelectric sensing element. Periodically this information shall be written to its permanent memory.
When the detector accumulates dust in the chamber above the allowed limit, the control panel shall indicate a
maintenance urgent warning.
Response based on event: The panel software functions shall provide means to program a variety of
output responses based on various initiating events.
The system shall support at least 500 general purpose software zones for linking inputs to outputs. When
an input device activates, any zone programmed into that device's zone map will be active and any
output device.
Maintenance Menu: The Main LCD in the FACP shall also allow the System Operator to access system maintenance
functions through a multi level password system.
Enclosures: The control panel shall be housed in cabinet suitable for surface or semi-flush mounting. The
cabinet and front shall be corrosion protected, given a rust-resistant prime coat, and manufacturer's
standard finish.
The back box and door shall be constructed of steel with provisions for electrical conduit connections into
the sides and top.
The door shall provide a key lock and shall include a glass or other transparent opening for viewing of all
indicators. For convenience, the door may be site configured for either right or left hand hinging.
Power Supply: The Addressable Main / auxiliary Power Supply shall operate on 120/240 VAC, 50/60 Hz,
and shall provide all necessary power for the FACP and the notification appliances.
The Addressable Main Power Supply shall also incorporate a battery charger for 24 hours of standby
power for normal working & another ½ hour in alarm condition using dual-rate charging techniques for
fast battery recharge
The Addressable Main Power Supply shall provide a very low frequency sweep earth detect circuit,
capable of detecting earth faults.
Event Display: here shall be an event display field to display the current event. When there are no events
then it shall display an ALL CLEAR message. It shall be possible to manually scroll all the current events
both forwards & backwards. Facility shall be provided to add notes to the current event display. Each
type of event shall be represented in different colours It shall be possible to acknowledge the event
Status Bars shall be provided for events such as Fire, Fault, Disabled and warning. The Status Bar shall
flash in different colours when an event occur and shall revert back to its original status once the event is
acknowledged and are no other pending events for acknowledgement.
The scrolling of the current event display with corresponding graphics shall also be shown automatically.
It shall be possible to manually select, view the details of devices and zones by selecting the relevant sub
screens.
It shall also be possible to enable or disable any zone or device and the same shall be restricted to higher
level users only.
Control Functions: It shall be possible to mute the PC alarm sound and the fire Panel buzzer, activate &
silence all sounders and print automatically alarm events from the software. It shall be possible to
add/delete new users.
2. The two-wire monitor module shall mount in a 4-inch square (101.6 mm square), 2-1/8 inch (54 mm) deep
electrical box or with an optional surface backbox.
3. The IDC zone shall be wired for operation. An LED shall be provided that shall flash under normal
conditions, indicating that the monitor module is operational and in regular communication with the control panel.
C. ADDRESSABLE CONTROL MODULE
1. Addressable control modules shall be provided to supervise and control the operation of one
conventional devices of compatible, 24 VDC powered, polarized audio/visual notification appliances. For fan
shutdown and other auxiliary control functions, the control module may be set to operate as a dry contract relay.
2. The control module shall mount in a standard 4-inch square (101.6 mm square), 2-1/8 inch (54 mm) deep
electrical box, or to a surface mounted backbox.
3. The control module shall be wired with up to 1 amp of inductive A/V signal, or 2 amps of resistive A/V
signal operation, or as a dry contact relay. The relay coil shall be magnetically latched to reduce wiring connection
requirements, and to insure that 100% of all auxiliary relay may be energized at the same time on the same pair of
wires.
4. Audio/visual power shall be provided by a separate supervised power circuit from the main fire alarm
control panel or from a supervised remote power supply.
5. The control module shall be suitable for pilot duty applications and rated for a minimum of 0.6 amps at 30
VDC.
D. ADDRESSABLE RELAY MODULE
2. Shall be rated for fully charging a completely discharged battery within 48 hours while simultaneously
supplying any loads connected to the battery.
3. Shall have protection to prevent discharge through the charger.
4. Shall have protection for overloads and short circuits on both AC and DC sides.
3.0 EXECUTION
3.1. INSTALLATION:
A. Installation shall be in accordance with the NEC, NFPA 72, local and state codes and as recommended by
the major equipment manufacturer.
B. All conduit, junction boxes, conduit supports and hangers shall be concealed in finished areas and may be
exposed in unfinished areas. Smoke detectors shall not be installed prior to the system programming and test
period. If construction is ongoing during this period, measures shall be taken to protect smoke detectors from
contamination and physical damage. Conduits shall be marked in color for easy identification OR colored conduits
shall be used.
C. All fire detection and alarm system devices, control panels and remote annunciators shall be flush
mounted when located in finished areas and may be surface mounted when located in unfinished areas.
3.2. TEST
Provide the service of a competent, factory-trained engineer or technician authorized by the manufacturer of the
fire alarm equipment to technically supervise and participate during all of the adjustments and tests for the
system.
1. Before energizing the cables and wires, check for correct connections and test for short circuits, ground
faults, continuity, and insulation.
2. Close each sprinkler system flow valve and verify proper supervisory alarm at the FACP.
3. Verify activation of all flow switches.
4. Open initiating device circuits and verify that the trouble signal actuates.
5. Open signaling line circuits and verify that the trouble signal actuates.
6. Open and short notification appliance circuits and verify that trouble signal actuates.
7. Ground initiating device circuits and verify response of trouble signals.
8. Ground loop circuits and verify response of trouble signals.
9. Ground notification appliance circuits and verify response of trouble signals.
1.0 OBJECTIVES
The main objective of the Public Address System is to convey clear and audible instructions to all the
people on all floors / buildings incase of occurrence of fire / other emergency to reach a place of safety in
the open, outside the buildings. The sound output should not be so loud that people nearest to the
speakers feel uncomfortable, nor so weak that people away cannot discern what is being broadcast. This
is achieved by working the system at 60 to 75% power output and distributing speakers uniformly all over
floor area.
g. The racks shall have lockable steel doors having proper ventilation slots for heat dissipation.
h. Cable entry parts should be provided at the bottom.
I. Terminal blocks for connecting to control desk shall be provided.
1.4 SPEAKERS
The following type of speakers shall be used in public address system.
Wall mounted talk back speakers of 6 watts power rating on landings of staircases on all floors
1.3.2 CONDUITS
These shall be 16 swg mild steel, welded, thread type and having perfectly circular tubing and capable of
being cleaned and tight fitting joints. Conduits shall be laid either surface or in recess as required. All
conduits / junction / fittings should be painted with approved color and shall be marked for easy
identification.
1.6 WIRES
The wiring shall be approved make and PVC insulated copper multi strand as specified.
1.7 SAMPLES
The contractor shall submit the samples of all equipments for approval by architects / consultants before
installation.
F. FIRE EXTINGUISHERS
Fire extinguishers shall be in such a way that the occupants shall not travel more than 15m to reach a Fire
extinguisher. Also there shall be a Fire extinguisher for every 300 sq.m of floor plate / rooms of suitable
type / size. Fire extinguishers shall be on each landing of every floor, inside Electrical room, D.G. rooms,
Meter rooms, RMU and parking areas. In addition to above mention areas Extinguishers to be provided at
Surface car parks, out door Transformers / electrical instillations.
All Fire extinguishers shall be portable and hand held, a operating instruction should be pasted on the
extinguisher body.
Portable Fire extinguishers should be BIS approved and valid ISI certificates to be furnished at the time of
delivery to site.
G. SIGNAGE
st
Required, as per Local fire force like exit signs & Floor indication (Eg: Ground floor, 1 floor..), size shall
200mm x 500mm & action chart ( size shall be 600mm x 1000mm) in case of fire / emergency, Staircase
location indication etc. The location / quantity shall be on each landing of every staircase on each floor.
Signs shall be made out of 3mm thick PVC foam board with PVC non – reflective self-adhesive vinyl foam
board OR equivalent material with Mirror fasteners for fixing complete.
Please refer the specimen BOQ format for the details to be printed on the Fire order boards.
SECTION - 6
MAKE OF EQUIPMENT
NOTES:
. The VRF system’s Indoor and outdoor units shall be tested in accordance the provision of ARIstandards, AHRI -
1230 2009 for VRF System.
Refrigerant
-Type (R-410)
-Qty. Charged
-Any additional control or
features provided
Refrigerant
-Type (R-410)
-Qty. Charged
-Any additional control or
features provided
2.0
INDOOR UNITS (VRF SYSTEM)
1.6 TR 3.2 TR 4.0 TR 4.6 TR
Make
Model
Type
Cooling Capacity (TR) at
design conditions
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
1 VRF System
2 HRV Unit
5 G.I. Sheets
7 Copper Piping
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
SEAL OF COMPANY DATE _______________________
2. __________________________________ ________________________________
3. _________________________________ _______________________________
4. __________________________________ ________________________________
5. __________________________________ ___________________________
DECLARATION
I, _______________________, certify that all the furnished data and information pertaining to this offer are
correct and are true representation of the equipment offered by our proposal number_____________________
dated _____________.
I confirm that the plant offered has been designed to achieve performance as per the design
parameters and guarantee to achieve the same.
I confirm that I am duly authorized representative of the Bidder whose name appears below my signature.
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
The refrigerant piping interconnecting to indoor & outdoor units shall be made out of hard copper tubes, in brazed
construction. The refrigerant line sizing should be designed to achieve minimum pressure drop and avoid oil return
problem. The pipe sizes and connections shall be designed such that the evaporator units do not face back
pressure due to the functioning of the evaporator next to it. All suction piping shall be insulated with closed cell
elastomeric class ‘O’ nitrile rubber foam tubes of suitable diameter and thickness. All piping shall be neatly laid and
supported on galvanized perforated sheet metal trays and clamped firmly. Piping should be shrouded, where
necessary, to protect it from accidental damage/leaks during work by any agencies. All the wiring interconnecting
the indoor and outdoor units shall be PVC insulated copper conductor flexible wires of appropriate rating, and shall
be laid through PVC conduits. The refrigerant piping for the VRF system shall be of minimum wall thickness as per
Copper pipe- ASTM B88, L-Type standard HARD drawn copper pipes. The copper pipe shall be internally
chemically cleaned, free of dirt, dust, oxidation and any other deposits. All joints shall be made by brazing. Inert
gas purging shall be used during the brazing process to prevent oxidation Suction line shall be insulated with 19mm
thick sleeve made out of closed cell elastomeric nitrile rubber foam insulation of fire retardant ‘O’ class. Wiring
interconnecting the indoor and outdoor unit shall be done with PVC insulated copper conductor flexible wires of
appropriate rating. U-bends shall be provided for efficient oil return in suction line, at appropriate locations. All
piping shall be supported on GI perforated cable trays, and covered by GI sheet channels from the top, to prevent
accidental damage during work of other agencies. The GI covers and trays shall be fixed to MS angle supports by
bolting, to facilitate removal of the trays for verification of pipe leaks. All pipe supports/clamps shall be painted
with red oxide primer followed by 2 coats of synthetic enamel finish paint.
The piping and wiring shall be laid such that it does not spoil the aesthetics of the premises, and is safe, secure and
approachable for leak detection/repair/replacement.
1. SCOPE
The scope of this section will cover supply fabrication, installation and testing of all sheet metal ductsand diffusers
and balancing thereof in accordance with these specifications, general arrangement shownon the Drawings and
Bill of quantities.
Raw Material
1. Coil stock required to minimize longitudinal joints.
3. Dampers
All dampers shall be of robust construction and tightly fitting. The design, method of handling, andcontrol shall be
suitable for the location and service required. Dampers shall be provided with suitable links, levers and quadrants
as required for their proper operation. Control or setting devices shall be made robust, easily operable and
accessible through suitable access doors in the ducts. Every damper shall have an indicating device clearly showing
the damper position at all times. Dampers shall be placed in ducts and at every branch supply or return air duct
connection, whether or not indicated on the drawings, for the proper volume control and balancing of the system.
The entire air distribution system shall be balanced. Measured air quantities at fan discharge and atvarious outlets
shall be identical to or less than 5 percent in excess of those specified and quoted.
4.Acoustic Treatment
The material for acoustic treatment of ducts, shall be resin bonded fibre glass, as described earlier, conforming to
I.S. 8183 of 1976. The density of fibre glass shall be 32 kg/cub.m and the material shall be in the form of boards of
uniform density. The ‘k’ value at 10oC shall not be less than 0.03 W/mK. Facing shall be provided with 0.5 mm
perforated aluminium sheet held with G.I. Nuts bolts or nailed to the batten work as required.
5.Material Specifications
Ducts shall be made out of galvanized steel sheets of ducting quality. The galvanized sheet shall have thickness as
specified below and zinc coating of minimum 120 gms/sqm.
Fabrication of Ducts
The ducts shall be fabricated as per following specifications:
Up to 750 2.4 40 x 40 x 3 10
Duct hangers shall be fixed to R.C.C. slab of the roof by means of anchor fasteners and M.S. anglecleats. Hangers
for ducts running below pitched sheet roof shall be fixed to M.S. angle cleats weldedto roof structure. Soft
neoprene rubber gasket of uniform thickness and width shall be used as gasketbetween flange joints. The gasket
will be fixed with a suitable adhesive to the flange.
Galvanized hexagonal full threaded nut-bolts of minimum 6mm dia. shall be used for fastening theflanges. Spacing
between two nut-bolts shall not exceed 125mm.All ducts shall be rigid and shall be adequately supported and
braced where required with cross breaking of M.S. angle bracings of ample size to keep the ducts true to shape
and to prevent buckling, vibration or breathing.
Ducting over false ceiling shall be supported independently from the roof structure above. In no case a duct shall
be supported from the false ceiling hangers or be permitted to rest on a hung ceiling. Bottom level of all ducts
should be maintained as shown in the drawing. Leveling of ducts should be checked with a PVC tube water level
from a reference point.
Fans shall be connected to duct work by a double canvass sleeve. Each sleeve shall be minimum150mm long,
securely bolted to duct and units. Each sleeve shall be made smooth and the connectingduct work rigidly held in
line with unit inlet or outlet.
All grills/diffusers shall have soft continuous rubber/foam gasket between the periphery of the grills/diffusers and
surface on which it has to be mounted. The colour of grills/diffusers shall be as per the approval of the Engineer in
Charge
The colour of grills shall be as per the approval of the Engineer in Charge. The volume control device made of
extruded aluminium construction in black anodized finish shall be provided in supply air duct collars only.
All painting works shall form part of the cost of equipment, piping etc. No separate payment shall beapplicable.
1. Balancing:
Area-wise air balancing to establish air quantity as per design
2. Room Conditions:
Room conditions in each A/C Area to be recorded under full load conditions.
Corresponding ambient conditions should also be recorded.
niformity of temperature
NOTES:
1. After completing air & refrigerant-side balancing, the HVAC Contractor shall carry out testing of the entire HVAC
System; and submit specified test results to Consultant in a Test Results Format pre approved by the HVAC
Consultant. After carrying out modifications/balancing/corrections (as required),the Contractor shall carry out final
testing in the presence of representatives of IPR & the Architect KGA.
2. The VRF system’s Indoor and outdoor units shall be tested in accordance the provision of ARI standards, AHRI
-1230 2009 for VRF System.
3. In addition to the initial testing of the System on commissioning, two subsequent tests shall be carried outonein
the following summer and the second in the following monsoon.
4. Noise level & vibrations of all equipment shall be within acceptable limits appropriate for the application& use
of the Area.
5. All the instruments, special test materials (e.g. Nitrogen gas, helium gas for VAC) required for Testing
6. If additional parameters are required to be tested/measured for the purpose of troubleshooting, or
forestablishing performance of the system/equipment, or if required by the Consultant; the same shall becarried
out by the Contractor, without additional cost to the IPR.
7. In addition to the above, tests & measurements specified in Technical Specifications of the respectiveequipment
shall also be performed, and test-results thereof submitted.
SIGNATURE __________________________
NAME __________________________
DESIGNATION _______________________
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
5 G.I. Sheets
6 Nitrile Rubber Foam Insulation
7 Copper Piping
8 Metallic Grid Ceiling
9 G.S. Tiles for Grid Ceiling
SIGNATURE __________________________
NAME __________________________
2. __________________________________ ________________________________
3. __________________________________ ________________________________
4. __________________________________ ________________________________
5. __________________________________ ________________________________
6. __________________________________ ________________________________
DECLARATION
I, _______________________, certify that all the furnished data and information pertaining to this offer arecorrect
and are true representation of the equipment offered by our proposal number_____________________ dated
_____________.
I confirm that the plant offered has been designed to achieve performance as per the design parameters
andguarantee to achieve the same.
I confirm that I am duly authorized representative of the Bidder whose name appears below my signature.
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
Specification
2 for Portland Pozzolana Cement 1489-1976
Portland
3 Slag Cement (Fourth revision) 455-1989
Method
4 for physical tests for hydraulic cement (Reaffirmed 1980) 4031-1968
Method
5 of Chemical analysis for hydraulic cement (First revision) 4032-1985
II. AGGREGATES
Specification
1 for coarse and fine Aggregates from natural source for concrete 383-1970
(Second Revision)
Specification
2 for sand for masonry mortars 2116-1965
Method
3 of Tests for aggregates for concrete 2385-1969 (Part- I to
Part- VIV)
Standard
4 sand for testing of cement (First revision) with amendment 1 and 2 650-1966
Reaffirmed 1980
Methods
5 for sampling of aggregates for concrete 2430 -1969
Method
6 of test for determining aggregates impact value of soft coarse aggregates 5640-1970
III. STEEL
Code1of practice for bending and fixing of bars 2502-1963
Specification
2 for cold worked steel deformed bars for concrete reinforcement 1786-1979
Code3of practice for welding of MS Bars used for reinforced concrete construction. 2751-1966
Deformed
5 bars for concrete reinforcement hot rolled mild steel and medium 1139-1966
tensile steel (Revised)
Recommendations
6 for detailing of reinforcement in reinforced concreted works 5525-1969
Specification
7 for Mild Steel and medium tensile steel Bars for Concrete 432-1966(Part I)
reinforcement.
Code8for practice for safety and health requirement in Electric and Gas welding and 818-1968
cutting operations
Code9for practice for fire precautions in welding and cutting operation. 3016-1965
Measurement of building and Civil Engineering works, method part VIII steel work 1200-1974
and iron work (Part VIII)
Code of procedure for manual or metal ARC and welding of Mild steel 823-1964
Specification for filler rods and wires for gas welding 1278-1972
Recommendations for welding cold worked steel bars for reinforced concrete 9417-1979
construction
IV. CONCRETE
Method
1 of Measurement of building and Civil Engineer work Part-II cement 1200-1968
concrete works. (Part-II)
Code2of practice for plain and reinforced concrete 456-2000
Specification
3 for pre cast concrete coping blocks. 5751-1969
Methods
4 of tests for strength of concrete 516-1959
Code5of practice for laying in situ cement concrete lining on canals 3873-1993
Specification
6 for Admixtures for concrete 9103-1979
Specification
9 of Batch type concrete mixtures (Second Revision) 1791-1968
Specification for fly ash for use as pozzolana as admixture for Concrete 3812-1981
(Part-II)
Specification for Portable swing weigh batch for concrete (single and double bucket 2722-1964
type)
Code of practice for general construction of plain and reinforced concrete for dams 457-1957
and other massive structures
General requirement for concrete vibrator screed board type (First revision) 2506-1985
Code of practice for concrete structures for shortage of liquids 3370 (Part-1 to 4)
Code of practice for use of immersion vibrator for consolidating concrete (First 3558-1983
revision)
Specification
3 for admixtures for concrete (First Revision) 9103-1999
V. EARTH WORK
Method
1 of Measurement of building and Civil Engineering 1200-1969
Code3of practice for Design installation, observation and Maintenance of uplift 6532-1972
pressure pipes for Hydraulic structures on permeable foundation.
Safety
4 code for excavation works 3764-1966
Code5of practice for protection of slope for Reservoir embankment 8237-1985
Method
8 of test for soils Part-II Determination of water concrete 2720-1973
(Part-II)
Method
9 of test for soils Determination of water content dry density relation using 2720-1974
light compaction. (Part-VII)
Method of test for soils determination of dry density of soils in place by the sand 2720-1974
replacement method (Part-XXVIII)
Method of test for soils determination of dry density of soils in place by the core 2720-1975
cutter method (Part-XXIX)
Classification and identification of soils for general 1498-1970
Safety code for blasting and related drilling operation with Amendment No. I 4081-1967
(Reaffirmed 1978)
Guidelines for design of under seepage control measures for earth and rock fill 8414-1977
dams
Method for standard penetration test for soil (first revision) 2131-1981
Safety
2 code for scaffolds and ladders Part 2 ladders. 3696-1966
(Part-II)
Plywood
4 for general purposes ( Second revision amendment 1 to 3) 303-1975
Code7of for practice for in situ permeability test 5529 (Part-1 & 2)
Structural
8 steel (Standard quality) (with amendment No.1 to 3) IS: 226-1975
Specification for mild steel tubes, tubular and other wrought Steel fittings Part-I IS:1239-1979
mild steel tubes (fourth revision) (With Amendments No. 1 to 5)
Hard drawn steel wire fabric for concrete reinforcement (Second revision) IS: 1566-1982
Cast iron detachable joints for use with asbestos cement pressure pipes. IS:8794-1978
Code of practice for laying of cast iron pipe (With amendment No. I) IS: 3114-1965
Centrifugally cast (spun) iron low pressure pipes for water gas and sewage (First IS: 6163-1978
revision)
Cast iron detachable joints for use with asbestos cement pressure pipes IS: 8794-1978
Other Publications: Ministry of shipping and transport Specification for Road and No. 7900
Bridge works
Cut back
2 bitumen (Revised) IS: 217-1982
Glossary
3 of terms relating to bitumen and tar(2nd revision) IS:454-1961
Digboi
4 type cut back bitumen (revised) IS: 454-1961
Distributors
5 for hot tar and bitumen (first revision) IS: 2093-1974
Heaters
6 for tar and bitumen (first revision) IS: 2094-1974
Hot asphalt
7 mixing plants (with amendment No.1) IS: 3066-1965
Bitumen
8 emulsion for roads (anionic type) IS: 3117-1965
Asphalt
9 pavers’ finisher (first revision with amendment No.1) IS: 3251-1965
Method of test for determining aggregates impact value of soft coarse aggregates. IS: 5640-1970
Safety code for construction involving use of hot bituminous materials. IS: 5916-1970
Method of test for determination of stripping value of road aggregates. IS: 6241-1971
Coarse aggregates for water bound macadam (first revision) IS: 6579-1981
Method for testing tar and bituminous materials Determination of effect of heat IS: 9382-1979
and air by thin film over test.