NANDED CITY DEVELOPMENT &

CONSTRUCTION COMPANY LIMITED

METHOD STATEMENT
APPLICATION OF INTERNAL PAINT
TO WALLS & CEILING

NAME DATE SIGNATURE

PREPARED BY : G. Sai Prasanth

REVIEWED BY : Mr. Vipul Patil


REVISION STATUS

Rev No. Date of Rev. Description

00 12.01.2019 Initial Submission for Approval


TABLE OF CONTENTS

1. Scope ……………………………………………………………

2. Resources ………………………………………………………

3. Responsibility Matrix ………………………………………..

4. References …..…………………………………………………

5. Construction Procedure ……………………………………..

6. Construction Sequence ………………………………………

7. Control Measures ……………………………………………..

8. Records …………………………………………………………

9. Checklist ……………………………………………………….
1. Scope
The following method statement describes the work process for application of
Internal Painting to walls & Ceiling. This method statement has been developed
to provide a safe working system and must be adhered to at all times, any
significant deviation from this system must first be authorized by Project
Manger/Engineer or safety representative

2. Resources:

Material:

1.) New world Interior Primer

2.) New world putty

3.) New world Acrylic Distemper

Manpower:

1.) Painter

2.) Helper

Tools & Machinery:

1.) Steel trowel (straight edge).

2.) Aluminium Box section

3.) Plum bob

4.) Electrical Hand mixer

5.) Mixing rod

6.) Line string

7.) Manual Roller

10.) 4 inch Bristle Hair Brush

11.) Ladder

12.) Caution Board


3. Responsibility Matrix:

Responsible Accountable Consulted Inform

Vendor Site Engineer Sr. Engineer/ Project Manager


Manager

4. References:

 For –“Primer” refer Technical Data Sheet of New world Primer.


 For Putty refer Technical Data Sheet of New world wall care putty.
 For Internal Paint refer Technical Data Sheet of New world Acrylic Distemper
 Regarding Material Safety refer “Material Safety Data Sheets of “New world
Primer, New world wall care putty & New world Acrylic Distemper”

5. Construction Procedure

1. Before starting the Internal Painting work make sure that P.O.P work has
completed.
2. PP sheet should be laid on the flooring to avoid the damage to the floor from
paint.
3. Before starting painting work ensure that masking is done for kitchen otta,
doors, windows.
4. The surface should not be painted until it has dried completely. Trial patches
of primer shall be laid at intervals and where drying is satisfactory, painting
shall be then taken in hand
5. Clean the wall and ceiling area properly with emery paper 180 upon P.O.P
6. Apply 1st coat of wall Primer on ceiling followed by walls after sanding
with emery paper.
7. Allow it to dry for a minimum period of 6-8 hours.
8. Prepare acrylic putty and apply it on the ceiling to fill dents and cracks.
9. Apply putty on the ceiling followed by walls with the help of steel trowel.
10.Sand the surface with emery paper 180 to clean the surface
11.Apply 2nd coat of primer on ceiling and walls and allow it to dry for a
minimum period of 6-8 hours.
12.Sand the surface with emery paper 320.
13.Apply 1st coat of acrylic distemper with proportion of (1kg of paint : 600 ml
of water) on ceiling followed by walls.
14.Allow it to dry for 6 hours
15.Apply 2nd coat of acrylic distemper with proportion of (1kg of paint : 500
ml of water) on ceiling followed by walls.
16.Clean the surroundings and remove the masking’s

6. Construction Sequence/Flow Chart:

Surface
Take perCleaning with
Emery Paper

Apply 1st Coat Primer

Apply Wall Care Putty

Apply 1st coat Acrylic


Distemper

Apply 2nd coat Primer

Apply 2nd coat Acrylic


Distemper

Cleaning the surroundings


& Handling over
7. Control Measures

 Working Labour must be “competent” to carry out the task.

 Ensure that Painter & Helper follow the PPE’S & Safety Precautions

 Ensure that the working personnel should not lift beyond your capabilities, get
help if necessary.

 Ensure that while working in Heights ladder or working platform should be in a


safe condition.

 It is a must to follow all directions given by the site Engineer/Supervisor or his


agents.

 You must have suitable respiratory protection.

8. Records:

 Check List
 Inspection Test Report
 Clearances
CHECKLIST FOR INTERNAL PAINTING

Description Yes No
 Check for any cracks, or leakages before starting the work

 Check for the paint specification

 Ensure cleaning the surface with sand paper

 Check for cracks, dampness and any leakages to be

identified and repaired

 Check for kitchen otta, windows and doors, electrical switches

to be covered with masking tape.

 Check whether all PPE’s are followed by labours working on site like

Safety Helmets, Googles, Hand Gloves, Safety Shoes

 Ensure PP Sheet is Laid on the Flooring before

commencement of the work

 Ensure Hand Mixer is used for mixing the materials

 Ensure 1st coat Primer is applied on the surface

 Check Putty is Applied after 1st coat Primer to fill undulations

 Ensure 2nd coat Primer is applied on the surface

 Ensure 1st coat Acrylic Distemper is applied on Ceiling & Walls

 Ensure after completion of paint surrounding are cleaned