Sr.No. Description of System QTY

Part - 02 ….. Critical Room Air-Conditioning Work Details

A Supply of Hi-Side Ac Equipment’s in Rs…………..


job Work
B Installation Allied Low Side Work Ac Equipment’s in Rs…..
SUB TOTAL IN RS………..
Forwarding & Transportation, loading/unloading up to Site - 3%
GST @ 28 %
Mathadi Charges @ 1%
Total (Consolidated) for HVAC Works - Ex Taxes in Rs….
Note - Above Rates are excluding of all local taxes & Duties but the quantities are based on our Design Estimation. However, if the same ex
final bill & Work other than BOQ will be charge extra.

We hope that the above is self-explanatory; However, in case you require any information or clarifications on the subject matte
please feel free to call on us.

Yours truly,

transitions DESIGNS PVT. LTD.

Ar. Kapil Sedani


Cell - 91 98231 21877
Email - kapil@transitionsdesigns.com www.transitionsdesigns.
tions Designs Pvt. Ltd.
Turn-Key Project Solutions / Project Management Consulatants

lue Ridge, Hinjewadi - Pune. (Maharashtra - India)

BILL OF QUANTITY FOR HVAC WORK


fting of the following equipment / material and erection, testing and commissioning of the HVAC Work as
under:

DATE - 28th March 2018

transitions Designs Pvt. Ltd.


AMOUNT (INR) AMOUNT (INR) AMOUNT (INR)
Alternative- 01… With Alternative- 01… With Only
Alternative- 01… With Only
Complete Critical Room Ac Provisional Installtion Work
Ele./Ups Room Ac Provision
Provision of Critical Room Ac
179820.00 59940.00 0.00
363600.00 137720.00 363600.00
543420.00 197660.00 363600.00
As Applicable Extra
As Applicable Extra
As Applicable Extra
543420.00 197660.00 363600.00
sed on our Design Estimation. However, if the same exceed / receded the same will be added / subtracted from the

information or clarifications on the subject matter, or even our assistance in taking a decision on the same,

www.transitionsdesigns.com
transitions Designs Pvt. Ltd.
Architects / Interior Designers / Turn-Key Project Solutions / Project Management Consulata

PROJECT - P-24_IT -08 @ Blue Ridge, Hinjewadi - Pune. (Maharashtra - Ind

SCHEDULED BILL OF QUANTITY FOR CRITICAL AC WORK - 01

Designing, engineering, fabricating and supplying, unloading, shifting, lifting of the following equipment / material and
commissioning of the HVAC Work as under:
OUR;REF;- MR-Pune_HVAC-Blue Ridge IT-08/2017-18 DATE -
SR. NO ITEM DESCRIPTION QTY
UNIT RATES & PRICES IS BEEN FILLED FOR SUPPLY, INSTALLATION, TESTING, COMMISSIONING AND COMPREHENCIVE WARRANTEE & PREVE
FIRST YEAR FROM HAND OVER

PART…A………. Supply Of Air Conditioning Equipments……… TOSHIBA


2.0 Hi-Wall Split Air-Conditioning Equipments….. Stand Alone

Supply of Wall Mounted Aircooled Hi-Wall Split Air-conditioners complete with having Indoor,
Outoor machine with Recep/Rotary compressor technology,Refrigerant piping,controls,
condenser with weather proof IPS-55 Motor,inter-connecting Ref piping,wiring,starter/control
panel, Indoor,machines with Blower,Cooling coil and washable filters & inbuilt Digital type
Cordless remote Control Set (High End -INVERTER- 5 STAR RATING)

2.1 Capacity - 1.8 TR Design to work For Server- 01 Stand By 1.00


2.2 Capacity - 1.8 TR Design to work For Server-02… Stand by 1.00
2.3 Capacity - 1.8 TR Design to work For Electrical/Ups…Stand by 1.00
Basic Total In Rs………

PART…B………. Installation, Testing & Commissioning Charges of Air Conditioning Equipments………


Installation, testing & commissioning charges for following air conditioner Units……..(Including
a Loading, Unloading, Lifting/Shifting & Floor Placement)
For 2/1.5 TR Cassette/Hi-Wall Ac Units 3.00
Interconnected Refrigeration piping with 9mm thk superlon insulation couverd with black PVC
b tape of following sizes, -
For Size.. 5/8" x 3/8" Soft Drawn 244.00
c Interconnected Communication cabling between indoor to outdoor as required
For 2/1.5 TR Hi-Wall Ac Units 288.00
e 8 SWG GI wire for earthing for ODU 1.00
f End terminations of control cabling with luging, numbering & coading for safety control devices 1.00

HD-PVC Condenset Drain piping with 6mm thk superlon insulation & couvered with black PVC
g tape bfor following sizes, -
25mm dia 20.00
32 mm dia 40.00
40 mm dia 40.00
h Additional Oil & Regrigerant gas charging as required 1.00
i M.S. Outdoor Stand Fabrication for
For 2/1.5 TR Hi-Wall Ac Units 3.00
j Provision of Drian Pump Set with required control wiring & Flow Sensor 2.00
SUB TOTAL OF PART….B……IN INR…..

Total Project Cost In Rs………


Transpotation & Loading unloading Charges in Lumpsum basis
GST @ 28 %
Mathadi charges in Lumpsum Basis
GRAND TOTAL IN RS………..
Note - Above Rates are excluding of all local taxes & Duties but the quantities are based on our Design Estimation. However, if the same ex
will be added / subtracted from the final bill & Work other than BOQ will be charge extra.

TERMS OF PAYMENT ; For Ac Equipments…….100% advance with technically and commercially clear purchase order

TERMS OF PAYMENT ; For Low Side…….50% advance with technically and commercially clear purchase order, 40% Against Com
balance after satisfactory Commissioning /Handingover

DELIVERY ; We shall be able to deliver the Ac Equipments within 2 – 4 weeks from the date of receipt of your techno-commerc
Order with requisite advance, But Low Side Material may get Immediately against confirmation of your techno-commercially-c
requisite advance.

INSPECTION ; If necessary, the goods will be offered for visual inspection only at our supplier’s works. The date of inspection w
about 7 days in advance. If inspection is not carried out on the date so advised, we shall be free to dispatch the consignment a
delivery.

VALIDITY ; This offer is valid for a period of 30 days from the date stated hereof.

We hope that the above is self-explanatory; However, in case you require any information or clarifications on the subject matte
in taking a decision on the same, please feel free to call on us.

Yours truly,

transitions DESIGNS PVT. LTD.

Ar. Kapil Sedani


Cell - 91 98231 21877
Email - kapil@transitionsdesigns.com www.transi
s Pvt. Ltd.
t Management Consulatants

. (Maharashtra - India)

AC WORK - 01

g equipment / material and erection, testing and

DATE - 28th March 2018


UNIT UNIT RATE AMOUNT
HENCIVE WARRANTEE & PREVENTIVE MEINTENANCE FOR

Nos 59940.00 59940.00


Nos 59940.00 59940.00
Nos 59940.00 59940.00
179820.00

………

No. 6880.00 20640.00

RMT 880.00 214720.00

RMT 210.00 60480.00


Lot 3860.00 3860.00
Lot 3800.00 3800.00

RMT 210.00 4200.00


RMT 240.00 9600.00
RMT 280.00 11200.00
Lot 11460.00 11460.00

Nos 2680.00 8040.00


Sets 7800.00 15600.00
363600.00

543420.00
As Applicable Extra
As Applicable Extra
As Applicable Extra
543420.00
mation. However, if the same exceed / receded the same

ar purchase order

hase order, 40% Against Completion of Work and

ipt of your techno-commercially-clear Purchase


your techno-commercially-clear Purchase Order with

ks. The date of inspection will be intimated by us


dispatch the consignment as per the terms of

cations on the subject matter, or even our assistance

www.transitionsdesigns.com
transitions Designs Pvt. Ltd.
Architects / Interior Designers / Turn-Key Project Solutions / Project Management Consulata

PROJECT - P-24_IT -08 @ Blue Ridge, Hinjewadi - Pune. (Maharashtra - Ind

SCHEDULED BILL OF QUANTITY FOR CRITICAL AC WORK - 01

Designing, engineering, fabricating and supplying, unloading, shifting, lifting of the following equipment / material and
commissioning of the HVAC Work as under:
OUR;REF;- MR-Pune_HVAC-Blue Ridge IT-08/2017-18 DATE -
SR. NO ITEM DESCRIPTION QTY
UNIT RATES & PRICES IS BEEN FILLED FOR SUPPLY, INSTALLATION, TESTING, COMMISSIONING AND COMPREHENCIVE WARRANTEE & PREVE
FIRST YEAR FROM HAND OVER

PART…A………. Supply Of Air Conditioning Equipments……… TOSHIBA


2.0 Hi-Wall Split Air-Conditioning Equipments….. Stand Alone

Supply of Wall Mounted Aircooled Hi-Wall Split Air-conditioners complete with having Indoor,
Outoor machine with Recep/Rotary compressor technology,Refrigerant piping,controls,
condenser with weather proof IPS-55 Motor,inter-connecting Ref piping,wiring,starter/control
panel, Indoor,machines with Blower,Cooling coil and washable filters & inbuilt Digital type
Cordless remote Control Set (High End -INVERTER- 5 STAR RATING)

2.3 Capacity - 1.8 TR Design to work For Electrical/Ups…Stand by 1.00


Basic Total In Rs………

PART…B………. Installation, Testing & Commissioning Charges of Air Conditioning Equipments………


Installation, testing & commissioning charges for following air conditioner Units……..(Including
a Loading, Unloading, Lifting/Shifting & Floor Placement)
For 2/1.5 TR Cassette/Hi-Wall Ac Units 1.00
Interconnected Refrigeration piping with 9mm thk superlon insulation couverd with black PVC
b tape of following sizes, -
For Size.. 5/8" x 3/8" Soft Drawn 88.00
c Interconnected Communication cabling between indoor to outdoor as required
For 2/1.5 TR Hi-Wall Ac Units 110.00
e 8 SWG GI wire for earthing for ODU 1.00
f End terminations of control cabling with luging, numbering & coading for safety control devices 1.00

HD-PVC Condenset Drain piping with 6mm thk superlon insulation & couvered with black PVC
g tape bfor following sizes, -
25mm dia 10.00
32 mm dia 40.00
40 mm dia 0.00
h Additional Oil & Regrigerant gas charging as required 1.00
i M.S. Outdoor Stand Fabrication for
For 2/1.5 TR Hi-Wall Ac Units 1.00
j Provision of Drian Pump Set with required control wiring & Flow Sensor 1.00
SUB TOTAL OF PART….B……IN INR…..

Total Project Cost In Rs………


Transpotation & Loading unloading Charges in Lumpsum basis
GST @ 28 %
Mathadi charges in Lumpsum Basis
GRAND TOTAL IN RS………..
Note - Above Rates are excluding of all local taxes & Duties but the quantities are based on our Design Estimation. However, if the same ex
will be added / subtracted from the final bill & Work other than BOQ will be charge extra.

TERMS OF PAYMENT ; For Ac Equipments…….100% advance with technically and commercially clear purchase order

TERMS OF PAYMENT ; For Low Side…….50% advance with technically and commercially clear purchase order, 40% Against Com
balance after satisfactory Commissioning /Handingover

DELIVERY ; We shall be able to deliver the Ac Equipments within 2 – 4 weeks from the date of receipt of your techno-commerc
Order with requisite advance, But Low Side Material may get Immediately against confirmation of your techno-commercially-c
requisite advance.

INSPECTION ; If necessary, the goods will be offered for visual inspection only at our supplier’s works. The date of inspection w
about 7 days in advance. If inspection is not carried out on the date so advised, we shall be free to dispatch the consignment a
delivery.

VALIDITY ; This offer is valid for a period of 30 days from the date stated hereof.

We hope that the above is self-explanatory; However, in case you require any information or clarifications on the subject matte
in taking a decision on the same, please feel free to call on us.

Yours truly,

transitions DESIGNS PVT. LTD.

Ar. Kapil Sedani


Cell - 91 98231 21877
Email - kapil@transitionsdesigns.com www.transi
s Pvt. Ltd.
t Management Consulatants

. (Maharashtra - India)

AC WORK - 01

g equipment / material and erection, testing and

DATE - 28th March 2018


UNIT UNIT RATE AMOUNT
HENCIVE WARRANTEE & PREVENTIVE MEINTENANCE FOR

Nos 59940.00 59940.00


59940.00

………

No. 6880.00 6880.00

RMT 880.00 77440.00

RMT 210.00 23100.00


Lot 1860.00 1860.00
Lot 1800.00 1800.00

RMT 210.00 2100.00


RMT 240.00 9600.00
RMT 280.00 0.00
Lot 4460.00 4460.00
Nos 2680.00 2680.00
Sets 7800.00 7800.00
137720.00

197660.00
As Applicable Extra
As Applicable Extra
As Applicable Extra
197660.00
mation. However, if the same exceed / receded the same

ar purchase order

hase order, 40% Against Completion of Work and

ipt of your techno-commercially-clear Purchase


your techno-commercially-clear Purchase Order with

ks. The date of inspection will be intimated by us


dispatch the consignment as per the terms of

cations on the subject matter, or even our assistance

www.transitionsdesigns.com
transitions Designs Pvt. Ltd.
Architects / Interior Designers / Turn-Key Project Solutions / Project Management Consulata

PROJECT - P-24_IT -08 @ Blue Ridge, Hinjewadi - Pune. (Maharashtra - Ind

SCHEDULED BILL OF QUANTITY FOR CRITICAL AC WORK - 01

Designing, engineering, fabricating and supplying, unloading, shifting, lifting of the following equipment / material and
commissioning of the HVAC Work as under:
OUR;REF;- MR-Pune_HVAC-Blue Ridge IT-08/2017-18 DATE -
SR. NO ITEM DESCRIPTION QTY
UNIT RATES & PRICES IS BEEN FILLED FOR SUPPLY, INSTALLATION, TESTING, COMMISSIONING AND COMPREHENCIVE WARRANTEE & PREVE
FIRST YEAR FROM HAND OVER

PART…A………. Supply Of Air Conditioning Equipments……… TOSHIBA


2.0 Hi-Wall Split Air-Conditioning Equipments….. Stand Alone

Supply of Wall Mounted Aircooled Hi-Wall Split Air-conditioners complete with having Indoor,
Outoor machine with Recep/Rotary compressor technology,Refrigerant piping,controls,
condenser with weather proof IPS-55 Motor,inter-connecting Ref piping,wiring,starter/control
panel, Indoor,machines with Blower,Cooling coil and washable filters & inbuilt Digital type
Cordless remote Control Set (High End -INVERTER- 5 STAR RATING)

2.1 Capacity - 1.8 TR Design to work For Server- 01 Stand By 0.00


2.2 Capacity - 1.8 TR Design to work For Server-02… Stand by 0.00
2.3 Capacity - 1.8 TR Design to work For Electrical/Ups…Stand by 0.00
Basic Total In Rs………

PART…B………. Installation, Testing & Commissioning Charges of Air Conditioning Equipments………


Installation, testing & commissioning charges for following air conditioner Units……..(Including
a Loading, Unloading, Lifting/Shifting & Floor Placement)
For 2/1.5 TR Cassette/Hi-Wall Ac Units 3.00
Interconnected Refrigeration piping with 9mm thk superlon insulation couverd with black PVC
b tape of following sizes, -
For Size.. 5/8" x 3/8" Soft Drawn 244.00
c Interconnected Communication cabling between indoor to outdoor as required
For 2/1.5 TR Hi-Wall Ac Units 288.00
e 8 SWG GI wire for earthing for ODU 1.00
f End terminations of control cabling with luging, numbering & coading for safety control devices 1.00

HD-PVC Condenset Drain piping with 6mm thk superlon insulation & couvered with black PVC
g tape bfor following sizes, -
25mm dia 20.00
32 mm dia 40.00
40 mm dia 40.00
h Additional Oil & Regrigerant gas charging as required 1.00
i M.S. Outdoor Stand Fabrication for
For 2/1.5 TR Hi-Wall Ac Units 3.00
j Provision of Drian Pump Set with required control wiring & Flow Sensor 2.00
SUB TOTAL OF PART….B……IN INR…..

Total Project Cost In Rs………


Transpotation & Loading unloading Charges in Lumpsum basis
GST @ 28 %
Mathadi charges in Lumpsum Basis
GRAND TOTAL IN RS………..
Note - Above Rates are excluding of all local taxes & Duties but the quantities are based on our Design Estimation. However, if the same ex
will be added / subtracted from the final bill & Work other than BOQ will be charge extra.

TERMS OF PAYMENT ; For Ac Equipments…….100% advance with technically and commercially clear purchase order

TERMS OF PAYMENT ; For Low Side…….50% advance with technically and commercially clear purchase order, 40% Against Com
balance after satisfactory Commissioning /Handingover

DELIVERY ; We shall be able to deliver the Ac Equipments within 2 – 4 weeks from the date of receipt of your techno-commerc
Order with requisite advance, But Low Side Material may get Immediately against confirmation of your techno-commercially-c
requisite advance.

INSPECTION ; If necessary, the goods will be offered for visual inspection only at our supplier’s works. The date of inspection w
about 7 days in advance. If inspection is not carried out on the date so advised, we shall be free to dispatch the consignment a
delivery.

VALIDITY ; This offer is valid for a period of 30 days from the date stated hereof.

We hope that the above is self-explanatory; However, in case you require any information or clarifications on the subject matte
in taking a decision on the same, please feel free to call on us.

Yours truly,

transitions DESIGNS PVT. LTD.

Ar. Kapil Sedani


Cell - 91 98231 21877
Email - kapil@transitionsdesigns.com www.transi
s Pvt. Ltd.
t Management Consulatants

. (Maharashtra - India)

AC WORK - 01

g equipment / material and erection, testing and

DATE - 28th March 2018


UNIT UNIT RATE AMOUNT
HENCIVE WARRANTEE & PREVENTIVE MEINTENANCE FOR

Nos 59940.00 0.00


Nos 59940.00 0.00
Nos 59940.00 0.00
0.00

………

No. 6880.00 20640.00

RMT 880.00 214720.00

RMT 210.00 60480.00


Lot 3860.00 3860.00
Lot 3800.00 3800.00

RMT 210.00 4200.00


RMT 240.00 9600.00
RMT 280.00 11200.00
Lot 11460.00 11460.00

Nos 2680.00 8040.00


Sets 7800.00 15600.00
363600.00

363600.00
As Applicable Extra
As Applicable Extra
As Applicable Extra
363600.00
mation. However, if the same exceed / receded the same

ar purchase order

hase order, 40% Against Completion of Work and

ipt of your techno-commercially-clear Purchase


your techno-commercially-clear Purchase Order with

ks. The date of inspection will be intimated by us


dispatch the consignment as per the terms of

cations on the subject matter, or even our assistance

www.transitionsdesigns.com

You might also like