Extra Providing & fixing 200 mm dia PVC Pipe ( 6 kg / cm2 ) below the Concrete to interconnect

Item the drains in the Basement 3 level


Sr.No. Description Unit Rate Qty. Total Remarks
A Material Cost For 1 R.M. ( Landed Price )
1 200 mm dia PVC Pipe ( 6 kg / cm2 ) R.M. 1,400.00 1.1 1,540.00 Including 10 % wastage
Per piece rate is 550 /- for
2 200 mm dia PVC Pipe coupling R.M. 191.00 1 191.00 3 mtr of pipe 1 nos , 575 /
3 = 191
Considering cement /
3 Bedding Mortar R.M. 100.00 1 100.00 sand
Total Material Cost 1,831.00
B Labour cost
Labour cost for laying PVC pipe below
concrete for interconnecting drains in
1 proper R.M. 200 1 200.00
slope line and Level including laying
mortar bed etc complete
Total Labour Cost 200.00
Total M + L 2,031.00
Add: Sundries @ 3.00% 60.93
Total 2,091.93
Add: OH & P charges 15.00% 313.79
Total 2,405.72
Say 2,405.00 Per R.M.
Providing & fixing Minimum 3 mm thick Polypropylene copolymer is injection moulded
Extra around a 12 mm dia tor-steel bar ( Orange Color Foot Step with 2 mm tread on Top Surface
Item dots for providing an antiskid surface ) in The Domestic and fire Tanks of size 260 mm x 165
mm in line , level and as per the location shown in the drawing etc Complete.

Sr.No. Description Unit Rate Qty. Total Remarks


A Material Cost For 1 No

Manufacturers K.K
1 Orange Color Foot mm
step size 260mm x 165 No 80.00 1 80.00 Manholes and Grating Pvt
ltd

Considering 6000 Rs for


2 Cost of Transportation No 20.00 1 20.00 300 Nos
Total Material Cost 100.00
B Labour cost

Labour cost for fixing foot step in line , level


1 as per the location shown I the drawing No 100 1 100.00
including making holes and seal it after
fixing completed in the form work

Total Labour Cost 100.00


Total M + L 200.00
Add sundries 3% 6.00
Total 206.00
Add: OH & P charges 15.00% 30.90
Total 230.90
Say 231.00 Per No
Say Rs Two Hundred and Thirty one only