In the process of designing a water reticulation system. A research was conducted to find out the technical and
practical aspects of such an undertaking. Based on this research, calculations were done to determine the various
parameters that would make this a pragmatic design. The size of the tank, the types of pipes, height of the tank
stand, the flow rate and velocity were determined. The tank size was double the daily water consumption
requirements of the community for contingency purposes. The pipe size from the pump to the tank was selected
based on the diameter of the pump’s outlet. The size of the pipe from the outlet of the tank was chosen based on
its advantages in terms of velocity. The size of the pipes connecting the tank’s outlet pipe to the households were
chosen based on research.
Table of Contents
ABSTRACT ......................................................................................................................................................................1
1.0.Introduction .............................................................................................................................................................3
2.0 BACKGROUND THEORY ............................................................................................................................................4
2.1 FLOW RATE ..........................................................................................................................................................4
2.2 DERIVATION OF FLOW RATE ................................................................................................................................4
3.0 DESIGN AND PROCEDURE ........................................................................................................................................6
3.1 POPULATION ........................................................................................................................................................6
TABLE 3.1.2. ESTIMATED PRESENT WATER NEEDS ................................................................................................6
3.2 STORAGE TANK ....................................................................................................................................................7
3.3 PIPE SIZE...............................................................................................................................................................7
3.3.1 𝟏𝟏𝟒 Inch ..........................................................................................................................................................8
3.3.2 1inch .................................................................................................................................................................8
3.3.3 2inch ................................................................................................................. Error! Bookmark not defined.
3.4 Calculations showing the flow rate and speed from the outlets of the tank and 1inch pipe. .............................9
4.0 CONCLUSION .........................................................................................................................................................10
5.0 REFERENCES ...........................................................................................................................................................11
1.0.Introduction
A water reticulation system is in basic terms how water is distributed at various point in a
network .This distribution is made possible by use of pipes, tanks and boreholes. For this
system to function a good design is of the essence.
The primary aim of this project is to design a water reticulation system that will supply a
community of ten (10) households with an average of four (4) people per house. This project
focuses on the design of the water reticulation system.
Objectives
Determine the amount of water required by an individual per day.
Determine the amount of water required by a single household per day.
Determine the amount of water required by the community.
Determine the size of the tank required by the community.
Determine the sizes of the pipes to be used at various point in the system.
To show the engineering drawing of the designs.
Our problem was solve by determining an appropriate design of the system, the right size of the
tank and the sizes of pipes to be used at various points. In our case we chose a 5000Litres
1
tank, a. 1 4 inch from the pump to the storage tank, a 2inch pipe for the main supply pipe and
1inch pipes from the main supply to each household.
2.0 BACKGROUND THEORY
In our design of the water reticulation system, it was cardinal to determine the mass flow rate. This was
imperative in determining the velocity of the water in the household supplying pipes.
Flow rate refers to the measure of the volume of the liquid per unit of time. It is dependent on the area
of the path that the liquid is flowing through and the velocity of the liquid through it.
Consider an incompressible fluid (e.g. water) flowing through a pipe as shown in figure 2.1
𝑉 =𝐴×𝐿 eq.2.1
But the velocity (v) is given by distance peer unit time I.e.
𝑣 = 𝑙/𝑡 eq.2.3
The volumetric flow rate must be the same for both pipes. Because we cannot gain or lose any fluid thus
Eq.2.4
𝑄 = 𝑉1 𝐴1 = 𝑉2 𝐴2 eq2.5
This is referred to as the continuity equation and is true for any changes in pipe diameter for a single
flow path
3.0 DESIGN AND PROCEDURE
3.1 POPULATION
=4 × 10
=40 PEOPLE
40 60 2400
The tank size was doubled taking into account various water usages stated below;
Irrigation
Losses such as leakages
Water for domestic usage
Water for domestic animals
= 4800L
3.2 STORAGE TANK
The standard tank size for the design chosen was 5000L. This tank is made up of polyethylene. The reason
the tank design was made of this material was because this was the most recommended material for the storage
of drinking water. The figure below shows an example of the ideal tank chosen for the design
Having conducted a research, pipe size from the pump to tank was selected on the basis of the pump
used. For this design the pump selected was DSP 1-10 as in appendix B. DSP 1-10 has an outlet diameter
1
of 1 4inch which requires that the pipe attached should be of the same diameter. Based on the same
research, the recommended outlet pipe from the storage tank was 2inch and the pipe size branching
from the main supply to each house-hold is 1 inch
All pipes used in this design are Poly Vinyl Chloride (PVC) which have now become a replacement for metal piping.
The following advantages where the key factors in helping make this selection. These include;
Corrosion resistant ;corrosion is one of the most harmful and threatening issues, especially in water pipes, as
it threatens our ability to get safe and pure drinking water.
Light weight; the low weight facilitates easy and effortless installation without the risk of getting injured or
needing a large workforce.
This was the pipe chosen from the borehole to the inlet of the tank.
This pipe was used from the main supply to each household
This is the main supply pipe from the outlet of the tank
3.4 Calculations showing the flow rate and speed from the outlets of
𝑄 = 𝑉1 𝐴1
=2.48 × 10−3 𝑚3 /𝑠
Where v1 is the velocity of the water from the outlet of the tank in the 2inch diameter pipe and A1 is
the cross section area of the 2inch dimeter pipe
Where v2 is the velocity of water in the 1inch diameter pipe and A2 is the cross area of the 1inch pipe.
𝑄 = 𝑉2 𝐴2
𝑉2 = 𝑄/𝐴2
= (2.84 × 10−3 × 4)/(𝜋 × 25.82 × 10−6 )
5.43𝑚/𝑠
4.0 CONCLUSION
The water reticulation system design was finalized. This was achieved through the subsequent
completion of each objective. This included determining the amount of water required by the
community, the tank size, and the pipe sizes finally the drafting of a suitable engineering drawing using
Computer Aided Design Software. By and large, the project was a success. Further alterations and
upgrades to this project will include an electrical system which will be the main concern of future
projects relating to this one.
5.0 REFERENCES