PLANILLA DE METRADOS VIVIENDA MULTIFAMILIAR

1.00 TRABAJOS PRELIMINARES


1.01 LIMPIEZA DEL TERRENO (m2)
DESCRIP. # VECES LARGO ANCHO ALTO AREA m2 VOLUMEN
AREA TOTAL DEL TERRENO 1 8.50 4.19 35.62
TOTAL 35.62

1.02 TRAZO Y REPLANTEO DEL TERRENO (m2)

DESCRIP. # VECES LARGO ANCHO ALTO AREA m2 VOLUMEN


AREA TOTAL DEL TERRENO 1 8.50 4.19 35.62
TOTAL 35.62

2.00 MOVIMIENTO DE TIERRAS


2.01 EXCAVACIONES DE CIMIENTOS CORRIDOS (m3)

DESCRIP. # VECES ANCHO LARGO ALTO AREA VOLUMEN m3


EJE A-A TRAMO 1-2 1 0.60 1.10 1.25 0.825
EJE A-A TRAMO 2-3 1 0.60 1.10 1.25 0.825
EJE B-B TRAMO 1-2 1 0.60 1.10 1.25 0.825
EJE B-B TRAMO 2-3 1 0.60 1.10 1.25 0.825
EJE 1-1 TRAMO A-B 1 0.60 0.99 1.25 0.7425
EJE 3-3 TRAMO A-B 1 0.60 0.99 1.25 0.7425
TOTAL 4.785

2.02 EXCAVACIONES DE ZAPATAS m3

DESCRIP. # VECES ANCHO LARGO ALTO AREA VOLUMEN m3


ZAPATA Z-1 un solo tipo de zapata 6 1.60 1.60 0.60 9.216
TOTAL m3 9.216
2.02.01 EXCAVACIONES SOBRE LAS ZAPATAS (incluye viga y sobrecimiento)

DESCRIP. # VECES ANCHO LARGO ALTO VOLUMEN m3


SOBRE LA ZAPATA 6 1.60 1.60 0.75 11.52
TOTAL m3 11.52

TOTAL DE EXCAVACIONES: 25.52 (m3)


FACTOR DE EXPONJAMIENTO: 31.90 (m3)

2.03 RELLENOS CON MATERIAL DE PRESTAMOS (AFIRMADO) (m3)

DESCRIP. # VECES ANCHO LARGO ESPESOR AREA VOLUMEN m3


EN TODA EL AREA DE LA VIVIENDA CONSTRUIDA 1 4.19 7.00 0.10 2.933
TOTAL 2.933

2.04 RELLENOS CON MATERIAL PROPIO EN CIMIENTOS CORRIDOS(m3)


DESCRIP. # VECES ANCHO LARGO ALTO VOLUMEN m3
2 0.30 1.10 0.40 0.264
EJE A-A dividimos en dos partes
2 0.45 1.10 0.25 0.2475
2 0.30 1.10 0.40 0.264
EJE B-B dividimos en dos partes
2 0.45 1.10 0.25 0.2475
1 0.30 0.99 0.40 0.1188
EJE 1-1 y 3-3 dividimos en dos partes
EJE 1-1 y 3-3 dividimos en dos partes
1 0.45 0.99 0.25 0.1114
TOTAL 1.253175

RELLENOS CON MATERIAL PROPIO EN ZAPATAS (m3)


h: 0.65
DESCRIP. # VECES ANCHO LARGO ALTO VOLUMEN m3
ZAPATA Z-1 UN SOLO MODELO PARA RELLENO 6 1.3350 1.60000 0.65000 8.33
TOTAL m3 8.33

2.06 ELIMINACION DEL MATERIAL EXCEDENTE (m3)


tierra suelta E = 25%

volumen excavado - volumen de relleno propio

DESCRIP. VOLUMEN (m3) COEFICIENTE #VECES PARCIAL (m3)


VOLUMEN EXCAVADO 25.52 1.25 1 31.90125
VOLUMEN DE RELLENO PROPIO 12.516575 0.90 1 11.2649175
TOTAL (m3) 43.1662

3.00 CONCRETO SIMPLE (m3)

3.01 Cimientos Corridos Concreto Ciclopeo (Cº Cº) (m f'c 210 Kg/cm2

DESCRIP. # VECES ANCHO LARGO ALTURA PARCIAL m3


EJE 1-1 TRAMO A-B 1 0.45 0.99 0.50 0.22
EJE 2-2 TRAMO A-B 1 0.45 0.99 0.50 0.22
EJE 3-3 TRAMO A-B 1 0.45 0.99 0.50 0.22
EJE B-B TRAMO 2-3 1 0.60 1.10 0.50 0.33
EJE A-A TRAMO 1-2 1 0.60 1.10 0.50 0.33
EJE A-A TRAMO 2-3 1 0.60 1.10 0.50 0.33
EJE B-B TRAMO 1-2 1 0.60 1.10 0.50 0.33
TOTAL 1.99
3.02 SOLADOS EN ZAPATAS (m2)

DESCRIP. # VECES ANCHO LARGO ALTURA PARCIAL m2


ZAPATA 01 UN SOLO MODELO 6 1.60 1.60 0.10 15.36
TOTAL 15.36

3.02 FALSOS PISOS (m2)


DESCRIP. # VECES ANCHO LARGO PARCIAL m2
AREA DE TODA LA HABITACION se calculo en la maquina (autocad) 25.732
TOTAL DE TODA EL AREA se calculo en la maquina (autocad) 25.732

3.03 ENCOFRADOS Y DESENCOFRADOS EN SOBRECIMIENTOS (m2)

DESCRIP. # VECES ANCHO LARGO ALTURA PARCIAL m2


EJE 1-1 TRAMO A-B 2 3.60 0.50 3.60
EJE 2-2 TRAMO A-B 2 3.60 0.50 3.60
EJE 3-3 TRAMO A-B 2 3.60 0.50 3.60
EJE A-A TRAMO 1-2 2 2.90 0.50 2.90
EJE A-A TRAMO 2-3 2 2.90 0.50 2.90
EJE B-B TRAMO 1-2 2 2.90 0.50 2.90
EJE B-B TRAMO 2-3 2 2.90 0.50 2.90
TOTAL 22.40

3.04 CONCRETO CICLOPEO EN SOBRECIMIENTOS (m3)

DESCRIP. # VECES ANCHO LARGO ALTURA PARCIAL m3


EJE A-A TRAMO 1-2 1 0.15 2.90 0.50 0.22
EJE A-A TRAMO 2-3 1 0.15 2.90 0.50 0.22
EJE B-B TRAMO 1-2 1 0.15 2.90 0.50 0.22
EJE B-B TRAMO 2-3 1 0.15 2.90 0.50 0.22
EJE 1-1 TRAMO A-B 1 0.15 3.60 0.50 0.27
EJE 2-2 TRAMO A-B 1 0.25 3.60 0.50 0.45
EJE 3-3 TRAMO A-B 1 0.25 3.60 0.50 0.45
TOTAL 2.04
3.05 CONCRETO SIMPLE EN LOSAS DE TECHO
concreto simple dividido por areas

descripcion ancho altura largo parcial (m3)


losa de techo(area 1) 3.6 0.05 2.9 0.522
losa de techo(area 2) 3.6 0.05 2.9 0.522
losa de techo(area 3) 3.6 0.05 1.2 0.216
total 1.26

3.06.01CONCRETO EN VIGAS

descripcion ancho altura largo cantidad parcial (m3)


viga VS 0.4 0.2 3.6 3 0.864
viga VS (voladiso) 0.3 0.2 3.6 1 0.216
viga VP 0.3 0.35 2.9 4 1.218
viga VP (voladiso) 0.3 0.35 1.5 2 0.315
total 2.613

3.06.02 ACERO EN VIGAS


descripcion detalle ø cantidad #veces longitud f.c (m-kg) parcial (kg)
longitud de 5/8" 4 3 4.14 1.552 77.10336
barilla 1/2" 2 3 4.14 0.994 24.69096
vigas VS
longitud de
los estribos 3/8" 32 3 1.24 0.56 66.6624
longitud de 3/4" 4 2 8.45 2.235 151.086
la barilla 5/8" 2 2 8.45 1.552 52.4576
vigas VS
longitud de
los estribos 3/8" 80 2 1.38 0.56 123.648
total 495.64832
Calculo de la longitud de los estribos:
0.34(2)+0.14(2)+0.04+0.12(2)=1.24

recubrimiento
0.025

3.07 TARRAJEOS
3.07.01 TARRAJEOS EN TODA LA VIVIENDA
descripcion #veces longitud altura parcial m2
tarrajeos en las caras
laterales 2 7.35 3.15 46.305
tarrajeos en las caras 1 3.6 1.2 4.32
frontales 1 2.45 1.2 2.94
total 53.565
4.01 CONCRETO ARMADO
4.01.01 CONCRETO EN ZAPATAS (m3)
DESCRIP. # VECES ANCHO LARGO ALTURA PARCIAL m3
ZAPATA 01 6 1.60 1.60 0.50 7.68
TOTAL 7.68

4.02 ACERO (Kg)

FACTORES DE CONVERSION Y DATOS DE ANCLAJES, TRASLAPES Y ESTRIBOS

DIAMETRO 6 mm 1/4 " 8 mm 3/8" 12 mm 1/2"


(ø)
Factor de 0.22 0.25 0.395 0.56 0.888 0.994
comb.
5/8" 3/4" 1" 1 3/8"
1.552 2.235 3.973 7.907

4.02.01 ACERO EN ZAPATAS


LONGITUDES recubrimient
ZAPATAS # DE ACEROS EN ZAPATAS H # DE ACERO EN ZAPATA V
o (m)
ANCHO LARGO
ZAPATA 1 1.60 1.60 9 9 0.025

DESCRIPCION ø # DE VECES LONGITUD F.C (m-Kg) PARCIAL (Kg)


HORIZONTAL. Y
VERTICAL

Z-1 (Hor. Y 1/2" 9 1.55 0.994 83.1978


6
Vert.)
1/2" 9 1.55 0.994 83.1978
TOTAL (Kg) 166.40
4.03 COLUMNAS
4.03.01 CONCRETO EN COLUMNAS (m3)

DESCRIPCION LARGO ANCHO ALTURA PARCIAL (m3)


CANTIDAD
COLUMNA 1 6 0.3 0.4 4.2 3.024
TOTAL 3.024

4.04 ENCOFRADO Y DESENCOFRADO (m2)

Descrip. CANTIDAD PERIMETRO ALTURA PARCIAL (m2)


C1 - 1º 6 1.4 3.35 28.14
TOTAL 28.14