Q) For Block Wall


Location: Makkah Road Muzamiyah Client: Private
Work: Block Wall with Columns & beams Total Length: 42 L.m
S.Nos Description of work Unit Quantity Blocks Steel Concrete Sand Cement Labour Cost Cost
1)- Excavation & Cu.m 48 480.00
Backfilling Work
Reinforced Concrete
2)- Work for Footings, Cu.m 19 1400 KG 19 Cu.m 4000 SR 12250.00
G.Beam, Columns &
Top Beam
3)- Block Masonry Work Sq.m 126 1450 4 Cu.m 20 bags 3150 SR 6128.00
Old wall dismantle &
4)- removing from the Site LS 1 1000.00
126 Sq.m

Total Cost = 19858.00

NOTE: This Cost is Minimum to make Block Wall without including overhead