Scheduling/Leveling Report - Jan-25-19 - PM.

exe
===============================================

Default Project..................................................MCBI-H-1 -
B7

Projects:
MCBI-H-1 - B7....................................................HOLCIM
BL - 2 NEW WAREHOUSE - COMPRESSED REVISED

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............Yes
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................Yes
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................660
# Not Started....................................................348
# In Progress....................................................13
# Completed......................................................299
# Relationships..................................................672
# Activities with Constraint.....................................9
Project: MCBI-H-1 - B7 Activity: A14950 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A14990 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A1640 Geodetic Survey: Bench
Markings Vertical & Horizontal Controls
Project: MCBI-H-1 - B7 Activity: A1690 Mobilization ( This is
Based On Issuance or Releasing Of NTP or Downpayment )
Project: MCBI-H-1 - B7 Activity: A21790 Start Of
Backilling
Project: MCBI-H-1 - B7 Activity: A6060 Demobilization
Project: MCBI-H-1 - B7 Activity: A7410 Procurement: Engineering
Works Phase 1
Project: MCBI-H-1 - B7 Activity: A7490 Procurement: Engineering
Works Phase 2
Project: MCBI-H-1 - B7 Activity: A7740 Geodetic Survey: Final
Grade Checking
Errors:
-------
Warnings:
---------
Activities without predecessors..................................5
Project: MCBI-H-1 - B7 Activity: A1720 Mobilization: Start of
Implementation
Project: MCBI-H-1 - B7 Activity: A21790 Start Of
Backilling
Project: MCBI-H-1 - B7 Activity: A7410 Procurement: Engineering
Works Phase 1
Project: MCBI-H-1 - B7 Activity: A7420 Procurement: Anchor Bolt
Project: MCBI-H-1 - B7 Activity: A7740 Geodetic Survey: Final
Grade Checking

Activities without successors....................................247


Project: MCBI-H-1 - B7 Activity: A14660 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A14680 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14700 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14720 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14740 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14760 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14780 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14800 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14820 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14840 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14860 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14900 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14910 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14920 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A14940 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A15030 WF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A15040 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15150 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15200 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A15210 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A15270 WF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A1550 Board Up Installation
Project: MCBI-H-1 - B7 Activity: A15520 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15530 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15540 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15550 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15560 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15570 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15580 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15590 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A1560 Site Barrack/Fabrication
Construction
Project: MCBI-H-1 - B7 Activity: A15600 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15610 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15620 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15630 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A1590 Structure Warehouse
Layouting
Project: MCBI-H-1 - B7 Activity: A16040 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A16050 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A16060 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A16200 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16230 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16240 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16250 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16260 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16270 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16280 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16290 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16300 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16310 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16320 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16330 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16340 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A1640 Geodetic Survey: Bench
Markings Vertical & Horizontal Controls
Project: MCBI-H-1 - B7 Activity: A16570 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16580 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16590 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16600 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16610 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16620 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16630 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16640 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16650 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16660 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A16670 SOG : Levelling
Project: MCBI-H-1 - B7 Activity: A1670 Grubbing
Project: MCBI-H-1 - B7 Activity: A17480 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17510 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17520 SOG : Stripping
Project: MCBI-H-1 - B7 Activity: A17530 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17540 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17550 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17560 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17570 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17580 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17590 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17600 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17610 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17620 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17630 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17860 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17870 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17880 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17890 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17900 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17910 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17920 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17930 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17940 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17950 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A17960 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A18330 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18350 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18360 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18370 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18380 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18390 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18400 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18410 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18420 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18430 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18440 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18450 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18460 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A18580 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18590 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18600 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18610 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18640 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18650 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18670 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A18950 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19090 Unsuitable
Materials Disposals
Project: MCBI-H-1 - B7 Activity: A19230 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19280 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19340 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A19350 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A19360 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A19370 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A19380 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19590 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A19610 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A19650 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A19660 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A19670 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19720 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19760 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A19770 WF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A19780 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19830 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19880 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19940 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A19950 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A19960 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A19970 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A19980 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A19990 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20000 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20010 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20020 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A20030 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20080 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20130 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20190 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20200 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20210 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20230 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20290 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20300 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20310 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20320 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A20330 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20440 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20450 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20460 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20470 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A20480 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20590 CP : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20600 CP : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20610 CP : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20620 CP : @ GL 10
Project: MCBI-H-1 - B7 Activity: A20630 CP : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20780 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20830 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A20890 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20900 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20910 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20940 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20950 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A20960 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A20970 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A20980 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21000 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21020 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21050 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A21060 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21070 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A21080 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21110 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21140 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21180 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21190 WF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A21210 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21220 WF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A21230 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21240 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A21250 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21300 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21310 WF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A21320 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21400 Walling: @ GL 10
Project: MCBI-H-1 - B7 Activity: A21460 Walling : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21480 Walling : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21500 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21520 WF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21550 Walling : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21590 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21600 Walling : @ GL 11
Project: MCBI-H-1 - B7 Activity: A21610 Walling: @ GL 1
Project: MCBI-H-1 - B7 Activity: A21620 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21630 Walling: @ GL 11
Project: MCBI-H-1 - B7 Activity: A21640 Walling: @ GL 1
Project: MCBI-H-1 - B7 Activity: A21700 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21730 WF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21740 Anchor Bolt : @ GL
O, B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21750 Anchor Bolt : @
GL 2
Project: MCBI-H-1 - B7 Activity: A21760 Anchor Bolt : @ GL
11
Project: MCBI-H-1 - B7 Activity: A21780 Anchor Bolt : @
GL 1
Project: MCBI-H-1 - B7 Activity: A21810 SOG : Stripping
Project: MCBI-H-1 - B7 Activity: A4660 Cross Bracing Inst'n 3rd
Batch @ GL F to J
Project: MCBI-H-1 - B7 Activity: A6060 Demobilization
Project: MCBI-H-1 - B7 Activity: A6370 Storm Drainage:
Installation of 200 diam. PVC Pipe
Project: MCBI-H-1 - B7 Activity: A6380 Downspout: Fabrication
of 100mm diam PVC Pipe
Project: MCBI-H-1 - B7 Activity: A6440 Concrete Culvert: Collar
Concreting
Project: MCBI-H-1 - B7 Activity: A6500 Rain Water Tank:
Backfilling
Project: MCBI-H-1 - B7 Activity: A6550 Catch Basin: Backfilling
Project: MCBI-H-1 - B7 Activity: A6560 Waterline (CWL):
Fabrication
Project: MCBI-H-1 - B7 Activity: A6580 Sanitary Line:
Excavation
Project: MCBI-H-1 - B7 Activity: A6590 Sanitary Line: Pipe
Installation & Fiitings
Project: MCBI-H-1 - B7 Activity: A6600 Septic Tank: Excavation
Project: MCBI-H-1 - B7 Activity: A6610 Septic Tank:
Reinforcement & Forms Fabrication
Project: MCBI-H-1 - B7 Activity: A6620 Septic Tank:
Reinforcement & Forms Installation
Project: MCBI-H-1 - B7 Activity: A6640 Septic Tank: Backfilling
Project: MCBI-H-1 - B7 Activity: A6720 Comfort Room: Tile
Setting
Project: MCBI-H-1 - B7 Activity: A6740 Fire Hydrants: Pipe
Fabrication
Project: MCBI-H-1 - B7 Activity: A6750 Fire Hydrants: Pipe
Laying and Fittings Installation
Project: MCBI-H-1 - B7 Activity: A6880 Street Lighting:
Reinforcement & Forms Fabrication
Project: MCBI-H-1 - B7 Activity: A7000 MCC Room: Concreting &
Curing (Suspended Beam and Slab)
Project: MCBI-H-1 - B7 Activity: A7060 Dwarf Wall: 2nd Coat
Application
Project: MCBI-H-1 - B7 Activity: A7090 Architecftural Punch
List
Project: MCBI-H-1 - B7 Activity: A7130 Electrical:
Testing(Megger Test)
Project: MCBI-H-1 - B7 Activity: A7140 Plumbing: Leak &
Pressure Test
Project: MCBI-H-1 - B7 Activity: A7150 Mechanical: Leak &
Pressure Test
Project: MCBI-H-1 - B7 Activity: A7160 Occupancy Permit:
Asbuilt
Project: MCBI-H-1 - B7 Activity: A7170 Occupancy Permit:
Application
Project: MCBI-H-1 - B7 Activity: A7470 Procurement: Arrival of
Steel Structures on Site Includes Sorting Phase 1
Project: MCBI-H-1 - B7 Activity: A7480 Procurement: Arrival of
Steel Structures on Site Includes Sorting Phase 2
Project: MCBI-H-1 - B7 Activity: A7540 Conveyor Gallery:
Foundation Trimming & Gravel Bedding
Project: MCBI-H-1 - B7 Activity: A7550 Conveyor Gallery:
Foundation Backfilling
Project: MCBI-H-1 - B7 Activity: A7610 Roofing/Tinnery: Laying
Project: MCBI-H-1 - B7 Activity: A7640 Procurement: Arrival of
Steel Structures on Site Includes Sorting Gallery Conveyor
Project: MCBI-H-1 - B7 Activity: A7660 Procurement: Engineering
Works Gallery Conveyor
Project: MCBI-H-1 - B7 Activity: A7670 Procurement: Shipment of
Steel Structures Gallery Conveyor
Project: MCBI-H-1 - B7 Activity: A7680 Procurement: Steel
Fabrication Gallery Conveyor
Project: MCBI-H-1 - B7 Activity: A7700 Grounding & Lighting
System: Backfilling
Project: MCBI-H-1 - B7 Activity: A7730 Flooring: Epoxy Paint
Application
Project: MCBI-H-1 - B7 Activity: A7780 MCC Room: Concrete Stair
Works
Project: MCBI-H-1 - B7 Activity: A7790 Door : Sliding Door
Installation

Out-of-sequence activities.......................................48
Project: MCBI-H-1 - B7 Activity: A14680 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14700 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14720 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14740 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14760 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A14920 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A15110 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15520 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15530 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15540 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15550 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A15560 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A16210 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A16350 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A16360 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A16370 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A16380 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17490 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17640 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17650 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17660 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17670 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17810 SOG : Shuttering
Project: MCBI-H-1 - B7 Activity: A18400 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A19090 Unsuitable
Materials Disposals
Project: MCBI-H-1 - B7 Activity: A19620 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A19730 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A20790 CF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21010 WF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A21210 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21330 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21360 WF : @ GL O, B, A,
8 & 4
Project: MCBI-H-1 - B7 Activity: A21390 Walling : @ GL 2
Project: MCBI-H-1 - B7 Activity: A21450 Walling : @ GL 2
Project: MCBI-H-1 - B7 Activity: A21560 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21590 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21630 Walling: @ GL 11
Project: MCBI-H-1 - B7 Activity: A21640 Walling: @ GL 1
Project: MCBI-H-1 - B7 Activity: A21870 Start Of Grounding
Project: MCBI-H-1 - B7 Activity: A6600 Septic Tank: Excavation
Project: MCBI-H-1 - B7 Activity: A6780 Roads: Excavation
Project: MCBI-H-1 - B7 Activity: A6800 Roads: Compaction
Project: MCBI-H-1 - B7 Activity: A6850 Roads: Reinforcement &
Forms Installation (2nd Phase)
Project: MCBI-H-1 - B7 Activity: A6950 MCC Room: Reinforcement
& Forms Installation(CF, WF< FTB, & CP)
Project: MCBI-H-1 - B7 Activity: A7470 Procurement: Arrival of
Steel Structures on Site Includes Sorting Phase 1
Project: MCBI-H-1 - B7 Activity: A7480 Procurement: Arrival of
Steel Structures on Site Includes Sorting Phase 2
Project: MCBI-H-1 - B7 Activity: A7640 Procurement: Arrival of
Steel Structures on Site Includes Sorting Gallery Conveyor
Project: MCBI-H-1 - B7 Activity: A7760 MCC Room: Start of MCC

Activities with Actual Dates > Data Date.........................28


Project: MCBI-H-1 - B7 Activity: A15110 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15120 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15130 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15140 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A15150 SOG : Compaction
Project: MCBI-H-1 - B7 Activity: A17590 SOG : Procurement
Project: MCBI-H-1 - B7 Activity: A17700 SOG : Fabrication
Project: MCBI-H-1 - B7 Activity: A17810 SOG : Shuttering
Project: MCBI-H-1 - B7 Activity: A17920 SOG : Checking
Project: MCBI-H-1 - B7 Activity: A19080 CF : @ GL 11
Project: MCBI-H-1 - B7 Activity: A2040 CF : @ GL 2
Project: MCBI-H-1 - B7 Activity: A2050 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A2060 CF : @ GL 1
Project: MCBI-H-1 - B7 Activity: A21560 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21590 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A21650 Walling : @ GL O,
B, A, 8 & 4
Project: MCBI-H-1 - B7 Activity: A6800 Roads: Compaction
Project: MCBI-H-1 - B7 Activity: A6850 Roads: Reinforcement &
Forms Installation (2nd Phase)
Project: MCBI-H-1 - B7 Activity: A6930 MCC Room: Foundation
Excavation & Trimming
Project: MCBI-H-1 - B7 Activity: A6940 MCC Room: Reinforcement
& Forms Fabrication (CF,WF,FTB & CP)
Project: MCBI-H-1 - B7 Activity: A6950 MCC Room: Reinforcement
& Forms Installation(CF, WF< FTB, & CP)
Project: MCBI-H-1 - B7 Activity: A6960 MCC Room: Gravel Bedding
Project: MCBI-H-1 - B7 Activity: A7470 Procurement: Arrival of
Steel Structures on Site Includes Sorting Phase 1
Project: MCBI-H-1 - B7 Activity: A7480 Procurement: Arrival of
Steel Structures on Site Includes Sorting Phase 2
Project: MCBI-H-1 - B7 Activity: A7530 Conveyor Gallery:
Foundation Excavation
Project: MCBI-H-1 - B7 Activity: A7640 Procurement: Arrival of
Steel Structures on Site Includes Sorting Gallery Conveyor
Project: MCBI-H-1 - B7 Activity: A7760 MCC Room: Start of MCC
Project: MCBI-H-1 - B7 Activity: A7770 Conveyor Gallery: Start
of Conveyor Gallery

Milestone Activities with invalid relationships..................0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................660
# Relationships with other projects..............................0
Data Date........................................................Jan-25-19
Earliest Early Start Date........................................Jan-25-19
Latest Early Finish Date.........................................Apr-22-19
Exceptions:
-----------
Critical Activities..............................................27
Project: MCBI-H-1 - B7 Activity: A14830 SOG : Filling &
Spreading
Project: MCBI-H-1 - B7 Activity: A15710 SOG : Laying
Project: MCBI-H-1 - B7 Activity: A16520 SOG : Installation
Project: MCBI-H-1 - B7 Activity: A18530 SOG : Pouring
Project: MCBI-H-1 - B7 Activity: A18540 SOG : Pouring
Project: MCBI-H-1 - B7 Activity: A18550 SOG : Pouring
Project: MCBI-H-1 - B7 Activity: A18660 SOG : Curing
Project: MCBI-H-1 - B7 Activity: A20870 CF : @ GL 10
Project: MCBI-H-1 - B7 Activity: A21770 Anchor Bolt : @
GL 10
Project: MCBI-H-1 - B7 Activity: A4520 Rigid Frame Erection 1st
Batch @ GL A to E
Project: MCBI-H-1 - B7 Activity: A4530 Rigid Frame Erection 2nd
Batch @ GL F to J
Project: MCBI-H-1 - B7 Activity: A4540 Rigid Frame Erection 3rd
Batch @ GL K to O
Project: MCBI-H-1 - B7 Activity: A4580 Purlin Laying 1st Batch
@ GL A to E
Project: MCBI-H-1 - B7 Activity: A4590 Purlin Laying 2nd Batch
@ GL F to J
Project: MCBI-H-1 - B7 Activity: A4600 Purlin Laying 3rd Batch
@ GL K to O
Project: MCBI-H-1 - B7 Activity: A6940 MCC Room: Reinforcement
& Forms Fabrication (CF,WF,FTB & CP)
Project: MCBI-H-1 - B7 Activity: A7010 Roofing: Roofing &
Accessories Installation
Project: MCBI-H-1 - B7 Activity: A7090 Architecftural Punch
List
Project: MCBI-H-1 - B7 Activity: A7160 Occupancy Permit:
Asbuilt
Project: MCBI-H-1 - B7 Activity: A7180 Turnover: Project Turn
Over
Project: MCBI-H-1 - B7 Activity: A7560 Gallery Structural
Frame: Erection of Rigid Frames & Accessories
Project: MCBI-H-1 - B7 Activity: A7570 Gallery Structural
Frame: Checkered Plate Installation
Project: MCBI-H-1 - B7 Activity: A7580 Roof Frame: Purlins
Laying
Project: MCBI-H-1 - B7 Activity: A7590 Roof Frame: Sagrod &
Cross Bracing Installation
Project: MCBI-H-1 - B7 Activity: A7600 Wall Framing: Side
Railing/Girt Installation
Project: MCBI-H-1 - B7 Activity: A7620 Wall Cladding:
Installation
Project: MCBI-H-1 - B7 Activity: A7630 Anchor Bolt:
Installation

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0