Professional Documents
Culture Documents
Plastering
Area:___________sq.m
1. Portland Cement Area x.328
2. Sand Area x.027
Concreting Works
Volume:________cu.m
1. Portland Cement Volume x9.5 bags
2. Sand(S-1) Volume x.50 cu.m
3. Gravel(G-1) Volume x1.0 cu.m
4. Good Lumber(4uses) Volume x70/4 x70/4 bd.f
5. Asstd. CW Nails Volume x.7 x.7 kgs
6. 13mm THK Marine Plywood Volume x1.6/4 x1.6/4 pcs
7. Concrete Epoxy Volume
Structure Excavation
a) Common Earth 1.00 cu.m/MD
b) Sand 5.17 cu.m/MD
c) Clay 4.15 cu.m/MD
d) Rock 2.58 cu.m/MD
Embankment
a) Backfilling 8.30 cu.m/MD
b) Spreading Tamping and Grading 14.21 cu.m/MD
Termite Control
Termite Control Works
a) Soil Poisoning - Cordoning 20.40 sq.m/MD
b) Soil Poisoning - Drenching 34.00 sq.m/MD
Formworks
A. Formworks Installation sq.m/MD
a) Wall on Ground 3.4 sq.m/MD
b) Wall above ground 2.86 sq.m/MD
c) Beams 2.18 sq.m/MD
d) Columns 2.86 sq.m/MD 4.70
e) Suspended Slab sq.m/MD
1.0m up 2.04 sq.m/MD
C. Stripping of Formworks
a) Wall on Ground 27.2 sq.m/MD
b) Wall above ground 5.24 sq.m/MD
c) Beams 6.60 sq.m/MD
d) Columns 7.96 sq.m/MD
e) Suspended Slab
1.0m up 6.26 sq.m/MD
Reinforcement
a) Fabrication (Cut&Bend) 68.00 kg/MD
b) Placing
Ftg & Foundations 95.74 kg/MD
Slab on grade 95.74 kg/MD
Columns,Beams,RC Walls 85 kg/MD
Concreting
Place,Finish & Cure Concrete
a) Ftg. & Foundation 3.32 cu.m/MD
b) Slab on grade 1.89 cu.m/MD
c) Columns/beams 1.02 cu.m/MD 2.605
d) RC Walls 0.94 cu.m/MD
e) Structural Slabs(6") 0.88 cu.m/MD
2.415
Concrete Mixing
a) Manual/Hand Mixing 0.41 cu.m/MD
b) One-bagger Mixing 3.81 cu.m/MD
Masonry Works
CHB Laying
a) CHB 4" 5.10 sq.m/MD
b) CHB 6" 4.25 sq.m/MD
Steel Windows
Casement Type 1.00 set/MD
Awning Type 1.00 set/MD
Jalousie Windows
Glass Jalousie 2.70 sq.m/MD
Wood Jalousie 2.70 sq.m/MD
Windows
Casement Type 1.92 sq.m/MD
Jalousie Type 1.92 sq.m/MD
Finishes
Ceramic Tiles
Glazed Tiles 2.24 sq.m/MD
Unglazed Tiles 1.56 sq.m/MD
Painting/Varnishing Works
A. Painting
Plain Cement Paint Exterior 16.73 sq.m/MD
Plain Cement Paint Interior 16.73 sq.m/MD
Galvanized Metal 13.94 sq.m/MD
Wood Paint 23.05 sq.m/MD
B. Varnishing
Plain Varnish Paint 15.78 sq.m/MD
Waterproofing Works
Cement - Base Integral 5.00 sq.m/MD
Floor Finish
Plain Cement Floor Tiles/Topping 9.52 sq.m/MD
Plain Cement Floor Finish w/ color 4.83 sq.m/MD
Plaster Finish
Cement Plaster Finish 9.5 sq.m/MD
TOTAL
2. COLUMNS
No. of
Description Length Width Thickness
Column
C1 4 0.25 0.25 16
Stair Step
Stiffener Columns
TOTAL
3. BEAMS
No. of
Description GRID LINE Length Width Thickness
Beams
GTB 10,11,12 11 0.2 0.3 4
GTB 12 8 0.2 0.3 4
GTB A,B,C,D,I,J,K,L 0.15 0.25 23
SUBTOTAL
LB 0.3 2
SUBTOTAL
TOTAL
4. SLABS
5.STAIRS
Number of Stringer
Description Stair Width Rise Run
Steps Thickness
STAIR 1.8 0.2 0.3 16 0.15
TOTAL
Portland
Vol. of
ITEMS Cement
Conc. (m³)
(Bags)
1. FOOTING AND SLAB ON FILL 19.55 186
2. COLUMNS 4.00 38
3. FOOTING TIE BEAMS 4.56 43
4. SUSPENDED SLABS 17.51 166
5. BEAMS 0.00 0
6.CANOPY, STAIR & CONCRETE GUTTER 21.28 202
TOTAL 66.89 635.00
Vol. of Conc.
(m³)
3.07
0.00
0.00
3.07
Vol. of Conc.
(m³)
4.00
0.00
0.00
4.00
Vol. of Conc.
(m³)
2.64
1.92
0.00
4.56
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.56
Vol. of Conc.
(m³)
8.82975
7.644
16.47375
8.82975
7.64
16.46975
1.038
1.038
32.9435
2 4.84
TOTAL 4.84
Vol. of Conc.
(m³)
2.02
0.89
0.14
3.05
2.23
0.51
0.23
1.86
4.84
4.03
0.89
0.45
3.18
8.55
16.43
SUMMARY
10 15 342 14 8
2 3 70 3 2
2 4 80 3 2
9 13 306 12 7
0 0 0 0 0
11 16 372 15 9
34.00 51.00 1170.00 47.00 28.00
1
S
1. FOOTING
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
F2 Foundation 12 1.2 16 24
Stair Footing 12 0.4 6 4
Stiffener Footing 12 0.6 8 4
2. COLUMNS
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
3. BEAMS
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
FB-3 CB 16 7.5 4 4
CB 16 2.8 4 4
ETB 16 1.05 6 23
EBB 16 2.1 3 23
4. SLABS
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
Slab on Fill 10 4 5 11
10 3 7 11
10 1.5 6 6
10 6 3 2
10 3.3 3 2
S-1 (Steel Deck) 2nd Flr Temp. Bar 10 6 26 1
Temp. Bar 10 3.6 4 1
Bend Bars 12 6 12 1
Bend Bars 12 3.6 2 1
Temp. Bar 10 7.5 16 1
Temp. Bar 10 2.65 16 1
Bend Bars 12 7.5 8 1
Bend Bars 12 2.65 8 1
ETB 12 1.05 20 1
ETB 12 2.1 12 1
ETB 12 1.3 12 1
ETB 12 1.98 12 1
ETB 12 0.68 6 1
Bend Bars 12 1.6 8 1
S-1 BB 12 6 38 1
BB 12 3.5 22 1
BB 12 6 37 1
BB 12 4.15 25 1
Temp. Bar 10 6 30 1
Temp. Bar 10 4.15 20 1
Temp. Bar 10 6 30 1
Temp. Bar 10 3.5 18 1
Bend Bars 12 7.5 15 1
Bend Bars 12 2 9 1
Bend Bars 12 7.5 12 1
Bend Bars 12 2.65 8 1
ETB 12 1.05 23 1
ETB 12 2.1 21 1
ETB 12 1.3 15 1
ETB 12 1.98 15 1
ETB 12 0.68 3 1
Landing Slab 12 1.47 12 2
12 3 6 2
5. CONCRETE CANOPY
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
6. CONCRETE GUTTER
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
7. STAIR
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
Member/Structure Flr. Level Bar Description Bar Ø Cut Length # Pcs. Sets
Vertical Bars 12 1 10 2
Horizontal Bars (Cross Tie) 10 1.5 20 2
Step Temperature Bars 10 1.5 26 2
Step Bars 10 1 84 2
Bottom Bars 16 3.6 10 2
Bottom Bars 16 2.4 10 2
SUMMARY
COMMERCIAL LENGTHS
BAR Ø 6 7.5 9
10 mm 722 113 112
12 mm 422 123 13
16 mm 258 82 18
20 mm 0 0 0
25 mm 0 0 0
28 mm 0 0 0
32 mm 0 0 0
36 mm 0 0 0
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
384 6 0 0 0 77 0 0 0 0 0
24 6 0 0 0 2 0 0 0 0 0
32 6 0 0 0 4 0 0 0 0 0
Subtotal 0 0 0 83 0 0 0 0 0
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
96 6 0 0 0 0 0 0 96 0 0
96 6 0 0 0 0 0 0 48 0 0
16 6 0 0 0 8 0 0 0 0 0
32 6 0 0 0 6 0 0 0 0 0
1392 6 279 0 0 0 0 0 0 0 0
72 6 8 0 0 0 0 0 0 0 0
Subtotal 287 0 0 14 0 0 144 0 0
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
24 6 0 0 0 24 0 0 0 0 0
24 6 0 0 0 24 0 0 0 0 0
32 6 0 0 0 32 0 0 0 0 0
28 7.5 0 0 0 0 14 0 0 0 0
324 9 0 0 30 0 0 0 0 0 0
22 7.5 0 3 0 0 0 0 0 0 0
483 9 0 0 44 0 0 0 0 0 0
24 6 24 0 0 0 0 0 0 0 0
24 6 24 0 0 0 0 0 0 0 0
32 6 32 0 0 0 0 0 0 0 0
28 7.5 0 14 0 0 0 0 0 0 0
48 6 7 0 0 0 0 0 0 0 0
8 6 2 0 0 0 0 0 0 0 0
92 6 14 0 0 0 0 0 0 0 0
8 7.5 0 0 0 0 0 0 0 4 0
12 6 0 0 0 0 0 0 3 0 0
6 6 0 0 0 0 0 0 2 0 0
54 6 9 0 0 0 0 0 0 0 0
16 7.5 0 0 0 0 0 0 0 16 0
16 7.5 0 0 0 0 0 0 0 8 0
36 6 0 0 0 0 0 0 9 0 0
36 6 0 0 0 0 0 0 12 0 0
36 6 0 0 0 0 0 0 18 0 0
408 6 82 0 0 0 0 0 0 0 0
9 6 0 0 0 0 0 0 2 0 0
0 0 0 0 0 0 0 0 0 0
16 7.5 0 0 0 0 0 0 0 16 0
16 6 0 0 0 0 0 0 8 0 0
138 7.5 0 0 0 0 0 0 0 20 0
69 9 0 0 0 0 0 0 0 0 18
8 7.5 0 0 0 0 0 0 0 8 0
8 7.5 0 0 0 0 0 0 0 4 0
12 6 0 0 0 0 0 0 3 0 0
12 6 0 0 0 0 0 0 2 0 0
12 6 0 0 0 0 0 0 4 0 0
6 6 0 0 0 0 0 0 1 0 0
28 6 0 0 0 0 0 0 14 0 0
42 7.5 0 0 0 0 0 0 0 6 0
21 6 0 0 0 0 0 0 6 0 0
Subtotal 194 17 74 80 14 0 84 82 18
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
55 9 0 0 28 0 0 0 0 0 0
77 6 39 0 0 0 0 0 0 0 0
36 6 9 0 0 0 0 0 0 0 0
6 6 6 0 0 0 0 0 0 0 0
6 7.5 0 3 0 0 0 0 0 0 0
26 6 26 0 0 0 0 0 0 0 0
4 7.5 0 2 0 0 0 0 0 0 0
12 6 0 0 0 12 0 0 0 0 0
2 7.5 0 0 0 0 1 0 0 0 0
16 7.5 0 16 0 0 0 0 0 0 0
16 6 8 0 0 0 0 0 0 0 0
8 7.5 0 0 0 0 8 0 0 0 0
8 6 0 0 0 4 0 0 0 0 0
20 7.5 0 0 0 0 3 0 0 0 0
12 7.5 0 0 0 0 4 0 0 0 0
12 6 0 0 0 3 0 0 0 0 0
12 6 0 0 0 4 0 0 0 0 0
6 6 0 0 0 1 0 0 0 0 0
8 7.5 0 0 0 0 2 0 0 0 0
38 6 0 0 0 38 0 0 0 0 0
22 7.5 0 0 0 0 11 0 0 0 0
37 6 0 0 0 37 0 0 0 0 0
25 9 0 0 0 0 0 13 0 0 0
30 6 30 0 0 0 0 0 0 0 0
20 9 0 0 10 0 0 0 0 0 0
30 6 30 0 0 0 0 0 0 0 0
18 7.5 0 9 0 0 0 0 0 0 0
15 7.5 0 0 0 0 15 0 0 0 0
9 6 0 0 0 3 0 0 0 0 0
12 7.5 0 0 0 0 12 0 0 0 0
8 6 0 0 0 4 0 0 0 0 0
23 7.5 0 0 0 0 4 0 0 0 0
21 7.5 0 0 0 0 7 0 0 0 0
15 6 0 0 0 4 0 0 0 0 0
15 6 0 0 0 5 0 0 0 0 0
3 6 0 0 0 1 0 0 0 0 0
24 6 0 0 0 6 0 0 0 0 0
12 7.5 0 0 0 0 6 0 0 0 0
Subtotal 148 30 38 122 73 13 0 0 0
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
154 6 0 0 0 20 0 0 0 0 0
38 7.5 0 0 0 0 4 0 0 0 0
14 6 0 0 0 2 0 0 0 0 0
33 6 17 0 0 0 0 0 0 0 0
6 7.5 0 3 0 0 0 0 0 0 0
6 6 2 0 0 0 0 0 0 0 0
204 6 0 0 0 51 0 0 0 0 0
120 6 0 0 0 30 0 0 0 0 0
12 6 12 0 0 0 0 0 0 0 0
9 7.5 0 9 0 0 0 0 0 0 0
3 6 2 0 0 0 0 0 0 0 0
6 7.5 0 6 0 0 0 0 0 0 0
9 6 9 0 0 0 0 0 0 0 0
Subtotal 42 18 0 103 4 0 0 0 0
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
32 7.5 0 0 0 0 32 0 0 0 0
32 6 0 0 0 16 0 0 0 0 0
192 7.5 0 48 0 0 0 0 0 0 0
106 7.5 0 27 0 0 0 0 0 0 0
Subtotal 0 48 0 16 32 0 0 0 0
Commercial Quantity (Pcs.) 10mm Quantity (Pcs.) 12mm Quantity (Pcs.) 16mm
Total Pcs.
Length
Commercial
Total Pcs.
Length 6m 7.5m 9m 6m 7.5m 9m 6m 7.5m 9m
20 6 0 0 0 4 0 0 0 0 0
40 6 10 0 0 0 0 0 0 0 0
52 6 13 0 0 0 0 0 0 0 0
168 6 28 0 0 0 0 0 0 0 0
20 6 0 0 0 0 0 0 20 0 0
20 6 0 0 0 0 0 0 10 0 0
Subtotal 51 0 0 4 0 0 30 0 0
MMERCIAL LENGTHS
10.5 12
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
TIE WIRES
1. FOOTING
Description Grid Line No. of Footing Total Points
F2 24 64
Stair Footing 4 9
Stiffener Footing 4 16
2. COLUMNS
No. of
Description Grid Line Total Points
Columns
C-1 24 232
Stiffener Footing 4 72
3.BEAMS
Description GRID LINE No. of Beams Total Points
GTB 10,11,12 12 108
12 2 44
A,B,C,D,I,J,K,L 23 84
4. SLABS
Description GRID LINE No. of Slabs Total Points
Slab on Fill 11 154
6 60
S-1 BB 1 950
BB 1 264
Temp. Bars 5 120
Temp. Bars 3 40
ETB 10 36
ETB 6 18
ETB 8 24
ETB 6 12
Bend Bars 10 36
Bend Bars 6 18
Bend Bars 8 24
Bend Bars 6 12
Bend Bars 1 35
Landing Slab 2 66
4. STAIRS
Description Grid Line No. of Stairs Total Points
Vertical Bars 2 64
Stair Footing 4 9
Bottom Bars 2 180
Step Bars 2 84
TOTAL
Cut Length Kg.
0.3 8.69
0.3 0.20
0.3 0.36
9.26
0.3 31.52
0.3 1.63
33.15
0.3 7.34
0.3 0.50
0.3 10.94
0.3 1.22
0.3 0.75
0.3 0.37
0.3 9.24
0.3 4.89
0.3 2.85
0.3 2.17
0.3 1.43
0.3 0.82
0.3 10.55
0.3 4.30
0.3 0.39
0.3 9.24
0.3 4.89
0.3 2.85
0.3 0.20
0.3 0.10
0.3 0.10
0.3 10.55
0.3 9.37
0.3 5.47
119.29
0.3 1.81
0.3 0.82
0.3 1.63
0.3 1.86
0.3 0.71
0.3 0.61
0.3 0.11
0.3 5.38
0.3 1.49
0.3 3.40
0.3 0.68
0.3 2.04
0.3 0.61
0.3 1.09
0.3 0.41
0.3 2.04
0.3 0.61
0.3 1.09
0.3 0.41
0.3 0.20
0.3 0.75
39.36
TOTAL 220.45
1. Soil Poisoning
Description Length Width #
Footing 1.2 1.2 24
Footing (Side) 1.2 1.2 96
GTB 2.7 0.15 23
3.7 0.15 12
1.2 0.15 2
GTB (Side) 2.7 0.9 46
3.7 0.9 24
1.2 0.9 4
Slab 4 3 11
3 1.5 6
TOTAL AREA
Area
34.56
138.24
9.315
6.66
0.36
111.78
79.92
4.32
132
27
544.155
Length Width
Description Location (Grid Line) # (m) (m)
GROUND FLOOR
D1 2 2.50 1.9
D4 8 2.50 1
W3 8 1.60 2
W4 2 1.60 1.2
SUBTOTAL
SECOND FLOOR
D4 8 2.50 1
W3 10 1.60 2
W4 2 1.60 1.2
SUBTOTAL
TOTAL
W1 15 3.84 57.6
W2 6 3.84 23.04
W3 51 3.2 163.2
W4 8 1.92 15.36
W5 6 1.92 11.52
W6 5 0.96 4.8
W7 1 1.32 1.32
W8 4 1.2 4.8
W9 6 0.96 5.76
W10 2 0.48 0.96
W11 4 0.96 3.84
TOTAL 483.13
Area
( m² )
9.500
20.000
25.600
3.840
58.940
20.000
32.000
3.840
55.840
114.780
Area
Description Location (Grid Line) # Length (m) Width (m) ( m² )
GROUND FLOOR
GRID LINE 9-10 1 9.50 2.85 27.075
GRID LINE 9-10 1 5.35 2.85 15.248
GRID LINE 10-12 8 3.85 2.85 87.780
GRID LINE 10-12 2 5.80 1.35 15.660
SECOND FLOOR
GRID LINE 9-10 1 9.50 2.85 27.075
GRID LINE 9-10 1 5.35 2.85 15.248
GRID LINE 10-12 8 3.85 2.85 87.780
PLASTERING WORKS
SECOND FLOOR
GRID LINE 12 4 8.60 3 103.200
GRID LINE 11 8 3.70 3 88.800
GRID LINE 10 8 3.70 3 88.800
GRID LINE 9 3 3.70 3 33.300
GRID LINE 9 2 1.20 3 7.200
GRID LINE A 6 2.70 3 48.600
GRID LINE B 6 2.70 3 48.600
GRID LINE C 6 2.70 3 48.600
GRID LINE D 6 2.70 3 48.600
GRID LINE I 4 2.70 3 32.400
GRID LINE J 6 2.70 3 48.600
GRID LINE K 6 2.70 3 48.600
GRID LINE L 6 2.70 3 48.600
GROSS AREA 693.900
LESS 110.000
PLASTERING
1. PORTLAND CEMENT 632 Bags
2. SAND 52 Cubic Meter
GROUND FLOOR
1. PORTLAND CEMENT = 196 Bags
2. SAND = 16 Cubic Meter
117.88
SECOND FLOOR
1. PORTLAND CEMENT = 192 Bags
2. SAND = 16 Cubic Meter
CONCRETE CANOPY
1. PORTLAND CEMENT = 99 Bags
2. SAND = 9 Cubic Meter
Water Proofing
4 10.20 1.3
2 10.60 1.3
53.040
27.560
0.000
0.000
80.600
PAINTING WORKS
WOOD
TOTAL
STEEL
Masonry/Concrete
TOTAL
Net Area
Area
( m² )
87.875
13.780
50.875
23.100
46.000
0.000
221.630
Area
( m² )
53.040
27.560
0.000
0.000
80.600
Area
( m² )
125.440
23.680
144.640
52.160
439.040
271.040
38.720
1386.000
1265.400
571.500
142.200
140.400
30.000
61.440
472.320
140.400
136.800
41.400
14.800
13.800
37.940
40.980
234.592
0.000
0.000
0.000
0.000
5824.692
5341.542
Description Location (Grid Line) # Length (m)
CHB WALL 6"
GRID LINE 12 2 6.15
GRID LINE 10 1 6.15
GRID LINE A, D, L 3 6.15
GRID LINE I 1 6.15
GRID LINE J 1 6.15
CHB 4"
1.CHB = 3603
4 172.200 2. PORTLAND CEMENT = 152
3 147.600 3. SAND = 13
0.2 8.400 4. RSB 10mmØ X 6.00m = 156
0.2 4.760 5. GI Tie Wire # 16 = 12
Gross Area 328.200
less 40.000
Net Area 288.200
Pcs.
Bags (40 Kgs.)
Cubic Meter
Kgs 236 Pcs.
CHB 4"
Pcs.
Bags (40 Kgs.)
Cubic Meter
Kgs 254 Pcs.
1. PURLINS
Description GRID LINE No. of Purlins
2mm x 50 x 125 4
4
4
4
4
4
4
4
4
4
2
2
2
2
2
2
2
2
2
TOTAL LENGTH
2. TRUSS/ HIPTRUSS/RAFTER
Description GRID LINE #
Top Chord (2 - 6mm x 50 x 50) Truss 1 8
Diagonal Member (2 - 6mm x 50 x 50) Truss 1 8
Diagonal Member (2 - 6mm x 50 x 50) Truss 1 8
Diagonal Member (2 - 6mm x 50 x 50) Truss 1 8
Diagonal Member (2 - 6mm x 50 x 50) Truss 1 8
King Post (2 - 6mm x 50 x 50) Truss 1 4
Bottom Chord (2 - 6mm x 50 x 50) Truss 1 4
Total Length of 6mm x 50 x 50 angle Bar
TOTAL LENGTH
8.5 34
x 37 x 37 angle Bar 34 6 Pcs. Of 6mm x 37 x 37 Angle Bars
7.15 57.2
3.98 31.84
1.9 15.2
1.93 15.44
1.59 12.72
2.74 10.96
6.72 26.88
x 50 x 50 angle Bar 171 29 Pcs. Of 6mm x 50 x 50 Angle Bars
7.91 31.64
x 37 x 37 angle Bar 32 6 Pcs. Of 6mm x 37 x 37 Angle Bars
3.6 28.8
2.28 18.24
1.61 12.88
3.35 26.8
x 50 x 50 angle Bar 86.72 15 Pcs. Of 6mm x 50 x 50 Angle Bars
5.1 40.8
x 37 x 37 angle Bar 41 7 Pcs. Of 6mm x 37 x 37 Angle Bars
4.51 36.08
2.91 23.28
2.36 18.88
4.01 32.08
m x 50x 50angle Bar 110.32 19 Pcs. Of 6mm x 50 x 50 Angle Bars
6.9 55.2
x 37 x 37 angle Bar 56 10 Pcs. Of 6mm x 37x 37 Angle Bars
0
0
0
0
0
0
0
19 76 PIECES REQUIRED 13
0
0
0
0
0
0
0
0
0
Ceiling Joist
6x 3.8 x 11 = 250.8
8x 2.8 x 11 = 246.4
6x 1.3 x 6 = 46.8
4x 2.8 x 6 = 67.2
total length = 611.2
pieces = 170
Ceiling Frame
4 3
4 3
3 1.5
3 1.5
14 9
154 99
Ficem Board
Area of Partition or Ceiling = 10.64
Area of Board = 2.88
Number of Partition = 11
Number of Boards Required = 45
CW Nails
6 x 8 x 11 = 15
1004(4) Hardwares
a. Quantity: all ls
b. Materials: 47,580.00
1. Sand 2.02
2. Portland Cement 36.00
3. Waterproofing Compound 194.00
bags @ 240.00 = -
cum @ 270.00 = -
cum @ 300.00 = -
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 1.36 543.77
Skilled 2.0 1.94 394.13
Unskilled 8.0 1.94 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 1.48 543.77
Skilled 2.0 2.11 394.13
Unskilled 8.0 2.11 304.67
Installation/Removal of Forms
Skilled 2.0 2.11 394.13
Unskilled 4.0 2.11 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 0.32 543.77
Skilled 2.0 0.45 394.13
Unskilled 8.0 0.45 304.67
Installation/Removal of Forms
Skilled 2.0 0.45 394.13
Unskilled 4.0 0.45 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 0.28 543.77
Skilled 2.0 0.40 394.13
Unskilled 8.0 0.40 304.67
Installation/Removal of Forms
Skilled 2.0 0.40 394.13
Unskilled 4.0 0.40 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 1.22 543.77
Skilled 2.0 1.74 394.13
Unskilled 8.0 1.74 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 0.00 543.77
Skilled 2.0 0.00 394.13
Unskilled 8.0 0.00 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
DETAILED UNIT PRICE ANALYSIS
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Conrete Pouring
0.7 Construction Foreman 1.0 5.60 543.77
Skilled 1.0 8.00 394.13
Unskilled 1.0 8.00 304.67
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
DETAILED UNIT PRICE ANALYSIS
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
0.5 Electric Welding Machine 1.00 10.00 490.00
0.5 Electric Grinder 1.00 10.00 150.00
0.5 Bar Cutter/ Power Cutter 1.00 10.00 1758.00
0.25 Scaffolding(set) 1.00 10.00 30.00
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
A. SUB-TOTAL (LABOR)
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
B. Name and Capacity of Equipment No. of Units No. of Days Daily Rate
1 Electric Drill w/ Adaptor 2.0 5.02 150.00
0.25 Riveter 2.0 1.26 100.00
0.3 Portalift 1.0 1.51 2500.00
B. SUB-TOTAL (EQUIPMENT)
Installation
0.7 Construction Foreman 1.0 0.59 543.77
Skilled 1.0 0.84 394.13
Unskilled 1.0 0.84 304.67
A. SUB-TOTAL (LABOR)
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Installation
0.7 Construction Foreman 1.0 2.98 543.77
Skilled 2.0 4.25 394.13
Unskilled 4.0 4.25 304.67
A. SUB-TOTAL (LABOR)
B. SUB-TOTAL (EQUIPMENT)
C. Name and Description Quantity Unit Unit Cost
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
Project:
Location:
Welding Machine
0.25 Scaffoldings
Set 15.00 10.00 30.00
B. SUB-TOTAL (EQUIPMENT)
C. SUB-TOTAL (MATERIAL)
SUMMARY:
A. Labor
B. Equipment
C. Materials
D. TOTAL DIRECT COST
DIRECT UNIT COST
E. OCM 8% of Direct Cost
F. Profit 8% of Direct Cost
G. VAT 5% of (Direct Cost + OCM + Profit)
H. Total Cost (D+E+F+G)
I. Unit Cost H/ Quantity
53.30
cu.m
2,028.81
4,201.43
12,991.13
19,221.36
-
-
-
-
-
-
-
-
19,221.36
-
-
19,221.36
360.63
1,537.71
1,537.71
1,114.84
23,411.62
439.24
150.00
cu.m
6,879.02
7,122.83
38,542.59
52,544.44
-
-
-
-
-
-
-
-
-
52,544.44
-
-
52,544.44
350.30
4,203.56
4,203.56
3,047.58
63,999.13
426.66
19.55
cu.m
738.08
1,528.49
4,726.19
6,992.76
2,668.15
565.43
3,233.58
52,710.00
6,992.76
3,233.58
52,710.00
62,936.34
3,219.95
5,034.91
5,034.91
3,650.31
76,656.46
3,921.90 ok
21.28
cu.m
803.47
1,663.89
5,144.86
1,663.89
2,572.43
11,848.53
2,904.51
615.52
113.98
5,040.00
3,634.01
48,480.00
3,240.00
5,400.00
57,120.00
11,848.53
3,634.01
57,120.00
72,602.54
3,412.22
5,808.20
5,808.20
4,210.95
88,429.89
4,156.09 ok
4.56
cu.m
172.19
356.59
1,102.62
356.59
551.31
2,539.30
Total Cost (Php)
622.48
131.91
27.14
781.53
10,320.00
810.00
1,200.00
12,330.00
2,539.30
781.53
12,330.00
15,650.84
3,432.20
1,252.07
1,252.07
907.75
19,062.72
4,180.42
4.00
cu.m
151.05
312.80
967.21
312.80
483.60
2,227.46
546.03
115.71
11.90
198.41
673.65
9,120.00
540.00
900.00
10,560.00
2,227.46
673.65
10,560.00
13,461.11
3,365.28
1,076.89
1,076.89
780.74
16,395.63
4,098.91
17.51
cu.m
6,263.64
2,389.95
506.47
208.43
868.44
2,896.42
39,840.00
2,700.00
4,500.00
47,700.00
1,500.00
96,240.00
6,263.64
2,896.42
96,240.00
105,400.06
6,020.19
8,432.00
8,432.00
6,113.20
128,377.27
7,332.60 ok
0.00
cu.m
Total Cost (Php)
-
-
-
0.00
-
-
-
-
-
-
-
-
-
-
-
-
#DIV/0!
-
-
-
-
#DIV/0! ok
10083.00
kgs
Total Cost (Php)
5,690.96
23,570.66
36,441.13
65,702.75
12,612.72
13,141.99
c
25,754.71
78,176.00
24,832.00
5,440.00
71,936.00
20,960.00
2,208.00
85,408.00
13,376.00
13,248.00
13,260.00
328,844.00
65,702.75
25,754.71
328,844.00
420,301.46
41.68
33,624.12
33,624.12
24,377.48
511,927.18
50.77 ok
80.64
sq.m.
653.08
1,352.45
4,181.89
6,187.42
17,864.00
46,800.00
3,055.00
350.00
68,069.00
6,187.42
-
68,069.00
74,256.42
920.84
5,940.51
5,940.51
4,306.87
90,444.32
1,121.58 ok
544.16
sq.m
3,045.98
3,153.94
2,438.05
8,637.97
11,011.14
-
1,680.48
12,691.62
1,950.00
8,637.97
12,691.62
1,950.00
23,279.59
42.78
1,862.37
1,862.37
1,350.22
28,354.54
52.11 ok
all
L.S.
4,948.31
10,247.38
31,685.68
46,881.37
1,800.00
1,200.00
5,400.00
10,140.00
5,040.00
960.00
11,520.00
11,520.00
47,580.00
46,881.37
-
47,580.00
94,461.37
94,461.37
7,556.91
7,556.91
5,478.76
115,053.95
115,053.95
65.28
sq.m
3,235.43
13,400.42
16,635.85
4,165.00
4,165.00
132,480.00
17,664.00
6,450.00
156,594.00
16,635.85
4,165.00
156,594.00
177,394.85
2,717.45
14,191.59
14,191.59
10,288.90
216,066.93
3,309.85 ok
115.00
Lin.m
1,072.88
2,221.81
5,152.51
8,447.20
17,280.00
1,430.00
100.00
875.00
700.00
930.00
21,315.00
8,447.20
-
21,315.00
29,762.20
258.80
2,380.98
2,380.98
1,726.21
36,250.36
315.22 ok
49.50
sq.m
Total Cost (Php)
1,613.15
3,340.66
7,747.17
12,700.98
4,000.00
28,800.00
32,800.00
12,700.98
-
32,800.00
45,500.98
919.21
3,640.08
3,640.08
2,639.06
55,420.20
1,119.60 ok
80.60
sq.m.
Total Cost (Php)
766.99
1,588.34
3,683.46
6,038.79
544.05
8,640.00
19,400.00
28,584.05
6,038.79
-
28,584.05
34,622.84
429.56
2,769.83
2,769.83
2,008.12
42,170.62
523.21 ok
324.11
sq.m.
1,619.88
6,709.16
5,186.31
13,515.35
35,040.00
2,430.00
37,470.00
13,515.35
0.00
37,470.00
50,985.35
157.31
4,078.83
4,078.83
2,957.15
62,100.16
191.60 ok
1,927.85
sq.m.
6,436.97
39,990.71
30,913.58
77,341.27
151,920.00
14,310.00
166,230.00
77,341.27
0.00
166,230.00
243,571.27
126.34
19,485.70
19,485.70
14,127.13
296,669.80
153.89 ok
5,341.54
sq.m.
8,680.72
71,907.16
41,689.21
122,277.09
6,000.00
6,000.00
178,500.00
214,200.00
2,400.00
3,000.00
2,250.00
3,000.00
35,700.00
6,800.00
10,400.00
456,250.00
122,277.09
6,000.00
456,250.00
584,527.09
109.43
46,762.17
46,762.17
33,902.57
711,954.00
133.29 ok
221.63
sq.m.
457.49
947.41
2,197.09
3,601.99
19,760.00
36,600.00
4,650.00
27,090.00
1,950.00
150.00
3,400.00
2,800.00
1,500.00
97,900.00
3,601.99
0.00
97,900.00
101,501.99
457.98
8,120.16
8,120.16
5,887.12
123,629.43
557.82 ok
65.28
sq.m.
371.31
768.94
594.41
1,734.66
600.00
520.00
60.00
180.00
65.00
520.00
1,945.00
1,734.66
0.00
1,945.00
3,679.66
56.37
294.37
294.37
213.42
4,481.83
68.66 ok
288.20
sq.m.
2,688.73
5,568.05
12,912.63
21,169.41
36,030.00
36,240.00
3,510.00
4,960.00
780.00
200.00
81,720.00
21,169.41
-
81,720.00
102,889.41
357.01
8,231.15
8,231.15
5,967.59
125,319.31
434.83 ok
267.78
sq.m.
Total Cost (Php)
2,997.81
6,208.13
14,397.00
23,602.94
33,470.00
48,720.00
5,940.00
4,608.00
715.00
200.00
93,653.00
23,602.94
-
93,653.00
117,255.94
437.89
9,380.48
9,380.48
6,800.84
142,817.74
533.35 ok
all
ls
5,437.70
7,882.60
18,280.20
31,600.50
19,380.00
162,000.00
40,600.00
2,000.00
32,450.00
1,260.00
4,560.00
2,030.00
2,160.00
5,040.00
3,770.00
1,950.00
120.00
520.00
540.00
259,000.00
31,600.50
19,380.00
259,000.00
309,980.50
309,980.50
24,798.44
24,798.44
17,978.87
377,556.25
377,556.25 ok
96.00
l.m
1,522.56
3,153.04
7,312.08
11,987.68
1,960.00
1,500.00
2,000.00
5,460.00
2,400.00
2,760.00
300.00
110.00
270.00
4,050.00
9,890.00
11,987.68
5,460.00
9,890.00
27,337.68
284.77
2,187.01
2,187.01
1,585.59
33,297.29
346.85 ok
200.00
sq.m.
1,910.84
7,914.26
6,117.87
15,942.97
39,200.00
9,840.00
15,040.00
12,480.00
200.00
130.00
1,828.50
395.00
1,920.00
121.00
70.00
3,700.00
84,924.50
15,942.97
5,522.09
84,924.50
106,389.56
531.95
8,511.16
8,511.16
6,170.59
129,582.48
647.91 ok
35.80
ln.m.
320.63
332.00
256.64
909.27
2,160.00
909.27
-
2,160.00
3,069.27
85.73
245.54
245.54
178.02
3,738.37
104.42 ok
170.00
ln.m.
1,619.34
3,353.46
5,184.57
10,157.37
-
Total Cost (Php)
13,680.00
1,900.00
520.00
570.00
75.00
16,745.00
10,157.37
-
16,745.00
26,902.37
158.25
2,152.19
2,152.19
1,560.34
32,767.08
192.75 ok
11.28
13.48
13.6
3.88
17.36
6,607.89
27,368.39
10,578.14
37,946.53
0.00
4,500.00
4,500.00
306,670.00
37,946.53
4,500.00
306,670.00
349,116.53
349,116.53
27,929.32
27,929.32
20,248.76
425,223.93
425,223.93 ok
S U M M A R Y
Total
Engineering Services
GRAND TOTAL PROJECT COST
Recommending Approval:
ANDRES Z. TAGUIAM
University Preside
s Dormitory
g Campus
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
644,656.9 94,692.61 2,529,253.55 3,268,603.01
51,572.55 7,575.41 202,340.28 261,488.24
51,572.55 7,575.41 202,340.28 261,488.24
37,390.10 5,492.17 146,696.71 189,578.97
3,981,158.47
1,018,841.53
5,000,000.00
#DIV/0! - -
#DIV/0!
### - -
### - -
### - -
Recommending Approval:
Approved:
ANDRES Z. TAGUIAM, Ed. D.
University President
ED: Bar Cutter/Bender
nding/Cutter Portable
TOTAL COST
23,411.62
63,999.13
76,656.46
88,429.89
19,062.72
16,395.63
128,377.27
#DIV/0!
511,927.18
90,444.32
28,354.54
115,053.95
425,223.93
216,066.93
36,250.36
55,420.20
42,170.62
62,100.16
296,669.80
711,954.00
123,629.43
4,481.83
125,319.31
142,817.74
377,556.25
33,297.29
129,582.48
3,738.37
32,767.08
1.00
1.00
1.00
1.00
1.00
#DIV/0!
#DIV/0!
5,000,000.00
EBREO, Ph.D.
on and Finance