You are on page 1of 46

ASSOCIATION FRANÇAISE DES TUNNELS

ET DE L’ESPACE SOUTERRAIN

Organization member of the AFTES


www.aftes.asso.fr

AFTES
Recommendations
Characterisation of
geological, hydrogeological
and geotechnical
uncertainties and risks
GT32R2A1
315a355RECO UK_Mise en page 1 24/08/12 09:59 Page315

M
AFTES RECOMMENDATION N°GT32.R2A1

Recommendation on the characterisation


of geological, hydrogeological and
geotechnical uncertainties and risks
Text submitted by Gianpino Walter BIANCHI (SEA Consulting) and Jean Piraud (ANTEA), leaders of Working Group GT32-2

Contributors:
Alain ROBERT (CETU) and Emmanuel EGAL (BRGM)
with additional material from:
François BERBET (Bouygues Construction), Lorenzo BRINO (LTF), Gilbert CASTANIER (EDF), Yves CHAMEROIS (SNCF), Daniel COLLOMB (BG Ing. Conseils),
Michel DUCROT (Eiffage TP), Elisabeth DEMAS (Coyne & Bellier), Denis FABRE (CNAM), Stefano FUOCO (SWS), Cédric GAILLARD (CETU),
Bernard GAUDIN (Egis Tunnels), Jean-Louis GIAFFERI (Chartered Geologist), Patrick LACOMBE (SNCF), Hervé LE BISSONNAIS (Terrasol), Nathalie MONIN (LTF),
Patrick PIERRON (Géo-CSP), Christian PLINE (Geodata), Fabien RIVAL (DREAL Rhône-Alpes, formerly of CETU), Jacques ROBERT (Arcadis),
Adrien SAITTA (Egis Tunnels), Hubert TOURNERY (Egis Tunnels), Philippe VASKOU (Geostock), Christophe VIBERT (Coyne & Bellier)
With thanks for assistance from the following reviewers:
Andrew BOURGET (Egis Tunnels), Roger COJEAN (Ecole des Mines-ParisTech), Jean-Louis DURVILLE (CGEDD), Attilio EUSEBIO (Geodata),
Jean-Bernard KAZMIERCZAK (Ineris), Georges SCHAEREN (Norbert) and Thierry YOU (Geostock)

The work of AFTES on risks relating to underground space has attracted interest on the part of the French Committee for Soil Mechanics and Geotechnical Engineering
(Comité Français de Mécanique des Sols et de Géotechnique, CFMS), the French Committee for Rock Mechanics (Comité Français de Mécanique des Roches, CFMR)
and the French Committee of Engineering Geology and the Environment (Comité Français de Géologie de l’Ingénieur et de l’environnement, CFGI). At their request,
these three commissions have also reviewed this recommendation and suggested a number of changes. This is because while they recognise that this text has been
drafted with “underground works” in mind, they also believe that it may easily be used or adapted for other types of structure for which risks relating to underground
space are a major factor.
The French original of the following text was validated by AFTES’ Technical Committee on 23/07/12.
AFTES welcomes all suggestions relating to this text.

Summary

1 - Purpose of the Recommendation- . . . . . . . . . . . . . . .318- 4.2 - General conduct of studies . . . . . . . . . . . . . . . . . . . . . . . . .329


1.1 - Review of the current situation . . . . . . . . . . . . . . . . . . . . .318 4.3 - Preliminary studies phase (EP) . . . . . . . . . . . . . . . . . . . . . .330
1.2 - Scope of the Recommendation . . . . . . . . . . . . . . . . . . . . . .318 4.4 - Preliminary Design phase (AVP) . . . . . . . . . . . . . . . . . . . . .330
1.3 - Objectives of the Recommendation . . . . . . . . . . . . . . . . . . .318 4.5 - Project phase (PRO) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .331
4.6 - Assistance with awarding contracts of works phase (ACT) . .331
4.7 - Case of design / construction or other advance assignment
2 - Terminology- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .319- processes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .332
2.1 - Vocabulary used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .319
2.2 - Comments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .319
5 - Bibliography- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .333-

3 - Rick management methodology- . . . . . . . . . . . . . . .321- 6 - Appendices- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .334-


Important note . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .321 1 - Relationship with existing texts . . . . . . . . . . . . . . . . . . . . . . .334
3.1 - Review of Geotechnical Knowledge and Uncertainties . . . .323 2 - Quality of data and reliability of interpretations . . . . . . . . . .336
3.2 - Geotechnical risk assessment . . . . . . . . . . . . . . . . . . . . . . .324 3 - Development of the geological model and graphical
3.3 - Risk treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .327 representation of uncertainties . . . . . . . . . . . . . . . . . . . . . . .341
4 - Hydrogeological risks and uncertainties . . . . . . . . . . . . . . . .348
4 - Application of risk analysis in each phase- 5 - Uncertainties and risks relating to geotechnical parameters . .350
of the project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .328- 6 - Summary of risk sources . . . . . . . . . . . . . . . . . . . . . . . . . . . .351
4.1 - Correspondence between geotechnical engineering missions 7 - Methods used to quantify risks . . . . . . . . . . . . . . . . . . . . . . .353
and the French Public Works procurement law (MOP) . . . .328 8 - Acronyms and abbreviations . . . . . . . . . . . . . . . . . . . . . . . . .355

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 315
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page316

AFTES RECOMMENDATION N°GT32.R2A1 M

Summary
Purpose of the recommendation For instance, risk is defined as the effect of uncertainty on objectives; the level
(seriousness) of this risk is the result of a combination of the likelihood of the
This Recommendation follows on from previous work by AFTES investigating event under consideration and its consequences.
the problems raised by uncertainties that are specific to underground works:
• Recommendation GT1 on “Characterization of rock masses useful for the
Risk management methodology
design and the construction of underground structures” (2003),
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

• research by GT32 itself, including its work “Taking into account geological AFTES is of the opinion that studying geotechnical uncertainties and risks is
uncertainties in Tender Documents” (GT32-1 2004), an iterative process that must be repeated at the end of each project phase
• work by GT25 concerning best practices in terms of cost control and project (e.g. EP, AVP, PRO, etc.) before moving on to the next one. Indeed, this study
contractualisation (2007). and the conclusions the project owner draws from it with regard to the risks
the latter may or may not wish to bear will form the basis for proposals by the
It is needed because as yet, there is no shared method to characterise geo- project manager for additional survey work, changes to the project, the mode
technical uncertainties or to provide a framework for risk analysis. In addition, of construction, and so on.
new types of contract such as Design & Build, PPPs, concession agreements
and so on have sometimes resulted in discrepancies or potentially misleading This approach assumes that adequate geotechnical survey work has been car-
information in terms of the way these risks are assigned. ried out (even in the event of advance contractor consultation): risks that have
not been properly defined beforehand cannot be fairly assigned or shared. It
AFTES is of the firm opinion that the geotechnical risks and uncertainties that comprises three successive sequences, to be repeated for each phase of the
affect underground works projects must be identified, represented and project. These are shown in the logical diagram that forms Figure 1 (page 322):
evaluated as soon, and as objectively, as possible. To control the effects of - The review of geotechnical knowledge and uncertainties
such factors, construction methods and method of payment must be detailed - The resulting risk assessment
in the DCE, then validated by both parties prior to signature of the contract of - Treatment of these risks.
works. The aim of this Recommendation is thus to encourage all stakehol-
ders to provide the resources required to cater for uncertain geotechnical a) Review of knowledge and uncertainties. This sequence largely covers
events in advance, so that when these occur, they will have the least and supplements the establishment of Books A and B defined in the first GT32
possible impact on costs and construction lead times for the structure Recommendation. It comprises four stages:
in question. • Compilation of factual data, whether gathered specifically for the project
or derived from previous worksites or publications (Book A).
The term “geotechnical” is being used here in its broadest sense, to include • Analysis of the reliability of data, following which data may be adopted or
all issues relating to geology and hydrogeology as well as geotechnics in the rejected to establish geological and hydrogeological models and define the
strict sense of the term. It may be extended by analogy to “anthropic risks” geotechnical context this critical analysis is to be carried out and recorded
relating to old foundations, galleries, shafts and other remains. It could also at the start of Book B.
be similarly extended to cover risks created by underground works on neigh- • Drafting the Summary Geotechnical Report (MSG), supplemented by the
bouring buildings (the purpose of AFTES GT16). longitudinal geotechnical profile. Together, these items form Book B.
• Lastly, drafting the Register of Geotechnical Uncertainties, which in a sense
is the “negative” of the MSG. This register lists all the unknowns and uncer-
Terminology
tainties without analysing their consequences in terms of civil engineering
To minimise all-too-frequent misunderstandings, AFTES has decided to recom- and forms the last chapter of the MSG.
mend the strict and exclusive use of the terminology defined at the international
level in French and English by two ISO standards: b) Risk assessment. This sequence can be engaged as soon as a first
• ISO 31000: 2009 (F) – “Management du risque - Principes et lignes idea of the mode of construction of the work has been formed, in other
directrices”. words a first draft of the Design Report (Book C). This consists of three
• ISO: Guide 73: 2009 (E / F) – “Risk Management - Vocabulary”. stages:
• Risk identification. This involves reviewing all the uncertainties and imagi-
This vocabulary, which is non-specific to geotechnics, is detailed in chapter 2 ning all the positive or negative consequences these might have on the condi-
of the Recommendation. It includes fifteen or so terms. These may sometimes tions in which the structure is to be built. This stage draws on experience
differ from what is widely believed to be common usage, but their use makes with previous structures in similar rock or soil, including bibliographical
it possible to avoid the introduction of new definitions which are liable to research and consultation with experts.
confuse matters further. • Risk analysis. As much as is possible, this involves quantifying (or at least

316 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page317

AFTES RECOMMENDATION N°GT32.R2A1

qualifying) the likelihood of uncertain events and the seriousness of their stronger construction solutions, and so on. This analysis will lead to the Register
consequences in terms of costs, lead times, worksite safety, environmental of Risks being updated.
impact and so on. Since the consequences of an event may affect different
objectives in different ways, the resulting level of risk varies depending c) Project phase (PRO). This phase includes an update to the Project Geo-
on the objectives and priorities defined by the project owner. To illustrate technical Investigation (G2) in order to have a clearly defined project. Issues
this analysis, a matrix with two inputs (likelihood x consequences) is often to be settled include the investigations to be carried out as works progress,
used, combined with multiplying factors. threshold values appropriate to the construction methods used (convergence,
• Risk evaluation involves comparing the results of the previous analysis with settlement, vibrations, etc) and the inspection procedures. Since there should
the acceptability criteria defined by the project owner. It makes it possible not be any more new surveying, the Register of Risks can be finalised. This
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

to determine which risks require treatment to bring their seriousness down allows the project owner to measure the residual risks, check whether these
to an acceptable level. are acceptable, and define its definitive risk management strategy.

c) Risk treatment. This sequence involves reducing the level of a risk, or even d) ‘Assistance with awarding contracts of works’ phase (ACT). This phase
eliminating it altogether, by using the following types of means: reducing like- consists chiefly in establishing the most recent versions of previous documents
lihood by carrying out additional investigations, reducing consequences by as books A, B and C of the DCE, supplemented by chapters or documents rela-
modifying tunnel axis, layout, profile, methods used and so on. Once these ting to risk management. Pursuant to the new Fascicle 69 of the CCTG (to be
measures have been applied, the level of risk is again evaluated and compared published in 2012), it is at this stage that the project manager must draft the
to the project owner’s criteria, and so on. Risk Management Plan. This must set out the assignment of residual risks in
This iterative analysis process involves amending and supplementing Book C agreement with the project owner.
at every stage, particularly if new survey work has been launched in an attempt
to reduce some uncertainties. To ensure study traceability, a “Register of Risks” Lastly, detailed recommendations are supplied in appendix 3. These cover the
should be established and maintained, in which to log all treatment actions way geological cross-sections are drawn, the type of data to be shown on
implemented, along with their expected outcomes. them and how uncertainties should be shown. After a definition of what consti-
tutes a 3D Geological Model, there is a presentation of the successive docu-
ments to be drafted: the map of outcrops and the interpreted geological map,
Application of this method
the Outline Geological Diagram, followed by the Documentary Cross-Section
in each phase of the project
and the Interpretative Cross-Section. Lastly, the importance of the Longitudinal
The purpose of chapter 4 of the Recommendation is to explain how the method Geotechnical Profile is emphasised. This is a summary document that is an
set out above should be applied to a standard project governed by the French illustration of the Summary Geotechnical Report and an indispensable com-
Public Works Procurement Law (MOP), with contractor consultation at the Pro- plement to the latter.
ject stage. Firstly, the way MOP design phases relate to geotechnical enginee-
ring missions set out in French standard NFP 94-500 is reviewed. The risk
study process is then detailed for each project phase:

a) Preliminary Study phase (EP). This phase corresponds to geotechnical


mission (G11) in the relevant standard. It comprises an inventory and complete
identification of risks and uncertainties for the project, drawing on the expe-
rience of prior works (i.e. expert analysis). In addition to the Preliminary Study
File specified by the MOP law, the resulting documents include:
• a completed data sheet for each risk identified;
• the Register of Uncertainties and the Register of Potential Risks for the work-
site;
• the programme of treatment actions to be undertaken, notably geological,
hydrogeological and geotechnical investigations.

b) Preliminary Design phase (AVP). This phase includes both a Preliminary


Design Geotechnical Study (G12) and an initial Project Geotechnical Investi-
gation (G2) with the aim of providing an initial cost estimate for the structure.
The geological model derived from investigation campaigns allows geotech-
nical conditions that may be a source of risk to be properly identified, as well
as the general principles to minimise their consequences. These may include Collapse at the top of a tunnel excavation head
altering the route, the longitudinal profile, carrying out a survey gallery, using (St-Martin-la-Porte gallery).

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 317
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page318

AFTES RECOMMENDATION N°GT32.R2A1 M

1 - Purpose of the recommendation-

1.1 - Review of the current situation 1.2 - Scope of the Recommendation


Since the late 1990s, AFTES has been very concerned with the impact of geo- This recommendation relates to geological, hydrogeological and geotechnical
logical, hydrogeological and geotechnical uncertainties on underground works. uncertainties and risks. These three terms have been deliberately kept in the
Consequently, it has set up three working groups: title to underscore the fact that in a tunnel project, risk analysis must call on
a range of expertise that lies at the meeting-point of earth science and physical
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

• GT1 (Characterisation of rock formations), which has established a method science (Geology, Geological engineering, Hydrogeology, Soil mechanics, Rock
for semi-quantitative description of rock formations from the point of view Mechanics, etc.). However, the body of the text speaks simply of “geotechnical
of underground works; its recommendations were published in 2003 1; risks”, this adjective being used in its broad English sense of “Geotechnical
• GT32, which in its first configuration (known as GT32-1) suggested a metho- Engineering”, covering all aspects relating to underground space.
dology for taking into account these uncertainties in Tender Documents
(DCE), in particular by establishing Books A, B and C, the content of which The problems posed by anthropic remains (piles, shafts, galleries and old
is set out in § 4.6 (Recommendations published in 2004) [2]; infrastructures, etc.) surrounding a planned underground structure or one under
• Lastly, GT25 (control of risks and contractualisation), which examined every- construction require a similar procedure, as they also involve uncertainties
thing which could favour good control of project costs and made a recommen- which are difficult to resolve due to their location, state and behaviour. AFTES
dation to this end for the attention of all stakeholders (text published in 2007) [3]. is of the opinion that “anthropic risks” relating to these remains can be dealt
with using the same methodology as that suggested for geotechnical risks.
In the light of experience however, it appears that the situation is still far from
satisfactory for all aspects relating to the characterisation of uncertainties, The approach of this recommendation must also be applied to uncertainties
unforeseen circumstances and risks relating to underground space: and risks relating to the surroundings. This term refers to the neighbouring
• The graphical representation of these uncertainties on geological cross-sec- structures and buildings and their foundations; these structures, located in the
tions is often incomplete, ambiguous or completely lacking; Zone of Geotechnical Influence (ZIG), may either affect the structure to be
• In reports, the description of uncertainties is often insufficient, whether they constructed (by disrupting uniformity or affecting load distribution, for example),
relate to geotechnical properties (natural dispersion), the location of events or more often, be affected by it (settlement or cracking in built structures,
(crossing faults), the frequency of unpredictable phenomena (crossing karst vibrations, etc.). This approach may usefully be supplemented by the Recom-
cavities). mendation currently being drawn up by AFTES working group GT16 (“Effects
• Often, the prime contractor of an underground structure project does not of settlement and vibrations on built structures”).
have sufficient geotechnical engineering capacity, despite this being a vital
component for developing and managing a works contract; Lastly, this recommendation does not deal with contractual risk management,
• There is no recognised, unequivocal methodology for taking these uncer- nor the way in which this can be shared or compensated for financially during
tainties into account in so-called “Risk analysis” reports. These have the course of works. These aspects are within the remit of GT25 (“Contrac-
become commonplace for tunnel projects and are even virtually mandatory tualisation”), which was relaunched in 2010 and whose work follows on from
for international insurance companies (cf. ITIG, 2006) [9]; that of GT32.
• The new methods of contractualisation, particularly with early contractor
consultation, have sometimes led to the illusion that the contracting authority
1.3 - Objectives of the Recommendation
could thereby transfer to the contractor most of the risks relating to under-
ground space, and even reduce the investigation efforts incumbent upon it. Geotechnical risks and uncertainties that affect underground works projects
In fact this is not the case: even in the event of advance consultation, it is must be identified, represented and evaluated as soon, and as objectively, as
not possible to proceed with a serious analysis and fair allocation of the risks possible. To control the effects of such factors, construction methods and their
other than on the basis of thorough geotechnical investigations. method of payment must be detailed in the DCE, then validated by both parties
prior to signature of the contract of works. The aim is to encourage all stake-
Faced with these findings, in 2009, AFTES reactivated working group GT32, holders to provide the resources and procedures required to cater for uncer-
with a view to establishing a methodology for properly identifying and repre- tain geotechnical events in advance, so that when these occur, they will
senting uncertainties related to underground space, then analysing and dealing have the least possible impact on costs and construction lead times for the
with the risks arising from them for underground projects. structure in question.

1 The recommendation published in 2003 (TOS No.177) replaced a previous recommendation, of a much more summary nature, published in 1978 (TOS No.28).

318 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page319

AFTES RECOMMENDATION N°GT32.R2A1

To contribute to this objective, the GT32 recommendation aims mainly to Appendices 1 to 7 of this document bring together a set of recommendations
achieve the following: relating to particular points not dealt with in the text of the Recommendation
• Specifying terminology in terms of uncertainties and risks relating to under- in the required amount of detail. These recommendations do not interfere with
ground space (see chapter 2); the general approach set out in the body of the text, but should be taken as aids
• Establishing a methodology for examining risks (chapter 3); or tools which are useful for applying it. They relate to the following main points:
• Identifying the place of these risk studies in project procedure according to 1 - Relationship of the GT32.2 Recommendation with existing texts
regular French procedures, in particular those governed by the MOP law 2 - Quality of data and reliability of interpretations
(Public Works Procurement), from preliminary design work through to pre- 3 - Development of the geological model and graphical representation of uncer-
paration of the DCE (chapter 4); tainties
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

• Making proposals with a view to improving certain practices and tools requi- 4 - Hydrogeological risks and uncertainties
red, such as analysis of the reliability of investigations, graphical represen- 5 - Uncertainties and risks relating to geotechnical parameters
tation of uncertainties on geological cross-sections, etc. (cf. appendices). 6 - Summary of risk sources
7 - Methods used to quantify risks

2 - Terminology -

1.1 - Vocabulary used related to understanding or knowledge of an event, its consequence, or like-
lihood.
As the initial discussions of the working group have shown, each engineer has → Note 2 - Objectives can have different aspects (such as financial, health and
a particular understanding of terms such as: uncertainty, unexpected event, safety, and environmental goals) and can apply at different levels (such as
risk, etc.; each engineer ascribes a meaning to these terms roughly based on strategic, organization-wide, project, product or process).
everyday language, convinced that their understanding is the same as every- → Note 3 – Risk is often characterized by reference to potential events and
body else’s. This however is far from being the case, and this leads to constant consequences or a combination of these.
misunderstandings in this area. → Note 4 – Risk is often expressed in terms of a combination of the conse-
quences of an event (including changes in circumstances) and the associated
It has therefore appeared vital to adopt a very strict reference list used as likelihood of occurrence.
widely as possible. For this reason, it has been agreed that the ISO definitions,
which have broad international recognition, will be used. The text of this Risk source: element which alone or in combination has the intrinsic poten-
Recommendation makes strict use of the vocabulary defined in an ISO standard tial to give rise to risk.
and guide:
• ISO 31000: 2009(F) – “Management du risque - Principes et lignes direc- Risk assessment: overall process of risk identification and risk evaluation.
trices” [9].
• ISO: Guide 73: 2009 (E / F) – “Risk Management - Vocabulary” [10]. Risk identification: process of finding, recognizing and describing risks.
→ Note 1: Risk identification involves the identification of risk sources, events,
The definitions of the main terms used in ISO documents (in bold type) are their causes and their potential consequences.
provided below in italics; the notes mentioned are also part of the ISO standard. → Note 2: Risk identification can involve historical data, theoretical analysis,
They are excerpts (without edits or comments) of the French version of the informed and expert opinions, and stakeholders’ needs.
standard, which has also been published in English.
Event: occurrence or change of a particular set of circumstances.
Risk: effect of uncertainty on objectives → Note 1: An event can be one or more occurrences, and can have several
→ Note 1 - An effect is a deviation from the expected - positive and/or negative. causes.
→ Note 5 2 - Uncertainty is the state, even partial, of deficiency of information → Note 2: An event can consist of something not happening.

2 The numbers of notes appearing in the ISO standard have been kept, although it has been deemed more logical to alter the order of presentation.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 319
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page320

AFTES RECOMMENDATION N°GT32.R2A1 M

→ Note 3: An event can sometimes be referred to as an “incident” or “accident”. → Note 2: Risk treatments that deal with negative consequences are some-
times referred to as “risk mitigation”, “risk elimination”, “risk preven-
Risk analysis: process to comprehend the nature of risk and to determine tion” and “risk reduction”.
the level of risk.
→ Note 1: Risk analysis provides the basis for risk evaluation and decisions about Residual risk: risk remaining after risk treatment
risk treatment. → Note 1: Residual risk can also be known as “retained risk”.

Level of risk: magnitude of a risk or combination of risks, expressed in


2.2 - Comments
terms of the combination of consequences and their likelihood.
2.2.1 - An example of risk: the case of a TBM in hard rock
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

Consequence: outcome of an event affecting objectives.


→ Note 1: An event can lead to a range of consequences. The definitions listed in § 2.1 above, quoted verbatim from ISO standard 31000,
→ Note 2: A consequence can be certain or uncertain and can have positive or are not very intuitive and require a certain amount of use to become familiar.
negative effects on objectives. To help with learning these terms, a simplified example of a risk illustrating
→ Note 3: Consequences can be expressed qualitatively or quantitatively. the use of the main terms is presented below.
→ Note 4: Initial consequences can escalate through knock-on effects.
The case is that of a tunnel to be excavated using a TBM in a single geological unit
Likelihood: chance of something happening. composed of hard rock with virtually no fractures. The design of the TBM depends
→ Note 1: In risk management terminology, the word “likelihood” is used to refer in part on the unconfined compressive strength (UCS) values of the rock matrix;
to the chance of something happening, whether defined, measured or deter- this is determined by means of laboratory tests conducted on core samples.
mined objectively or subjectively, qualitatively or quantitatively, and described
using general terms or mathematically (such as a probability or a frequency One risk source is an under-estimation of unconfined compressive strength
over a given time period). (UCS) values.
→ Note 2: The English term “likelihood” does not have a direct equivalent in
some languages; instead, the equivalent of the term “probability” is often The event in question is the occurrence of one or more areas of terrain where
used. However, in English, “probability” is often narrowly interpreted as a resistance to cutting proves to be much more difficult than expected, due to
mathematical term. Therefore, in risk management terminology, likelihood is uniaxial compressive strength being much higher than expected.
used with the intent that it should have the same broad interpretation as the
term “probability” has in many languages other than English. The consequences of this event with respect to expectations are mainly as
follows:
Risk evaluation: process of comparing the results of risk analysis with risk ➨ slower rate of progress
criteria to determine whether the risk and/or its magnitude is acceptable ➨ greater wear and tear on tools and therefore higher tool consumption
or tolerable. ➨ longer completion times
→ Note 1: Risk evaluation assists in the decision about risk treatment. ➨ additional costs due to excessive tool consumption and longer comple-
tion times.
Risk criteria: terms of reference against which the significance of a risk is These consequences are exacerbated when there are many, long areas with
evaluated. higher uniaxial compressive strength and when the difference between the
→ Note 1: Risk criteria are based on organizational objectives, and external and actual value and forecast value is large.
internal context.
→ Note 2: Risk criteria can be derived from standards, laws, policies and other The likelihood of risk (the probability that one or more areas have a higher
requirements. unconfined compressive strength value than the value used for the project)
depends on several factors:
Risk treatment: process to modify risk. ➨ the number and distribution of core samples along the project,
→ Note 1: Risk treatment can involve: ➨ the number of tests conducted (statistical population),
- avoiding the risk by deciding not to start or continue with the activity ➨ the uniformity of the material forming the geological unit,
that gives rise to the risk; ➨ the dispersion of measured values.
- removing the risk source;
- changing the likelihood; Likelihood is all the lower when:
- changing the consequences; ➨ the material forming the geological unit concerned is highly uniform,
- sharing the risk with another party or parties (including contracts and ➨ there are many surveys, spread adequately along the project,
risk financing; ➨ there is a high number of tests which are also well distributed over all
- retaining the risk by informed decision boreholes,

320 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page321

AFTES RECOMMENDATION N°GT32.R2A1

➨ the statistical distribution of values measured is highly uniform (narrow of GT32-1, AFNOR NF X 50-117, the ITIG “Code of Practice”, the RFF Book for
Gauss curve). risk control and ITA/AITES Guidelines (2004) [6].

Risk treatment The tables of equivalent terms presented in this appendix indicate fairly good
During preliminary study phases, the level of risk is high because the geological consistency between the different documents; however, it appears that certain
context is known only summarily and there is a very high degree of uncertainty. important terms are sometimes used with different meanings. This has made
At this stage the treatment measures consist in an initial investigation cam- it necessary to adopt a single reference, which has led to the choice made in
paign aimed at drawing up a summary geological model. this Recommendation in favour of strict use of the ISO 31000 terminology [9].
During the ensuing study phases until the project is finalised, the treatment is
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

aimed at reducing the likelihood of risk by increasing the number of samples In addition, GT32.R2F1 suggests the use of the term “seriousness”, which is
and strength measurements. not included in the vocabulary suggested by ISO 31000, but is nonetheless
When the works contract is drawn up, the risk treatment may consist, for ins- accepted to describe the magnitude of consequences.
tance, of the following:
➨ a prudent choice regarding the projected values for the unconfined com- 2.2.4 - GT32-1 recommendation
pressive strength : maximum measured value, mean plus one or two
standard deviations, etc.; From the point of view of its form, the previous recommendation of GT32-1
➨ in addition, a prudent TBM design, taking into account an additional mar- will need to be corrected to bring it into line with the terminology determined
gin with respect to the maximum unconfined compressive strength; here (cf. Appendix 1, § 1).
➨ possibly, abandoning TBM excavation.

2.2.2 - The term “Uncertainty”

In ISO documents, uncertainty is defined as “... the state, even partial, of defi-
ciency of information related to, understanding or knowledge of, an event, its
consequence, or likelihood.” (cf. § 2.1. Definition of Risk, Note 5). In the following
part of this Recommendation, the term “uncertainties” (in the plural) is used
to mean the result of the uncertainty defined above, i.e. to refer to events the
occurrences of which (number and location) and/or the related geotechnical
conditions are affected by this state of uncertainty.

2.2.3 - Comparison with other documents dealing with risk

Appendix 1 presents a comparison of the terms used in a number of documents


dealing with how risks are taken into account: the previous Recommendation A frequent risk: falling blocks at excavation front.

3 - Risk management methodology-

➨ the studies must be conducted in a global, concomitant and interactive


Important note
manner, without the missions being compartmentalised;
The risk management methodology defined below should be used in ➨ an iterative process must be applied through to completion of the design
conjunction with the design process for the underground structure in studies.
question to form a single design procedure fully incorporating the issue
of risks. The designer must bear in mind at all times that the surrounding formation
To conduct such a design procedure, including all the different issues (geo- in which the structure is excavated is a part of the structure itself, as are
metry, geotechnics, construction methods, costs, lead times, planning and the structural elements added during the construction of the structure (sup-
contractualisation, etc.), the following is necessary: ports, linings, etc.). This means that for a given functional geometry (the
➨ the “designer” in charge of design studies must be constituted of a mul- inside cross-section of a typical profile for example), the choice of construc-
tidisciplinary team with all the necessary skills; tion method and dimensioning of the structure are closely and directly linked

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 321
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page322

AFTES RECOMMENDATION N°GT32.R2A1 M

to the geotechnical characteristics of the formation which will be encoun- All these operations are shown on the flowchart below.
tered throughout the duration of the project. It should be emphasised that the Risk Management procedure suggested here
is applicable to all stages of a project, and that it is an iterative process to be
Any unsuitability of construction methods with regard to the geotechnical conducted throughout the study process.
conditions actually encountered may have extremely detrimental conse-
quences. This is the essential reason why, during the studies for a tunnel
project, the civil engineering aspect cannot and must never be disasso-
ciated from the geotechnical aspect:
both are necessarily closely intertwi- REVIEW OF KNOWLEDGE
AND UNCERTAINTIES
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

ned, right from the preliminary stu-


dies. § 3.1
The geotechnical risk management ANALYSIS OF RAW DATA
methodology which AFTES recom-
mends should be applied for studies
comprises three major phases:
• Compiling a Knowledge Review
RELIABILITY OF THE DATA
covering geological, hydrogeological
and geotechnical data (§ 3.1);
• Geotechnical risk assessment based
on the summary of data; this phase
in turn comprises three stages: risk SUMMARY AND INTERPRETATION
identification, analysis and evaluation
(§ 3.2);
• Geotechnical risk treatment (§ 3.3).
COMPLEMENTARY
REGISTER OF UNCERTAINTIES
INVESTIGATIONS

RISK ASSESSMENT

RISK IDENTIFICATION

RISK RISK ANALYSIS DEFINITION


TREATMENT
DEFINITION OF AND UPDATE
RISK MITIGATION
MEASURES OF THE RISK
RISK EVALUATION
REGISTER

(Appendix 7)

DEFINITION OF
RESIDUAL RISK
(Appendix 7)
Figure 1 - Flowchart summarising risk
management methodology.

322 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page323

AFTES RECOMMENDATION N°GT32.R2A1

3.1 - Review of Geotechnical Knowledge complexity of the local geological context, the nature of investigation works
and Uncertainties as well as the physical distribution of this work and its spatial “density”
may be mentioned (cf. appendix 3). At this stage the choice may be made
The review of geological, hydrogeological and geotechnical knowledge and not to retain certain data; proper reasons for any such decision must be
uncertainties may be viewed as being equivalent to the “Presentation of supplied, as for a GBR (Geotechnical Baseline Report) type file.
geotechnical data in the Summary Report” stage, as described in the first
AFTES GT32-1 recommendation [2]. This phase itself comprises four stages: 3.1.3 - Summary and interpretation
• Presentation of the raw data available;
• Assessment of its reliability; The third stage consists in drawing up a geological, hydrogeological and
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

• Summary and interpretation; geotechnical model, on the basis of knowledge available at this stage, dis-
• Summary (“register”) of uncertainties and in particular gaps in know- playing the designer’s idea of the geological context and expected construc-
ledge. tion environment. This model is designed to become more specific and
detailed as the investigation works advance. The presentation of this model
3.1.1 - Presentation of the raw data available includes producing two types of documents:
• a report, detailing the hypotheses deemed the most likely by the designer
During this first stage, as complete as possible a list must be drawn up based on their analysis of all the data. This report should include distinct,
comprising all documentary data, whether this be geological, hydrogeolo- detailed chapters on Geology, Hydrogeology and Geotechnics;
gical or geotechnical in nature, and relating to worksites conducted in simi- • graphical documents: geological and hydrological models and especially
lar terrain; the results of specific investigations conducted for the project provisional longitudinal geotechnical profiles, along with as many cross-
should of course be added to these data. sections as necessary and, if required, a horizontal cross-section of the
project.
The nature and quantity of available data, their distribution, source and date
of acquisition must be clearly stated. For example, the map of outcrops and It is in these documents that uncertainties with respect to interpretation
the geological map, drawn up according to the recommendations set out should be pointed out, in particular on graphical elements (cf. appendix 3).
in appendix 3, form an integral part of the raw data to be taken into account. The provisional longitudinal geotechnical profile presents, in compliance
with the AFTES GT1 Recommendation, a break-down of the structure into
With respect to geotechnical parameters, and with reference to the AFTES sections or geotechnical sub-sections deemed to be uniform along their
GT1 Recommendation relating to the characterisation of rock formations, entire length from the point of view of the various applications for the pro-
these raw data correspond to the significant values provided by investiga- ject: design, dimensioning, construction methods, etc. This longitudinal pro-
tions (‘significant values’ means values measured by tests once non-repre- file should also include information about the variability of the parameters
sentative values have been removed with justification). within each sub-section, such as the following:
• the dispersion of parameters, to allow the finalisation of methods (exca-
The way in which data are presented is important. A presentation in the vation, mucking, temporary support, etc.);
form of tables and bar charts of values is to be preferred, for instance to • the characteristic values (as defined by GT1) chosen for the various geo-
present data about identical rock types or facies. Generally speaking, the technical magnitudes. These values may be different depending on the
total number of measurements for each sort of parameter must always be issue under consideration (excavation, temporary support, convergence,
specified. In addition to the summary, it must be possible to place all raw settlement, etc.);
data at the disposal of those working on the project, including values clas- • the limits within which the main parameters vary.
sified as non-representative.
In the event of the possibility of geological uncertainties leading to signifi-
3.1.2 - Data reliability cantly different geological models, two provisional longitudinal geotech-
nical profiles should be proposed, corresponding to the most contrasting
The second stage consists of conducting a critical evaluation of the quality hypotheses, in uncertain areas, with the actual situation probably located
of the different types of data available: remote detection images, site obser- somewhere between them. The risk study will be conducted for the two
vations, boreholes, geophysical investigations, laboratory and in situ tests, provisional longitudinal geological profiles. If necessary, the provisional geo-
investigation in shafts or galleries, experience feedback from neighbouring logical profile(s) may be supplemented by explanatory diagrams deemed
structures, etc. This stage is highly recommended to correctly define the to be useful for a proper understanding of the geological context.
contribution of these data to drawing up the geological, hydrogeological
and geotechnical model. It is also appropriate to evaluate the extent of gaps 3.1.4 - Register of Geotechnical Uncertainties
in knowledge, i.e. “what is not known”.
This evaluation may be of a qualitative, semi-quantitative or quantitative The fourth stage consists of summarising the uncertainties identified at the
type; among the factors to be taken into account to evaluate reliability, the end of the previous operation and bringing them together in a “Register of

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 323
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page324

AFTES RECOMMENDATION N°GT32.R2A1 M

Uncertainties”3. To illustrate this, the non-exhaustive list below sets out the 3.2.1 - Risk identification
main uncertainties likely to feature in this register:
⇒ uncertainties corresponding to gaps in geological, hydrogeological and Excerpts from ISO 31000 standard: 2009 (§ 5.4.2 of the standard: risk
geotechnical knowledge: these relate to areas where the level of know- identification):
ledge is insufficient to offer a reliable model;
⇒ uncertainties relating to the location of certain events, for example
“...The aim of this stage is to make a comprehensive list of risks based
contacts between geological formations or different facies within the
on events likely to cause, enhance, prevent, degrade, accelerate or delay
same formation, singular areas such as faults, overlapping, shearing
the achievement of objectives..... Risk identification should include an
zones, etc.;
examination of chain reactions of particular consequences, including
⇒ uncertainties relating to geotechnical conditions (extension, nature and
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

knock-on and cumulative effects. A wide range of consequences should


characteristics of component materials, hydrogeology, etc.) associated
also be examined, even if the source or cause of the risk may not be
with certain events and possibly their location (for example areas that
obvious. Whilst identifying what may happen, it is necessary to examine
have been identified as singular in other respects: faults, etc.); the possible causes and hypotheses of potential consequences. All signi-
⇒ uncertainties as to the occurrence of well-identified uncertain events ficant causes and consequences should be examined.
(possible or probable), the number, location and related geotechnical The organisation should use risk identification tools and techniques to
conditions of which are not known, for example: singular areas (faults, suit its objectives and aptitudes, and the risks to which it is exposed.
etc.), areas with high water inrush, karst cavities, quartz seams, etc.; All the information used for risk identification must be relevant and up-
⇒ uncertainties due to the natural dispersion (variability) of ground to-date. Whenever possible this should be backed up by appropriate
properties. documentation. The people with the appropriate knowledge should take
part in risk identification.”
This Register of Uncertainties should be limited to a list of the uncertainties
identified, without analysing the consequences. It must relate to the entire
Zone of Geotechnical Influence (ZIG) which is specific to each site and Risk identification therefore requires the analysis of uncertainties with res-
each planned structure. This zone, defined in NF P 94-500 [8], corresponds pect to their effects on expected results. Normally all uncertainties are a
to the volume of terrain within which there is interaction between the struc- source of risk, but some of them may have virtually no effect at all. One
ture (due to its construction or operation) and the environment (soil, ground- example is the uncertainty relating to the location of the contact between
water, surrounding structures and buildings, etc.). The scope of the ZIG two geologically distinct but geotechnically similar formations. This contact
depends on the geotechnical conditions, the diameter of excavation, depth will not therefore require any change in construction plans; the position of
and the methods envisaged for construction. This scope is therefore not the contact, although uncertain, will have no bearing on the achievement
intrinsic to the site and is liable to vary according to the different options of objectives.
envisaged for the construction, so it must be constantly updated.
It follows that only uncertainties for which the deviations induced with res-
On completion of this first phase of “Review of Geotechnical Knowledge pect to the geological and hydrogeological models (or the provisional lon-
and Uncertainties”, the elements drawn up during the four stages described gitudinal geotechnical profile) are sufficiently significant to cause notable
above are brought together in a single document including both a report consequences, need to be identified as risks. These deviations may be
and diagrams, as well as the Register of Uncertainties. When the works opportunities if these changes in circumstances are favourable for the pro-
contract is drawn up, this single document constitutes the Summary ject, or risks (in the usual sense of the term) if these changes are detrimental
Geological, Hydrogeological and Geotechnical Report (as defined in CCTG to the project.
Fascicle 69), or Summary Geotechnical Report (MSG).
The risk identification stage therefore consists of ascertaining which of the
uncertainties listed are likely to lead to the occurrence of events of which
3.2 - Geotechnical risk assessment
the consequences would constitute a change of circumstance with respect
For each of the risks under consideration, the risk assessment phase (as to those taken into account in the geological/hydrogeological models and
defined by ISO and this document) includes three distinct phases: in the provisional longitudinal geotechnical profile chosen.
• risk identification,
• risk analysis (in the strict sense of the term), For each of the uncertainties identified, several hypotheses may be formed,
• risk evaluation. e.g.:
➨ for a given event, a variable number of occurrences, different locations
or more or less serious consequences;

3 In a large number of risk studies, the Register of Geotechnical Uncertainties is often improperly called the “Register of Risks”.

324 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page325

AFTES RECOMMENDATION N°GT32.R2A1

➨ for a “lack of geological knowledge”, various configuration hypotheses The Risk analysis stage includes three operations:
for the geological context. • quantification of the consequences arising from an event identified as a
risk;
To help with risk identification, it is very useful to conduct bibliographical • quantification of the likelihood of this event and/or consequences;
research on experience feedback from underground works built very close • determination of the level of risk (significance of the risk) by combining
to and/or in similar geotechnical and environmental conditions. Research the consequences and likelihood.
and analysis of experience feedback is carried out as and when investiga-
tions supply a detailed description of the geological model and provisional
longitudinal geotechnical profile. This kind of approach is highly profitable 3.2.2.1 - Quantification of the consequences arising
from an event
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

for better risk identification, as well as to judge the relevance of the methods
to be used and direct the investigations to be carried out. To proceed with risk assessment, the designer must draw up one or more
hypotheses for each event identified, describing the circumstances caused
3.2.2 - Risk analysis by the occurrence of the event. This description of circumstances must be
sufficiently detailed to allow proper evaluation of all the consequences. The
Excerpts from ISO 31000 standard: November 2009 (§ 5.4.3 of the standard: consequences of the same event may affect several objectives and each
“Risk analysis”): of these objectives in a different way. For each event, an analysis of its
consequences on each of the objectives should therefore be conducted.

Depending on the case, there may be a number of objectives 4: cost, lead


“ …Risk analysis supplies the data for evaluating risks and taking the
time, environment, safety, performance, legal issues, image, etc. Practically
decision to treat them or not, and enables the most appropriate treat-
ment strategies and methods to be chosen. Risk analysis may also speaking, for geotechnical risks only, the most relevant general objectives
contribute to decision-making when choices must be made and the are site safety, cost, lead time, performance and the environment. The conse-
options involve different types and levels of risk. quence is usually estimated as being the additional costs and/or extra time
Risk analysis involves risk causes and sources being taken into account, required by the construction work necessary to treat the event encountered.
as well as their positive and negative consequences and the likelihood
of these consequences occurring. The factors affecting the conse- Examples of methods for quantifying consequences are provided in appendix 7.
quences and their likelihood must be identified, as well as other attri-
butes of risk. An event may have a number of consequences and affect 3.2.2.2 - Quantification of the likelihood of an event
a number of objectives. The existing risk control methods must be taken
into account, as well as their efficiency and performance. The following stage consists of determining the “likelihood” of the identified
The way in which the consequences and their likelihood are expressed event and/or its consequences. Likelihood may concern the event and its
and the way in which they are combined in order to determine the level consequences, or only the consequences:
of risk must correspond to the type of risk, the information available ⇒ One example of the first case is an event identified as being possible,
and the risk assessment objective. Consistency with risk criteria must with a range of possible consequences if the event occurs. Several
be ensured. It is also important to take into account the interdependence occurrence hypotheses should then be envisaged according to the
of the different risks and risk sources. seriousness of the consequences:
The level of confidence in the determination of the level of risk and its
⇒ In the second case, the event is certain but its consequences are unsure.
sensitivity to prior conditions and hypotheses should be taken into
This may be the case for a fault, the occurrence of which is certain, but
account in the analysis. Decision-makers should be informed of this as
well as other stakeholders if necessary. Factors, such as a difference the location and/or seriousness of which are not precisely known.
in expert opinion, uncertainty, the availability, quality, quantity and vali-
dity of the relevance of information and the limits of modelling should The likelihood of the event itself depends on a number of factors charac-
be mentioned or even emphasised. terising the level of knowledge; the designer is responsible for analysing
Risk analysis may be conducted to different levels of detail according the following:
to the risk, the purpose of the analysis as well as the information, data ➨the amount of investigation works carried out, its relevance (appropriate
and sources available. This analysis may be qualitative, semi-quanti- type of investigation for the context being examined) and its quality of
tative or quantitative type, or a combination of the three, depending on execution;
the circumstances ...” ➨the geographical proximity of investigation works to the structure;
➨the complexity of the geological context.

4 In the document “Guidelines for tunneling risk management” produced by AITES WG2, seven categories of consequence are suggested (cf. § 7.3.2), distinguished according to the field concerned.

RFF opts for four categories of consequences (cost, lead time, performance and “other”).

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 325
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page326

AFTES RECOMMENDATION N°GT32.R2A1 M

In short, likelihood depends essentially on the quality of the geological model b) Role of the designer and project owner
and its capacity to adequately represent reality and be as close to it as pos-
sible. It is the project owner’s responsibility to establish the criteria to be used to
The table below provides qualitative or quantitative determination of like- evaluate the acceptability of the risk. These criteria and the given threshold
lihood in the form of probability. values may be different depending on the expected objectives. For example,
they may be as follows:
Indicative probability, ➨maximum cost (or with very small likelihood of it being more), expressed
Matrix Likelihood scale to be adjusted according as an absolute value or as a percentage of the total estimated amount;
score to the project being studied ➨maximum time (or with very small likelihood of it being more), expressed
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

as an absolute value, as a percentage of the total time or as a deadline


4 Possible 1/5 = 20%
such as the commissioning date for the structure;
➨adverse effects on the project image deemed to be unacceptable (unac-
3 Unlikely 1/20 = 5%
ceptable environmental impact, for example).

2 Highly unlikely 1/50 = 2%


For the same risk, the criterion may also relate to the aggregated conse-
Improbable 1/200 = 0.5% quences for each of the expected objectives.
1

The designer then proceeds with risk evaluation by comparing their esti-
Several approaches that may be used to determine the likelihood value are mated level of risk (by combining the likelihood and consequence) to the
described in appendix 2. risk criteria expressed by the project owner. For each of the risks, the project
owner may take two attitudes:
3.2.2.3 - Determining the level of risk (significance of the risk)
The “level of risk” (‘NR’) qualifies the significance of the risk and is usually 1) Refuse the risk and request that the designer:
expressed by combining the likelihood with the consequence, both of which ⇒ either revises the project, eliminating the risk source entirely (by modi-
are evaluated by the designer. fying the planned alignment and/or longitudinal profile, for example);
The combination of the likelihood and consequences may be “qualitative, ⇒ or carries out more investigation works, with the aim of accurate iden-
semi-quantitative, quantitative or a combination of the three, depending tification of likelihood and consequence values in order to determine the
on the circumstances.” level of risk more accurately.
2) Accept the risk, with or without treatment:
The level of risk may be determined either objective by objective, or for a ⇒ in the first case, the project owner asks the designer to treat the risk to
set of objectives, i.e. by adding together the impact of the consequences reduce its impact;
on the different objectives. The level of risk is very frequently presented in ⇒ in the second case, the project owner decides to “take the risk”, incor-
the form of a two-variable risk matrix (consequence and likelihood), as porating the possibility of increasing the production costs and lead times
shown in § 3.2.3c. below. estimated by the designer.

3.2.3 - Risk evaluation c) The risk matrix


To help with the project owner’s decision, the risk evaluation presentation
a) Reference texts by the designer may take the form of a “risk matrix”, establishing the accep-
Excerpts from standard ISO 31000 (cf. § 5.4.3 of the standard: Risk tability criteria according to the level of risk (LR). The risk matrix presented
evaluation): below is supplied simply for the purposes of illustrating risk evaluation. In
this example, the four levels of risk (each associated with a colour to
improve visual appreciation) are defined in terms of likelihood multiplied
“ Based on the results of the risk analysis, the aim of the risk evaluation
by consequence.
is to help decision-makers determine the risks requiring treatment and
priority for the implementation of treatments.
Each project and project owner has its own risk matrix, as its usefulness
Risk evaluation consists of comparing the level of risk determined during
relates solely to help with decision making. It is nonetheless recommended
the analysis process with the risk criteria established when the back-
ground was established. On the basis of this comparison, the necessity that there should be an even number of likelihood categories and conse-
of treatment can be studied. quence categories in order to avoid a central positioning.

In certain cases, risk evaluation may lead to the decision to undertake a


more thorough analysis... ”

326 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page327

AFTES RECOMMENDATION N°GT32.R2A1

Risk matrix

Possible 4 8 12 16
Likelihood

Not likely 3 6 9 12
Very Unlikely 2 4 6 8 Table 1 - Example of a two-variable risk matrix (likelihood
Improbable 1 2 3 4 and consequence) and 4 levels of risk. The coefficients
are supplied for illustrative purposes only and must be
Slight Medium Significant High adjusted according to each project.
Consequences
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

A colour legend corresponding to the different levels of risk is presented below:

RN index Indicative qualification of the level of risk to be adjusted according to each project

NR < 2 Negligible / minor risk No action required, the risk factors must be subject to specific monitoring by means of procedures.
Construction work may commence; risk factors must be subjected to specific monitoring by means of
2 < NR < 5 Significant risk (but in principle acceptable) procedures and the project may possibly be supplemented by a series of predefined measures which may
undergo adjustments during the execution.
Construction work may not commence until the risk has been reduced or removed. Solutions are possible without
5 < NR < 10 Major risk (to be monitored) major changes to the project.
Construction work may not commence until the risk has been reduced or removed. If the risk cannot be controlled,
NR > 10 Unacceptable risk the project may be abandoned or altered.

Table 2 - Illustrative example of definition and qualification of levels of risk (to be adjusted according to each project).

It should be emphasised that the coexistence of several risks, each of which


is deemed individually to be acceptable, may lead overall to a level of risk - altering its likelihood,
- altering its consequences,
deemed to be unacceptable.
- risk-sharing with another party (including contracts and funding of the
risk),
It should also be pointed out that since the matrix is only one element to - and maintaining the risk based on a reasoned choice.”
aid with decision-making, each case must then be reassessed for confir-
mation or otherwise of the classification of the resulting Level of Risk. § 5.5.2 - Selection of risk treatment options: “Selection of the most appro-
priate risk treatment options involves comparing the implementation costs
and efforts with respect to the advantages gained, taking into account legal
3.3 - Risk treatment and regulatory obligations and other requirements such as social respon-
sibility and protection of the natural environment. Decisions should also
3.3.1 - Reference text
take into account risks whose treatment cannot be justified from an eco-
nomic point of view, for example certain serious risks (highly negative conse-
Excerpts from standard ISO 31000: November 2009 (§ 5.5 of the standard: quences) which are however rare (low likelihood)....”.
Risk treatment):

§ 5.5.1 - Overview: “Risk treatment implies the choice and implementation


of one or more options for modifying risks. Once implemented, treatments
3.3.2 - Treatment actions
produce or modify risk control resources.
Risk treatment implies an iterative process: Risk treatment therefore aims at reducing the importance of risk, or eliminating
- evaluating risk treatment; it altogether. Possible actions may include the following:
- deciding whether the levels of residual risk are tolerable; ➨ eliminating the risk source, for instance by performing a specific inves-
- if they are not tolerable, generating a new risk treatment; tigation enabling uncertainty to be eliminated locally
- and appraising the efficacy of the treatment. ➨ altering likelihood, also by means of additional investigation enabling
Risk treatment options are not necessarily mutually exclusive, and are not
the geological model to be further clarified
appropriate for all circumstances. These options may include the following:
➨ reducing the consequences of an event on the circumstances of com-
- refusal of the risk, marked by the decision not to commence or pursue
the activity involving the risk, pletion, through the implementation of preventive technical measures or
- taking or increasing a risk in order to pursue an opportunity, modification of construction methods
- eliminating the risk source, ➨ implementation of an early detection method for the occurrence of an
event and early definition of remedial technical measures.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 327
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page328

AFTES RECOMMENDATION N°GT32.R2A1 M

Following application of these measures, a fresh evaluation of each risk is versions of the Register of Risks established during the different project phases
conducted. If, despite the treatment measures, the risk remains unacceptable, must be maintained by the project owner, with the aim of ensuring traceability
a new “risk treatment” process is launched. of the changes in risk analysis.

It should be noted that during design phases, most treatment actions consist
either in investigations aimed either at reducing uncertainty, or adjusting the
process itself, with the aim of making it as robust as possible with respect to
the consequences of these uncertainties. During the construction phase, resi-
dual risk treatment takes the form of anticipatory measures (investigation while
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

progressing) and predefined specific construction procedures.

In order to ensure the traceability of the entire risk management process, it is


appropriate to establish a “Register of Risks”, for which a framework is
suggested in appendix 7. This Register must provide a comprehensive list of
all the treatment measures implemented, with their results in terms of risk
reduction, as well as the measures decided during the study phase in progress
and to be implemented during the subsequent design phase. The successive An investigation gallery eliminates almost all geological uncertainties.

4 - Application of risk analysis in each phase of the project-

4.1 - Correspondence between geotechnical


engineering missions and the French Public Works
for public clients.
procurement law (MOP)
Although this Public Procurement Law relates only to French projects establi-
The table below shows the correspondence between typical geotechnical engi- shed for certain public Project Owners, the different phases of studies shown
neering missions, as described in standard NF P 94-500 (December 2006) [8] in the following table are a good representation of the developments in the
and the study phases defined in the French Public Works procurement law design phases of a project, even if the project is not subject to the Public Pro-
(and its application legislation) [4]. This law lays down the conditions for project curement Law. “Project Engineer” is used in the Public Procurement Law to
management for construction works (buildings or infrastructure) completed refer more generally to the designer of the structure.

Stage Typical geotechnical engineering missions (standard NFP 94-500) MOP law study phase

“Preliminary Geotechnical Site Study - G 11” Preliminary Studies (EP)


1 “Preliminary Design Geotechnical Study - G 12” (a)
Preliminary Design (AVP)
“Project Geotechnical Investigation Study – G 2 - Project Phase” (b)

“Project Geotechnical Investigation Study – G 2 - Project Phase” (b) or


Project Studies (PRO)
2 Updating and more thorough examination wherever necessary
Project Geotechnical Investigation Study – G 2 - Works Contract Assistance Phase” (c) Assistance with awarding contracts of works (ACT)
“Geotechnical study and monitoring for “Geotechnical supervision for the works phase G 4
Construction studies (EXE) Approval of construction studies (VISA)
the works phase -G 3 – Study Phase” (d) Phase “Works studies supervision phase” (e)

3 “Geotechnical study and monitoring for the Geotechnical supervision for the works phase - G 4
Supervision of construction department (DET)
works phase G 3 – Monitoring Phase” (d) Phase - Works supervision phase” (e)

“Geotechnical supervision for the works phase - G 4 - Works supervision phase” (e) Acceptance assistance (AOR)

a) With respect to Initial Geotechnical Investigation Studies (G1) including the Geotechnical Site Study (G11) and the Preliminary Design Geotechnical Study (G12), the
wording of the standard specifies that “These missions exclude any examination of construction quantities, lead times and costs of construction of geotechnical
structures, which form part of a Project Geotechnical Investigation assignment (stage 2). The cost of these is normally incumbent upon the Project Owner.” Given
that according to the MOP Public Procurement Law, the provisional cost for works is established on completion of the preliminary design studies, it is appropriate to
conduct a G2 Project Geotechnical Investigation at the time of this MOP law “Preliminary Study” phase. In the same spirit, as the feasibility of underground works
depends essentially on the geotechnical conditions, it may prove necessary to proceed with a Preliminary Design Geotechnical Study (G12) at the preliminary design
phase.

328 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page329

AFTES RECOMMENDATION N°GT32.R2A1

b) For underground works, the G2 Project Geotechnical Investigation is almost always incorporated into the general project management mission (as stated in the
wording of the standard). It is during this G2 assignment that the essential part of the Summary Geotechnical Report (MSG) is drafted, or at least that the elements
required to draft it are gathered.
c) The DCE includes, notably, additional geotechnical investigations to be completed during the construction phase, the different threshold values depending on
the methods (convergence, settlement, vibration velocities, etc.), as well as the necessary inspection procedures to ensure measures are monitored and to control
adherence to threshold values. The definition of all these provisions forms an integral part of the G2 Project Geotechnical Investigation (cf. Standard 94-500:
Table 2 and chapter 8) drawn up by the Project Engineer.
d) The cost of this mission is incumbent upon the contractor.
e) This supervision mission is similar to an external control, and its cost is borne by the Project Owner.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

4.2 - General conduct of studies Risk treatment is adjusted to each phase of progress of the project.
4.2.1 - Place of the risk study in the project procedure The usual treatment pattern is as follows:
- the risk associated with a major event 5 is reduced or removed by appro-
For the purposes of project study work, risk analysis is global, i.e. it concerns priate measures (project modifications) from the preliminary design phase
onwards (stage 1);
all risks, whether they are of a political, regulatory, land, environmental, orga-
- the risk associated with an important event is reduced or removed by
nisational or technical nature, etc. Even within technical aspects, the analysis
appropriate measures during the project stage (stage 2): adjustment of
of geotechnical risks forms only one part, which is nonetheless very important
the project, specific monitoring with predefined measures and related
given the role played by geological, hydrogeological and geotechnical condi-
threshold values, as well as possible adjustment to be introduced during
tions in the construction of a tunnel.
the construction phase;
- the risk associated with a residual event usually has a minor impact on
During the design phases, i.e. from the preliminary studies until the project
quality, costs, safety and lead times and may be grounds for an optimi-
(missions G11 through to G2), the geotechnical risk analysis concerns only the
sation solution, during the construction stage (stage 3).
designer and Project Owner (the latter may be assisted by their engineer’s
assistant (‘AMO’). Throughout the study process, the designer, who is deemed Risk management (and the ensuing management of potential costs) is based
to be knowledgeable, must supply the Project Owner with the elements which on detecting them as early as possible and controlling the effectiveness of
are necessary for the latter to decide on the strategy to be adopted, based on the solutions planned. This is based on the following actions:
their own risk criteria. a) in the design stage of the structure:
- evaluation of the uncertainties and variability of major parameters
For each study phase or geotechnical engineering mission, the methodology - environmental surveying, in particular for partially concerned surrounding
described in chapter 3 should be applied, with its three major stages: areas
⇒ Review of knowledge and listing uncertainties - definitions of any additional construction provisions to be implemented
⇒ Risk assessment = Identification + Analysis + Evaluation of each risk if the geotechnical situation or observed behaviour of the structure does
⇒ Risk treatment not comply with the provisions
- definition of possible adjustments and investigating potential opportu-
The nature and content of the documents supporting the various components nities
- taking inherent risks into account by budgeting for them
of the risk study are set out in § 4.6 for the DCE. These documents are of
- maintenance inherent to certain types of geotechnical structures
course more succinct in the initial phases of the project, but they should be
individualised as soon as possible, at least in the form of distinct chapters: b) during the performance of works: continuous geotechnical monitoring
these are living documents that should be developed, corrected and added to and control (as appropriate for related threshold values)
throughout the project. c) after works: any implementation of maintenance inherent to certain types
of geotechnical structures, to suit the geotechnical situation of the site and
4.2.2 - Excerpt from the NFP 94-500 standard relating to the specific characteristics of the surroundings of the structure.”
“risk treatment” 5 In order to ensure consistency with the vocabulary recommended by standard ISO 31000,

the term “event” replaces the term “unexpected event” used in standard NFP 94-500.

“...For each identified risk, the possible preventive action for reducing it
(reduction of uncertainties and the potential impact of these uncertainties)
should be defined, as well as the provisions to be implemented to detect 4.2.3 - Conducting surveys and other investigations
its occurrence as soon as possible (monitoring and control programme with
associated threshold values) and remedial action to minimise the impact if Geotechnical risk management throughout the project design process (from
it occurs (adjustment of the project). the preliminary studies through to the DCE) and during construction supposes
that at each stage of study, relevant and thorough soil investigation is conducted.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 329
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page330

AFTES RECOMMENDATION N°GT32.R2A1 M

This is aimed at reducing the significance of residual risks as much as possible. Documents to be supplied: Standard NFP 94-500 defines very specifically (cf.
Particular attention should therefore be paid to these investigation processes § 7.1 of the standard) the content of the preliminary site geological study which
from the establishment of the programme through to receipt of the results. is necessary for compiling the Preliminary Studies File as defined by the MOP
law. In addition to the report as specified in § 7.1.3. of the standard, the pre-
The programme must respond to the need, which means accurately describing liminary studies file must include formalised material:
the methods and resources to be implemented, best suited to eliminating ➨ the “Register of Uncertainties” listing all the uncertainties relating to the
uncertainties. After the initial general investigation campaigns, priority must preliminary geological model drawn up following this first study phase;
be given to targeted investigations for identified risks based on the geological ➨ the “Register of Risks” providing an assessment of the identified risks
model and the experience feedback from previous works in similar terrains. based on the Register of Uncertainties, i.e. the identification, analysis
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

and evaluation of these risks;


The services to be delivered, the procedures to be followed and the reports requi- ➨ the programme of treatment actions to be conducted to reduce the level
red must also be described very accurately in the consultation documents, in of residual risks so as to make these acceptable.
order to guarantee that the expected results are achieved. When the service pro-
viders’ bids are examined, checks must be made to ensure that the references Attention is drawn to the level of expertise also required by this work to avoid
and human and material resources featuring in the bid enable quality of the ser- two pitfalls:
vice to be guaranteed. Control of execution also ensures procedures are adhered ➨ eliminating a solution or alternative too hastily due to a view which is
to and that the services are indeed performed in accordance with the order. too pessimistic (or too cautious), when appropriate studies could have
Lastly, presentation of the results must highlight the uncertainty margins. shown that with certain provisions this would have been a technically
and economically acceptable solution;
➨ underestimating or failing to detect very serious difficulties with a solu-
4.3 - Preliminary studies phase (EP)
tion or alternative which at a later point, after studies and investigation,
It should be noted that one of the objectives set by standard NFP 94-500 for could prove to be far more complex and costly than shown by the pre-
a “Preliminary Geotechnical Site Study” (G11) is to proceed with an initial iden- liminary study.
tification of risks. At the preliminary studies phase, the following should the-
refore be carried out: Comment: In certain complex cases, it may prove necessary to proceed with
⇒ listing all geological, hydrogeological and geotechnical data, by means a more thorough Preliminary Geotechnical Site Study (G 11), and at this point
of a documentary survey covering the site and neighbouring structures also proceed with a Preliminary Design Geotechnical Study (G12), in order to
(within the ZIG perimeter); consolidate the assessment of the technical feasibility and of the planned
⇒ an inspection of the site and its surroundings in order to directly check structure at a reasonable cost. It may then prove necessary to proceed with
the geological characteristics of the project site; major investigation work at this phase: core drilling, or even exploratory adit
⇒ on the basis of the information gathered, identifying the main uncertain- (cf. note a of § 4.1).
ties and related risks.

4.4 - Preliminary Design phase (AVP)


This initial risk review, which must be as comprehensive as possible, is expert
work, requiring extensive experience of underground works and making For this phase, initially there is a “Preliminary Design Geotechnical Study”
constant reference to cases experienced in construction conditions similar to (G12). This follows a procedure which is virtually identical to that of the previous
those of the project concerned. For each of the risks, a sheet must be drawn phase apart from two differences:
up, describing the following: ⇒ there is more data which is (in principle) more relevant as this data
⇒ the risk sources; shows the findings of investigation work and specific studies for the project
⇒ the likelihood of occurrence of any adverse event; (decided on either at the end of the previous phase or at the beginning of
⇒ the consequences of the event should it occur; this phase);
⇒ possible risk treatment to reduce the level of risk. ⇒ the risk assessment and choice of treatment procedure starts to take
into account the construction methods envisaged and vice versa.
At this stage of preliminary studies, risk treatment is essentially aimed at offering
an investigation and study programme to specify the geological, hydrogeological The result of this is, firstly, a more detailed geological model which is (in prin-
and geotechnical situation as well as the seriousness of the geotechnical pro- ciple) more reliable and, secondly, a table describing the risks which is also
blems likely to be encountered. This programme is based on a preliminary geo- more detailed; in particular, major events 6 are identified, along with the general
logical model summarising the available data, as well as the uncertainties and principles for limiting their consequences. It should be noted that the risk des-
unknown factors, which are still (very) numerous at this stage. cription also depends on the construction method envisaged; this may lead to

6 In order to ensure consistency with the vocabulary recommended by standard ISO 31000, the term “event” replaces the term “unexpected event” used in standard NFP 94-500.

330 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page331

AFTES RECOMMENDATION N°GT32.R2A1

the exclusion of certain construction methods. The risks not fully treated at the end of this phase are therefore all residual
risks, the level of which must be brought to the attention of the project owner
Secondly, since the MOP law specifies that the provisional cost of works must to check their acceptability. To do this, for this final study phase a summary
be established on completion of the Preliminary Design survey, at this phase table of all the risks examined is recommended (Register of Risks) such as the
the G12 mission should be followed by a Project Geotechnical Investigation one presented in appendix 7, setting out in detail the likelihood and conse-
(G2), leading to a design which is sufficiently thorough to enable an estimation quence for each of the project owner’s objectives. The project owner should
of this nature. This G2 mission is distinct from the previous ones due to the use this table as a basis for the Risk Management Plan to be drawn up for
clearly higher level of knowledge (specific surveying has already been carried the finalisation of the DCE and contract.
out), taking into account the construction methods which have already been
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

defined, dimensioning of structures and the identification of major events and NB: As already stated (cf. § 4.1, note c), the Project Geotechnical Survey defines
measures planned to reduce their consequences (cf. note a of § 4.1). the additional geotechnical investigations to be conducted during the construc-
tion phase, the different threshold values associated with the methods (conver-
Documents to be supplied. As for the previous phase, standard NFP 94-500 gence, settlement, vibration velocities, etc.) as well as the necessary inspection
lays down very specifically (cf. § 7.2 of the standard) the content of the Pre- procedures to ensure measures are monitored and to check adherence to
liminary Design Geotechnical Study necessary for compiling the Preliminary threshold values.
Design file (AVP) as specified by the MOP law. Similarly, in addition to the ser-
vices laid down by § 7.2.2. of the standard, the Preliminary Design file (AVP) Lastly, at this stage, it may be desirable for the project owner to involve its
must include a formalised presentation of the same documents as the Preli- insurers (if this has not already been done).
minary Survey file, including of course, a greater degree of detail using the
information gathered during the investigation and treatment works conducted
4.6 - Assistance with awarding contracts of works
between the two phases.
phase (ACT)
This paragraph is limited to the consultation phase and does not deal with the
4.5 - Project phase (PRO)
means of remuneration for residual risks, which is within the remit of AFTES GT25.
During this phase, the Project Geotechnical Investigation (G2) carried out during
the previous phase is updated and finalised, including in particular the addi- To present all the elements playing a part in taking into account uncertainties and
tional investigation work and the measures aimed at minimising the risks. In geotechnical risks in an underground works project, an architecture replicating
principle, the project is fully defined at the end of this phase, except in certain that of the first AFTES GT32-1 recommendation (2004) is suggested. This
cases where certain details are finalised when the DCE is compiled. It is also suggested breaking down the DCE geotechnical file into three Books A, B and C.
at the end of this phase that the table shown below listing and presenting the
risks is drawn up in its almost final form (cf. Appendix 7). 4.6.1 - Raw data – Book A

Attention is drawn to the fact that this table of risks forms the basis upon which All the available raw data relating to geology, hydrogeology and geotechnics
the Project Owner makes the final decision as to the risk management strategy is grouped together in a factual file known as “Book A”. This Book also includes
(acceptance of residual risks and determining related measures), before data relating to anthropic remains (shafts, galleries, pits and old foundations).
moving on to the contract of works. It is therefore necessary for the project
manager to proceed with a detailed analysis of possible scenarios and conse- In addition, it is suggested that raw data relating to the existence, location and
quences for each of the risks, describing these in detail and estimating their pathological condition of neighbouring structures belonging to the ZIG and
possible additional costs and extended lead times, in order to inform the Project likely to be affected by the works (such as surface constructions, above and
Owner’s strategy as much as possible. below-ground infrastructures, etc.) should be treated in the same way; this
data should be listed as geotechnical data and included in the factual file known
Documents to be supplied. As for the two previous phases, standard as “Book A”.
NFP 94-500 lays down very specifically (cf. § 8.2 of the standard) the content
of the Preliminary Design Geotechnical Study necessary for compiling the Pro- 4.6.2 - Summary and Register of Uncertainties - Book B
ject file (PRO) as specified by the MOP law. Similarly, in addition to the services
laid down by § 8.2. of the standard, the Project file (PRO) must include a for- Pursuant to Fascicle 69 of the CCTG – Works and the first GT32 recommen-
malised presentation of the same documents as the Preliminary Survey and dation, the interpretation of geotechnical data by the project manager and their
Preliminary Design files, but in a more finalised form, as in principle this phase view of the geological situation and expected construction conditions are the
is the final study phase and, except in particular cases, there is no investigation subject of the Summary Geotechnical Report (MSG). This document has been
or design work after this phase other than additional investigation work required designed to be made contractual (cf. Fascicle 69) and was referred to as “Book
for the treatment of certain risks and on-progress investigations during the B” in the first GT32 recommendation. The “Register of Uncertainties” described
course of works. above (§ 3.1.4) may constitute the last chapter of this Report.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 331
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page332

AFTES RECOMMENDATION N°GT32.R2A1 M

As for geotechnical data, the interpretation of the data relating to the tain information does not allow the project owner to ensure the compatibility
surroundings and the designer’s assessment of their condition and sensitivity of possible risks and compliance with its objectives.
may be included in the Summary Geotechnical Report (Book B).
Furthermore, project owners can sometimes erroneously believe that involving
4.6.3 - Design Report and Register of Risks – Book C the construction company in the design will make the contractor liable for all
risks inherent in the construction of the project. In fact, it is not possible to
Following on from Books A and B, the first GT32-1 recommendation defined contractually transfer risks which have not been defined, at least in the form
a “Book C” or “Design Report”, in which the project manager presents and of potential events, just as an insurance firm will insure only clearly defined
gives grounds for the construction provisions proposed in the DCE. These may risks (events, consequences, and likelihoods). To enable a stakeholder (project
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

be adjusted or modified by the contractor in its offer. This document lists owner or construction company) to bear or transfer a risk in any manner what-
all the risk treatment measures required or proposed by the project manager, soever, they must have the information enabling potential events and their
in particular action aimed at protecting the environment (buildings, existing consequences to be identified, and therefore an appropriate level of know-
structures, underground and surface water, wildlife) with respect to harmful ledge of the situation. If, on occurrence of a risk, it is proven that the information
consequences of the works undertaken. available did not allow this risk to be identified and defined, the consequences
of this “unforeseeable event” will be borne by the project owner.
The “Register of Risks”, presented in the form of a table as shown in the PRO
phase (cf. § 4.5 below), may form the final chapter of this “Book C”, be the Given this state of affairs, some project owners may envisage transferring all
subject of a separate document, or be included in the “Risk Management possible, imaginable risks, defining these them very broadly, aiming to cover
Plan” planned in the new version of Fascicle 69, to be published in 2012. This all eventualities. However, to do so they must then check beforehand that the
Register of Risks would thus form the database required for drawing up the occurrence of these risks remains compatible with their objectives; in actual
Risk Management Plan, in particular for the envisaged remuneration provisions. An fact, this will rarely be the case. In addition, they may not formally transfer
example for the presentation of the Register of Risks is provided in appendix 7. these risks, since bidders do not have the information enabling them to define
these risks and will therefore be incapable of defining their level of cover. As
a result, bidders who decide to respond to calls for tender will take gambles
4.7 - Case of design / construction or other advance
which they are not really in a position to shoulder. This leads to unfair, unhealthy
assignment processes
contracts between stakeholders, and therefore to unmanaged risks.

Use of processes in which the construction contract is assigned well before Lastly, it is important to note that these non-conventional processes for assi-
the works is observed increasingly frequently, with the call for tender and resul- gning contracts have been designed for specific situations which must have
ting bids often carried out with very little investigation work having been done. proper grounds and be legally valid. They do not provide solutions or improved
In these cases, the level of uncertainty and risk is potentially very high, and in risk management for a project in and of themselves. On the contrary, it may
any case poorly known by the project owners (or concession awarder), as well even be considered that operations with high levels of uncertainty (with high
as by tenderers. risk) are unsuited to this type of approach and contract. This is for the above
reasons and also due to the following factors:
This lack of knowledge is sometimes obscured by the provision of a Register • Construction companies cannot be asked to manage the project owner’s
of Risks that is supposed to compensate for the low level of knowledge. This risks, in the sense of “identifying them, evaluating their consequences, choo-
approach is not satisfactory; indeed, experience shows that when a project is sing the means of treating them and/or covering them”: the normal, legiti-
drawn up, the lack of investigation work often leads to an initial view of the mate interests of construction companies are not those of the project owner;
geological model that is simplistic and optimistic, concealing its high degree • If each bidder offers its own analysis and risk cover, the principles of equality
of uncertainty. and fairness of bids are very difficult to observe in the case of structures
with high levels of uncertainty, leading to very high legal risks, unless the
Often, initial investigation work in this case have the effect of significantly financial criterion is made the main criterion. If it is, this will mean choosing
increasing the level of uncertainty “felt” by designers: this means that they the bid involving the least risk, which in turn will lead to risks not being
become aware of the complexity of the actual situation as they acquire initial managed by the project owner, and thus to uncontrolled drift in costs and
information drawn from the terrain. The upshot of this is that apart from certain lead times.
geological situations which have already been investigated elsewhere, it is
appropriate to treat risk studies compiled when little investigation work If the project owner has to choose this type of procedure for unavoidable rea-
has been done with extreme caution, as they are often far removed from sons, the risk management principles developed in this Recommendation
the actual situation. remain relevant. To carry through the process described, the project owner
must ensure it benefits from a high level of competence in geotechnics and
Risk control is therefore based above all on the relevance of investigation work underground works, so that the following can be achieved:
and the use made of this work. Consultation carried out on the basis of uncer-

332 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page333

AFTES RECOMMENDATION N°GT32.R2A1

a) prior to launch of the consultation: carrying out investigation campaigns risk management process implemented by the designer and construction com-
for fundamental data (geology-hydrogeology-geotechnics, existing structures, pany, and more particularly assess the treatment measures adopted or
buildings, etc.), the level of which must be appropriate to the complexity of planned, as well as the seriousness of the consequences of residual risks with
the situation. This must be even more detailed than in a conventional case, respect to its objectives.
because the design by the designer and construction company will be “valid”
only if this data is relevant. c) during construction: monitoring the progress of works, and being able to
judge the acceptability of any requests for additional remuneration presented
b) during the consultation process: being able to judge the relevance of the by the design-construction company.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

5 - Bibliography-

AFTES Recommendations Other publications


[1] AFTES (2003) – GT1 recommendations: Caractérisation des massifs [13] Piraud, J. (1996) – Vers une meilleure maîtrise de l’incertitude propre aux
rocheux utile à l’étude et à la réalisation des ouvrages souterrains. Revue coupes géologiques prévisionnelles. AFTES study days, Chambéry, pp.
Tunnels & OS, no. 177, pp. 138-186. 245-250. Editions Spécifique.
[2] AFTES (2004) – GT32-1 recommendations: Prise en compte des risques [14] Lombardi G. (2002) – Les risques géotechniques dans l’évaluation finan-
géotechniques dans les DCE. Revue Tunnels & OS, no. 185, pp. 316-327. cière des tunnels non urbains. Revue Tunnels & Ouvrages souterrains, no.
[3] AFTES (2007) – GT25 recommendations: Comment maîtriser les coûts de 173, pp. 321-325.
son projet. Revue Tunnels & OS, no. 201, pp. 128-168. [15] Bianchi, G.W, Perello P, Venturini G., Dematteis A. (2009) – Determination
of reliability in geological forecasting for tunnel projects: the method of
the R-index and its application on two case studies. Proc. ITA-AITES World
Standards, regulatory texts and other
Tunnel Congress, Budapest, pp. 23-28.
recommendations
[16] Bieth, E., Gaillard C., Rival F., Robert, A. (2009) – Geological Risk: a metho-
[4] MOP law – Amended law 85-704 of 12 July 1985 relating to public sector dological approach and its application to 65 km of tunnels under the
contracting and its relationship with private project management. French Alps – AITES/ITA World Tunnel Congress, Budapest.
[5] Swiss standards: [17] Robert, J. (2009) – L’accompagnement géotechnique indispensable pour
SIA 197 - Tunnel projects; general basis la réussite d’un projet – 17th International Conference on Soil Mechanics
SIA 199 - Study of surrounding rock formations for underground works and Geotechnical Engineering, Alexandria, vol. 3, pp. 2711-2714.
SIA 118/198 - General conditions for underground constructions [18] Gaillard C., Humbert E., Rival F., Robert A., (2011) Le management des
[6] AFNOR – Documentary fascicle no. FD X 50-117 (April 2003): “Management risques géotechniques est-il toujours pertinent ? - AFTES International
de projet – Gestion du risque” congress, Lyon – 17-19 October 2011.
[7] ITA/AITES, Working Group No. 2 (2004) - Guidelines for Tunneling Risk Mana-
gement – Tunneling & Underground Space Technology, No. 19, p. 217-237
[8] AFNOR standard no. NFP 94-500 (Dec. 2006) – Geotechnical engineering
missions, classification and specifications.
[9] ITIG (2006) – Code of Practice for Risk Management of Tunnel Works.
Recommendations of the International Tunnelling Insurance Group, English
and French versions published in Tunnels & OS, no. 214, Nov. 2009, pp.
188-224.
[10] ISO 31000 standard: 2009 (F) – Management du risque; principes et lignes
directrices
[11] ISO standard Guideline 73: 2009 (E / F) – Risk management; vocabulary
[12] Ministry of Ecology – Fascicle 69 (Travaux en souterrain) of CCTG-Travaux
– New version (introducing the principle of a Risk Management Plan). To
be published in 2012.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 333
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page334

AFTES RECOMMENDATION N°GT32.R2A1 M

6 - Appendices-

Appendix 1 - Correlations with existing literature

The purpose of Appendix 1 is to compare this Recommendation with other A) As to the three Books, this recommendation, GT32 R2F1, is in full agreement
documents dealing with risk management, more particularly the previous with GT32-1, in that structuring the geotechnical file into three books A, B and
Recommendation, GT32-1. C has been preserved and extended either fully or in part to the preliminary
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

design phases.

1 - GT32-1 recommendation
B) Concerning the distinction made between type 1, 2 and 3 uncertainties,
Published in 2004 [Ref. 2], Recommendation GT32-1, “Prise en compte des the further examination carried out in this recommendation offers an oppor-
risques géotechniques dans les dossiers de consultation des entreprises pour tunity to replace this categorisation into three types of uncertainty by the list
les projets de tunnels”, (“Taking into account geotechnical risks in tender docu- and description of uncertainties presented in § 3.1.4, “Register of Uncertain-
ments for tunnel projects”) took into account only the drafting of tender docu- ties” in the text of the recommendation.
ments (DCE), as its name indicates. This Recommendation was applied AFTES will undertake a review of recommendation GT32-1.
immediately on publication and is currently widely used in the profession. In
order to preserve the benefit of this Recommendation, it should be revised in C) Regarding the application to tender documents (DCE), which is not dealt
terms of both form and content, in order to make it consistent with this Recom- with by this recommendation, GT32.R2F1, care should be taken to ensure that
mendation, GT 32.R2F1. any revision of recommendation GT32-1 is consistent with the text of the new
fascicle 69 (to be published in 2012) and its application document (yet to be
1.1 - Consistency in terms of form drafted).

The application of the strict terminology selected for standard ISO 31000
2 - AFNOR document: FD X 50-117
involves rewording certain terms and expressions. Examples:
• “unforeseen event” should be replaced by “risk” or “event” This is a documentary fascicle rather than a standard. The document, entitled
• “uncertainty” should usually be replaced by “risk”, “Management de projet – Gestion du risque” (Project management - Risk
• “difficulties” should be replaced by “consequences” or “events”, management) [Ref. 6] is applicable during the implementation of a project risk
• “probability of occurrence” should be replaced by “likelihood”. management process.

Lastly, revision of Recommendation GT32-1 is an opportunity to rectify a num- 2.1 - Consistency in terms of form
ber of copywriting issues, including the following:
• In § 1 “Purpose of the recommendation”, the note discusses specific termi- “Project risk” is defined in this fascicle as an “event the occurrence of which
nology for natural risks (including the term “unforeseen event” (‘aléa’)), is not certain, and the manifestation of which is liable to affect the project’s objec-
which, apart from this specific term, is never used in the text. tives”. This definition is very close to the definition of risk supplied in the ISO
• In the same note – cf. § 1 “Purpose of the recommendation”, the following standard. Moreover, it is relatively simple to establish a correlation between
is stated: “the term “geological accident” should not be used to refer to…”, the principal definitions (see the table below, although the term “seriousness”,
whereas in § 5.2 section 3, “Description of persistent uncertainties”, this used here and in the RFF manual examined subsequently, used to define the
exact term is used; it also features in the legend for a figure entitled “Collapse magnitude of the consequence, has no equivalent in the ISO standard, which
of the cutting face”. AFTES confirms that this term is ambiguous and should does not make use of this concept).
be avoided.

1.2 - Consistency in terms of content AFNOR FD X 50-117 April 2003 AFTES GT32.R2F1

“project risk” “risk”


The main contributions of recommendation GT32-1 include the following: “seriousness” “Magnitude of consequences”
• presentation of the elements making up the geotechnical file in three books, “criticality” “level of risk”
A, B and C, (and particularly the creation of this third book C: Design Report);
“probability of occurrence” “likelihood”
• distinguishing three types of uncertainty: type 1, type 2 and type 3 uncer-
“risk estimation” “risk analysis”
tainties, with the latter equivalent to “unforeseen” in the sense of “unfore-
“risk evaluation” “risk evaluation”
seen events”;
“residual risk” “residual risk”
• their application to DCE.

334 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page335

AFTES RECOMMENDATION N°GT32.R2A1

This AFNOR document also suggests classifying events into four categories, direct project ownership. Although it uses different terms (or the same terms
as presented in the table below: with differing definitions), its vocabulary is very similar to that of the GT32.R2F1
recommendation and it is relatively simple to establish correlation between
Non-identifiable unexpected
terms:
Virtual event Identifiable Non-quantifiable unforeseen event
Identifiable Quantifiable Risk RFF Manual AFTES GT32.R2F1
Event that has occurred problem “acceptability”
“acceptability”
“treatment action” “treatment action”
It should be emphasised that the acceptance of “risk” adopted in recommen-
“unexpected event” “event in question”
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

dation GT32 R2F1 differs from this classification to the extent that it also deals
“cause” “risk source”
with identified events of which the consequences are very difficult to quantify,
“consequences” “consequence”
and for which it is necessary to envisage multiple scenarios corresponding to
“criticality” “level of risk”
consequences with varying degrees of seriousness.
“probability” “likelihood”

2.2 - Consistency in terms of content “seriousness” “Magnitude of consequences”

Apart from the distinction specified above, the approach proposed in recom- 4.2 - Consistency in terms of content
mendation GT32 R2F1 draws very largely on elements developed in this AFNOR
document. The approach put forward in the RFF document is worth taking into consi-
deration and certainly represents an excellent basis on which to establish
a detailed methodology of the risk management process.
3 - ITIG recommendations for risk management for
underground works
5 - ITA WG2: Guidelines for tunneling
3.1 - Consistency in terms of form risk management
Although it uses different terms (or the same terms with different definitions), 5.1 - Consistency in terms of form
the International Tunnelling Insurance Group (ITIG) document features vocabu-
lary that is very similar to the GT32.R2F1 Recommendation. It is relatively simple Although the language difference may result in translation issues, a fair
to establish correlation between terms (see the table below), although it should degree of correspondence may be observed between the GT32-2 Recom-
be emphasised that a degree of ambiguity exists regarding the term “risk eva- mendation and terms and definitions used in the ITA’s working group WG2’s
luation”, whose meaning differs depending on the document in question. Guidelines [7]. It is relatively easy to establish correlation between terms
as shown in the table below:
International Tunnelling Insurance
AFTES GT32.R2F1
Group [Ref. E 9]
ITA-AITES Guidelines AFTES GT32.R2F1
“risk” “level of risk”
“hazard” “risk source”
“consequence” “consequence”
“risk analysis” “risk analysis”
“probability” “likelihood”
“risk evaluation” “risk evaluation”
“peril” or “danger” “risk source”
“risk assessment” “risk assessment”
“risk evaluation” “risk analysis”
? “risk evaluation”

5.2 - Consistency in terms of content


3.2 - Consistency in terms of content
The approach put forward in the GT32.R2F1 Recommendation is consistent
The approach put forward in the GT32.R2F1 Recommendation is entirely with that described in the ITA-AITES Guidelines. The ITA-AITES document also
consistent with that described in the ITIG’s document. provides considerations relating to risk management during the call for tender
phase and finalisation of the contract, but these aspects are not dealt with in
the GT32 Recommendation, since they are taken into account by GT25.
4 - RFF risk control manual (Internal RFF document)

4.1 - Consistency in terms of form

This RFF document is destined for use with operations carried out under

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 335
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page336

AFTES RECOMMENDATION N°GT32.R2A1 M

Appendix 2 - Data quality and reliability of interpretations

of investigation and survey work and the methods used to carry these out.
In order to assess the resulting data quality, the various types of investiga-
1 - Assessment of the reliability of data and
tions used must be described and classified. The main types of investigation
anticipation of geotechnical conditions
are described in brief below:
As stated in § 3.1.2, analysis of the reliability of data is one of the most • Surface geological mapping: in this case, data quality is determined by
important tasks if the state of knowledge is to be properly assessed and the size of zone investigated, the scale of the mapping, the percentage
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

geotechnical uncertainties defined. of outcrops, and the type of measurements taken (lithological, structural,
etc.);
Experience shows that defining a geological, hydrogeological and geotech- • Boreholes: data quality is here defined by the type of borehole (full or
nical model and the reliability of the forecasts derived from it always partial core sampling or destructive), the depth compared to that of the
involves a certain degree of uncertainty. This may relate to two groups of project, the distance from the axis of the project, location with respect to
variables: critical zones, the nature of structural measurements (“reoriented” or
• the geological, hydrogeological and geotechnical context, particularly its not), the occurrence of in situ tests in boreholes, etc;
complexity • Geophysical investigations: quality here depends on the length of the
• the quality of investigations. profiles investigated, the distance from the project alignment, the depth
of the investigation and the method used;
This section describes the factors to be taken into account when assessing • Existing underground structures: if such structures exist, the distance
the reliability of data and the anticipations of future conditions. It also des- from the projected structure must be appraised, as must the availability
cribes two methods currently in use to carry out this assessment. of data carried out during the excavation, similarities with the geological
context of the project, etc;
1.1 - Complexity of the geological, hydrogeological and • Exploratory shafts and galleries: in complex geological contexts, this
geotechnical context type of structure (which sometimes forms part of the final main structure)
may be the only method enabling geological uncertainties to be signifi-
Geological contexts may involve very different degrees of variability and cantly reduced.
thus complexity. Two extreme examples may be given:
1. Simple contexts, such as certain granite and gneiss formations with geo-
2 - Assessment of the reliability of forecasts using
technical characteristics that are either uniform or only slightly variable
the R-Index method
(except those relating to the degree of alteration); certain sedimentary basins
comprised of horizontal layers with a constant thickness usually fall within A number of methods designed to evaluate the reliability of geological and
this category, except in the event of significant lateral variations in facies; geotechnical forecasts as accurately as possible have been published in
2. Highly complex contexts, such as formations characterised by intense recent years. The method known as the R-Index (for “Reliability Index”) is
tectonics that are both ductile and brittle, including multiple folding and shown below (cf. Bianchi et al., 2009; Perello et al., 2005) [15]. Another
a number of fault systems and/or with significant geotechnical variation method of analysis,which also involves the evaluation of reliability, is repre-
between the different lithological types. sented by the method for cost estimate of geotechnical risks, developed by
CETU (cf. Bieth, Gaillard et al., 2009) [16], [18], described in Appendix 7.
To provide a framework for the degrees of complexity in geological contexts,
the following may be distinguished: The R-Index method was designed to correlate the quality of geological
• the complexity of the lithological and stratigraphic conditions, investigations with the complexity of the project’s geological setting.
• the complexity of the ductile tectonics,
• the complexity of the brittle tectonics, The first stage involves subdividing the tunnel axis into sections of uniform
• the complexity of the hydrogeological context. length, irrespective of the encountered geological conditions. In the following
stages, two types of parameters are analysed for each section: firstly, the inves-
Interaction between the different degrees of complexity of these lithological tigation parameters, and secondly the “system parameters”, more particularly
and tectonic contexts allows all geological situations to be described and those allowing the geological setting and its complexity to be defined.
represented.
The investigation parameters comprise the following elements:
1.2 - Quality of the investigations and data • Surface geological mapping: the size of zone investigated, the scale of
the mapping, the percentage of outcrops, and the type of survey (geo-
Experience shows that data quality may vary widely depending on the type logical, geological/structural, etc.);

336 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page337

AFTES RECOMMENDATION N°GT32.R2A1

• Boreholes: their number, type (cored boreholes or destructive, with or


3 - How to improve the reliability of geological
without diagraphy, etc.), their depth with respect to the depth of the tunnel
forecasts?
and their distance from the alignment;
• Geophysical investigations: the method used, the length of the sections, A list of general recommendations is given below. These are supplied for
the distance from the alignment and the depth of investigations. informational purposes and are designed to improve data quality and relia-
bility in the resulting anticipated geological and geotechnical forecasts.
Analysis of investigation parameters makes it possible to define a quality
index for the investigation works carried out for each section. A. Surface geological measurements
• An investigated area that is sufficiently large (the size will depend on the
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

The system parameters are represented by the following elements: overall geological structure)
• Geological and structural measurements including characterisation of
• The complexity of the lithological context: this relates to the lateral and fault zones
vertical variation of thickness of lithological layers; • Analysis on a scale consistent with the project phase
• The complexity of the ductile structural context: this relates to the number With the development of 3D modelling (see below) the acquisition of new
and type of ductile deformation phases; data will increasingly make it possible to test and update interpretations
• The complexity of the brittle structural context: this relates to the number and models for the section under consideration, virtually in real time.
and type of fault systems occurring in each section.
B. Boreholes
Similarly, analysis of the system parameters makes it possible to define a • A sufficient number of boreholes to characterise the entire length of the
complexity index for the geological setting in each section. project alignment
• Core sampling for the entire length of the boreholes
The following phase involves establishing a correlation between the inves- • Boreholes whose length is appropriate for the depth of the structure
tigation parameters and system parameters for each section being analy- • As close as possible to the project alignment
sed. The aim of this is to check whether the investigations carried out are • Representative sampling of the various geotechnical units identified
capable of providing reliable forecasts in the light of the complexity of the • Conducting in situ testing for detailed characterisation of the formation
system. Correlation between these various parameters is established by
means of interaction matrices, often used for problems of a statistical nature C. Geophysical investigations
in applied geology. The final result is thus a Reliability Index (R-Index) value Geophysical investigations often make it possible to optimise the location
ranging between 0 and 10 assigned to each section of the project layout. of boreholes. Consequently, the former should be carried out first, with their
The various degrees of reliability are supplied in the table below: interpretation updated if necessary once the results of direct investigations
are available.
• A sufficient number of sections to characterise the entire length of the
project alignment
R-Index • An investigation depth that is appropriate to the depth of the structure
Reliability Description
Value • As close as possible to the axis of the project
• In zones that are tectonically complex, structural analysis using a method
Limits and faults reported in this kind of section are to reorient structures in their real position
Good to definitely present and will be encountered within an interval of • High-resolution methods to be preferred
7,5 - 10
very good ± 25-50 m; the margin of error for the thickness of lithological
layers may be between 10 and 20%.
• Using a method that is appropriate to the type of information being sought
and the depth of the project
Limits and faults reported in this kind of section are • Benchmarking using core samples is vital for all indirect investigation
definitely present and will be encountered within an interval
Average to methods
5 - 7,5 of ± 50-100 m; the margin of error for the thickness of
good
lithological levels may be between 30 and 50%. In addition to • Interpretation carried out jointly by the geophysicist and the geologist
those indicated, other minor faults may be present.
Limits and faults reported in this kind of section are D. Establishing a geological model and 3D modelling
definitely present and will be encountered within an interval of
Poor to ± 100-200 m; the margin of error for the thickness of In order to improve interpretation of a zone under investigation, multiple
2,5 - 5
average lithological layers may be between 50-100%. In addition to geological cross-sections (longitudinal, horizontal and transverse) should
those indicated, other principal faults may be present.
be carried out and their consistency checked.
3D modelling will certainly come to be used more widely in this respect,
Limits and faults reported in this kind of section may be absent,
Unreliable particularly for complex zones, to test and improve the consistency of data
and other elements may be present. The thickness of lithological
0 - 2,5 or not at
layers is not defined. Geological elements other than those and interpretation within 3D space. However, care must still be taken to
all reliable
forecast may be present.
ensure reliability of the anticipated geological predictions resulting from

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 337
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page338

AFTES RECOMMENDATION N°GT32.R2A1 M

extrapolation of geological surfaces using 3D digital models: the purpose Some 100 questions have been developed using a checklist type approach,
of these tools is not to provide a single solution, and in isolation they are specifically with regard to surveying underground works. The aim is to provide
not sufficient to ensure the quality of the geological model. assistance in the conduct and assessment of investigations campaigns, from
establishment of the programme and site monitoring through to the proce-
GT32 recommends that the geologist responsible for modelling should be dures used to analyse the results. More pragmatically, this sheet can serve
the project geologist and not a modelling specialist from outside the project. as a reminder, destined mainly to ensure that no major technical elements
Moreover, it should be noted that 3D modelling is only meaningful if the have been forgotten and that procedures for monitoring and analysing inves-
amount and types of factual data are representative of the zone under consi- tigation work are in line with established best professional practice.
deration.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

The “Quality of Investigation” sheet is qualitative in nature, and should be used


E. Investigation planning. very early in a project where investigations are required. It may be completed
Once again, the extremely important nature of investigation works carried several times during the development and progress of a single project. The
out right at the beginning of design work is emphasised, in order to have investigation results may then be the subject of a quantitative estimation of
time to optimise the project, particularly by modifying the alignment or their reliability, for instance using analysis such as the R-Index (cf. Appendix 1).
layout of the project.
On this sheet, each line corresponds to a question; ideally, it should be pos-
sible to answer each question in the affirmative. However, some questions
4 - “Quality of Investigation” assessment sheet
are highly dependent on the survey phase under consideration; as a result,
The “Quality of Investigation” sheet below has been established on the no answer may be possible for some questions, particularly during the pre-
model of the Protocol Sheets developed by the ISRM’s Rock Engineering liminary study phase. Nevertheless, especially during preliminary design
Design Methodology Commission. These sheets deal with such specific and project phases, explanations of points that remain unanswered or with
fields as geological conditions, local stress conditions, fractures and faults, a negative answer should be provided (for instance, deferred to a subse-
rock mass properties and so on. quent phase, deemed non appropriate for the site, etc.)

338 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:29 Page339

AFTES RECOMMENDATION N°GT32.R2A1


All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 339
315a355RECO UK_Mise en page 1 23/08/12 14:29 Page340

AFTES RECOMMENDATION N°GT32.R2A1 M


All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

340 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page341

AFTES RECOMMENDATION N°GT32.R2A1

Appendix 3 - Development of the geological model and graphical


representation of uncertainties

In addition, most importantly, it allows the space taken up by the projected


1 - A relatively unsatisfactory state of the art
structures to be superimposed on the geology in 3D. The advantage of digital
models is clear, particularly since both the geology and the structures in
It must be observed that the representation of uncertain geological objects question are geometrically complex.
such as interfaces, faults, changes of facies and local heterogeneous fea- All the various types of geological cross-sections that may be drawn are
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

tures is sometimes clumsy, incomplete, ambiguous or completely lacking. based on such a model, from which a cross-sectional segment is taken.
This is a source of misunderstandings and may lead to disputes. Given that For this to be properly done, particularly in geologically complex sites, the
the geological cross-section drawn by the geologist will often be used “as following documents should be established in succession:
it is” by design and works engineers, who have little geological knowledge, a) A map of outcrops and an interpreted geological map (see § 4.1 below)
it is vital to bear this state of affairs in mind when representing geological b) An Outline Geological Scheme (or “conceptual geological cross-sec-
information. tion”). This is a clear, simple drawing (although with no precise scale), esta-
blished by the geologist at the preliminary design phase. Its primary purpose
Moreover, experience shows that the comments and reservations expressed is to explain the geological structure of the site with regard to its history
by the geologist are gradually forgotten (or in some cases deleted) from (origins, tectonics, erosion, alterations, etc.).
successive project documents, and the Summary Geotechnical Report is c) A Documentary Geological Profile: this is an intermediate working docu-
not properly read or digested by all stakeholders. Consequently, the provi- ment, which should be drafted as soon as investigation data is available
sional longitudinal geotechnical profile, displayed in every site office, ends and implemented after each phase of surveying. On this, all the available
up acquiring a status far in excess of that intended by the geologist who factual data are displayed using a detailed scale: topography, core logs,
originally drew the geological model that underpins this longitudinal geo- diagraphy, piezometer readings, test results, geophysical horizons, outcrops,
technical profile. exploratory galleries, etc. This cross-section interfaces with the borehole
location plan and, where applicable, with the outcrop map. Its purpose is
to show information from a variety of origins together, on a single document,
2 - Development of geological cross-sections
in order to sketch out the outline of interfaces, correlate data in space in
A provisional geological cross-section is always established right at the the light of the geological model, identify wild values, etc.
outset of a tunnel project. This document is characteristic of any under-
ground project, and will change significantly as studies progress, eventually
becoming a vital tool in the conduct of the worksite. The purpose of this
section is to define a number of specifications for establishing these geo-
logical cross- sections, as appropriate for each stage of progress of the
project.

2.1 - From the geological model to the geological


cross-section

Fundamentally, any geological cross-section is derived from a Geological


Model. This may be defined as the idea established of the configuration of
terrain in space, at a given time and on the basis of available data. This
model is never more than an approximate representation of a little-known
reality, interpreted as well as possible by the geologist on the basis of its
knowledge and observations. Naturally, this interpretation will change and
become more accurate as survey work progresses.
“Optimistic”

In the mind of the geologist, the geological model is necessarily three-


dimensional. In order to represent it, a series of cross-sections have been
“Realistic”
“Pessimistic”
} Limits of the valanginian marls

“Optimistic”

}
Limits tertiary schists / limestones and
often used, or sometimes even models. Today, computer technology makes “Realistic” sandstones of the Axen formation
“Pessimistic”
it possible to create a virtual model and visualise it from any angle. This
also makes it easier to achieve geometrical consistency between investi- Figure 1 - Example of graphic display of several geological hypothesises
gation data, outcrops and interpretative vertical or horizontal cross-sections. (radioactive waste storage project, Wellenberg, Switzerland).

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 341
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page342

AFTES RECOMMENDATION N°GT32.R2A1 M

d) An Interpretative Geological Profile: on this document, often established Geological maps and cross-sections are established by geologists on the
on a less detailed scale than the documentary cross-section, initial data basis of data supplied in varying degrees of reliability and abundance. They
may be partially eliminated in favour of interpreted information, representing reflect the author’s understanding of the geology in question, in line with
the geologist’s best guess: drawing the most probable interfaces (with, available data, the geological environment and regional geographical know-
wherever possible, a graphical representation of the uncertainty), the sup- ledge (cf. Appendix 2). The abundance and relevance of data will of course
posed position of faults, a graphical description of the relations between have a primary influence on the reliability of the document. However, this
units, whether deformation is ductile or brittle, etc. reliability may be enhanced by feedback from neighbouring geological
contexts that are also used to draw up the document.
In order to prevent information loss, documents “c” and “d” above may be brought
With regard to geological cross-sections destined for civil engineering,
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

together into a single document, known as the provisional geological profile.


unlike more conceptual “academic” cross-sections, it is particularly impor-
tant to be meticulous and accurate regarding the geometry of layers (thick-
2.2 - The longitudinal geotechnical profile
ness, incline, folds, etc), the location of contacts and faults, and the
uncertainty of these locations. Indeed, the consequences of these uncer-
Once the preliminary design survey work has been completed, the results
tainties may be highly significant when it comes to design of the structure,
should be shown on a summary sheet known as a “Longitudinal Geotech-
its mode of construction, and so on.
nical Profile” (equivalent to the term “geotechnical model” used in the rail
industry). This document is drawn at a horizontal scale that varies depending GT32 has therefore formulated a number of recommendations on the way
on the complexity of the site and the progress of the project (generally bet- to represent geology and the related uncertainties on documents used for
ween 1/10,000 1/2,000). It comprises two parts: civil engineering. The aim is that ultimately, a graphical representation
⇒ at the top, the interpretative geological profile described above. In gra- should be achieved that makes it possible to see the extent of both know-
phical format, and including notes and boxes, this incorporates all the ledge and lack of knowledge regarding the terrain that may be crossed by
relevant information enabling geological uncertainties and heteroge- an underground structure. In general, GT32 recommends the following:
neous features to be clearly shown; • Drawing a clear distinction between the factual data that enabled the
⇒ at the bottom, horizontal lines, describing, for each encountered geolo- geologist to draw a map or cross-section and the interpretations (and
gical formation, its lithological, hydrological and geotechnical characte- keeping these separate). Indeed, it may be important for other stakehol-
ristics in the form of mean values and comments (for instance, the ders (such as other geologists that may take on the project subsequently)
percentage of occurrence of each class of terrain, mean strength +/- to know what data has been used to draw up the map or cross-section.
standard deviation, probable discharge per lm, etc.). The best way of showing the degree of uncertainty of a map or cross-
section is to feature both the certain factual data that has been used to
The presentation and content that is desirable in this longitudinal geotechnical draw it and the extrapolations made by the geologist;
profile has been detailed in AFTES’ 2003 GT1 Recommendation (p.168), but may • Ensuring that maps and cross-sections feature only unambiguous figures
vary considerably depending on the site. In practice, this longitudinal profile is and symbols. It should not be possible for these to be considered as pro-
still the major undertaking by the project’s geotechnician: this means that it must perly located and geometrically constrained elements of the geological
be immediately understandable and usable by civil engineers responsible for the structure of the formation. In particular, this applies to symbols relating
design and construction of the underground structure. Experience shows that it to karst cavities, folds, seams and other non-uniform features that cannot
will become their principal worktool: consequently, particular care must be taken be represented with accurate geometry and location;
with the drawing, the related comments and the terms used in the legend. • Representing the uncertainty with regard to the existence and/or geome-
try of the geological object shown as well as possible on cross-sections,
Furthermore, it is recommended that the following text should feature in a particularly adjacent to the projected structure.
box: “this Longitudinal Profile should not be taken in isolation from the Sum-
mary Geotechnical Report of which it is an illustration”; similar notes
4 - Graphical representation of geological data
should be included in the latter.
4.1 - Data to be shown on the geological map
3 - General recommendations
The geological map constitutes the foundation document for any geological
Maps and geological cross-sections are designed to provide a continuous study. It is vital in order to establish geological profiles and 3D models.
representation of the geological nature of underground space on the basis
of discontinuous observation and data available in varying degrees of abun- For underground works, the geological map is an intermediate document
dance and density. They are therefore interpreted documents or “models” that will be little used by the civil engineer. However, it is worth observing
providing a two-dimensional representation of the most likely geology. 3D a number of “rules” when drawing up these maps, particularly in order to
models are constructed on the same basis; they will be dealt with subse- avoid any information loss in the event of a change in the geologist res-
quently, due to the fact that they are more complex. ponsible for the project.

342 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page343

AFTES RECOMMENDATION N°GT32.R2A1

Ideally, any geological map should be accompanied by an outcrop map, • At depth, direct observations may be made using boreholes (particularly
either in the form of a separate document (a “documentary map”), or cored boreholes), and in some cases existing underground works (quarry
on the geological map itself, with outcrop zones distinguished by darker workings, mineshafts, hydraulic shafts, etc.) or exploratory adits . These
or closer shading, for instance, or with a specific outline, as shown can be very reliable with respect to lithological information (except for
figure 2. positioning errors), but are less accurate with regard to structural data
(measuring these in the “actual position” in a borehole or core sample
The outcrop map should also show superficial loose soil that may have an is always a cumbersome and delicate task).
impact on the project (alluvial deposits, landslips, active soil movements,
alteration facies, etc.); many urban tunnels are excavated entirely in so- Moreover, observations made in boreholes or exploratory adits are not
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

called superficial formations (loose or cohesive) that should be dealt with always exactly located on the cross-section. The further away the borehole
like any other geological formation. For deep structures, representing is, the greater the degree of uncertainty of the projection on the cross-sec-
outcrops for superficial formations is important when these are thick enough tional plane. Furthermore, the best projection direction must be chosen in
to completely conceal the bedrock (in this case, representing them indicates line with the direction of the layers; this requires these must be known.
that no direct observation of the bedrock has been possible from the Potential projection errors therefore introduce an additional degree of uncer-
surface). tainty in how the layers are represented. Consequently, it is recommended
that boreholes should be indicated on cross-sections (along with their pro-
jected trajectory) by distinguishing (using an unbroken line) those that are
“close” to the profile plane (with a distance to be determined on the basis
of context) from those (using a dotted line) that are farther away (either in
front or behind) with respect to the profile plane.

Where possible, it is worth adding an excerpt from the outcrop map along
the tunnel alignment above the geological cross-section, in such a way as
to present the location of the factual data used (the position of outcrops,
boreholes, etc) on a single document.

Geophysics (seismic elements, magnetism, gravimetry, etc.) may supply


indirect information about the nature and structure of the soil and the loca-
tion of interfaces, if there are significant litho-structural contrasts. However,
the results of geophysics may only be used if they can be pegged to core
samples and if the geological structure is not too complex: if both these
conditions are fulfilled, they may supply highly valuable information as to
the continuity of layers between boreholes (or lack thereof).
Figure 2 - Part of an interpreted geological map with indication of outcrops.

4.3 - Representing interpreted geology


In addition to outcrop zones, all the numbered geo-referenced observation
points (GPS) should be indicated on the final geological map (or at least on 4.3.1 - Representation
the documentary map). Particular information relating to these observation Care must be taken when choosing representations on a map or geological
points can be indicated directly on the map (for instance, structural mea- cross-section:
surements). The presence of these observation points on the outcrop map • anisotropic representation may be used to represent the anisotropy of
indicates that they have been directly observed. These points and their geo- rocks (alternating sedimentary beds, the principal schistosity, etc.), but this
location should also be recorded in a database or Excel spreadsheet and is only worthwhile if there is a clear idea of the actual orientation of this
supplied with the cartographic documents. anisotropy. Indicating a potentially erroneous orientation on a cross-section
may lead the engineers that will be using the cross-section into error;
4.2 - Data to be shown on geological profiles • representing multiple folds of the terrain by a representation of folds pro-
bably has fewer implications, but clarification is required as to whether
Geological profiles are established using both surface and below-ground this is a “symbolic representation” showing the repeated existence of
data: folding, or if it concerns actual folds that have been observed on site;
• On the surface, the geological map makes it possible to locate contact • in the event of a non-uniform formation, heterogeneous aspects such
points, faults and other specific data (faults, families of discontinuities, as enclaves of varying sizes, major beds, lateral variations in facies, karst
sinkholes, etc.) with the related degree of uncertainty (see below); cavities and so on should only be shown if their presence is proven or

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 343
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page344

AFTES RECOMMENDATION N°GT32.R2A1 M

highly likely at the location at which they are indicated. If this is not the contours and faults. We recommend three levels of representation for each
case, the presence of these heterogeneous aspects should be indicated of these linear elements (although it should be noted that these levels have
in the legend, and perhaps by an unambiguous, symbolic representation slightly different meanings depending on whether they refer to contours or
(and, locally, by a warning signal, see below). faults):
a) For geological contours, the uncertainty represented relates mainly to
More generally, rather than using potentially ambiguous representations, the cartographic line of the contour (and not, generally speaking, to its exis-
geological formations should be differentiated by plain colours (or shades tence):
of grey), with representations being reserved for highly specific cases. An ⇒ Unbroken line: reserved for contact points that can be directly obser-
alternative solution involves representing the detailed tectonic style in ved on site (shown by the outcrops indicated or by an observation
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

“close-ups”, surrounded by circles, as if a magnifying glass was being pla- point): there is little or no uncertainty as to their location at the scale
ced over a particular area. of the representation in question;
⇒ Broken line: the contour has been drawn with average accuracy (with
4.3.2 - Legends a numerical degree of uncertainty that depends on the scale of the
Legends are extremely important on maps and geological cross-sections. representation, to be specified in each case);
They must be complete, sufficiently detailed, meticulous, and above all ⇒ A dotted line with, if appropriate, interspersed question marks: the
consistent with the text of the report. Explanatory notes and comments may contour has been drawn very approximately, and its existence in the
also be of use. zone under consideration is in doubt.

4.3.3 - Additional graphical elements In some cases, the geologist may draw a number of different scenarios in bro-
On geological cross-sections (and in some cases on maps), it may be worth ken dotted lines, on a number of different sheets or in separate boxes (fig. 1).
drawing attention to the rock characteristics using a warning sign similar If there is doubt as to the presence of a formation, a question mark at the
to that shown below (in this case, highly folded rock with poorly determined location of the represented formation (and not simply at the contact point)
geometry). is desirable. In the event of major doubt as to the geological nature of the
soil, it is preferable not to draw anything at all (a white area with question
marks) rather than suggesting geology which is in all likelihood erroneous.
However, the option of leaving empty areas on cross-sections should be
reserved for cross-sections drawn in the preliminary stages or, in extreme
cases, when there is an outstanding, major unknown. “Minor” gaps in know-
Figure 3 - Example of a warning sign ledge may be brought together within a heterogeneous formation and detai-
led in the description of the latter. Another alternative is to suggest a number
On geological cross-sections (and in some cases on maps), it may be worth dra- of different possible lithologies, marking various rock grades on a white
wing attention to the rock characteristics using a warning sign similar to that background (on the map) or by drawing a number of different cross-sections
shown above (in this case, highly folded rock with poorly determined geometry). (on the geological profile).
This type of warning sign may be used to indicate the local presence of a
highly fractured or extremely karstic zone (in addition to the information For a gradual shift from one formation to another, a dotted representation
supplied in the legend). This data must also feature on the horizontal lines may be used: this does not supply information as to the accuracy of the
located beneath the longitudinal geotechnical profile, with large dots or red location (which is less important in this case) but only on the gradual nature
stars to alert readers. of the contact.

It may also be worth introducing additional graphical representations on b) Concerning faults, uncertainty relates both to their existence and to
the geological cross-sections (or on a separate document), for instance in their cartographic route:
the form of miniatures (“close-up” windows centred on key sectors) or per- ⇒ Unbroken line: the fault has been seen (on-site or using aerial/satel-
pendicular cross-sections. References to other written or graphical docu- lite imagery) or clearly deduced (from observed displacement of )
ments are also encouraged. at least locally, and has been drawn quite accurately;
⇒ Broken line: the fault probably exists, and its path is relatively accurate;
⇒ Dotted line with interspersed question marks: the existence and path
5 - Representing uncertainty relating to geological
of the fault is hypothetical.
interfaces
5.1 - Line thicknesses At present, for both contours and faults, representation using these different
types of line is very often practised only partially, using only two types of
For both maps and geological cross-sections, representing uncertainty is line. Furthermore, it is generally over-optimistic, making too much use of
usually achieved by differentiating the type of line used to mark geological unbroken lines.

344 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page345

AFTES RECOMMENDATION N°GT32.R2A1

5.2 - Representing fault thicknesses These various interpretations may be presented as “extreme” hypotheses,
within the bounds of realism, or as “optimistic” and “pessimistic” scenarios
The thickness of the damage zones associated with faults crossed by a tun- that can be defined as being “unlikely” to be exceeded at either end (in other
nel project is a variable which is of considerable interest to engineers. Hat- words, reality is “highly likely” to lie somewhere between the optimistic and
ching is commonly used and indeed appropriate to represent these damage pessimistic scenarios). It should be noted that this concept of “optimistic”
zones, if they have actually been observed (and if the hatching is appropriate and “pessimistic” geological configurations already assumes some idea of
to the scale of the document). However, in most cases these fractured zones the consequences in terms of civil engineering.
are not observable from the surface, since they are covered by shallow depo-
sits. In this case, they are best characterised by means of cored boreholes. It is true that representing extreme scenarios does not allow the varying
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

degrees of uncertainty along the profile to be catered for, and means that the
Representing fault thicknesses by a line whose thickness is proportional to geologist has made a restricted choice. However, making such a choice has
the actual thickness is only an option on extremely detailed cross-sections. the major advantage of being simple, very easy to understand, and immedia-
Showing a 5 m fault (by using a line with a minimum visible thickness of 2 tely attracting attention. In most cases, it is virtually impossible to represent
mm) requires a scale of at least 1/2500. Otherwise, the type of represen- the plethora of potential scenarios on a single geological cross-section.
tation used may make it possible to distinguish “major” and “minor” faults
and even give numerical values (on the cross-section) for the full thickness. It is highly difficult, and probably illusory, to imagine that probability can be
quantified any better than as falling between two extremes, except if a sim-
However, care should be taken when it comes to the distinctions made bet- ple geological context and an abundance of data make it possible to carry
ween major and minor faults on some maps and cross-sections. From an out a geo-statistical estimation based on meticulous calculations. In this
engineering perspective, the distinction should be based principally on case, the extreme scenarios are equivalent to the bounds of the confidence
faults’ geotechnical characteristics, whereas cartographic geologists tend interval comprised between (m + σ) and (m - σ), where m is the estimated
to look more at their geodynamic role. For tunnel projects, it is therefore mean and σ the standard error. The probability that reality will lie in this
important to be clear as to the nature and significance of the faults indicated interval is equal to 68% for a standard deviation distribution; if the bounds
on geological cross-sections. are (m ± 2σ), this probability rises to 96%. This approach was used to auto-
matically calculate and design the most probable longitudinal geological
5.3 - Representation using extreme contact point positions profile along the axis of the Channel Tunnel (cf. figure 4).

To show the degree of uncertainty concerning


contours and faults clearly, another solution involves
showing the possible extreme positions (in other
words, what is commonly referred to as the “uncer-
tainty range”). In most cases, it will be the geologists
who estimate this range on the basis of locally avai-
lable data, their regional knowledge and their expe-
rience. Any such estimate is therefore interpretative,
but the geologist’s doubts should be clearly expressed
in the form of representation adopted. Geologists are
required to “show the remaining level of doubt or
ignorance with regard to their comprehension of
underground geology” in the properly understood
interest of the project owner.

5.3.1 - Representing extreme scenarios


Uncertainties and questions may be shown by presen-
ting multiple (generally two), relatively contrasting
interpretations, as is the practice in Switzerland (fig. 1).

Figure 4 - Geological longitudinal profile of the Channel


Tunnel calculated between kilometre points PK 7 and
10.5; the median line in the middle of the red area
represents the most probable elevation of the top of the
Gault Clay; the half-width of the red uncertainty area is
equal to the standard error.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 345
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page346

AFTES RECOMMENDATION N°GT32.R2A1 M

5.1.2 - Other types of uncertainty representation Representation 3: Here, the extreme locations of the contact points are not
The degree of uncertainty relating to the location of each geological object shown by their actual geometry on the vertical longitudinal profile, but by stan-
(contact between two layers, fault, etc.) should be represented in detail along dard symbols indicated on a strip located beneath the principal cross-section.
the entire length of a cross-section. To achieve this, the extreme positions of Two types of symbol may be used (fig. 7):
the contact point should be imagined, as defined above. It should be noted
that a gradual transition between two formations may be represented in the Type 3a: the uncertainty bar. The strip features a bar centred on the most
same way. Four possible ways of representing these extreme positions are probable location of the contact point. This method allows uncertainty to be
described below. shown even in the event of close contact points, by slightly offsetting the
various bars so that they do not overlap (enlarging the strip if necessary).
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

Representation 1: The uncertainty range is shown on the whole of the longi-


tudinal profile for each contact or fault (fig. 5). The resulting uncertainty range This form of representation may be simplified if the thickness of successive
may be shown as a line, both on the surface (outcrops) and at depth (for ins- layers is well known and the uncertainty relates only to their location. In this
tance, at a borehole which has passed through a clear contact point between case, only one uncertainty bar is shown for the entire stratigraphic series.
formations A and B).

This type of representation is appropriate if it only concerns a few contact


points, but can quickly become illegible in the event of multiple contact points,
with overlapping uncertainty ranges.

Tunnel axis

Uncertainty bars on the contacts

Tunnel axis

Contact A/B : most probable estimated position and range


of possible positions (uncertainty bar). Uncertainty range represented with a line +/- inclined
joinings the possible extreme positions of the contact.
Figure 5 - Representation 1: geological longitudinal profile with
uncertainty range for a contact location. Figure 7 - Representations 3a and 3b: geological longitudinal profile and
strips showing the location of contact points for the elevation of the project,
Representation 2: Representing the uncertain position of contact points or faults with an uncertainty bar (3a) or oblique line (3b).
should be done only at the tunnel depth, on a “mini profile” located beneath
the principal cross-section and confined to a narrow vertical area along the tun- Type 3b: oblique line. At the top and bottom of the strip, the extreme positions
nel axis (fig. 6). The uncertainty is expressed by a strip of variable width, cor- of the contact point are shown for the project, connected by an oblique line:
responding to the zone where formations in contact may be encountered. the steeper its gradient, the lower the degree of uncertainty. The advantage of
this method is that it clearly visualises the contrasting uncertainty along the
The advantage of this type of representation is that it only shows uncertainties cross-section, and it can be applied to successive geological contact points
at the project depth, which is precisely where they need to be ascertained. even when these are very close together (cf. fig. 8).
However, it also has the drawback mentioned above in the event of close and/or 3b type representations must however be clearly explained in the legend,
multiple contact points, with overlapping uncertainty ranges. because they are less intuitive than 3a. Experience has shown that the unini-
tiated often confuse the uncertainty range with a horizontal geological cross-
section at the tunnel depth, which is not the case. For instance, the following
diagram (fig. 8) shows part of a provisional geological cross-section that indi-
cates uncertainties using oblique lines.

Tunnel axis

Contact A/B : most probable estimated position and uncertainty bar.

Figure 6 - Representation 2: vertical geological cross-section and


“mini-profile” at the elevation of the project with an uncertainty range.

346 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page347

AFTES RECOMMENDATION N°GT32.R2A1

the project area to be clearly displayed, and the geometric consis-


tency of the setting to be ensured. Ideally, each project should be
illustrated by the longitudinal geological profile, one or more trans-
verse cross-sections and a horizontal cross-section at the elevation
of the project.

Together, compared to a single longitudinal profile, these cross-


sections constitute a more complete representation of the project’s
geological model. However, these cross-sections cannot be any-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

thing more than a discontinuous representation of 3D geology. In


such a model, uncertainties relating to contacts may be represen-
ted on each of the geological cross-sections, following the proce-
dures set out above.

There have always been attempts to represent 3D geology in an


approximately continuous way, with the manual completion of
block diagrams. However, the arrival of digital technology has
Figure 8 - Example of provisional geological longitudinal profile really made it possible to tend towards continuous 3D geological modelling
showing uncertainty using oblique lines.
and representation. Since the end of the 20th century, 3D modelling software
has appeared and is frequently being developed further. Use of such software
5.1.3 - Contacts which are tangent to the alignment will certainly increase as its potential and ease of use progresses.
of a linear project
The preceding representations are appropriate for contact points that are at However, 3D modelling will always be a complex operation. For linear struc-
a considerable angle to the vertical plane of the alignment; these will cross- tures, it is probable that 3D modelling will remain confined to specific sectors,
cut by the tunnel axis. For contacts which are tangent to the alignment, uncer- due to either of complex geology or the variable complexity of civil engineering
tainty about a contact may relate to whether it will be cross cut by the tunnel structures. 3D digital modelling is first and foremost a tool that enables the
axis. This uncertainty may be shown in one of two ways: coherence of data and interpretations to be checked and new interpretations
• by attaching a horizontal section (which may take the form of a narrow strip) to be suggested. For projects that relate to underground volumes rather than
to the vertical profile, on which the tangent nature of the contact (with an linear structures (underground storage sites, hydroelectric caverns, under-
uncertainty range as appropriate) is clearly shown; ground stations, etc), 3D modelling and representation of the zone in question
• and/or by showing other formations that may be encountered if the contact will be increasingly called for.
is not cross-cut by the project. Figure 8 bis shows this possibility, combined
with an “oblique line” type representation. Graphical representation of uncertainties relating to contacts within a zone
modelled in 3D cannot take the form of uncertainty ranges, which by nature
are two-dimensional. This means that a representation in the form of a 3D
Uncertainty about the position of contact
uncertainty area around contacts, bounded by the estimated extreme positions
PK 9 of these contact points, must be devised. To make the model clearer, this repre-
maximum Pk sentation must be confined to contacts that are considered to be major in
jmCM terms of geotechnical incidence. Here again, the plausible extreme positions
minimum Pk of the major contacts may be represented on separate models.
Other possible formations jmC, I, tsD, tGsb
Degree of reliability about Other forms of representing uncertainty in three dimensions are also possible
occurrence of formations:
1-high, 2-medium, 3-low if “stochastic” modelling methods are used. In this case, the modelling software
will automatically construct n geological models, all compatible with the data,
Figure 8 bis - Diagram showing a formation that may or may not be crossed
(“oblique line” style). and constituting n possible variations on reality. If these models are expressed
in terms of voxels, the probability of each 3D cell lying within a given formation
may be calculated. This opens the way for a 3D representation of uncertainty.
5.4 - Representing uncertainties in 3D space For instance, all 3D cells with a probability of lying within a formation F in
excess of 80% may be shown: they will form the boundary of a 3D object which
For projects involving linear structures, representing 3D geology is often based has a highly complex shape.
on a number of intersecting 2D cross-sections. This enables the geology in

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 347
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page348

AFTES RECOMMENDATION N°GT32.R2A1 M

Appendix 4 - Hydrogeological risks and uncertainties

Fundamentally speaking, hydrogeology (the study of underground water) forms the various permeability values of hydrogeological units is shown in figure 9.
an integral part of engineering geology in its broadest sense, and is even one For appropriate risk analysis, effects relating to poor evaluation of permeability
of its most important aspects. must be assessed, and measures defined to reduce these effects (additional
permeability investigations and tests, specific tunnel installations, prior treat-
In terms of underground works, the principal hydrogeological aspects to be ment of soil, etc.).
taken into account as potential sources of uncertainty or risk concern the fol-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

lowing:
2 - Chemical and physical characteristics of
• The hydrogeological characteristics of the rock formations, particularly
underground water
their permeability;
• The characteristics of underground water (chemical composition, tempe- The main chemical and physical characteristics of underground water include
rature, etc); the following:
• The hydraulic load at the depth of the structure; • The chemical composition of water, which dictates its behaviour with regard
• The foreseen inflow rate, with the impact of water ingress on excavation to materials;
works and dealing with discharge water; • Temperature values, particularly in the case of hydrothermal water or high
• The environmental aspects (the impact of structures on springs and super- thermal gradients, for instance in deep tunnels.
ficial hydrographic networks, the drown-dawn risk of the latter, the risks of
downstream pollution, etc.). The related uncertainties and risks relate mostly to determining the values of
these characteristics, since in general, few tests are carried out to ascertain
these parameters for logistic reasons (the need for deep boreholes, sampling
1 - Hydrogeological characteristics of formations
difficulties, etc.).
The overall permeability of a formation and more particularly, the permeability The main risks are as follows:
of the various lithological types interested by the underground structure, may • With regard to the chemical composition of water:
be a major source of risk and uncertainty, since it has a direct influence on the - Aggressivity with regard to concrete, with for instance, the presence
foreseen water inflow rate during excavation. of sulphates, magnesium, ammonia ions, free CO2 and hardness;
Consequently, it is important to distinguish and characterise the various hydro- - Aggressivity with regard to steel (O2 saturation, HCO3/Ca ratio, pH value,
geological units in terms of permeability. The methods used to measure this Larson index value);
permeability have been described in the recommendation by GT1 “Caractéri- - The scaling tendency (the CaCO3 saturation index value), particularly
sation des massifs rocheux utile à l’étude et à la réalisation des ouvrages sou- important when designing the tunnel drainage system.
terrains” (“Characterising rock formations for designing and building • With regard to temperature values, particularly high-temperature water:
underground works”) [1]. - The impact of discharge water on the environment;
The most significant sources of uncertainty and risk relate to insufficient know- - Difficulties relating to the need to drain the hot water separately.
ledge of permeability values and/or variations in these values within the rock
mass. Uncertainty regarding permeability and its variations within a single To become more aware of these risks, a detailed study of the water resource
lithological type must be properly indicated and represented in geotechnical should be planned from the design stage (including a water sampling campaign
profiles and in the Summary Geotechnical Report. One way of representing for chemical analysis, monthly monitoring of physical characteristics such as
flow rate, temperature and conductivity at water
Permeability (AFTS classes) Occurrence of dissolution phenomena and karst
Hydrogeological Unit points) as well as systematic control of water cha-
Low - Very low Low - Medium Medium - High High - Very high Low Medium High Low Medium High racteristics during the construction phase. It should
be possible to adjust construction methods in due
Unit 1
time and plan preventive measures to be implemen-
Unit 2 ted to minimise impacts; in some cases, compen-
satory measures need to have been studied
Unit 3 beforehand so that they can be implemented as
quickly as possible in the event of proven disruption
Unit 4
of the water resource.

Unit 5

Variation of permeability
Lateral variations of permeability due to variation of fracture degree (rock mass) or of granulometry (deposits). Figure 9 - One way of representing permeability
values within hydrogeological units.

348 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page349

AFTES RECOMMENDATION N°GT32.R2A1

Various methods are available to estimate values of flow rate. These depend
mostly on the permeability of the formation, the hydraulic head and to a lesser
degree the cross-section of the excavation.
This information must be clearly indicated on the horizontal lines of the
longitudinal geotechnical profile (§ Appendix 3). The following information is
also worth supplying:
• estimated momentary inflow rates at the cutting face;
• estimated specific, stabilised flow rates to the rear of the cutting face (expres-
sed, for instance, in l/s/100 m of tunnel or l/min/10 m of tunnel);
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

• clearly indicating critical points (zones with very high flow rates and high
gradient or hydraulic charge);
• estimating aquifer recharging conditions (perennial water ingress or pro-
gressively draining the rock mass).

In terms of risk analysis, water is rarely a crucial problem in and of itself. Its
Fig 9 bis - Statistical distribution of permeability values measured in boreholes impacts are confined to disruption to works, payment of compensation if water
in the Cenomanian blue chalk (Channel tunnel).
sources dry up, the installation of additional conduits, pumping, dealing with
discharge water, and so on. These impacts are more significant if a major karst
conduit is intercepted and/or in the event of downward excavation.
Lastly, the adverse effects of water may be considerably magnified in the event
3 - Hydraulic head
of unfavourable geotechnical conditions, such as loose soil that may be
Hydraulic head values at the elevation of the structure may be one of the most washed away, highly permeable formation beneath a thin overburden, etc...
important data with regard to the design of the structure itself.
In the event of shallow tunnels (defined as tunnels with an overburden, and
5 - Environmental aspects
thus a hydraulic head, of less than 20 m), the impact of uncertainty relating to
the water head may be considered as minor. However, for deep tunnels, this There are many risks to the environment relating to the management of dis-
aspect is of major importance. Determining the hydraulic head may be one of charge water during the excavation of tunnels. However, the purpose of this
the main scopes of survey work. Recommendation is not to describe or analyse these in detail. Nonetheless, it
Uncertainties with regard to the hydraulic head are mainly linked to the follo- should be emphasised that these risks must be clearly analysed and taken
wing factors: into account during the various stages of the project, specifically as regards
• Uncertainty relating to defining structural characteristics of the rock mass, the following:
particularly the hydraulic characteristics of discontinuities and the degree ⇒ the impact of works and final structures on springs and other water
to which these are interconnected; points used to supply the area with water (the risk draw-down of
• Variations in permeability within the rock mass, particularly due to occurrence sources) ;
of fault and/or fracture zones. ⇒ the impact of structures on superficial watercourses (risk of pollution).
To reduce the degree of uncertainty, a specific survey campaign must be plan-
ned in order to determine the hydrogeological characteristics of the rock mass
and terrains, particularly as regards the following:
- Setting up a network to monitor the surface water resource, including
tracing tests to model the underground water flows;
- Quantifying permeability and hydraulic head values for the rock formation
using Lugeon tests or slug testing between packers;
- Installing piezometric cells at various depths to measure the water head
in the formation at different levels and establish whether there are
different aquifers.

4 - Flow rates
Given the impact of water ingress at a high rate and/or pressure on excavation
works, as well as on the management of discharge water (momentary, tem-
porary and permanent rates) uncertainties relating to this factor may be at the
origin of significant risks.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 349
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page350

AFTES RECOMMENDATION N°GT32.R2A1 M

Appendix 5 - Uncertainties and risks relating to geotechnical parameters

Geotechnical uncertainties in underground works projects may be classified One way of remedying this omission is to include a transitional zone that is
into two broad categories: equivalent to the zone of uncertainty as to the position of the geological contact
• Geotechnical uncertainties arising from uncertainties in the geological model; as part of the “horizontal lines” (representation 2 in figure 10). The geotech-
• Uncertainties relating to the indeterminate nature or variability of the geo- nical characteristics QAB (“Q” for “quality”) of this transitional zone will be
technical parameters of identified geotechnical units. equivalent to either one (QA) or the other (QB) of the formations in contact (both
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

scenarios must be taken into account). This type of representation will be valid
for all types of soil “properties” (such as hydrogeology and geo-mechanics)
1 - How to express geological uncertainty on
and may also be applied to faults whose position is uncertain (in this case the
geotechnical profiles
transitional zone would show the possible area within which the fault may be
Since the longitudinal geotechnical profile is itself based on the interpretative located). An alternative solution involves including the uncertainty bar for the
longitudinal geological profile and geological cross-sections (cf. Appendix 3), contact point between the different geotechnical units in the lines of geotech-
it should feature a number of geological uncertainties: nical characteristics.
• the location of contacts between the different lithological types and thus bet-
ween different geotechnical units; As for geological cross-sections, geological uncertainties may also be trans-
• the presence or absence of fault zones and other critical points; posed onto the longitudinal geotechnical profile by showing a number of alter-
• the presence of any lithological types (or geotechnical units) that differ from native profiles incorporating different scenarios that are favourable or
those expected. unfavourable in geotechnical terms. This type of approach is of interest because
it makes it possible to develop the subsequent analysis stages (risk analysis,
Uncertainty as to the presence of a fault may be shown on the longitudinal analysis of the costs of the project using probabilistic analysis such as the DAT
geotechnical profile in the same way as on the longitudinal geological profile, system, etc.) for each of the identified scenarios. This means the technical and
by using various specific types of broken line. economic impacts of the various hypotheses can be compared. However, as
has already been seen, the drawback of this type of representation is that it
The possible existence of lithological types that differ from those expected cannot take into account the multiple combinations of interpretative scenarios
may be represented on horizontal lines beneath the geotechnical profile by concerning the geology.
expanding the geotechnical characteristics to include alternative lithologies
that may be encountered in the zone in question.
2 - Representing uncertainties relating
to variable geotechnical parameters
As to the position of geological contacts, the boundary between two sections
with highly different geotechnical qualities is generally located with precision, This type of uncertainty is directly related to the definition of the fundamental
but does not take into account the uncertainty of the contacts denoting the geotechnical parameters used to characterise the formation and homogeneous
geotechnical contrasts, which may feature on the longitudinal geological profile sub-sections in geotechnical terms (“geotechnical units”) and parameters that
(representation 1 in figure 10). may influence the behaviour of the formation.

2.1 - Consequences of uncertainty on parameters

The parameters in question have been described in detail in Recommendations


Tunnel axis by GT1 “Caractérisation des massifs rocheux utile à l’étude et à la réalisation
des ouvrages souterrains” (“Characterising rock formations for the purposes
Uncertainty bar about the of designing and building underground works”) [1] and GT7 “Le choix des
position of A/B contact paramètres et essais géotechniques utiles à la conception, au dimensionne-
ment et à l’exécution des ouvrages creusés en souterrain” (“Choosing geo-
technical parameters and tests to design, dimension and construct structures
Geotechnical
characteristics : excavated underground”). For each category of parameter, uncertainties may
Representation 1 have the following consequences:
⇒ identification parameters (unit weight, water content, porosity, Atter-
Representation 2 berg limits, granulometry, state of alteration, etc.): sources of risk rela-
Figure 10 - Representing uncertainty relating to the contact between ting to the indeterminacy/variability of these parameters include
two geotechnical units with differing characteristics. behaviour of the formation during excavation, the choice of TBM type

350 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page351

AFTES RECOMMENDATION N°GT32.R2A1

(EPB, slurry shield, hydroshield), the strategy for confining the face, 2.2 - Representing uncertainties on longitudinal
mucking process, soil, treatment type, and so on; geotechnical profiles

⇒ mechanical parameters: strength parameters (uniaxial compressive Firstly, it should be noted that geotechnical parameters (or at least the principal
strength, tensile strength, cohesion, friction angle), deformation para- ones) should be represented by mean values and values that are representative
meters (modulus of elasticity, Poisson’s ratio). Risks may relate to fore- of their dispersion, and also by a characteristic value that must be determined
casting the behaviour of the formation during excavation, the choice for each geotechnical unit (cf. GT1, GT7 and GT32.1). Consequently, there is
and distribution of support sections and so on; a variety of ways in which uncertainty relating to geotechnical parameter values
may be illustrated on longitudinal profile horizontal lines:
⇒ discontinuity parameters (orientation, spacing, extension, ⇒ Indication of the characteristic value
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

roughness/ripple, alteration of wall rock, openings, type of filling, pre- ⇒ Possible upward or downward variations compared to the characte-
sence of water). These parameters play a key role in assessments of ristic value: such variations may be expressed in absolute terms (for
the overall strength of the formation on the basis of values for intact instance, 25 ± 5 MPa) or as a percentage (25 MPa ± 20%);
rock. Consequently, indeterminacy with regard to discontinuity para- ⇒ By a range of values, if it is not possible to estimate the characteristic
meters entails a high degree of uncertainty when defining the strength value or if this is not considered as being sufficiently reliable;
of the rock mass and its behaviour during excavation; ⇒ By supplementary indications in the summary report, particularly
concerning the number and statistical distribution of the values mea-
⇒ excavation parameters (hardness, drillability, abrasiveness, fragmen- sured, the dispersion from the mean value, and so on.
tability, degradability, and so on): these parameters have a direct
influence on the conditions for excavating and crushing techniques to
break the rock. Risks relating to these parameters include equipping
a cutterhead with inadequate tools, the need to change tools more fre-
quently than planned, insufficient power for the machine, different use
of excavated materials compared to forecasts, and so on.

Appendix 6 - Summary of risk sources

After due consideration, AFTES has decided that it would be illusory and GT1. In the “examples” column, it supplies a non-comprehensive list of
even dangerous to seek to establish a virtually exhaustive list of all possible geological configurations that often lead to the appearance of risks due to
risks relating to underground space and liable to affect projects of under- the fact that the geotechnical parameters in question are variable, many
ground structures. Indeed, the danger is that any such list might be used and/or difficult to determine with any degree of accuracy.
“mechanically” as a checklist, thereby dispensing project designers from
fully considering the geotechnical conditions of the project and obscuring Attention is particularly drawn to the sources of risk of anthropic origin.
the fact that each underground structure is in some sense a prototype. These are frequent sources of risk that are often poorly known because the
elements required for proper forecasting are not easily accessible, docu-
However, in the following table, which is of course not comprehensive, we mentary records are more often than not non-existent or inaccessible, and
have listed the most frequent sources of geotechnical risk for tunnels. This their distribution is sometimes more random than that of natural geological
table is based on the description of rock formations recommended by AFTES phenomena.

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 351
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page352

AFTES RECOMMENDATION N°GT32.R2A1 M

Table of risk sources


(classified according to the AFTES GT1 Recommendation)

Field of
Risk sources Parameters Examples of events
investigation

Alternating marls/limestone, volcanic or volcanic/sedimentary soil, unexpected alteration


Strength
(meteoric or hydrothermal), etc.

Cohesionless facies in a coherent formation (sandy lens in sandstone), karst void filled with clay,
Cohesion
ash/tuff within indurate volcanic soil, etc.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

Contrast
Hardness Chert nodules in chalk, seams of quartz in metamorphic shale, etc.
Matrix

Abrasiveness Extreme rock abrasiveness: Quartzite, very hard sandstone, quartz-rich granitoid, isolated seams, etc.

Changes Changeable material Swelling or spalling of materials after excavation (swelling clay), minerals of hydrothermal origin, etc.

Miscellaneous ... ...

Change in geometry of discontinuities, of tectonic or sedimentary origin (tilted block, slip, folds, etc)
Orientation class (OR)
(changes in stratification, etc.)
Changes across the whole
of the face
Discontinuities Density of
Fractured zone, shear strip or zone, etc.
discontinuities (ID)

Miscellaneous ... ...

Permeability Major water ingress up to and including flooding, hydraulic clearing, springs drying up

Contrast Hydraulic head Higher hydraulic head than forecast

Grading Block of rock within a loose formation, erratic block in fluvioglacial landforms, etc.

Formation
(Soil or Rock) Stress Variation classes CN1 - CN3, stress anisotropy in the rock formation, decompression, convergence, etc.

Variation in layer thickness, fossil valley, empty or filled karst cavity, deeper level of meteoric alteration,
Contact point geometry
Variation up-swelling of bedrock beneath loose surface formations, etc.

Physical and chemical Aggressivity of groundwater, chemical clogging phenomena, bacterial development,
characteristics of water surface water pollution, etc.

Miscellaneous ... ...

Emission of harmful gases (H2S, CO2) and/or consumption of oxygen (pyrites) liable to cause asphyxia,
Gas
presence of explosive gases (CH4), etc.
Contrast
Safety Cohesion/
Surface settlement, damage to built structures on the surface
permeability/granularity
and environmental
considerations
Specific materials
Asbestos, radioactivity (presence of radon), presence of chert particles, production of sulphuric
Changes subject to change
acid due to alteration of pyrite, etc.
(dealing with muck)

Archaeological remains, ancient foundations, sheet piling, anchors, abandoned underground


Miscellaneous Anthropic origin
quarry-workings, filled-in pits and moats, bombs, polluted soil, fragile surface structures, etc.

Miscellaneous ... ... ...

352 M TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012


315a355RECO UK_Mise en page 1 23/08/12 14:30 Page353

AFTES RECOMMENDATION N°GT32.R2A1

Appendix 7 - Methods used to quantify risks

1 - Quantifying consequences 3 - Determining the level of risk


As recommended in paragraph 3.2.3b, “Role of the designer and project For a quantitative approach, one solution involves multiplying the likelihood V
owner”, it is the responsibility of the project owner to define the criteria used (expressed in the form of a numerical value between 0 and 1) by the estimated
to evaluate acceptability of a risk. cost C of treating the consequences. The level of risk R = V x C related to an
event may incorporate various types of consequence, which can be weighted,
It is recommended that for each of the objectives of the project owner, the including the following:
C = αC1 (lead time) + βC2 (costs) + γC3 (other objective)
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

impact of the consequences should be ranked on a scale of 1 to 4, as shown


in the table below:
For a qualitative approach, a matrix can be
Delay (1-2), Cost (2), expressed Image (2),
Risk matrix Scale of used, showing likelihood and consequences
expressed in terms in terms of the expressed in terms of Other
score consequences expressed qualitatively:
of the overrun overrun media impact
4
• possible, unlikely, highly unlikely and
Very high t > 3 months C > 50% Worldwide
improbable for likelihood
3 High 1 month < t < 3 months 10% < C < 50% Continental
• slight, medium, significant and highly signi-
2 Medium 1 week < t < 4 weeks 5% < C < 10% Countrywide ficant for consequences.
1 Low t < 1 week C < 5% Local

(1) deadline overruns are indicated for a project lasting approximately one year
(2) indicative values: to be adjusted depending on the project Each of these descriptions corresponds to a numerical value of between 1 and
4 for both likelihood and consequences. The combination of these values the-
Each of these scores (1 to 4) corresponds to a description and to a range of refore results in a square matrix like that shown below, in which the level of
values, in order to quantify the seriousness of the consequences with regard risk may be expressed qualitatively by multiplying the two scores (this matrix
to the objectives. Clearly, for a given event, the degree of seriousness may is used to illustrate paragraph § 3.2.3 in the main body of the text).
differ depending on the objective under consideration.
Risk matrix
For instance, if a fault is encountered, a number of characteristics need to be Possible 4 8 12 16
Likelihood

envisaged: strength, orientation, type of infill materials, amount of related water Unlikely 3 6 9 12
ingress, etc. A number of scenarios may be envisaged with regard to these Highly unlikely 2 4 6 8
characteristics. Improbable 1 2 3 4
Slight Medium Significant Highly significant
On the basis of this new data, the project designer can establish the treatment Consequences
to be applied subsequently (cf. § 3.3 “Risk treatment”). Nevertheless, on the
basis of this new data and depending on the planned construction arrange-
ments, the project designer must determine the various consequences in terms An example of a calculation of the level of risk established on the basis of
of costs and delay and rank these in order to be able to evaluate the impact the value tables supplied to quantify consequences (§ 1) and likelihood
of the risk under consideration. (§ 2) is shown below. Take a given event A, with a likelihood of 1/20 and
consequences of €18 million, corresponding to approximately 15% of the
total construction cost and four months’ time overrun;
2 - Quantifying likelihood
• the correspondence tables above return a likelihood value of 3 and a
In practice, as for the consequences, and as shown in the table below, likelihood consequence value of 3 (significant) for the cost and 4 (catastrophic) for
may be ranked into 4 classes, ranked from 1 to 4 and corresponding to 4 the lead time;
ranges of probability. • Determination of the level of risk (NR) returns a value of 9 for cost and
12 for delay. These results should be compared with the acceptability cri-
Matrix Indicative probability, to be
Likelihood scale adjusted according to the project teria selected by the project owner (cf. § 3.2.3 in the main body of the
score
being studied text, “Risk evaluation”).

4 Possible 1/5 = 20 %
It should be noted that the Likelihood*Consequences multiple (€18 million
3 Unlikely 1/20 = 5 %
x 0.15 or 4 months x 0.15) could also have been established directly, and
2 Highly unlikely 1/50 = 2 %
this result compared to an acceptability chart drawn up in absolute values.
1 Improbable 1/200 = 0,5 %

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 353
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page354

AFTES RECOMMENDATION N°GT32.R2A1 M

4 - Other representations of the level of risk measurement of the complexity of the geological context, as well as the
relevance and reliability of the sources of information used to draw up the
4.1 - A probabilistic method: DAT (Decision Aid geological model. This approach was inspired by the R-index method.
for Tunnelling)
Analysis of the geological model makes it possible to assign a score to each
In addition to the risk matrix and its coloured boxes to represent the level tunnel section, characterising its geological complexity (Cx). The greater
of risk, this may also be represented in graphic form on a summary diagram the complexity of the geological model, the lower the score. Reliability of
showing the statistical distribution of possible costs and delays for com- the information obtained from all types of survey used to draw up the geo-
pletion of the structure. This representation is one of the most explicit results logical model is indicated in the form of a score (Fi) that depends on the
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

provided by the DAT (Decision Aid for Tunnelling) method, a system originally nature and proximity of the sources of knowledge. The more unreliable the
developed by MIT and EPFL, and subsequently by Geodata in Turin. This information, the lower the score,. The extent of knowledge is established
gives the project owner a visual representation of a range of costs/delays on the basis of the relationship between the reliability of these sources of
for completion of its structure, on the basis of the determined variability for knowledge and the complexity of the geological context (NC = Fi/Cx).
each of the geotechnical parameters selected.
By establishing the extent of knowledge in this way,
© Laboratoire de Mécanique des Roches, Ecole Polytechnique Fédérale de Lausanne.

supporting grounds can be provided for every point of


the tunnel and easily modified as new data are incor-
porated into the model following subsequent survey
work.

Next, after listing possible events and their location


along the longitudinal profile on the basis of the ana-
lysis step, the likelihood of each event is estimated
qualitatively. This method relies on the degree of
expertise of the designer and is also linked to the
degree of knowledge of the site. The extent of know-
ledge (NC) is incorporated with likelihood when cal-
culating the level of risk.
Figure 11 - Example of diagrams simulating the cost and lead times for
construction of a tunnel, produced using the DAT method.
Then, for each possible event that has been identified, a realistic estimation
of its financial consequences is made, based on a detailed description of
4.2. - Cost estimation of geotechnical risks the event itself. The level of risk for each analysis step is determined by
summing the multiples (likelihood x consequence) of all the events.
This method, developed by CETU, is designed to estimate costs of geotech-
nical risks and represent them in graphic form on the longitudinal geotech- The suggested mode of representation makes it easy to highlight the most
nical profile [16], [18]. The methods involves discretization of the geological striking results. For instance, on figure 12, it is immediately obvious where
model, and presents the results of risk management, namely the extent of in the tunnel the extent of knowledge NC (represented by a curve) is poor and
knowledge (NC) and the provision of the risks (PR) on the basis of a step- where the provision for risks PR (shown as a histogram) is high. These sum-
by-step analysis. mary charts offer a good representation of the risk management approach,
and should be read taking into account both parameters, NC and PR. This
Firstly, an “extent of knowledge” (NC) index is defined. This represents a makes it easy to locate the principal risks on the scale of the project.

Provision for risks Extent of knowledge

Figure 12 - Example of a longitudinal profile with synthetical representation of geotechnical risks.

354
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012
M
315a355RECO UK_Mise en page 1 23/08/12 14:30 Page355

AFTES RECOMMENDATION N°GT32.R2A1

5- Register of Risks However, it is vital to preserve successive versions of the table in order to
ensure traceability of the process of risk identification and treatment.
One possible presentation of the summary table of the risk management pro-
cess is shown below. For each individual risk (represented by a line), the various When the Risk Management Plan is drawn up, the table must be completed
columns representing the successive tasks in the process should be comple- by additional columns (not shown here) relating to the assignment of risks to
ted. Such a table is by nature subject to change. A given risk may be eliminated the contracting parties, as well as to the mode of remuneration chosen for
during the project due to construction measures being adopted to manage it. their treatment and their consequences.

Design phases Preliminary Studies Project Studies Finalisation of the Tender


Date: Preliminary Design DCE
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

Identification Risk source Likelihood Consequences Level of Preventive Level of residual Method of Compensation
Risk risk treatment risk detection treatment
Risk 1
Risk 2

The design phase is specified by ticking the appropriate box. The contents of the table, to be completed during each risk analysis, are detailed below with expla-
nations of the title of each column.

Identification: Free text that should provide the best possible description of the identified risk after the specific context of the structure and consideration
has been analysed: geology, hydrogeology, geotechnics, environment, surroundings, etc.
Risk source: Reference to one or more “types of event” including those defined in the table in Appendix 6
Likelihood: Qualitative expression using 4 levels.
Consequences: Detailed description of the possible consequences if the event in question occurs, in the form of several scenarios relating to the construction
conditions that may be encountered, with the possible inclusion of an index of seriousness for each scenario, expressed qualitatively with 4 levels.
Level of risk: The result of combining the likelihood and the seriousness of the consequences with the possible addition of a significance index expressed
quantitatively (a score of between 1 and 16).
Preventive treatment: Measures planned to reduce or eliminate the risk: abandonment of the solution, altering the location, changing the alignment and/or
longitudinal profile, survey and study programme to clarify the likelihood and/or consequences - selection of methods minimising the consequences if the
event in question occurs, etc.
During construction: Surveys as works progress, inspections, etc.
Level of residual risk: the level of risk after preventive treatment, accepted by the project owner or the contractor if there has been an express transfer of the risk
Curative treatment: Appropriate construction measures and/or adjustment of initial methods with a view to reducing the seriousness of the consequences
if the event in question occurs.

Appendix 8 - Acronyms and abbreviations


ACT: Phase covering assistance with awarding contracts of works (Assistance
à la passation du Contrat de Travaux) DCE: Tender Documents (Dossier de Consultation des Entreprises)
AITES: International Tunnelling and Underground Space Association (ITA) EP: Preliminary Studies phase (Etudes Préliminaires)
AMO: Engineer’s Assistant (Assistant au Maître d’Ouvrage) GBR: Geotechnical Baseline Report
AVP: Preliminary Design phase (Avant-Projet) GT: AFTES Working Group (Groupe deTravail)
CCAG: French Ecology Ministry’s General Terms of Contract (Cahier des Clauses ISRM: International Society of Rock Mechanics
Administratives Générales) ITA: International Tunneling Association
CCTG: French Ecology Ministry’s General Technical Specifications (Cahier des ITIG: International Tunneling Insurance Group
Clauses Techniques Générales) MOP: Project mission as per French Public Works Procurement Law (Maîtrise
CGEDD: French Council for Ecology and Sustainable Development (Conseil d’Ouvrage Publique)
Général de l’Écologie et du Développement Durable) MSG: Summary Geotechnical Report (Mémoire de Synthèse Géotechnique)
CFGI: French Committee of Engineering Geology and the Environmental PPP: Private-public partnership
(Comité Français de Géologie de l’Ingénieur et de l’environnement) PRO: Project phase
CFMR: French Committee for Rock Mechanics (Comité Français de Mécanique RFF: French Rail Network (Réseau Ferré de France)
des Roches) TOS: Tunnels & Ouvrages souterrains (AFTES journal)
CFMS: French Committee for Soil Mechanics and Geotechnical Engineering WG: Working Group (ITA)
(Comité Français de Mécanique des Sols et de Géotechnique) ZIG: Zone of Geotechnical Influence (Zone d’Influence Géotechnique)

M
TUNNELS ET ESPACE SOUTERRAIN - n°232 - Juillet/Août 2012 355
Notes :
www.aftes.asso.fr

All rights for reproduction or adaptation in whatever format are expressly reserved

You might also like