NEM CONCEPT SCENARIOS

Net Energy ENERGY IMPORT = ENERGY USAGE

Metering
100% ENERGY (EQUAL)
IMPORT FROM TNB
ON

WITHOUT NEM

(NEM)
ON ON

NEM
DISTRIBUTION
BOARD

Net Energy Metering Import

ENERGY USAGE = ENERGY IMPORT FROM TNB + SOLAR PV ENERGY EXCESS SOLAR ENERGY EXPORT TO TNB

WHAT IS NEM? ON OFF

INVERTER

INVERTER
ON ON ON
ON

NEM or Net Energy Metering is a practice


DISTRIBUTION
DISTRIBUTION
BOARD
BOARD

where energy produced from the solar PV Import Export


Import Export

system installed will be consumed first, and


any excess to be exported to TNB. Effective SCENARIO 1: ENERGY USAGE MORE SCENARIO 2: ENERGY USAGE LESS
1st January 2019, the new mechanism of NEM THAN SOLAR PV ENERGY GENERATED THAN SOLAR PV ENERGY GENERATED

will allow electricity users who had installed


solar PV system at their home or premises to WITH NEM
reduce electricity bills and hence create
savings. The excess energy calculation will
be based on the 'one-on-one' principle in this SCENARIO 3: NO ENERGY USAGE
(NO PEOPLE AT HOME)
SCENARIO 4: NIGHT TIME
NO ENERGY GENERATED FROM SOLAR

improved NEM mechanism.


EXCESS SOLAR ENERGY EXPORT TO TNB 100% ENERGY IMPORT FROM TNB

OFF ON

For more information regarding NEM or how to apply,


INVERTER

INVERTER
OFF OFF ON ON

please visit: DISTRIBUTION


BOARD
DISTRIBUTION
BOARD

www.NEMsolarMalaysia.com/contact-us Import Export Import Export


Net Energy Metering (NEM)
NEW NEM CALCULATION
For more information regarding NEM or how to apply, please visit: NEM
Net Energy Metering
www.NEMsolarMalaysia.com/contact-us

(200kWh)
(500kWh)

Import Export

PREVIOUS NEM Home with solar PV

500kWh x Gazetted Tariff = RM 180.20


Excess Energy Export to TNB (Solar PV)

200kWh x RM 0.31/kWh = RM 62.00

Import x Gazetted Tariff Export x Displaced Cost

Solar energy that is produced from the Block Tariff Prorate Rate Amount
installed PV system will be consumed (kWh) (kWh) (kWh) (kWh) Bill : RM 118.20
first. Any excess will be exported and First 200 200 0.218 43.60
sold to TNB at the prevailing Displaced First 100 100 0.334 33.40
Cost prescribed by Energy Commission. First 200 200 0.516 103.20
First 300 0 0.546 0.00
Total 500 180.20

(200kWh)
(500kWh)

Import Export

Effective 1 January 2019


st

NEW NEM Home with solar PV

500kWh x Gazetted Tariff = RM 180.20


Excess Energy Export to TNB (Solar PV)

200kWh x Gazetted Tariff = RM 103.20

Import x Gazetted Tariff


The new Net Energy Metering (NEM) has Block Tariff Prorate Rate Amount Block Tariff Prorate Rate Amount
been improved by adopting the true net (kWh) (kWh) (kWh) (kWh) (kWh) (kWh) (kWh) (kWh) Bill : RM 77.00
energy metering concept and this will First 200 200 0.218 43.60 First 200 0 0.218 0 (Additional Saving RM41.20)
allow excess solar PV generated energy First 100 100 0.334 33.40 First 100 0 0.334 0
to be exported back to the grid on a First 200 200 0.516 103.20
First 200 200 0.516 103.20
one-on-one offset basis. First 300 0 0.546 0.00
First 300 0 0.546 0.00
Total 500 180.20 Total 500 103.20

Export Charges are charged in descending order