1.

COLLECTION
Sl No Name of Item Unit Rate
1.1 SAND
Collection of sand at quarry free from dust & other
foreign materials including screening and paying of
necessary forest royalty etc, complete as directed.

(i) Without Contractor's Profit & GST CuM Rs. 396.67


( Rupees Three Hundred
NinetySix Paise SixtySeven
) Only

(ii) With Contractor's Profit & GST CuM Rs. 488.69


( Rupees Four Hundred
EightyEight Paise
SixtyNine ) Only

1.2 BOULDER
(A) Collection of one man size 25 cm to 30 cm hard river CuM Rs. 825.44
boulder including stacking in measurable stacks of not ( Rupees Eight Hundred
more than 1.00 M height at quarry site and making TwentyFive Paise
FortyFour ) Only
payment of forest royalty etc, complete as directed.

(B) Collection of blasted boulder of size 25 cm to 30 cm CuM Rs. 1022.56


including stacking at quarry site, complete as directed. ( Rupees One Thousand
TwentyTwo Paise FiftySix
) Only

(C) Collection of blasted boulder of size 15 cm to 23 cm CuM Rs. 1151.92


including stacking in measurable stacks not more than ( Rupees One Thousand
1.00 M in height at quarry site and making payment of One Hundred FiftyOne
Paise NinetyTwo ) Only
forest royalty etc, complete as directed.

(D) Collection of 15 cm to 23 cm hard river boulder CuM Rs. 899.36


including stacking in measurable stacks not more than ( Rupees Eight Hundred
1.00 M in height at quarry site and making payment of NinetyNine Paise ThirtySix
) Only
forest royalty etc, complete as directed.

1.3 HARD RIVER GRAVEL


(A) Collection of hard river gravel, chips of size 6 mm to 20 CuM Rs. 1034.88
mm free from dust and dirt from quarry including
mm free from dust and dirt from quarry including ( Rupees One Thousand
loading and unloading etc, complete as directed. ThirtyFour Paise
EightyEight ) Only
(B) Collection of hard river gravel, chips of size 13 mm to 25 CuM Rs. 960.96
mm free from dust and dirt from quarry including ( Rupees Nine Hundred
loading and unloading etc, complete as directed. Sixty Paise NinetySix )
Only

(C) Collection of hard river gravel of size 5 cm to 15 cm free CuM Rs. 825.44
from dust and dirt from quarry including loading and ( Rupees Eight Hundred
unloading etc, complete as directed. TwentyFive Paise
FortyFour ) Only

(D) Collection of hard river gravel of size 13 mm to 38 mm CuM Rs. 899.36


free from dust and dirt from quarry including loading ( Rupees Eight Hundred
and unloading etc, complete as directed. NinetyNine Paise ThirtySix
) Only

1.4 PEA GRAVEL


Collection of 4 mm to 8 mm river pea gravel free from
dust, dirt and other foreign materials, collecting from
approved quarry including double screening, loading,
unloading, local carriage and stacking in measurable
stacks at site not more than 1.00 M height including
paying forest royalty etc. complete as directed.

(i) Without Contractor's Profit & GST CuM Rs. 770.00


( Rupees Seven Hundred
Seventy ) Only

(ii) With Contractor's Profit & GST CuM Rs. 948.64


( Rupees Nine Hundred
FortyEight Paise SixtyFour
) Only

1.5 HARD BROKEN STONE


(A)(i) Collection of hard broken stone of size 6 mm to 20 mm CuM Rs. 1995.84
from river boulder free from dust and dirt and foreign ( Rupees One Thousand
materials including stacking at quarry site, complete as Nine Hundred NinetyFive
Paise EightyFour ) Only
directed.

(ii) Collection of hard broken stone of size 6 mm to 20 mm CuM Rs. 2156.00


from blasted boulder free from dust and dirt and
from blasted boulder free from dust and dirt and ( Rupees Two Thousand
foreign materials including stacking at quarry site, One Hundred FiftySix )
Only
complete as directed.
(B)(i) Collection of hard broken stone of size 13 mm to 25 mm CuM Rs. 1921.92
from river boulder free from dust and dirt and foreign ( Rupees One Thousand
materials including stacking at quarry site, complete as Nine Hundred TwentyOne
Paise NinetyTwo ) Only
directed.

(ii) Collection of hard broken stone of size 13 mm to 25 mm CuM Rs. 2069.76


from blasted boulder free from dust and dirt and ( Rupees Two Thousand
foreign materials including stacking at quarry site, SixtyNine Paise SeventySix
) Only
complete as directed.

(C)(i) Collection of hard broken stone of size 13 mm to 38 mm CuM Rs. 1774.08


from river boulder free from dust and dirt and foreign ( Rupees One Thousand
materials including stacking at quarry site, complete as Seven Hundred
SeventyFour Paise Eight )
directed.
Only

(ii) Collection of hard broken stone of size 13 mm to 38 mm CuM Rs. 1971.20


from blasted boulder free from dust and dirt and ( Rupees One Thousand
foreign materials including stacking at quarry site, Nine Hundred SeventyOne
Paise Twenty ) Only
complete as directed.

********

2. CARRIAGE
Sl No Name of Item Unit Rate
2.1 Carriage of boulders, gravels, metal screening, stacking
in measurable stacks at site, complete as directed.

(A) For Normal Road upto 25.00 KM

(i) Without Contractor's Profit & GST : CuM Rs. 424.00


( Rupees Four Hundred
TwentyFour ) Only
: CuM Rs. 16.96
/ KM ( Rupees Sixteen Paise
NinetySix ) Only
(ii) With Contractor's Profit & GST : CuM Rs. 522.37
( Rupees Five Hundred
TwentyTwo Paise
ThirtySeven ) Only

: CuM Rs. 20.89


/ KM ( Rupees Twenty Paise
EightyNine ) Only

(B) For 1st KM of Quarry Road

(i) Without Contractor's Profit & GST CuM Rs. 49.46


/ KM ( Rupees FortyNine Paise
FortySix ) Only
(ii) With Contractor's Profit & GST CuM Rs. 60.93
/ KM ( Rupees Sixty Paise
NinetyThree ) Only

********

3. JUNGLE CLEARANCE
Sl No Name of Item Unit Rate
3.1 Cutting jungles and trees upto 50 cm girth including
uprooting roots and stumps and removing them from
site of work etc, complete as directed.

(i) Light jungles SqM Rs. 9.93


( Rupees Nine Paise
NinetyThree ) Only

(ii) Medium jungles SqM Rs. 13.90


( Rupees Thirteen Paise
Ninety ) Only

(iii) Heavy jungles SqM Rs. 23.16


( Rupees TwentyThree
Paise Sixteen ) Only
3.2 FELLING AND REMOVING

(A) Bamboo clumps: SqM Rs. 232.23


( Rupees Two Hundred
ThirtyTwo Paise
TwentyThree ) Only

(B) Bamboo clumps including uprooting stumps: SqM Rs. 275.15


( Rupees Two Hundred
SeventyFive Paise Fifteen )
Only

(C) Cutting trees including uprooting and removing where


necessary

(i) 50 cm to 100 cm girth No. Rs. 192.19


( Rupees One Hundred
NinetyTwo Paise Nineteen
) Only

(ii) 100 cm to 150 cm girth No. Rs. 412.72


( Rupees Four Hundred
Twelve Paise SeventyTwo )
Only

(iii) 150 cm to 180 cm girth No. Rs. 878.42


( Rupees Eight Hundred
SeventyEight Paise
FortyTwo ) Only

(iv) Above 180 cm girth No. Rs. 1576.96


( Rupees One Thousand
Five Hundred SeventySix
Paise NinetySix ) Only

(D) Tea Bushes No. Rs. 10.22


( Rupees Ten Paise
TwentyTwo ) Only

(E) Tea Bushes including uprooting No. Rs. 35.86


( Rupees ThirtyFive Paise
EightySix ) Only
(F) Cutting and clearing bushes consisting of plants and all SqM Rs. 25.75
sorts of bamboos including uprooting and removing as ( Rupees TwentyFive Paise
necessary and filling up the holes with earth including SeventyFive ) Only
dressing, ramming, complete as directed.

********

4. SURVEYING
Sl No Name of Item Unit Rate
4.1 Carrying out compass survey including chaining, KM Rs.. 2231.97
marking, pegging, carrying instruments and clearing ( Rupees Two Thousand
jungles and other obstructions, complete as directed. Two Hundred ThirtyOne
Paise NinetySeven ) Only

4.2 Carrying out compass survey including chaining, SqKM Rs.. 18788.00
marking, pegging, carrying instruments and clearing ( Rupees Eighteen
jungles and other obstructions, complete as directed. Thousand Seven Hundred
EightyEight ) Only

4.3 Carrying out levelling survey taking long section and KM Rs. 18898.88
cross section at 30 M interval of proposed canal system, ( Rupees Eighteen
afflux bund, approach road and along the stream Thousand Eight Hundred
NinetyEight Paise
including chaining, pegging, holding staff, carrying out
EightyEight ) Only
instrument, clearing jungle etc, complete as directed.

4.4 Fly levelling for checking the level after completion of KM Rs. 1872.64
survey along the existing canal and connection of BM ( Rupees One Thousand
pillars. Eight Hundred SeventyTwo
Paise SixtyFour ) Only

4.5 Carrying out block contour survey of the commanded Hectare Rs. 1154.78
area covering stream, dong, channel, road etc. and the
area covering stream, dong, channel, road etc. and the ( Rupees One Thousand
whole area considering square block system and spot One Hundred FiftyFour
Paise SeventyEight ) Only
system and spot levels are to be within 30 M x 30 M for
preparation of contour including clearing light jungles,
chaining, pegging holding staff, umbrella and compass
lining etc. where required, complete as directed.

4.6 Carrying out levelling survey, taking long section KM Rs. 18759.58
including cross section at 30 M interval of proposed ( Rupees Eighteen
canal system, afflux bund, guide bund, approach road Thousand Seven Hundred
FiftyNine Paise FiftyEight )
and along the stream including chaining, pegging,
Only
holding staff, carrying out instrument, clearing jungle
etc, complete as directed.

4.7 Carrying out levelling survey for taking long section of KM Rs. 1694.00
field channel at an interval not more than 30 M or part ( Rupees One Thousand Six
thereof including ranging, chaining, holding staff, driving Hundred NinetyFour ) Only
pegs, clearing light jungles and carrying survey materials
etc, complete as directed.

4.8 Supplying wooden peg of different sizes including


pointing one end etc, complete as directed.

(i) size: 10 cm x 10 cm x 120 cm No. Rs. 768.36


( Rupees Seven Hundred
SixtyEight Paise ThirtySix
) Only

(ii) size: 7.5 cm x 7.5 cm x 90 cm No. Rs. 291.46


( Rupees Two Hundred
NinetyOne Paise FortySix )
Only

(iii) size: 5.0 cm x 5.0 cm x 60 cm No. Rs. 105.75


( Rupees One Hundred Five
Paise SeventyFive ) Only

4.9 Supplying of wooden pegs of size 0.60 M x 0.045 M x No. Rs. 60.28
0.045 M made of 2nd class local wood. ( Rupees Sixty Paise
TwentyEight ) Only

4.10 Supplying wooden hammer of size 15 cm x 10 cm with No. Rs. 528.77


45 cm long & 5 cm wodden handle etc, complete as
45 cm long & 5 cm wodden handle etc, complete as ( Rupees Five Hundred
directed. TwentyEight Paise
SeventySeven ) Only

4.11 Construction of RCC BM Pillar of size 0.15 M X 0.10 M in No. Rs. 3319.76
proportion 1:2:4 with required reinforcement including ( Rupees Three Thousand
E/W in excavation, brick soling, centering, shuttering Three Hundred Nineteen
Paise SeventySix ) Only
and propping, etc, complete as directed.

4.12 Final Survey before and after execution across existing KM Rs. 9862.16
damaged canal system for checking cross section and ( Rupees Nine Thousand
long section at the interval of 25 M including supplying Eight Hundred SixtyTwo
Paise Sixteen ) Only
of labour and other materials such as jati bamboo
kamies, coir rope, paint and local wood chainage peg of
size 1½" x 1½" x 3' etc, complete as directed.

5. TURFING
Sl No Name of Item Unit Rate
5.1 Turfing with grass sode of largest possible rectangular SqM Rs. 16.88
and minimum size 30 cm X 30 cm X 10 cm placing ( Rupees Sixteen Paise
closely after dressing hard the surface and fixing sode EightyEight ) Only
with split bamboo pegs, watering till the grass grows
with lead up to 90 M and lift of 1.50 M, complete as
directed.

********

6. EARTHWORK
Sl No Name of Item Unit Rate
A. EARTHWORK IN EXCAVATION
6.1 Earthwork in excavation in irrigation canal to the design
section and grade by depositing the spoils in the form of
embankment in 15 cm layers on both banks as
necessary including clearing light jungle, removing trees
upto 15 cm dia and uprooting roots and stumps etc.
from the seat of the embankment and canal free from
all vegetation including breaking clods not more than 10
mm cube, ramming, dressing and roughening the seat
of the embankment with a lead upto 30 M and lift upto
1.50 M, complete as directed.
(A) In ordinary Soil CuM Rs. 168.39
( Rupees One Hundred
SixtyEight Paise
ThirtyNine ) Only

(B) In hard Soil


(i) Soil with gravel or morum upto 50 mm size CuM Rs. 236.32
( Rupees Two Hundred
ThirtySix Paise ThirtyTwo
) Only

(ii) Soil with gravel or morum upto 30 cm size CuM Rs. 283.26
( Rupees Two Hundred
EightyThree Paise
TwentySix ) Only

(iii) Soil with gravel or boulder above 30 cm size CuM Rs. 1058.29
( Rupees One Thousand
FiftyEight Paise
TwentyNine ) Only

6.2 EXTRA LEAD AND LIFT


(A) Extra lead for every 30 M or part thereof beyond initial CuM Rs. 12.85
lead of 30 M ( Rupees Twelve Paise
EightyFive ) Only

(B) Extra lift for every 1.5 M or part thereof beyond initial CuM Rs. 12.85
lift of 1.5 M ( Rupees Twelve Paise
EightyFive ) Only
6.3 Earthwork in excavation in diversion / feeder channel to
the design section and grade by depositing the spoils in
the form of an embankment on either side to the design
section and grade in layers not exceeding 15 cm thick
including clearing light jungle and trees upto 15 cm dia
and uprooting roots and stumps etc. from the seat of
the embankment and canal and free from all vegetation
including breaking clods not more than 10 mm cube,
ramming, dressing, bailing out stagnant rain water
necessary complete as directed with a lead upto 30 M
and lift upto 1.50 M.
(A) In ordinary Soil CuM Rs. 172.11
( Rupees One Hundred
SeventyTwo Paise Eleven )
Only
(B) In hard Soil
(i) Soil mixed with gravel or morum upto 50 mm size CuM Rs. 240.04
( Rupees Two Hundred
Forty Paise Four ) Only

(ii) Soil mixed with gravel or boulders upto 30 cm size CuM Rs. 286.80
( Rupees Two Hundred
EightySix Paise Eighty )
Only

(iii) Soil mixed with gravel and boulders above 30 cm size CuM Rs. 1791.41
( Rupees One Thousand
Seven Hundred NinetyOne
Paise FortyOne ) Only

6.4 Earthwork in excavation in foundation of canal


structures in all types of soils as per design and drawing
including dressing the foundation, shoring etc. removing
the surplus spoils by head load to safe distance from the
working place and depositing the required spoils in
uniform layers, dressing, watering, breaking clods to not
more than 10 mm cube with compensation, complete
as directed at site. (Including bailing out stagnant rain
water where necessary).

(A) In all types of soils (except soil mixed with gravel and boulders)
(i) For normal lead of 30 M and lift of 1.50 M CuM Rs. 196.44
( Rupees One Hundred
NinetySix Paise FortyFour
) Only

(ii) For lead upto 60 M and lift of 3 M CuM Rs. 222.14


( Rupees Two Hundred
TwentyTwo Paise Fourteen
) Only
(B) In soil mixed with gravel and boulder upto 30 cm size
(i) For normal lead of 30 M and lift of 1.50 M CuM Rs. 308.57
( Rupees Three Hundred
Eight Paise FiftySeven )
Only

(ii) For lead upto 60 M and lift of 3 M CuM Rs. 334.27


( Rupees Three Hundred
ThirtyFour Paise
TwentySeven ) Only
B. EARTHWORK IN HEADWORK
6.5 Earthwork in excavation in foundation of head work in
all types of soil as per design and drawing including
dressing the foundation, shoring etc. removing the
surplus spoils by head load to safe distance from the
working place and depositing the required spoils in
uniform layers, dressing, watering, breaking clods to not
more than 10 mm cube with compensation, complete
as directed at site. (Including bailing out stagnant rain
water where necessary).
(A) In all types of soils (except soil mixed with gravel and boulders)
(i) For normal lead of 30 M and lift of 1.50 M CuM Rs. 201.70
( Rupees Two Hundred
One Paise Seventy ) Only

(ii) For lead upto 60 M and lift of 3 M CuM Rs. 227.40


( Rupees Two Hundred
TwentySeven Paise Forty )
Only
(B) In soil mixed with gravel and boulder upto 30 cm size
(i) For normal lead of 30 M and lift of 1.5 M CuM Rs. 319.61
( Rupees Three Hundred
Nineteen Paise SixtyOne )
Only

(ii) For lead upto 60 M and lift of 3 M CuM Rs. 345.31


( Rupees Three Hundred
FortyFive Paise ThirtyOne
) Only

( C) In soil mixed with gravel and boulder above 30 cm size


(i) For lead of 30 M and lift of 1.5 M CuM Rs. 420.51
( Rupees Four Hundred
Twenty Paise FiftyOne )
Only
(ii) For lead upto 60 M and lift of 3 M CuM Rs. 446.21
( Rupees Four Hundred
FortySix Paise TwentyOne
) Only

6.6 Earthwork in excavation and removal of swelled up


earth mixed with silt and slurry due to sand, bailing out
water in foundation trenches upto required level
including shuttering, shoring, dewatering by means of
pump set etc. removing the spoils to a safer distance
etc, complete as directed.
(i) Without dewatering CuM Rs. 1107.69
( Rupees One Thousand
One Hundred Seven Paise
SixtyNine ) Only

(ii) With dewatering CuM Rs. 1526.77


( Rupees One Thousand
Five Hundred TwentySix
Paise SeventySeven ) Only

6.7 Earthwork in excavation trenches of walls, retaining


walls, footing of columns, steps and septic tank
including refilling (return filling) the quantity as
necessary after completion of works, breaking clods in
return filling, dressing, ramming, watering etc. and
removal of surplus earth with all lead and lift upto 2
metre as directed and specified in following
classification of soils, including bailing out of water
where necessary upto depth below the existing ground
level as mentioned in the approved drawing and
complete as directed and specified.
(A) In ordinary soil CuM Rs. 375.93
( Rupees Three Hundred
SeventyFive Paise
NinetyThree ) Only

(B) In soft or laminated rock or medium shale CuM Rs. 390.87


( Rupees Three Hundred
Ninety Paise EightySeven )
Only

(C) Extra for lift beyond 2.00 M upto 3.00 M for all CuM Rs. 102.26
classification of soils.
classification of soils. ( Rupees One Hundred
Two Paise TwentySix )
Only
6.8 Earthwork in cutting in river bank etc. to the design CuM Rs. 330.08
section and grade and removing the spoils to a safe ( Rupees Three Hundred
distance including cutting, uprooting and removing Thirty Paise Eight ) Only
trees upto 15 cm dia, uprooting and removing roots and
stumps etc, including excavating the earth boulder
sausages of 1.00 M dia, 50 cm under river bed shape,
size and grade etc. with all lead and lift, complete as
directed.

6.9 Earthwork in excavation in foundation of structures by CuM Rs. 343.51


means of Hydraulic Excavator in all soils including mud, ( Rupees Three Hundred
silt, sandy clay from the river bed, etc, including clearing FortyThree Paise FiftyOne
) Only
the side, dressing, etc. and removing the earth by
loading to dumpers for further carriage to a safe
distance, complete as directed. (0.30 CuM bucket)

6.10 Earthwork in excavation of foundation trenches CuM Rs. 201.30


including filling up sides of trenches and removal of ( Rupees Two Hundred
spoils after completion of foundation, dressing, One Paise Thirty ) Only
ramming, shoring etc. complete including bailing out
water, where necessary, in ordinary soil.

6.11 Carriage of excavated earth by dumpers with a lead CuM Rs. 244.29
upto 2 KM unloading to a safe place as directed ( Rupees Two Hundred
including spreading, dressing etc, complete as directed. FortyFour Paise
TwentyNine ) Only

6.12 Earthwork in excavation of deposited silt, sand and river CuM Rs. 252.07
debris from the seat of Guide Bunds /Afflux Bunds,etc.
debris from the seat of Guide Bunds /Afflux Bunds,etc. ( Rupees Two Hundred
including clearing light jungle, removing tree upto 15 cm FiftyTwo Paise Seven )
Only
dia, and uprooting roots and stumps, etc, from the seat
of Guide Bunds / Afflux Bunds, etc. including dressing,
carriage of excavated earth and depositing the same in
stacks at a distance not less than 80 M from the axis of
the Guide Bunds / Afflux Bunds, etc. including bailing
out of water where necessary upto depth below the
existing ground level as mentioned in the approved
drawing and complete as directed and specified.

C. EARTHWORK IN FILLING
6.13 Earthwork in filling in Marginal bund / Guide bank /
Afflux bund / Canal embankment etc. to the design
section and grade by obtaining earth from outside
borrow pits and filling in uniform layers not exceeding
15 cm thick including clearing light jungle, removing
trees upto 15 cm dia and uprooting roots and stumps
from the seat of embankment and borrow pit area,
breaking clods not more than 10 mm cube, ramming,
watering, dressing and roughening the seat of
embankment, profiling etc. Paying compensation of
earth borrowed from private or forest land if any, lead
upto 30 M and lift upto 1.5 M, complete as directed.
(A) With ordinary Soil CuM Rs. 225.97
( Rupees Two Hundred
SixtyNine Paise
EightyThree ) Only

(B) With hard Soil


(i) Soil with gravel or morum upto 50 mm size CuM Rs. 287.82
( Rupees Two Hundred
EightySeven Paise
EightyTwo ) Only

(ii) Soil with gravel and boulder upto 30 cm size CuM Rs. 347.05
( Rupees Three Hundred
FortySeven Paise Five )
Only

( C) EXTRA LEAD AND LIFT


(i) Extra lead (for earthwork) for every 30 M or part CuM Rs. 12.42
thereof beyond the initial lead of 30 M. ( Rupees Twelve Paise
FortyTwo ) Only
(ii) Extra lift (for earthwork) for every 1.5 M or part thereof CuM Rs. 12.42
beyond the initial lift of 1.5 M. ( Rupees Twelve Paise
FortyTwo ) Only

6.14 Earthwork in back filling of structures, obtained from CuM Rs. 286.57
outside borrow pits filling in 15 cm layers, ramming, ( Rupees Two Hundred
dressing, watering, including paying compensation of EightySix Paise FiftySeven )
Only
land if any (with lead up to 30 M and lift 1.5 M).

6.15 River sand filling in plinth, canal bed, canal slopes, bases CuM Rs. 1005.16
of structure, etc in layers not more than 150 mm thick ( Rupees One Thousand
including necessary carriage, watering etc, complete as Five Paise Sixteen ) Only
directed as specified.

6.16 TRUCK & CART CARRIAGE


(A) Earthwork in filling in all soils in plinth, canal CuM Rs. 377.33
embankment and bed filling as per design section and ( Rupees Three Hundred
grade by truck carriage for a minimum distance of 4 SeventySeven Paise
ThirtyThree ) Only
KM including paying compensation of earth obtained
from private land if any loading, unloading, spreading
the same including light jungle, removing trees upto 15
cm dia and uprooting roots and stumps etc. from the
seat of the embankment, breaking clods not more than
10 mm cube, ramming, profiling etc. with all lift,
complete as directed. (Payment will be made after
deduction of 12.50 % shrinkage allowance from the
gross quantity).

(B) Earthwork in filling in all soils in canal embankment and CuM Rs. 357.75
bed filling as per design section and grade by cart ( Rupees Three Hundred
carriage for a minimum distance of 1 KM including FiftySeven Paise
SeventyFive ) Only
paying compensation of earth obtained from private
land if any loading, unloading, spreading the same in
embankment in layers not exceeding 15 cm thick
including clearing light jungle, removing trees upto 15
cm dia and uprooting roots and stumps etc. from the
seat of the embankment, breaking clods not more than
10 mm cube, ramming, dressing and roughening the
seat of the embankment, profiling etc. with all lift,
complete as directed. (Payment will be made after
deduction of 12.50% shrinkage allowance from the
gross quantity).
********

7. DEWATERING
Sl No Name of Item Unit Rate
A. DEWATERING IN EARTHWORK
7.1 Cost of dewatering in excavation of earthwork by HP Rs. 23.47
running required no. of pumps including the cost of / Hr ( Rupees TwentyThree
POL, hire charge, labour charge etc. and handling for a Paise FortySeven ) Only
depth of maximum 3.2 M, complete as directed.

B. DEWATERING IN C C WORK
7.2 Dewatering of CC works considering 1 no. 10 HP and 1
no. of 5 HP pump including POL, carriage and operator's
pay etc.

(i) Without Contractor's Profit & GST CuM Rs. 180.27


( Rupees One Hundred
Eighty Paise TwentySeven )
Only

(ii) With Contractor's Profit & GST CuM Rs. 222.10


( Rupees Two Hundred
TwentyTwo Paise Ten )
Only

********

8. SCAFFOLDING
Sl No Name of Item Unit Rate
8.1 Providing scaffolding work with rows of bhaluka CuM Rs. 63.76
bamboo and jati bamboo horizontal one row jati
bamboo and jati bamboo horizontal one row jati ( Rupees SixtyThree Paise
bamboo cross and placing second class planks of 0.025 SeventySix ) Only
M thick in between the rows tying with coir strings
lacing two nos. vertical jati bamboo at both end
including dismantling the scaffolding etc, complete as
directed.

********

9. SHUTTERING
Sl No Name of Item Unit Rate
9.1 Centering and shuttering including propping etc where
necessary and removal of forms after completion of CC
and RCC works, complete as directed. (Measurement to
be taken on the face area timbered).

(A) Shuttering (Slab). SqM Rs. 230.10


( Rupees Two Hundred
Thirty Paise Ten ) Only

(B)(i) Shuttering (Beam) without Prop. : SqM Rs. 144.00


( Rupees One Hundred
FortyFour ) Only

(Measure volume of concrete) : CuM Rs. 1440.02


( Rupees One Thousand
Four Hundred Forty Paise
Two ) Only

(ii) Shuttering (Beam) with Prop. : SqM Rs. 186.05


( Rupees One Hundred
EightySix Paise Five ) Only
(Measure volume of concrete) : CuM Rs. 2480.64
( Rupees Two Thousand
Four Hundred Eighty Paise
SixtyFour ) Only

(C) Shuttering (Column) : SqM Rs. 327.66


( Rupees Three Hundred
TwentySeven Paise SixtySix
) Only

(Measure volume of concrete) : CuM Rs. 4368.87


( Rupees Four Thousand
Three Hundred SixtyEight
Paise EightySeven ) Only

9.2 Centering and shuttering including propping, nailing,


bolting with earth oiling inside face etc and removal of
forms after completion of CC and RCC works etc,
complete as directed. (Measurement to be taken on the
face area timbered).
(Abutment / Return Wall / Piers / Pedestal etc.)

(i) With 19 mm thick plyboard : SqM Rs. 721.53


( Rupees Seven Hundred
TwentyOne Paise
FiftyThree ) Only

: CuM Rs. 3174.74


( Rupees Three Thousand
One Hundred SeventyFour
Paise SeventyFour ) Only

(ii) With 38 mm thick wood plank : SqM Rs. 242.49


( Rupees Two Hundred
FortyTwo Paise FortyNine )
Only

: CuM Rs. 1066.97


( Rupees One Thousand
SixtySix Paise NinetySeven
) Only
********

10. C C WORK
Sl No Name of Item Unit Rate
10.1 IN PROPORTION 1:1½:3 (M20)
(A) WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20 MM

(i) CC work in proportion 1:1½:3 with hard broken river CuM Rs. 7949.52
stone aggregate of size 6 mm to 20 mm including ( Rupees Seven Thousand
curing, with necessary timber shuttering, scaffolding Nine Hundred FortyNine
Paise FiftyTwo ) Only
where necessary, complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(ii) CC work in proportion 1:1½:3 with hard broken River CuM Rs. 8104.75
stone aggregate of size 6 mm to 20 mm including ( Rupees Eight Thousand
curing, bailing out water with necessary timber One Hundred Four Paise
SeventyFive ) Only
shuttering, scaffolding where necessary, complete as
directed. (Shuttering, scaffolding cost will be paid
separately).

(iii) CC work in proportion 1:1½:3 with hard broken river CuM Rs. 8171.61
stone aggregate from river boulder of size 6 mm to 20 ( Rupees Eight Thousand
mm including curing, dewatering with necessary timber One Hundred SeventyOne
Paise SixtyOne ) Only
shuttering, scaffolding where necessary, complete as
directed. (Shuttering, scaffolding cost will be paid
separately).

(B) WITH HARD RIVER SHINGLES 6 MM TO 20 MM

(i) CC work in proportion 1:1½:3 with hard river shingles of CuM Rs. 7009.01
size 6 mm to 20 mm including curing with necessary ( Rupees Seven Thousand
timber shuttering, scaffolding where necessary, Nine Paise One ) Only
complete as directed. (Shuttering, scaffolding cost will
be paid separately).

(ii) CC work in proportion 1:1½:3 with hard river shingles of CuM Rs. 7164.24
size 6 mm to 20 mm including curing, bailing out water ( Rupees Seven Thousand
with necessary timber shuttering, scaffolding where One Hundred SixtyFour
Paise TwentyFour ) Only
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).
(iii) CC work in proportion 1:1½:3 with hard river shingles of CuM Rs. 7231.10
size 6 mm to 20 mm including curing, dewatering with ( Rupees Seven Thousand
necessary timber shuttering, scaffolding where Two Hundred ThirtyOne
Paise Ten ) Only
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

10.2 IN PROPORTION 1:2:4 (M15)


(A) WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20 MM
(i) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 7657.32
piers / wing walls etc. with hard broken stone aggregate ( Rupees Seven Thousand
of size 6 mm to 20 mm including curing with necessary Six Hundred FiftySeven
Paise ThirtyTwo ) Only
timber shuttering, scaffolding where necessary
complete as directed. (Shuttering, scaffolding cost will
be paid separately).

(ii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 7812.55


piers / wing walls etc. with hard broken stone aggregate ( Rupees Seven Thousand
of size 6 mm to 20 mm including curing, bailing out Eight Hundred Twelve
Paise FiftyFive ) Only
water with necessary timber shuttering, scaffolding
where necessary, complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(iii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 7879.41


piers / wing walls etc. with hard broken stone aggregate ( Rupees Seven Thousand
of size 6 mm to 20 mm including curing, dewatering Eight Hundred SeventyNine
Paise FortyOne ) Only
with necessary timber shuttering, scaffolding etc. where
necessary complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(B) WITH HARD RIVER SHINGLES 6 MM TO 20 MM


(i) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 6539.90
piers / wing walls etc. with hard river shingles of size 6 ( Rupees Six Thousand Five
mm to 20 mm including curing with necessary timber Hundred ThirtyNine Paise
Ninety ) Only
shuttering, scaffolding where necessary, complete as
directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 6695.13


piers / wing walls etc. with hard river shingles of size 6 ( Rupees Six Thousand Six
mm to 20 mm including curing, bailing out water with Hundred NinetyFive Paise
Thirteen ) Only
necessary timber shuttering, scaffolding where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(iii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 6761.99


piers / wing walls etc. with hard river shingles of size 6
piers / wing walls etc. with hard river shingles of size 6 ( Rupees Six Thousand
mm to 20 mm including curing, dewatering with Seven Hundred SixtyOne
Paise NinetyNine ) Only
necessary timber shuttering, scaffolding where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).
( C) WITH HARD BROKEN STONE AGGREGATE 13 TO 38 MM

(i) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 7457.74


piers / wing walls etc. with hard broken stone aggregate ( Rupees Seven Thousand
of size 13 mm to 38 mm including curing with necessary Four Hundred FiftySeven
Paise SeventyFour ) Only
timber shuttering, scaffolding etc. where necessary
complete as directed. (Shuttering, scaffolding cost will
be paid separately).

(ii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 7612.97


piers / wing walls etc. with hard broken stone aggregate ( Rupees Seven Thousand
of size 13 mm to 38 mm including curing with bailing Six Hundred Twelve Paise
NinetySeven ) Only
out water with necessary timber shuttering, scaffolding
etc. where necessary, complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(iii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 7679.83


piers / wing walls etc. with hard broken stone aggregate ( Rupees Seven Thousand
of size 13 mm to 38 mm including curing including Six Hundred SeventyNine
Paise EightyThree ) Only
dewatering with necessary timber shuttering,
scaffolding etc. where necessary, complete as directed.
(Shuttering, scaffolding cost will be paid separately).

(D) WITH HARD RIVER SHINGLES 13 MM TO 38 MM


(i) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 6417.93
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Six Thousand Four
mm to 38 mm including curing with necessary timber Hundred Seventeen Paise
shuttering, scaffolding etc. where necessary, complete NinetyThree ) Only
as directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) CC work in proportion 1:2:4 in foundation / abutment / CuM Rs. 6573.16


piers / wing walls etc. with hard river shingles of size 13 ( Rupees Six Thousand Five
mm to 38 mm including curing, bailing out water with Hundred SeventyThree
Paise Sixteen ) Only
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(iii) CC work in proportion 1:2:4 in foundation / abutment/ CuM Rs. 6640.02


piers / wing walls etc. with hard river shingles of size 13
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Six Thousand Six
mm to 38 mm including curing with dewatering with Hundred Forty Paise Two )
Only
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).
10.3 IN PROPORTION 1:3:6 (M10)
(A) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 MM
(i) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 6558.39
piers / wing walls etc.with hard broken stone aggregate ( Rupees Six Thousand Five
of size 13 mm to 38 mm including curing with necessary Hundred FiftyEight Paise
ThirtyNine ) Only
timber shuttering, scaffolding etc. where necessary,
complete as directed. (Shuttering, scaffolding cost will
be paid separately).

(ii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 6713.62


piers / wing walls etc. with hard broken stone aggregate ( Rupees Six Thousand
of size 13 mm to 38 mm including curing, bailing out Seven Hundred Thirteen
Paise SixtyTwo ) Only
water with necessary timber shuttering, scaffolding etc.
where necessary complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(iii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 6780.48


piers / wing walls etc.with hard broken stone aggregate ( Rupees Six Thousand
of size 13 mm to 38 mm including curing, dewatering Seven Hundred Eighty
Paise FortyEight ) Only
with necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(B) WITH HARD RIVER SHINGLES 13 MM TO 38 MM


(i) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 5703.13
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 38 mm including curing with necessary timber Seven Hundred Three Paise
Thirteen ) Only
shuttering, scaffolding etc. where necessary, complete
as directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 5858.36


piers / wing walls etc. with hard river shingles of size 13
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 38 mm including curing, bailing out water with Eight Hundred FiftyEight
Paise ThirtySix ) Only
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(iii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 5925.22


piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 38 mm including curing, dewatering with Nine Hundred TwentyFive
Paise TwentyTwo ) Only
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

( C) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 25 MM

(i) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 6643.89


piers / wing walls etc. with broken stone aggregate of ( Rupees Six Thousand Six
size 13 mm to 25 mm including curing with timber Hundred FortyThree Paise
EightyNine ) Only
shuttering, scaffolding etc. where necessary complete
as directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 6799.12


piers / wing walls etc. with hard broken stone aggregate ( Rupees Six Thousand
of size 13 mm to 25 mm including curing, bailing out Seven Hundred NinetyNine
Paise Twelve ) Only
wate r with timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(iii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 6865.98


piers / wing walls etc. with hard broken stone aggregate ( Rupees Six Thousand
of size 13 mm to 25 mm including curing, dewatering Eight Hundred SixtyFive
Paise NinetyEight ) Only
with timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(D) WITH HARD RIVER SHINGLES 13 MM TO 25 MM

(i) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 5759.80


piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 25 mm including curing with timber shuttering, Seven Hundred FiftyNine
Paise Eighty ) Only
scaffolding etc. where necessary complete as directed.
(Shuttering, scaffolding cost will be paid separately).
(ii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 5915.03
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 25 mm including curing, bailing out water with Nine Hundred Fifteen Paise
Three ) Only
timber shuttering, scaffolding etc. where necessary,
complete as directed. (Shuttering, scaffolding cost will
be paid separately).
(iii) CC work in proportion 1:3:6 in foundation / abutment / CuM Rs. 5981.90
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 25 mm including curing, dewatering with timber Nine Hundred EightyOne
Paise Ninety ) Only
shuttering, scaffolding etc. where necessary, complete
as directed. (Shuttering, scaffolding cost will be paid
separately).

10.4 IN PROPORTION 1:4:8 (M5)


(A) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 MM
(i) CC work in proportion 1:4:8 in foundation / abutment / CuM Rs. 6063.13
piers / wing walls etc. with hard broken stone ( Rupees Six Thousand
aggregate of size 13 mm to 38 mm including curing with SixtyThree Paise Thirteen )
Only
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(ii) CC work in proportion 1:4:8 in foundation / abutment / CuM Rs. 6218.36


piers / wing walls etc.with hard broken stone aggregate ( Rupees Six Thousand Two
of size 13 mm to 38 mm including curing, bailing out Hundred Eighteen Paise
ThirtySix ) Only
water with necessary timber shuttering, scaffolding etc.
where necessary complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(iii) CC work in proportion 1:4:8 in foundation/ abutment/ CuM Rs. 6285.22


piers/ wing walls etc. with hard broken stone aggregate ( Rupees Six Thousand Two
of size 13 mm to 38 mm including curing and Hundred EightyFive Paise
TwentyTwo ) Only
dewatering with necessary timber shuttering,
scaffolding etc. where necessary, complete as directed.
(Shuttering, scaffolding cost will be paid separately).

(B) WITH HARD RIVER SHINGLES 13 MM TO 25 MM

(i) CC work in proportion 1:4:8 in foundation / abutment / CuM Rs. 5129.77


piers / wing walls etc. with hard river shingles of size 13
piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 38 mm including curing with necessary timber One Hundred TwentyNine
Paise SeventySeven ) Only
shuttering, scaffolding etc. where necessary, complete
as directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) CC work in proportion 1:4:8 in foundation / abutment / CuM Rs. 5285.00


piers / wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 38 mm including curing, bailing out of water Two Hundred EightyFive )
Only
with necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(iii) CC work in proportion 1:4:8 in foundation/ abutment/ CuM Rs. 5351.86


piers/ wing walls etc. with hard river shingles of size 13 ( Rupees Five Thousand
mm to 38 mm including curing, dewatering with Three Hundred FiftyOne
Paise EightySix ) Only
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

********

11. P C C WORK WITH PLUM


Sl No Name of Item Unit Rate
11.1 PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION 1:3:6
(A) WITH HARD BLASTED BOULDER
(i) Plain CC work in 40% plum hard blasted boulder of 15 CuM Rs. 4892.42
cm to 23 cm size and filled interstices with 60% cement ( Rupees Four Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size Eight Hundred NinetyTwo
Paise FortyTwo ) Only
stone aggregate including curing, shuttering etc,
complete as directed. (Shuttering cost will be paid
separately).

(ii) Plain CC work in 40% plum hard blasted boulder of 15 CuM Rs. 5114.51
cm to 23 cm size and filled interstices with 60% cement
cm to 23 cm size and filled interstices with 60% cement ( Rupees Five Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size One Hundred Fourteen
Paise FiftyOne ) Only
stone aggregate including curing, dewatering
shuttering etc, complete as directed. (Shuttering cost
will be paid separately).

(iii) Plain CC work in 40% plum hard blasted boulder of 15 CuM Rs. 4379.27
cm to 23 cm size and filled interstices with 60% cement ( Rupees Four Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size Three Hundred
SeventyNine Paise
river shingles including curing, shuttering etc, complete
TwentySeven ) Only
as directed. (Cost of shuttering will be paid separately).

(iv) Plain CC work in 40% plum hard blasted boulder of 15 CuM Rs. 4601.36
cm to 23 cm size and filled interstices with 60% cement ( Rupees Four Thousand Six
concrete in proportion 1:3:6 with 13 mm to 38 mm size Hundred One Paise
ThirtySix ) Only
river shingles including curing, dewatering , shuttering
etc, complete as directed. (Shuttering cost will be paid
separately).

(B) WITH HARD RIVER BOULDER

(i) Plain CC work in 40% plum hard river boulder of 15 cm CuM Rs. 4278.24
to 23 cm size and filled interstices with 60% cement ( Rupees Four Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size Two Hundred SeventyEight
Paise TwentyFour ) Only
river shingles including curing, shuttering etc, complete
as directed. (Shuttering cost will be paid separately).

(ii) Plain CC work in 40% plum hard river boulder of 15 cm CuM Rs. 4500.33
to 23 cm size and filled interstices with 60% cement ( Rupees Four Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size Five Hundred Paise
ThirtyThree ) Only
river shingles including curing, dewatering , shuttering
etc, complete as directed. (Shuttering cost will be paid
separately).

(iii) Plain CC work in 40% plum hard river boulder of 15 cm CuM Rs. 4791.39
to 23 cm size and filled interstices with 60% cement ( Rupees Four Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size Seven Hundred NinetyOne
Paise ThirtyNine ) Only
stone aggregate including curing, shuttering etc.
complete as directed. (Shuttering cost will be paid
separately).
(iv) Plain CC work in 40% plum hard river boulder of 15 cm CuM Rs. 5013.49
to 23 cm size and filled interstices with 60% cement ( Rupees Five Thousand
concrete in proportion 1:3:6 with 13 mm to 38 mm size Thirteen Paise FortyNine )
Only
stone aggregate including curing, dewatering
shuttering etc, complete as directed. (Shuttering cost
will be paid separately).

********

12. RCC WORK


Sl No Name of Item Unit Rate
12.1 IN PROPORTION 1:1½:3 (M20)
(A) WITH HARD BROKEN STONE AGGREGATE SIZE 6 MM TO 20 MM
(i) RCC work in slab, abutment cap and above abutment, CuM Rs. 8811.16
pier cap, pedestal, dirt wall etc. in proportion 1:1½:3 ( Rupees Eight Thousand
with hard broken stone aggregate of size 6 mm to 20 Eight Hundred Eleven Paise
Sixteen ) Only
mm with proper reinforcement as per design including
curing etc, complete as directed with necessary timber
shuttering, scaffolding etc. where necessary, complete
as directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) RCC work in slab, abutment cap and above abutment, CuM Rs. 9033.25
pier cap, pedestals, dirt wall etc. in proportion 1:1½:3 ( Rupees Nine Thousand
with hard broken stone aggregate of size 6 mm to 20 ThirtyThree Paise
TwentyFive ) Only
mm with proper reinforcement as per design including
necessary curing, dewatering etc. complete as directed
with necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

(B) HARD RIVER SHINGLES SIZE 6 MM TO 20 MM


(i) RCC work in slab, abutment cap and above abutment, CuM Rs. 7801.91
pier cap, pedestal, dirt wall etc. in proportion 1:1½:3
pier cap, pedestal, dirt wall etc. in proportion 1:1½:3 ( Rupees Seven Thousand
with hard river shingles of size 6 mm to 20 mm with Eight Hundred One Paise
NinetyOne ) Only
proper reinforcement as per design including necessary
curing etc. complete as directed with necessary timber
shuttering, scaffolding etc. where necessary, complete
as directed. (Shuttering, scaffolding cost will be paid
separately).

(ii) RCC work in slab, abutment cap and above abutment, CuM Rs. 8024.00
pier cap, pedestal, dirt wall etc. in proportion 1:1½:3 ( Rupees Eight Thousand
with hard river shingles of size 6 mm to 20 mm with TwentyFour ) Only
proper reinforcement as per design including necessary
curing, dewatering etc. complete as directed with
necessary timber shuttering, scaffolding etc. where
necessary, complete as directed. (Shuttering, scaffolding
cost will be paid separately).

12.2 IN PROPORTION 1:2:4 (M15)


(A) WITH HARD BROKEN STONE AGGREGATE SIZE 6 MM TO 20 MM
(i) RCC work in slab, abutment cap and above abutment, CuM Rs. 8197.40
pier cap, pedestal, dirt wall etc. in proportion 1:2:4 with ( Rupees Eight Thousand
hard broken stone aggregate of size 6 mm to 20 mm One Hundred NinetySeven
Paise Forty ) Only
with proper reinforcement as per design including
curing etc. with necessary timber shuttering, scaffolding
etc. where necessary, complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(ii) RCC work in slab, abutment cap and above abutment, CuM Rs. 8419.49
pier cap, pedestals, dirt wall etc. in proportion 1:2:4 ( Rupees Eight Thousand
with hard broken stone aggregate of size 6 mm to 20 Four Hundred Nineteen
Paise FortyNine ) Only
mm with proper reinforcement as per design including
necessary curing, dewatering etc. with necessary
timber shuttering, scaffolding etc. where necessary,
complete as directed. (Shuttering, scaffolding cost will
be paid separately).

(B) WITH HARD RIVER SHINGLES SIZE 6 MM TO 20 MM


(i) RCC work in slab, abutment cap and above abutment, CuM Rs. 7079.98
pier cap, pedestal, dirt wall etc. in proportion 1:2:4 with
pier cap, pedestal, dirt wall etc. in proportion 1:2:4 with ( Rupees Seven Thousand
hard river shingles of size 6 mm to 20 mm with proper SeventyNine Paise
NinetyEight ) Only
reinforcement as per design including necessary curing
etc. with necessary timber shuttering, scaffolding etc.
where necessary, complete as directed. (Shuttering,
scaffolding cost will be paid separately).

(ii) RCC work in slab, abutment cap and above abutment, CuM Rs. 7302.07
pier cap, pedestal, dirt wall etc. in proportion 1:2:4 with ( Rupees Seven Thousand
hard river shingles of size 6 mm to 20 mm with proper Three Hundred Two Paise
Seven ) Only
reinforcement as per design including necessary curing,
dewatering etc. with necessary timber shuttering,
scaffolding etc. where necessary, complete as directed.
(Shuttering, scaffolding cost will be paid separately).

SUPPLYING, FITTING, FIXING AND LAYING REINFORCEMENT


12.3 Supplying fitting fixing and laying reinforcement (TATA) Qntl Rs. 8003.00
in position in RCC work including cutting, bending, ( Rupees Eight Thousand
cranking with two piles 0.91 M (20 BWG) annealed wire Three ) Only

hooking tying, complete as directed.

13. BRICK WORK


Sl No Name of Item Unit Rate
13.1 1st class brick work in cement mortar in abutment and
wing wall, parapet wall etc, including racking out joints
and curing etc, complete as directed.

(i) in proportion 1:4 CuM Rs. 8199.45


( Rupees Eight Thousand
One Hundred NinetyNine
Paise FortyFive ) Only

(ii) in proportion 1:3 CuM Rs. 8416.65


( Rupees Eight Thousand
Four Hundred Sixteen Paise
SixtyFive ) Only
********

14. PLASTERING
Sl No Name of Item Unit Rate
14.1 6 mm cement plastering including clearing surface and
curing, complete as directed.

(i) In proportion 1:2 SqM Rs. 155.06


( Rupees One Hundred
FiftyFive Paise Six ) Only

(ii) In proportion 1:3 SqM Rs. 141.33


( Rupees One Hundred
FortyOne Paise ThirtyThree
) Only

14.2 12 mm cement plastering including clearing surface and


curing, complete as directed.

(i) In proportion 1:3 SqM Rs. 201.68


( Rupees Two Hundred One
Paise SixtyEight ) Only

(ii) In proportion 1:4 SqM Rs. 182.49


( Rupees One Hundred
EightyTwo Paise FortyNine
) Only

(iii) In proportion 1:5 SqM Rs. 172.89


( Rupees One Hundred
SeventyTwo Paise
EightyNine ) Only

********
15. BRIDGE
Sl No Name of Item Unit Rate
BAMBOO FOOT BRIDGE
15.1 Construction of 1.20 M wide bamboo foot bridge with RM Rs. 1015.99
100 mm dia bhaluka / barak bamboo posts driven 120 ( Rupees One Thousand
cm to 180 cm under ground 3 nos. of each row being at Fifteen Paise NinetyNine )
Only
3 M apart tied with cane or wire bhaluka / barak
bamboo dham placed over the posts and tied with the
cane or wire bhaluka / barak bamboo strut in each row
both upstream and downstream jati bamboo long girth
closely placed and tied with dham single layers of mat
placed over 75 mm thick brush wood and tied with
bhaluka / barak bamboo rail stand fixed in one side of
the bridge, complete as directed.

SUPPLYING AND DRIVING PILES


15.2 Supplying and driving Sal piles 25 cm to 30 cm dia
dressed to hard wood including marking length in every
30 cm interval and coaltaring 2 coats with best tar
applied hot. (Rate is inclusive of required quantity of the
tar).

(A) WITH PILE ENGINE


(i) Portion of pile actually driven under ground. RM Rs. 5129.60
( Rupees Five Thousand
One Hundred TwentyNine
Paise Sixty ) Only

(ii) Portion of pile to remain above ground. RM Rs. 4496.35


( Rupees Four Thousand
Four Hundred NinetySix
Paise ThirtyFive ) Only

(B) WITH HAND SHAKING

(i) Portion of pile actually driven under ground. RM Rs. 4502.34


( Rupees Four Thousand
Five Hundred Two Paise
ThirtyFour ) Only

(ii) Portion of pile to remain above ground. RM Rs. 4191.88


( Rupees Four Thousand
One Hundred NinetyOne
Paise EightyEight ) Only

15.3 Supplying and driving Azar / Nahar / Nageswar / Zamil


piles 25 cm to 30 cm dia dressed to hard wood including
marking length in every 30 cm interval and coaltaring 2
coats with best tar applied hot. (Rate is inclusive of
required quantity of the tar).

(A) WITH PILE ENGINE


(i) Portion of pile actually driven under ground. RM Rs. 3887.59
( Rupees Three Thousand
Eight Hundred EightySeven
Paise FiftyNine ) Only

(ii) Portion of pile to remain above ground. RM Rs. 3254.34


( Rupees Three Thousand
Two Hundred FiftyFour

(B) WITH HAND SHAKING

(i) Portion of pile actually driven under ground. RM Rs. 3276.50


( Rupees Three Thousand
Two Hundred SeventySix
Paise Fifty ) Only

(ii) Portion of pile to remain above ground. RM Rs. 2966.04


( Rupees Two Thousand
Nine Hundred SixtySix
Paise Four ) Only

WOODEN BRIDGE
15.4 Sal wood work including supplying fitting and fixing CuM Rs. 84362.74
complete with necessary MS nuts bolts, screws etc. and ( Rupees EightyFour
coaltaring 2 coats with best tar applied hot (rate is Thousand Three Hundred
SixtyTwo Paise
inclusive of required quantity of the tar).
SeventyFour ) Only
Undressed in floor planks collars, bracing standard
wheel guard struts and railing, tracking planks (alternate
railing to be done with checking in stage and wing),
runner belts, rail post.

15.5 Supplying fitting and fixing sal timber beam and bearing CuM Rs. 82859.70
beam rectangular in size fitted with MS cleats straps
beam rectangular in size fitted with MS cleats straps ( Rupees EightyTwo
including supplying spikes etc. as necessary and Thousand Eight Hundred
FiftyNine Paise Seventy )
coaltaring 2 coats with best tar applied hot. (Rate is
Only
inclusive of required quantity of the tar).

15.6 Supplying fitting 25 cm to 30 cm dia Sal wood long RM Rs. 2803.88


beam dressed to hardwood including supplying & fixing ( Rupees Two Thousand
with 20 mm dia MS bolts and nuts including coaltaring Eight Hundred Three Paise
EightyEight ) Only
2 coats with best tar, applied hot as directed. (Rate is
inclusive of cost of coaltar).

15.7 Azar / Nahar / Nageswar / Zarul / Cham / Sundi / Gumi CuM Rs. 44248.82
woodwork including supplying, fitting and fixing ( Rupees FortyFour
complete with necessary nut-bolts, nails, screws etc. Thousand Two Hundred
FortyEight Paise EightyTwo
and coaltaring 2 coats with coal tar applied hot as
) Only
directed. (Rate is inclusive of required quantity of the
tar).

15.8 Supplying fitting and fixing Azar / Nahar / Nageswar / CuM Rs. 43435.70
Zarul sawn timber beam and bearing beam rectangular ( Rupees FortyThree
in size fitted with MS cleats, straps including spikes etc. Thousand Four Hundred
ThirtyFive Paise Seventy )
as necessary and coaltaring 2 coats with best tar applied
Only
hot as directed. (Rate is inclusive of required quantity of
the tar).

15.9 Supplying fitting 25 cm to 30 cm dia Azar / Nahar / RM Rs. 2428.12


Nageswar / Zarul wood long beam dressed to hard ( Rupees Two Thousand
wood including supplying & fixing with 20 mm dia MS Four Hundred TwentyEight
Paise Twelve ) Only
bolts and nuts including coaltaring 2 coats with best
tar, applied hot as directed.

15.10 Supplying fitting and fixing RCC guard post of size 15 cm Post Rs. 1352.04
x 15 cm and 150 cm long of which 75 cm below ground
x 15 cm and 150 cm long of which 75 cm below ground ( Rupees One Thousand
including square base of size 45 cm x 45 cm x 15 cm Three Hundred FiftyTwo
Paise Four ) Only
with 4 nos. of 12 mm dia TS as main reinforcement and
6 mm dia stirrups at 30 cm c/c apart tying in position
with black wire with cement concrete in proportion
1:2:4 with broken stone aggregate of size 6 mm to 20
mm including centering, shuttering and curing with 6
mm thick cement plastering in proportion 1:3 painted
black & white alternatively in 23 cm stripe upto 75 cm
from top keeping necessary goods etc. as per design
and direction, complete as directed.

15.11 Supplying fitting and fixing 20 cm to 25 cm dia jungle Post Rs. 1197.66
wood dressed guard post 150 cm long 75 cm above ( Rupees One Thousand
ground and 72 cm to be driven under ground fitted with One Hundred NinetySeven
Paise SixtySix ) Only
a horizontal struts size 0.05 M x 0.05 M x 0.55 M long at
bottom with necessary nails including coaltaring 1 (one)
coat the portion below ground and painting black &
white 1 (one) coat alternately the portion above
ground.

15.12 Screwing & joining of piles 25 cm to 30 cm dia dressed Joint Rs. 1796.61
to hard wood 90 cm in length including supplying fitting ( Rupees One Thousand
and fixing with 2 nos. of 50 mm x 10 mm MS / FI clamps Seven Hundred NinetySix
Paise SixtyOne ) Only
and 16 mm dia MS bolts and nuts etc, complete as
directed.

15.13 Labour for taking out old piles of the bridge and Pile Rs. 1906.91
stacking them at suitable places as directed. ( Rupees One Thousand
Nine Hundred Six Paise
NinetyOne ) Only

15.14 Labour for driven piles 25 cm to 30 cm dia dressed to


hard wood making length in every 30 cm including
coaltaring with 2 coats with best tar applied hot
including providing necessary scaffolding or staging as
necessary. (Rate is inclusive of required quantity of tar).

(A) With Pile Engine

(i) Portion of pile actually driven under ground. RM Rs. 1433.60


( Rupees One Thousand
Four Hundred ThirtyThree
Paise Sixty ) Only
(ii) Portion of pile to remain above ground. RM Rs. 800.35
( Rupees Eight Hundred
Paise ThirtyFive ) Only

(B) With Hand Shaking

(i) Portion of pile actually driven under ground. RM Rs. 806.34


( Rupees Eight Hundred Six
Paise ThirtyFour ) Only

(ii) Portion of pile to remain above ground. RM Rs. 495.88


( Rupees Four Hundred
NinetyFive Paise
EightyEight ) Only

15.15 Labour for fitting & fixing RS joist, beam, CI saddle in RM Rs. 872.18
position including necessary scaffolding, cutting them to ( Rupees Eight Hundred
required size drilling holes and supply and fixing with SeventyTwo Paise Eighteen
) Only
necessary bolt, nuts, painting 2 coats, complete as
directed. (Rate inclusive. of cost of tar and steel paint).

15.16 Labour for fitting & fixing old RS joist, beam & old CI RM Rs. 766.50
saddle in position including necessary scaffolding and ( Rupees Seven Hundred
fixing with necessary cutting them to required size SixtySix Paise Fifty ) Only
drilling holes and supplying and fixing with necessary
bolts, nuts, painting 2 coats, complete as directed. (Rate
inclusive of cost of tar and steel paint).

15.17 Labour for end fitting MS / FI straps of cleats etc. in Qntl. Rs. 2854.39
position including drilling holes and carrying the same ( Rupees Two Thousand
to site. Eight Hundred FiftyFour
Paise ThirtyNine ) Only

15.18 Labour charge for making 0.5 M x 0.50 M x 0.30 M size No. Rs. 585.66
"U" shape MS flat iron strap from 150 mm x 12 mm size ( Rupees Five Hundred
MS flat including providing 10 nos of holes and fitted EightyFive Paise SixtySix )
Only
with 0.35 M long 20 mm dia MS bolts including fitting
lightly with bearing beam pits and RS beam etc,
complete as directed. (Rate inclusive of the cost of MS
bolts and nuts required).
15.19 Labour for fitting and fixing wood work including RM Rs. 2978.67
supplying and fixing with new bolts, nuts and spikes and ( Rupees Two Thousand
coaltaring the coats applied hot. (Rate inclusive the cost Nine Hundred SeventyEight
Paise SixtySeven ) Only
of coaltar).

15.20 Labour for refitting wood work including sizing RM Rs. 2712.56
supplying and fixing necessary MS bolts, nuts and spikes ( Rupees Two Thousand
and coaltaring 1 (one) coat applied hot as directed. Seven Hundred Twelve
Paise FiftySix ) Only
(Rate inclusive the cost of coaltar).

15.21 Labour for fitting & fixing 25 cm to 30 cm dia long beam RM Rs. 456.92
including supplying and fixing necessary MS bolts, nuts ( Rupees Four Hundred
etc. and coaltaring the 2 coats, complete as directed. FiftySix Paise NinetyTwo )
Only
(Rate inclusive the cost of coaltar).

15.22 Labour for refitting & refixing 25 cm to 30 cm dia long RM Rs. 503.21
beam including supplying and fixing necessary MS bolts, ( Rupees Five Hundred
nuts etc. and coaltaring 1(one) coat applied as directed. Three Paise TwentyOne )
Only
(Rate inclusive the cost of coaltar).

15.23 Labour for taking out work of the bridge and refitting SqM Rs. 3303.76
the same including supplying and fixing with necessary ( Rupees Three Thousand
new MS bolts, nuts and spikes and nails etc. and Three Hundred Three Paise
SeventySix ) Only
coaltaring the 1 (one) coat applied hot as directed. (Rate
inclusive. the cost of coaltar).

15.24 PAINTING WORKS IN BRIDGE


(A) Clearing and painting work with the white paint SqM Rs. 52.91
: 1 (one) coat. ( Rupees FiftyTwo Paise
NinetyOne ) Only

(B) Clearing and coaltaring wood works SqM Rs. 28.64


: 1 (one) coat. ( Rupees TwentyEight Paise
SixtyFour ) Only

( C) Clearing and painting iron works with aluminium paint - SqM Rs. 68.93
1 (one) coat. ( Rupees SixtyEight Paise
NinetyThree ) Only
********

16. CULVERT
Sl No Name of Item Unit Rate
16.1 Cement pointing including racking out joints and curing
etc, complete as directed.

(i) In proportion 1:3 SqM Rs. 129.25


( Rupees One Hundred
TwentyNine Paise
TwentyFive ) Only

(ii) In proportion 1:2 SqM Rs. 140.80


( Rupees One Hundred
Forty Paise Eighty ) Only

LABOUR FOR JOINING HUME PIPE


16.2 Labour for fitting and fixing hume pipe in position with
collars including joining the cement mortar in
proportion 1:3 and curing, including carrying the same
from godown to site and complete as directed.

(i) For 30 cm to 60 cm dia RM Rs. 211.45


( Rupees Two Hundred
Eleven Paise FortyFive )
Only

(ii) For 60 cm to 90 cm dia RM Rs. 318.87


( Rupees Three Hundred
Eighteen Paise EightySeven
) Only

(iii) For 90 cm to 120 cm dia RM Rs. 511.51


( Rupees Five Hundred
Eleven Paise FiftyOne )
Only

********

17. R C C WATER TROUGH


Sl No Name of Item Unit Rate
17.1 Construction and manufacturing of CC lined precast "U"
shaped section in proportion 1:2:4 with hard broken
stone aggregate of size 6 mm to 20 mm including
supplying expanded 18 gauge metal, horizontal
reinforcement and vibrating, carrying to stack yard,
curing, etc, complete as directed.

(i) For 1 cusec RM Rs. 1579.78


( Rupees One Thousand
Five Hundred SeventyNine
Paise SeventyEight ) Only

(ii) For 1.5 cusec RM Rs. 1987.75


( Rupees One Thousand
Nine Hundred EightySeven
Paise SeventyFive ) Only

(iii) For 2 cusec RM Rs. 2235.61


( Rupees Two Thousand
Two Hundred ThirtyFive
Paise SixtyOne ) Only

17.2 Labour charge for laying and fixing RCC "U" shaped RM Rs. 304.63
section in proper position and grade as per design
section in proper position and grade as per design ( Rupees Three Hundred
drawing and specification including fitting and joints Four Paise SixtyThree )
Only
voids as of main concrete on top inside to wall finished
with 12 mm thick cement mortar in proportion 1:3
including curing and local carriage, etc, complete as
directed.

********

18. CANAL WORK


Sl No Name of Item Unit Rate
18.1 Providing 50 mm wide expansion joints with bituminous RM Rs. 261.95
compound mixed with coarse sand for canal work at an ( Rupees Two Hundred
interval of 10 M apart including laying, fitting the SixtyOne Paise NinetyFive )
Only
compound in proper position, etc, complete as directed.

18.2 Soling in foundation at all levels including filling SqM Rs. 437.61
intersides, ramming etc complete as directed and of ( Rupees Four Hundred
specified thickness with 9 cm brick on flat including ThirtySeven Paise SixtyOne
) Only
sand packing.

18.3 Labour for preparation of subgrade of lined canal


section as per design drawing and grade by ramming
and rolled to level and according to the required cross
section of the typical lined canal including cutting, filling
the existing canal section where necessary compacting
the earth in layers in not more than 15 cm thick to form
a firm compacted bed & side for lining including
watering to obtain required moisture content where
necessary etc, complete as directed.

(i) For ordinary soil SqM Rs. 37.41


( Rupees ThirtySeven Paise
FortyOne ) Only

(ii) For sandy soil SqM Rs. 55.87


( Rupees FiftyFive Paise
EightySeven ) Only

18.4 CC Work in lined canal in prop 1:2:4 with river shingles CuM Rs. 6314.93
of size 6 mm to 20 mm free from dust, dirt and other ( Rupees Six Thousand
foreign materials conforming to IS 2116-1965 and 542- Three Hundred Fourteen
Paise NinetyThree ) Only
1962 as specified by the department, water used for
mixing the mortar should be free from all impurities
including laying the concrete over the subgrade,
moistened thoroughly by hand placing / mechanical
placing in canal of not more than 3 M sides with
suitable joints in between including providing bed
sleepers (cast-in-situ or pre cast) under joints in
between including providing all sealing materials as per
design and drawing before laying concrete including
finishing the surface smooth, clean of all impurities with
curing the bed by manual labours and side by sprinkling
for at least 28 days etc, complete as directed. (Proper
arrangement for obtaining clean water should be made at
site).

19. PVC DISTRIBUTION SYSTEM


Sl No Name of Item Unit Rate
19.1 Supplying, fitting, fixing PVC pipes (IS 12818, 6 kg/cm2 ),
joining pipes with relevant cement, levelling, testing
leakages etc, complete as directed. (Cost of E/W
foundation trenches will be paid separately).

(i) For 110 mm dia RM Rs. 523.56


( Rupees Five Hundred
TwentyThree Paise FiftySix
) Only

(ii) For 160 mm dia RM Rs. 1070.47


( Rupees One Thousand
Seventy Paise FortySeven )
Only

(iii) For 200 mm dia RM Rs. 1793.59


( Rupees One Thousand
Seven Hundred
NinetyThree Paise
FiftyNine ) Only
19.2 Supplying, fitting, fixing PVC equal tee joining with pipes
with solvent cement testing leakages etc, complete as
directed.

(i) Size : 110 mm x 110 mm x 110 mm No. Rs. 669.03


( Rupees Six Hundred
SixtyNine Paise Three )
Only

(ii) Size : 160 mm x 160 mm x 160 mm No. Rs. 1469.83


( Rupees One Thousand
Four Hundred SixtyNine
Paise EightyThree ) Only

(iii) Size : 200 mm x 200 mm x 200 mm No. Rs. 3933.83


( Rupees Three Thousand
Nine Hundred ThirtyThree
Paise EightyThree ) Only

19.3 Supplying, fitting, fixing PVC unequal tee joining with


pipes with solvent cement, testing leakages etc,
complete as directed.

(i) Size : 200 mm x 200 mm x 110 mm No. Rs. 4780.21


( Rupees Four Thousand
Seven Hundred Eighty
Paise TwentyOne ) Only

(ii) Size : 200 mm x 200 mm x 160 mm No. Rs. 3434.87


( Rupees Three Thousand
Four Hundred ThirtyFour
Paise EightySeven ) Only

(iii) Size : 160 mm x 160 mm x 110 mm No. Rs. 1001.67


( Rupees One Thousand
One Paise SixtySeven ) Only

19.4 Supplying, fitting, fixing PVC reducer joining with pipes


with solvent cement, testing leakages etc, complete as
directed.

(i) Size : 160 mm x 110 mm No. Rs. 478.56


( Rupees Four Hundred
SeventyEight Paise FiftySix
) Only

(ii) Size : 200 mm x 110 mm No. Rs. 928.24


( Rupees Nine Hundred
TwentyEight Paise
TwentyFour ) Only

(iii) Size : 200 mm x 160 mm No. Rs. 946.72


( Rupees Nine Hundred
FortySix Paise SeventyTwo
) Only

19.5 Supplying, fitting, fixing PVC bend pipe size joining with
pipes with solvent cement, testing leakages etc,
complete as directed.

(i) For 110 mm / 900 No. Rs. 606.30


( Rupees Six Hundred Six
Paise Thirty ) Only

(ii) For 160 mm / 900 No. Rs. 1345.50


( Rupees One Thousand
Three Hundred FortyFive
Paise Fifty ) Only

(iii) For 200 mm / 900 No. Rs. 2368.06


( Rupees Two Thousand
Three Hundred SixtyEight
Paise Six ) Only

19.6 Supplying, fitting, fixing 110 mm dia NTP valve at the No. Rs. 2812.53
top of PVC rising pipe of spout chamber as per ( Rupees Two Thousand
specification including local carriage, complete as Eight Hundred Twelve
Paise FiftyThree ) Only
directed.

19.7 Supplying, fitting, fixing 110 mm dia PVC rising pipe No. Rs. 691.71
from the toe of main line including local carriage, ( Rupees Six Hundred
testing leakage etc, complete as directed. NinetyOne Paise
SeventyOne ) Only

19.8(A) Supplying, fitting, fixing of PVC threaded coupler (FTA) No. Rs. 394.12
of size 110 mm dia fitting with solvent cement as per
of size 110 mm dia fitting with solvent cement as per ( Rupees Three Hundred
specification including local carriage, testing leakage NinetyFour Paise Twelve )
Only
etc, complete as directed.

19.8(B) Supplying, fitting, fixing of PVC threaded coupler fitted No. Rs. 496.55
with flange (MTA) of size 110 mm dia fitting with ( Rupees Four Hundred
solvent cement as per specification including local NinetySix Paise FiftyFive )
Only
carriage, testing leakage etc, complete as directed.

19.9 Supplying, fitting, fixing, joining of PVC end cap fitting


with solvent cement as per specification including local
carriage, testing leakage etc, complete as directed.

(i) For 110 mm dia No. Rs. 186.11


( Rupees One Hundred
EightySix Paise Eleven )
Only

(ii) For 160 mm dia No. Rs. 319.04


( Rupees Three Hundred
Nineteen Paise Four ) Only

(iii) For 200 mm dia No. Rs. 609.54


( Rupees Six Hundred Nine
Paise FiftyFour ) Only

19.10 Removing of old PVC pipes and relaying, fitting, fixing, RM Rs. 275.18
pipes in position after repairing and clearing debris, ( Rupees Two Hundred
testing leakage including fitting with solvent cement etc, SeventyFive Paise Eighteen
) Only
complete as directed. (Cost of any additional pipes and
accessories will be paid separately).

********

20. SHEET PILING


WILL BE SUPPLIED LATER

21. PROTECTION WORK


Sl No Name of Item Unit Rate
21.1 LABOUR CHARGE FOR BANK PITCHING
(A) Labour charge for pitching with one man size boulder CuM Rs. 438.59
including dressing and ramming the seat to proper size ( Rupees Four Hundred
and slope, pitching etc. with local carriage of boulders ThirtyEight Paise FiftyNine )
Only
from a distance of 60 M with lift upto 3 M, complete as
directed.

(B) Labour charge for spreading of hard river gravel or CuM Rs. 257.49
broken stone of size 13 mm to 38 mm to the required ( Rupees Two Hundred
thickness including dressing and ramming the seat FiftySeven Paise FortyNine
) Only
before laying the materials as directed with a lead upto
30 M and lift upto 1.5 M, complete as directed.

21.2 CONSTRUCTION OF BOULDER SAUSAGE


(A) Construction of 1.00 M dia boulder sausage including
supplying of materials with 25 cm to 30 cm size
boulders collecting from a lead of 25 KM encased in 15
cm mesh of 8G hexagonal wire netting and filling the
voids between the boulders with stone not exceeding
18 cm in size tied with 8G galvanized tying wire at 30 cm
apart, laid in position as directed including necessary
local carriage of materials, paying necessary forest
royalty including providing 1 (one) no. of jati bamboo
horizontal runner along the top of the sausage with
vertical bhaluka bamboo post 1.20 M apart driven at
least 0.60 M below ground and tying with sausage etc,
all complete as directed.
(i) With blasted boulder RM Rs. 2613.75
( Rupees Two Thousand Six
Hundred Thirteen Paise
SeventyFive ) Only

(ii) With river boulder RM Rs. 2458.96


( Rupees Two Thousand
Four Hundred FiftyEight
Paise NinetySix ) Only

(iii) Labour charge for making 1.00 M dia boulder sausage RM Rs. 382.74
( Rupees Three Hundred
EightyTwo Paise
SeventyFour ) Only
(B) Construction of 1.00 M square boulder sausage
including supplying of materials with 25 cm to 30 cm
size boulders collecting from a lead of 25 KM encased in
15 cm mesh of 8G hexagonal wire netting and filling the
voids between the boulders with stone not exceeding
18 cm in size tied with 8G galvanized tying wire at 30 cm
apart, laid in position as directed including necessary
local carriage of materials, paying necessary forest
royalty including providing 1 (one) no. of jati bamboo
horizontal runner along the top of the sausage with
vertical bhaluka bamboo post 1.20 M apart driven at
least 0.60 M below ground and tying with sausage etc,
all complete as directed.

(i) With blasted boulder RM Rs. 3281.58


( Rupees Three Thousand
Two Hundred EightyOne
Paise FiftyEight ) Only

(ii) With river boulder RM Rs. 3084.46


( Rupees Three Thousand
EightyFour Paise FortySix )
Only

( C) Construction of 1.50 M x 1.00 M rectangular boulder


sausage including supplying of materials with 25 cm to
30 cm size boulders collecting from a lead of 25 KM
encased in 15 cm mesh of 8G hexagonal wire netting
and filling the voids between the boulders with stone
not exceeding 18 cm in size tied with 8G galvanized
tying wire at 30 cm apart, laid in position as directed
including necessary local carriage of materials, paying
necessary forest royalty including providing 1 (one) no.
of jati bamboo horizontal runner along the top of the
sausage with vertical bhaluka bamboo post 1.20 M
apart driven at least 0.60 M below ground and tying
with sausage etc, all complete as directed.
(i) With blasted boulder RM Rs. 4646.19
( Rupees Four Thousand Six
Hundred FortySix Paise
Nineteen ) Only

(ii) With river boulder RM Rs. 4350.51


( Rupees Four Thousand
Three Hundred Fifty Paise
FiftyOne ) Only

(D) Construction of 2.00 M x 1.00 M rectangular boulder


sausage including supplying of materials with 25 cm to
30 cm size boulders collecting from a lead of 25 KM
encased in 15 cm mesh of 8G hexagonal wire netting
and filling the voids between the boulders with stone
not exceeding 18 cm in size tied with 8G galvanized
tying wire at 30 cm apart, laid in position as directed
including necessary local carriage of materials, paying
necessary forest royalty including providing 1 (one) no.
of jati bamboo horizontal runner along the top of the
sausage with vertical bhaluka bamboo post 1.20 M
apart driven at least 0.60 M below ground and tying
with sausage etc, all complete as directed.

(i) With blasted boulder RM Rs. 6010.80


( Rupees Six Thousand Ten
Paise Eighty ) Only

(ii) With river boulder RM Rs. 5616.56


( Rupees Five Thousand Six
Hundred Sixteen Paise
FiftySix ) Only

21.3 BAMBOO SPUR


(A) A' type bamboo spur with 75 mm dia whole jati bamboo RM Rs. 730.25
placed at 23 cm c/c driven 90 cm below ground and ( Rupees Seven Hundred
120 cm to 150 cm above ground tied with jati bamboo Thirty Paise TwentyFive )
Only
kamies on either sides at 45 cm apart horizontally with
galvanized wire etc, complete as directed.
(B) A' type bamboo spur with 75 mm to 100 mm dia whole RM Rs. 753.98
bhaluka bamboo placed at 23 cm c/c driven 90 cm ( Rupees Seven Hundred
below ground and 120 cm to 150 cm above ground tied FiftyThree Paise
NinetyEight ) Only
with jati bamboo kamies on either sides at 45 cm apart
horizontally with galvanized wire etc, complete as
directed.
21.4 BAMBOO PORCUPINE
Construction and launching of bamboo porcupine made Each Rs. 2668.90
of 12 nos. of 2 M long whole matured Bhaluka bamboo ( Rupees Two Thousand Six
of size 7.5 cm dia making 0.50 M x 0.50 M x 0.50 M size Hundred SixtyEight Paise
Ninety ) Only
cube in middle and filling, fixing cross bhaluka bamboo
2 M long, 8 nos. of four sides of the cube as directed
and nailing with patent nails of 30 cm long total 30 nos.
at each points and joints as directed including bending
the edges of the patents nails, tying each end of the
joints as directed with 12 G galvanized wire closing the
sides of the cubes with half bhaluka bamboo at 15 cm
apart placed from the inside of main members on all
sides including nailing with nails and bending the
protruding edge, tying with 18 G wire making holes in
each bamboo members with chisel filling the cubes with
boulder including local carriage to the site and
launching properly in river slope etc, complete as
directed.

21.5 BAMBOO PALLASIDING


(A) Construction of whole bamboo single pallasiding with RM Rs. 805.20
matured bhaluka bamboo post 7.5 cm to 10 cm dia 5 ( Rupees Eight Hundred
cm apart 1.5 M to 1.8 M above ground and 1 M to 1.2 Five Paise Twenty ) Only
M below ground with jati bamboo struts placed 1.2 M
to 1.5 M apart tied with galvanized wire with 16 G to 18
G complete with 3 rows of horizontal half jati bamboo
kamies, complete as directed.

(B) Construction of whole bamboo single pallasiding with RM Rs. 902.56


matured jati bamboo post of 6 cm to 7.5 cm dia fixed ( Rupees Nine Hundred
15 cm clear apart 1.2 M to 1.5 M above ground and 1 M Two Paise FiftySix ) Only
to 1.20 M below ground with jati bamboo struts placed
1.2 M to 1.5 M apart tied with galvanized wire with 16 G
to 18 G with three rows of horizontal half jati bamboo
double kamies fixed with 16 G to 18 G, complete as
directed.

21.6 LAYING CEMENT BAGS


(A)(i) Supply and laying of cement bags filled with sand/ earth Bag Rs. 33.08
(as locally available) including stitching the mouth, ( Rupees ThirtyThree Paise
laying, fixing in position as directed complete with Eight ) Only
supply of bags, sutlies etc, all complete as directed.

(ii) Labour charge for filling the cement bags with sand / Bag Rs. 18.30
earth (as locally available) including stitching the mouth, ( Rupees Eighteen Paise
laying the filled bags in position etc, all complete as Thirty ) Only
directed.

(B) Supplying and launching of trees branches of 50 to 75 Bundle Rs. 318.56


mm dia and 2.5 M to 3.0 M long with green foliage tied ( Rupees Three Hundred
in bundles (4 nos in a bundle) with coir string securely Eighteen Paise FiftySix )
Only
anchored to a strut of matured jati bamboo peg driven
down atleast 10 cm and keeping 1.00 M above at a
minimum safe distance of 7.50 M from the river bank
with 8 G galvanized tying wire, tying the bundle with 2
nos earth / sand (as locally available) filled cement bags
tied with coir string including payment of materials.

********

22. DISMANTLING
Sl No Name of Item Unit Rate

22.1 For Bridge


Labour for dismantling all member of the bridge (except RM Rs. 665.93
piles) and stacking them at suitable place as directed. ( Rupees Six Hundred
(All members will be under custody of the Contractors SixtyFive Paise NinetyThree
) Only
till taken over by the Department).

22.2 For Culvert


(A) Dismantling the existing culvert including clearing and
removing the dismantled materials to a safe place and
stacking the serviceable material at a suitable place as
directed.
(i) In Brick arch culvert CuM Rs. 848.64
( Rupees Eight Hundred
FortyEight Paise SixtyFour )
Only

(ii) In RCC slab culvert. CuM Rs. 1215.16


( Rupees One Thousand
Two Hundred Fifteen Paise
Sixteen ) Only

(iii) In ARMCO earthen pipe culvert. RM Rs. 426.07


( Rupees Four Hundred
TwentySix Paise Seven )
Only

(B) Dismantling the CC abutment wall and wing wall of RM Rs. 344.14
upper portion of ground level including removing the ( Rupees Three Hundred
debris from the site of works as directed. FortyFour Paise Fourteen )
Only

22.3 For Hume Pipe


Labour charge for dismantling / replacing the old No. Rs. 1421.73
damaged hume pipe of 1200 mm dia of canal structure ( Rupees One Thousand
and carriage of the same upto a lead of 30 M and lift of Four Hundred TwentyOne
Paise SeventyThree ) Only
2.5 M and depositing the same in a safe distance as
directed.

22.4 For Boulder Sausage


Dismantling of old serviciable hexagonal wire netting CuM Rs. 438.35
encased boulder sausage including hammering digging ( Rupees Four Hundred
carrying, unlifting the boulders including carriage upto ThirtyEight Paise ThirtyFive
) Only
60 M lead and upto 3.60 M lift including stacking in
suitable and measurable stacks etc, complete as
directed.

22.5 For Canal


(A) Labour charge for dismantling of old CC works of canal
structures and carriage the spoils and depositing the
same in a safe distance as directed.

(i) Carriage up to lead of 60 M and lift upto 9 M CuM Rs. 2625.39


(For Major & Medium works) ( Rupees Two Thousand Six
Hundred TwentyFive Paise
ThirtyNine ) Only
(ii) Carriage up to lead of 30 M and lift upto 1.50 M CuM Rs. 1694.00
(For Minor works) ( Rupees One Thousand Six
Hundred NinetyFour ) Only

(B) Labour cost for dismantling of old CC canal lining and


carriage of the materials and depositing the same in a
safe distance as directed.
(i) Carriage up to lead of 60 M and lift upto 9 M SqM Rs. 393.50
(For Major & Medium works) ( Rupees Three Hundred
NinetyThree Paise Fifty )
Only

(ii) Carriage up to lead of 30 M and lift upto 1.50 M SqM Rs. 207.22
(For Minor works) ( Rupees Two Hundred
Seven Paise TwentyTwo )
Only

22.6 For Building


(A) Dismantling of pucca flooring including sorting, SqM Rs. 49.03
screening, carriage and stacking serviceable materials at ( Rupees FortyNine Paise
a safe place as directed. Three ) Only

(B) Dismantaling of corrugated sheet roofing carefully and SqM Rs. 45.45
stacking materials including all local carriage as directed. ( Rupees FortyFive Paise
FortyFive ) Only

********

23. MISCELLANEOUS
Sl No Name of Item Unit Rate
23.1 Making and maintaining sub-way 3 M wide including RM Rs. 382.17
providing barrier and sign board and lamp etc. ( Rupees Three Hundred
EightyTwo Paise Seventeen
) Only

23.2 Providing weep holes with 50 mm dia GI pipes of No. Rs. 2677.22
required length and depth fitted with vertical non
required length and depth fitted with vertical non ( Rupees Two Thousand Six
return valve (50 mm) of brass inside including cost of Hundred SeventySeven
Paise TwentyTwo ) Only
making filter of size 0.6 M x 0.6 M x 0.6 M fitted with
graded filter media at back side and covering the back
side with MS wire netting in the abutment, face wall
wall of Head Work including shuttering for providing
space at the time of casting cement concrete including
supplying fitting bend, nipple, etc, complete as directed.

23.3 Providing 75 mm dia. Weep Holes including supplying No. Rs. 241.67
and fixing 75 mm dia PVC pipe in weep holes, complete ( Rupees Two Hundred
as directed. FortyOne Paise SixtySeven
) Only

23.4 Preparing / making level the ground surface for layout SqM Rs. 72.32
of Headwork / structures for fixing the required axis line ( Rupees SeventyTwo Paise
by cutting the high land and filling and levelling the low ThirtyTwo ) Only
land where necessary etc, complete as directed.

23.5 Labour charge for spreading of hard river gravel or CuM Rs. 335.10
broken stone of size 13 mm to 38 mm to the required ( Rupees Three Hundred
thickness including dressing and ramming the seat ThirtyFive Paise Ten ) Only
before laying the materials as directed with a lead upto
30 M and lift upto 1.5 M, complete as directed.

23.6 Construction of temporary shed with 0.30 M high earth SqM Rs. 2445.21
plinth and floor with bhaluka bamboo post of size 100 ( Rupees Two Thousand
mm to 120 mm dia driven at least 0.75 M below GL and Four Hundred FortyFive
Paise TwentyOne ) Only
2.75 M above plinth split jati bamboo walling tied with 3
lines of half bamboo (jati) kamies with 0.63 mm thick
GCI sheet roofing over jati bamboo framing with whole
bamboo struts fitted with post plate of bamboo purlins
tied with galvanized wire, coir string including providing
single dharamat jhap doors and windows, complete as
directed.

23.7 Supplying of quick setting concrete admixture of Litre Rs. 212.32


specified brand including loading and unloading, ( Rupees Two Hundred
carriage to the work site, complete as directed. Twelve Paise ThirtyTwo )
Only

23.8 Neat cement finishing 3 mm thick with cement slurry SqM Rs. 144.02
prepared by mixing 27.50 Kg of fresh cement in
prepared by mixing 27.50 Kg of fresh cement in ( Rupees One Hundred
appropriate quantity of clean water to cover 10 (ten) FortyFour Paise Two ) Only
SqM of work area and to give a smooth and hard
finishing including rounding corners, brooming, curing
etc, complete as directed.

23.9 Supplying 1 1/2" dia GI pipe for hand railing including RM Rs. 394.02
fitting & fixing the same in position etc, complete as ( Rupees Three Hundred
directed. NinetyFour Paise Two )
Only

********

24. BUILDING
Sl No Name of Item Unit Rate
24.1 Earthwork in filing in plinth in layers not more than 15 CuM Rs. 231.62
cm thick including necessary carriage, watering and ( Rupees Two Hundred
ramming etc, complete as directed and specified . Head ThirtyOne Paise SixtyTwo )
Only
load. (Lead up to 90 M and lift 2 M).

24.2 Shuttering and shoring the earth at different levels in SqM Rs. 125.95
foundation where necessary with required prop, struts, ( Rupees One Hundred
planks, timber, nails etc, complete as directed and TwentyFive Paise
NinetyFive ) Only
specified. (Measurement to be taken in the face area
timbered).

24.3 CC in RCC work as specified and directed and including CuM Rs. 8323.06
curing etc. (reinforcemcnt and shuttering will be
curing etc. (reinforcemcnt and shuttering will be ( Rupees Eight Thousand
measured and paid separately), the fine aggregate shall Three Hundred
TwentyThree Paise Six )
be approved clear river sand of coarse variety and shall
Only
be 5 mm downward and not to be pass through a 25 IS
sieve (width of apparatus is 0.25 mm) the coarse
aggregate shall be cubical, hard perfectly clean and free
from clay and adherents impurities and chemically inter
broken stone chips of approved quantity and shall pass
through 19 mm mesh without squeezing and be
retained on 15 mm mesh. The fine and coarse aggregate
shall be well graded and evenly distributed between the
limits and mixes shall be made with adequate quantity
of clean water required to have the strength as
specified in IS Code.

The rate is inclusive of cost of cube test before


starting the work ie. 3 nos. per each lot of cement as
directed and specified.
In the ties and plinth beam in foundation shaped
testing of column pile cap base slab retaining walls of
septic tank inspection pit intercepting trap yard gully
including formation of trap slap of septic tank etc. upto
plinth level in prop 1:2:4.

24.4 PCC FLOOR BASE


(A) Plain cement concrete floor base of thickness 38 mm in SqM Rs. 336.04
proportion 1:3:6 with coarse aggregate of size 6 mm to ( Rupees Three Hundred
20 mm including curing etc, complete as specified. ThirtySix Paise Four ) Only

(B) PIain cement concrete floor base of thickness 63 mm in SqM Rs. 485.25
proportion 1:3:6 with coarse aggregate of size 13 mm to ( Rupees Four Hundred
38 mm including curing etc, complete as specified. EightyFive Paise
TwentyFive ) Only

(C) PIain cement concrete floor base of thickness 100 mm SqM Rs. 656.33
in proportion 1:3:6 with coarse aggregate of size 13 ( Rupees Six Hundred
mm to 38 mm including curing etc, complete as FiftySix Paise ThirtyThree )
Only
specified.

24.5 DAMP PROOF COURSE (DPC)


(A) Providing and laying 2 cm thick damp proof course SqM Rs. 217.69
(DPC) with cement motor in proportion 1:2 with ( Rupees Two Hundred
approved damp proofing compound. Seventeen Paise SixtyNine )
Only
(B) Providing and laying 25 mm thick artificial stone damp SqM Rs. 294.74
proof course as specified in proportion 1:2:4 with ( Rupees Two Hundred
broken stone chips with "CICO' or other similar NinetyFour Paise
SeventyFour ) Only
approved damp proofing compound.

SOLING ITEM
24.6 Soling in foundation and under floor including filling
interstices, ramming etc, complete as directed and as
specified thickness.

(i) 9 cm brick on flat including sand packing. SqM Rs. 502.08


( Rupees Five Hundred Two
Paise Eight ) Only

(ii) 10 cm broken stone (13 mm to 38 mm). SqM Rs. 376.54


( Rupees Three Hundred
SeventySix Paise FiftyFour )
Only

24.7 Pucca floor with 1st class brick flat soling with sand and
cement packed in proportion 1:5 and cement plastering
in proportion 1:2 including toweling, finishing and
curing, complete as directed.

(i) 6 mm thick SqM Rs. 742.30


( Rupees Seven Hundred
FortyTwo Paise Thirty )
Only

(ii) 12 mm thick SqM Rs. 797.53


( Rupees Seven Hundred
NinetySeven Paise
FiftyThree ) Only

24.8 BRICK WORK


(A) Brick work in cement mortar with 1st class brick as
directed in foundation, retaining walls, plinth & steps
including racking out joints & curing :

(i) In proportion 1:3 CuM Rs. 8225.69


( Rupees Eight Thousand
Two Hundred TwentyFive
Paise SixtyNine ) Only

(ii) In proportion 1:4 CuM Rs. 8008.49


( Rupees Eight Thousand
Eight Paise FortyNine )
Only

(B) Brick work in cement mortar with 1st class brick as


directed above plinth level upto 1st floor level including
racking out joints, curing and necessary scaffolding.

(i) In proportion 1:3 CuM Rs. 8244.17


( Rupees Eight Thousand
Two Hundred FortyFour
Paise Seventeen ) Only

(ii) In proportion 1:4 CuM Rs. 8026.97


( Rupees Eight Thousand
TwentySix Paise
NinetySeven ) Only

(iii) In proportion 1:5 CuM Rs. 7850.18


( Rupees Seven Thousand
Eight Hundred Fifty Paise
Eighteen ) Only

24.9 Clearing and white washing : two coats SqM Rs. 14.20
( Rupees Fourteen Paise
Twenty ) Only
24.10 125 mm thick 1st class brick nogged wall in cement
mortar in proportion 1:4 including racking out joints
curing etc, complete as directed.

(i) 75 mm thick SqM Rs. 579.47


( Rupees Five Hundred
SeventyNine Paise
FortySeven ) Only

(ii) 125 mm thick SqM Rs. 903.89


( Rupees Nine Hundred
Three Paise EightyNine )
Only

24.11 75 mm thick reinforced brick wall in proportion 1:5 SqM Rs. 776.93
reinforced with one line of 6 mm dia MS rod placed in
reinforced with one line of 6 mm dia MS rod placed in ( Rupees Seven Hundred
36 mm thick concrete course in proportion 1:2:4 at SeventySix Paise
NinetyThree ) Only
every 3rd course, complete as directed.

24.12 BAMBOO WALL


(A) 50 mm thick single wattle / split Jati bamboo wall SqM Rs. 421.16
including mud plastering with trowel finished white ( Rupees Four Hundred
washed 3 (three) coats on both sides, complete as TwentyOne Paise Sixteen )
Only
directed. (Grooved walling).

(B) 50 mm thick single wattle or split Jati bamboo wall SqM Rs. 627.49
including trowel finished cement plastering in ( Rupees Six Hundred
proportion 1:8 white washing 3 (three) coats on both TwentySeven Paise
FortyNine ) Only
sides, complete as directed. (Grooved walling).

( C) Diagonally woven wall with split jati bamboo tied with SqM Rs. 329.31
necessary bamboo kamies on both side 30 cm apart tied ( Rupees Three Hundred
with wire or cane etc, complete as directed. TwentyNine Paise
ThirtyOne ) Only

24.13 Cement concrete work in topping in proportion 1:1:2 SqM Rs. 321.28
with 6 mm to 9 mm size aggregate over CC floor and ( Rupees Three Hundred
RCC floors, tread and rise of steps including finishing the TwentyOne Paise
TwentyEight ) Only
surface smooth with neat cement and curing etc,
complete as directed. (19 mm thick).
24.14 65 mm thick traced flooring with cement concrete in SqM Rs. 758.88
proportion 1:2:4 with broken stone aggregate of size 6 ( Rupees Seven Hundred
mm to 20 mm over one 1st class brick flat soling FiftyEight Paise EightyEight
) Only
including sand packing of the voids in between the
bricks, watering, ramming properly where necessary
etc. complete and 12 mm thick cement plastering.
Finishing on top trowelling, altering, curing, complete as
directed. (Brick soling to be paid seperately).

24.15 Brick on edge floor (with 1st class brick) with cement SqM Rs. 1102.28
mortar in proportion 1:4 including cement pointing in ( Rupees One Thousand
proportion 1:1 finished and curing, complete as One Hundred Two Paise
TwentyEight ) Only
directed.

24.16 Bricks on edge floor (with 1st class brick) with sand SqM Rs. 765.20
racking etc, complete as directed.
racking etc, complete as directed. ( Rupees Seven Hundred
SixtyFive Paise Twenty )
Only

24.17 Regular coarse stone masonry work with (29 cm x 20 cm CuM Rs. 8705.34
x 15 cm) size above stone in cement mortar with ( Rupees Eight Thousand
outside chisel dressed and in other sides rough dressed Seven Hundred Five Paise
ThirtyFour ) Only
including racking out joints and carrying as directed and
specified in foundation retaining / pillars plinth and step
etc. in proportion 1:4.

24.18 125 mm thick brick wall in proportion 1:5 reinforced SqM Rs. 1173.25
with two lines of 6 mm dia MS rod placed in 38 mm ( Rupees One Thousand
thick course in proportion 1:2:4 at every fourth course One Hundred
SeventyThree Paise
etc, complete as directed.
TwentyFive ) Only

24.19 Mud lapped floor and plinth including petty repair to SqM Rs. 21.68
exisiting plinth. ( Rupees TwentyOne Paise
SixtyEight ) Only

24.20 Split bamboo mudden floor with 75 mm wide strip SqM Rs. 194.78
diagonally over. ( Rupees One Hundred
NinetyFour Paise
SeventyEight ) Only

24.21 Providing galvanized CI sheet roofing including SqM Rs. 782.87


supplying fitting and fixing necessary galved, screws / ( Rupees Seven Hundred
iron "J" hooks bolts and nuts with washers etc, EightyTwo Paise
EightySeven ) Only
complete as directed excluding cost of roof truss
(measurement on net roof area) 0.63 mm thickness (24
BWG).

24.22 Providing 0.63 mm thick galvanized iron ridging RM Rs. 610.39


including suplying and fixing with necessary galvanized ( Rupees Six Hundred Ten
screw washer etc. (23 cm lapping). Paise ThirtyNine ) Only

24.23 Providing RCC lintel in super structure in proportion RM Rs. 548.62


1:2:4 with 6 mm to 20 mm size river shingles reinforced ( Rupees Five Hundred
with 4 nos. 12 mm dia TS rod as main tied with 6 mm FortyEight Paise SixtyTwo )
Only
dia stirrups @ 15 cm c/c including shuttering, curing,
complete as directed.
24.24 Regular coarse stone masonry works with 29 cm x 20 cm CuM Rs. 8711.50
x 15 cm size approved stone in cement mortar with ( Rupees Eight Thousand
outside chisel dressed and in other side rough dressed Seven Hundred Eleven
Paise Fifty ) Only
including racking out joints and curing as directed and
steps etc. in proportion 1:4.

24.25 Providing undressed wood work in roof frame, truss, CuM Rs. 84605.66
purlin etc. including supplying and fixing necessary spike ( Rupees EightyFour
nails, screw, straps, bolts and nuts of 16 mm dia etc, Thousand Six Hundred Five
Paise SixtySix ) Only
complete with kiricide oiling 2 coats as directed (sal
wood).

24.26 Providing dressed wood work in post, wallbatten post CuM Rs. 102876.62
plates, bressumers, brackets, etc. including supplying ( Rupees One Lakh Two
fixing with spikes, nails, screws, bolts and nuts of 16 mm Thousand Eight Hundred
SeventySix Paise SixtyTwo )
dia etc, complete with kircide oiling 2 coats of face in
Only
connected with CC work necessary, complete as
directed.

24.27 Providing fitting and fixing batten and braced door and SqM Rs. 2705.16
windows including supplying, fitting and fixing as ( Rupees Two Thousand
directed in APWD 25 mm thick (batten and braced). Seven Hundred Five Paise
Sixteen ) Only

24.28 Providing fitting and fixing 1st class local wood for
panelled / glazed doors and windows including
supplying fitting and fixing iron fittings as detailed in
APWD general specification except bim lock as directed.

(i) Full panelled doors and windows (25 mm thick). SqM Rs. 2996.22
( Rupees Two Thousand
Nine Hundred NinetySix
Paise TwentyTwo ) Only

(ii) Full panel doors and windows (38 mm thick). SqM Rs. 3314.70
( Rupees Three Thousand
Three Hundred Fourteen
Paise Seventy ) Only

(iii) 1/3rd panel and 2/3rd glazed door (30 mm thick). SqM Rs. 3877.10
( Rupees Three Thousand
Eight Hundred
SeventySeven Paise Ten )
Only

(iv) Full glazed door, windows and clearstory windows. SqM Rs. 3180.10
(25 mm thick). ( Rupees Three Thousand
One Hundred Eighty Paise
Ten ) Only

( v) Full glazed windows and clearstory windows (30 mm SqM Rs. 2973.12
thick). ( Rupees Two Thousand
Nine Hundred
SeventyThree Paise Twelve
) Only

24.29 Providing 0.63 mm thickness in BWG galvanized plain SqM Rs. 987.99
sheet doors at size 3.65 M x 2.15 M for motor garage ( Rupees Nine Hundred
fitted with 100 mm x 35 mm 1st class local wood frame EightySeven Paise
NinetyNine ) Only
(on both side) at corners and at the middle fitted with
screw nails etc, complete including necessary iron
fittings and painting 2 coats with best quality paint.

24.30 Supplying fitting and fixing iron grating in windows MS SqM Rs. 1639.25
rod (round) fixed at not more than 13 cm c/c apart with ( Rupees One Thousand Six
one line of 40 mm x 10 mm size MS flat horizontal Hundred ThirtyNine Paise
TwentyFive ) Only
middle including painting the iron work 2 coats with
approved paint etc, all complete as directed.

24.31 Supplying fitting and fixing iron grating in clearstory SqM Rs. 1382.71
windows with 2 nos. of MS round rods (one lower half ( Rupees One Thousand
and another on centre) including painting 2 coats with Three Hundred EightyTwo
Paise SeventyOne ) Only
approved paint etc, all complete as directed.

24.32 Providing fitting and fixing 20 cm wide bird proof RM Rs. 264.26
hexagonal wire netting fitted to dressed 1st class ( Rupees Two Hundred
wooden frame including nailing, screwing etc. SixtyFour Paise TwentySix )
Only

24.33 Providing bamboo sosalic ceiling with 25 mm mud SqM Rs. 281.64
plastering on top bottom and white washing 3 coats
plastering on top bottom and white washing 3 coats ( Rupees Two Hundred
below with out ceiling. EightyOne Paise SixtyFour )
Only

24.34 Providing single layer of bamboo mat ceiling with lattice SqM Rs. 186.77
pattern jeffery at bottom but without ceiling joists. ( Rupees One Hundred
EightySix Paise
SeventySeven ) Only

24.35 Providing bamboo / wattle ceiling mud plastering on top SqM Rs. 623.17
and 12 mm thick cement plaster in proportion 1:4 on ( Rupees Six Hundred
bottom, white washed 3 coats underneath including TwentyThree Paise
Seventeen ) Only
supplying and fixing with 75 mm x 50 mm sal wood
ceiling joist and not more than 140 cm apart both ways.

24.36 Supplying and fixing hessian cloth to the ceiling frame SqM Rs. 197.72
including supplying necessary tack and tape on 1st class ( Rupees One Hundred
local wood beads of size 38 mm at 2 mm and chalk NinetySeven Paise
SeventyTwo ) Only
washing 2 coats, the cloth and tape at two coats
painting to the beading, complete as directed.

24.37 Clearing and painting to CI sheet roofing with approved SqM Rs. 136.51
paints including clearing surface etc, complete as ( Rupees One Hundred
directed in 2 coats. ThirtySix Paise FiftyOne )
Only
24.38 Varnishing of wood works in doors and windows 2 SqM Rs. 110.17
coats with approved quality of varnish including clearing ( Rupees One Hundred Ten
and painting the brass fitting etc, all complete as Paise Seventeen ) Only
directed.

24.39 Distemper with approved distempering materials.

(i) One coat SqM Rs. 21.61


( Rupees TwentyOne Paise
SixtyOne ) Only

(ii) Two coats SqM Rs. 31.18


( Rupees ThirtyOne Paise
Eighteen ) Only

24.40 Distempering 2 coats including painting 2 coats to SqM Rs. 38.72


batten with approved paint, complete as directed. ( Rupees ThirtyEight Paise
SeventyTwo ) Only
24.41 Clearing and lime washing pale buff :

(i) For one coat SqM Rs. 12.02


( Rupees Twelve Paise Two
) Only

(ii) For two coats SqM Rs. 18.05


( Rupees Eighteen Paise
Five ) Only

24.42 Clearing and cement washing with gum and water


: For one coat SqM Rs. 27.24
( Rupees TwentySeven
Paise TwentyFour ) Only

24.43 Clearing and white washing :

(i) For one coat. SqM Rs. 11.19


( Rupees Eleven Paise
Nineteen ) Only

(ii) For two coats including painting two coats to woods SqM Rs. 21.35
works with approved paint etc, complete as directed. ( Rupees TwentyOne Paise
ThirtyFive ) Only

(iii) Including earth oiling in wood works in batten post, post


plate, etc.
(a) For one coat. SqM Rs. 16.55
( Rupees Sixteen Paise
FiftyFive ) Only

(b) For two coats. SqM Rs. 21.61


( Rupees TwentyOne Paise
SixtyOne ) Only

24.44 Clearing and colour washing 2 coats including painting 2 SqM Rs. 17.81
coats to wood works with approved paints etc, ( Rupees Seventeen Paise
complete as directed. EightyOne ) Only

24.45 Plastic painting to the wall, ceiling of the building SqM Rs. 77.83
including clearing the surface etc. with approved plastic ( Rupees SeventySeven
paints, complete as directed. (Inner surface). Paise EightyThree ) Only

24.46 Supplying fitting & fixing goat proof fencing with all RM Rs. 204.59
necessary materials such as staples, nails, eyes, bolt
necessary materials such as staples, nails, eyes, bolt ( Rupees Two Hundred
hooks, bolts etc. required including fitting with RCC Four Paise FiftyNine ) Only
angle iron timber posts etc, complete. (For post
separate payment should be made).

24.47 Supply sal wood fencing post of size 13 cm x 13 cm and Each Rs. 2566.26
1.8 M length including coaltaring 2 coats applied that ( Rupees Two Thousand
and supply at site etc, complete. Five Hundred SixtySix Paise
TwentySix ) Only

24.48 Cement concrete base of size 30 cm x 30 cm in Each Rs. 411.62


proportion 1:3:6 including fitting & fixing flat iron clamp ( Rupees Four Hundred
bolts and nuts etc, complete as directed. (Aggregate size Eleven Paise SixtyTwo )
Only
: 13 mm to 25 mm).

24.49 Providing jati bamboo jeora fencing of 105 cm to 120


cm height including bhaluka bamboo post 1.50 cm to
1.80 cm apart driven atleast 45 cm under ground and
ties with three lines of kamies and half bamboo on top
etc, all complete as directed.
(i) For Single Latic Pattern RM Rs. 177.90
( Rupees One Hundred
SeventySeven Paise Ninety
) Only
(ii) For Double Latic Pattern RM Rs. 257.41
( Rupees Two Hundred
FiftySeven Paise FortyOne )
Only

24.50 Split jati bamboo janana fencing upto 1.83 M to 2.10 M SqM Rs. 209.38
high woven with double longitudinal kamies 60 cm to 75 ( Rupees Two Hundred
cm apart with bhaluka bamboo post 1.50 M to 1.80 M Nine Paise ThirtyEight )
Only
apart driven atleast 70 cm below ground and four lines
of half bamboo kamies tied with wire with post and
complete as directed. (Including supplying all materials).

24.51 Supplying fitting fixing barbed wire fencing of height RM Rs. 914.85
1.20 M with 9 nos. of standard barbed wires of 12 BWG
1.20 M with 9 nos. of standard barbed wires of 12 BWG ( Rupees Nine Hundred
x 2 poles x 4 bricks at 15 cm interval including fixing Fourteen Paise EightyFive )
Only
with standard eye bolts and staples with angle iron post
of size 50 mm x 50 mm x 5 mm duly sloted and
embedded in CC base of size 25 cm x 25 cm x 75 cm
below ground in proportion 1:2:4 to be placed 2 M
apart with corner strut 2 nos. of same dimension will be
placed every 10 M interval, including painting 2 coats to
all iron works with anti-corrorrosive red paint etc,
complete as directed.

24.52 Construction of raised platform in block of size 1.90 M x SqM Rs. 4898.17
1.50 M made of sal wood plank of thickness 5 cm fitted ( Rupees Four Thousand
to sal wood plank of wood frame and fixed with patent Eight Hundred NinetyEight
Paise Seventeen ) Only
nails and supported by four wooden post log of size 10
cm x 10 cm x 20 cm fitting and fixing, complete as
directed.

24.53 Labour charge for packing out old doors and windows
and refitting the same in position with neccssary nails
screws etc, complete as directed.

(i) Without repair SqM Rs. 234.54


( Rupees Two Hundred
ThirtyFour Paise FiftyFour )
Only

(ii) After petty repair SqM Rs. 362.82


( Rupees Three Hundred
SixtyTwo Paise EightyTwo )
Only
24.54 Providing 1st class local wooden gate made of 38 mm x SqM Rs. 1629.53
10 mm size frame bracing and hailing 0.75 cm apart as ( Rupees One Thousand Six
ordered including supplying and fitting with necessary Hundred TwentyNine Paise
FiftyThree ) Only
iron fitting and painting 2 coats with approved paint etc,
all complete as directed. (90 cm to 18 cm wide double
leaf).

24.55 Taking out refitting old planked flooring including SqM Rs. 327.81
supplying and fixing new screw and nails. ( Rupees Three Hundred
TwentySeven Paise
EightyOne ) Only

24.56 Labour charge for providing 40 mm dia hand tube well RM Rs. 207.49
by sinking, lowering, fitting and fixing in position with 40
by sinking, lowering, fitting and fixing in position with 40 ( Rupees Two Hundred
mm dia GI pipe and stainer of best quality placed in Seven Paise FortyNine )
Only
water bearing strata including fixing with hand pump
necessary joining materials, cutting and threading the
pipes where necessary including cleaning, priming the
tube well, complete as directed.

24.57 Labour charge for boring with 40 mm dia GI pipe for RM Rs. 131.46
testing availability of water level including collection of ( Rupees One Hundred
soil sample packets at every 3 M or wherever there is a ThirtyOne Paise FortySix )
Only
change of strata with distinguishing marks and with
dewatering the pipe as directed.

24.58 Labour charge for lifting of damaged hand tube well of RM Rs. 104.90
40 mm dia with assembly including disjoining the pipes, ( Rupees One Hundred
strainers etc. from pump socket including washing, Four Paise Ninety ) Only
clearing the lifted materials and stacking at the safe
place, complete as directed.

24.59 Supplying fitting, fixing white glazed Indian made Each Rs. 3814.20
porcelain washing basin of standard size with necessary ( Rupees Three Thousand
bib cock, water pipe etc, complete as directed. Eight Hundred Fourteen
Paise Twenty ) Only

24.60 Supplying fitting fixing white glazed Indian made Set Rs. 1905.60
porcelain washing basin of standard size (composite ( Rupees One Thousand
ready made unit) with necessary bib cock water pipe Nine Hundred Five Paise
Sixty ) Only
etc, complete as directed.
24.61 Supplying fitting & fixing 100 mm x 50 mm dia horn Each Rs. 424.89
bend with access door laying in position, joining with ( Rupees Four Hundred
cement & sand mortar in proportion 1:2 collared joined TwentyFour Paise
EightyNine ) Only
etc, complete as directed.

24.62 Supplying fitting, fixing white glazed Indian made Each Rs. 1608.92
earthen ware standing type flat back "Urinal" with all ( Rupees One Thousand Six
fittings, complete as directed. Hundred Eight Paise
NinetyTwo ) Only

24.63 Construction of filter bed 60 cm wide 75 cm depth by RM Rs. 1802.50


excavation earth & filling the pit by coarse sand over
excavation earth & filling the pit by coarse sand over ( Rupees One Thousand
brick bats (60 cm) & covering the pit with earth over the Eight Hundred Two Paise
Fifty ) Only
bitumen drum sheet cover including necessary
arrangement for placing pipes etc, all complete as
directed.

24.64 Supplying fitting & fixing white glazed Indian made Set Rs. 1728.19
porcelain pan 45 cm long with 100 mm dia porcelain ( Rupees One Thousand
glazed siphon and glazed porcelain foot rest laying in Seven Hundred
TwentyEight Paise
position with necessary cement concrete works in
Nineteen ) Only
proportion 1:2:4 joined around finished the surface
smooth etc, complete as directed.

24.65 Supplying fitting and fixing 45 cm dia CI inspection pit No. Rs. 655.36
cover with frame in cement and sand mortar in ( Rupees Six Hundred
proportion 1:2, all complete as directed. FiftyFive Paise ThirtySix )
Only

24.66 Supplying fitting and fixing wall mirror with wooden No. Rs. 647.96
back of size 60 cm X 30 cm with necessary timber bend ( Rupees Six Hundred
and all arrangement for fixing in the wall etc, all FortySeven Paise NinetySix
) Only
complete as directed.

24.67 Supplying fitting and fixing 50 cm long towel rail made Each Rs. 323.98
of good quality steel to bathroom wall with necessary ( Rupees Three Hundred
fitting materials, complete as directed. TwentyThree Paise
NinetyEight ) Only

24.68 Supplying fitting and fixing 100 mm dia soil pipe with
cement and sand mortar in proportion 1:2 collared joint
laying exposed or in trench and covering the same with
earth after joining and laying etc, all complete as
directed.

(i) With 100 MM dia AC pipe RM Rs. 213.47


( Rupees Two Hundred
Thirteen Paise FortySeven )
Only

(ii) With 100 MM dia CI pipe RM Rs. 422.30


( Rupees Four Hundred
TwentyTwo Paise Thirty )
Only
24.69 Supplying and laying with fitting fixing 100 mm dia Each Rs. 437.21
junction with access door and socket with cement and ( Rupees Four Hundred
sand mortar in proportion 1:2 in collared joint etc, all ThirtySeven Paise
TwentyOne ) Only
complete as directed.

24.70 Supplying fitting and fixing 100 mm dia "T" with cement
and sand mortar in proportion 1:2 in collared joint,
exposed or in trench and trench covering the same with
earth after laying pipes etc, all complete as directed.

(i) With 100 mm dia AC "T" Each Rs. 325.12


( Rupees Three Hundred
TwentyFive Paise Twelve )
Only

(ii) With 100 mm dia CI "T" Each Rs. 571.52


( Rupees Five Hundred
SeventyOne Paise FiftyTwo
) Only

24.71(A) Supplying fitting and fixing 50 mm dia AC bend pipe RM Rs. 236.75
with cement and sand mortar in proportion 1:2 collared ( Rupees Two Hundred
joint with neccssary clamps etc, all complete as ThirtySix Paise SeventyFive
) Only
directed.

(B) Supplying fitting and fixing 50 mm dia AC bend pipe Each Rs. 183.22
cowl with cement and sand mortar in proportion 1:2 in ( Rupees One Hundred
collared joint etc, all complete as directed. EightyThree Paise
TwentyTwo ) Only

( C) Supplying fitting and fixing 100 mm dia CI horn bend Each Rs. 532.07
cowl with cement and sand mortar in proportion 1:2 in ( Rupees Five Hundred
collared joint etc, all complete as directed. ThirtyTwo Paise Seven )
Only

24.72 Supplying and laying in position 100 mm dia plain bend


with access door including fixing with cement and sand
mortar in proportion 1:2 in collared joint etc, all
complete as directed.

(i) With 100 mm dia AC bend Each Rs. 288.16


( Rupees Two Hundred
EightyEight Paise Sixteen )
Only
(ii) With 100 mm dia CI bend Each Rs. 571.52
( Rupees Five Hundred
SeventyOne Paise FiftyTwo
) Only

24.73 Supplying fitting and fixing 100 mm dia plain bend


without access door including fixing with cement and
sand mortar in proportion 1:2 in collared joint etc,
complete as directed.

(i) With 100 mm dia AC plain bend Each Rs. 328.16


( Rupees Three Hundred
TwentyEight Paise Sixteen )
Only

(ii) With 100 mm dia CI plain bend Each Rs. 595.52


( Rupees Five Hundred
NinetyFive Paise FiftyTwo )
Only

PVC DISTRIBUTION SYSTEM FOR BUILDING


24.74 Laying, joining, fitting, fixing, testing of PVC pipes and
special fittings to equal / unequal tee, bend, reducer,
end cap, threaded coupler, etc. including local carriage.

(i) With 200 M length PVC pipes of dia 200 mm RM Rs. 43.62
( Rupees FortyThree Paise
SixtyTwo ) Only

(ii) with 200 M length PVC pipes of RM Rs. 35.93


dia 90 mm to 160 mm ( Rupees ThirtyFive Paise
NinetyThree ) Only

24.75 Labour charge for taking out old doors and windows
and refitting the same in position with necessary nails,
screws etc, all complete as directed.

(i) Without repair SqM Rs. 262.26


( Rupees Two Hundred
SixtyTwo Paise TwentySix )
Only

(ii) After petty repair SqM Rs. 390.54


( Rupees Three Hundred
Ninety Paise FiftyFour )
Only

24.76 Labour for taking out refitting galvanized ridging RM Rs. 116.10
including supplying & fixing necessary galvanized ( Rupees One Hundred
screws, bolts & nuts, complete as directed. Sixteen Paise Ten ) Only

24.77 Labour for fitting & fixing corrugated iron roofing SqM Rs. 89.26
including supplying & fixing new galvanized screws, iron ( Rupees EightyNine Paise
"J" hook, bolts & nuts, washers etc, complete as TwentySix ) Only
directed & specified.

********

25. ADDITIONAL ITEMS FOR MAJOR & MEDIUM WORKS


Sl No Name of Item Unit Rate
25.1 Earthwork in filling in canal embankment, approach CuM Rs. 232.24
road, afflux bund, guide bund etc. to the designed ( Rupees Two Hundred
section and grade by obtaining earth from outside ThirtyTwo Paise
TwentyFour ) Only
borrow pits and filling in uniform layers not exceeding
15 cm thick including clearing light jungles, removing
trees upto 15 cm dia. and uprooting roots and stumps
from the seat of embankment and borrow pits area,
including breaking clods to not more then 10 mm cube
ramming, dressing, watering and roughening the seat of
embankment, profiling etc. paying compensation of
earth borrowed from private land if any, lead upto 30 M
and lift upto 1.5 M complete as directed. (By head lead
in sandy, clayey or loamy soil).

(i) Extra lead for every 30 M or part thereof beyond the CuM Rs. 13.10
initial lead of 30 M. ( Rupees Thirteen Paise
Ten ) Only

(ii) Extra lift for every 1.5 M or part thereof beyond the CuM Rs. 13.10
initial lift of 1.5 M. ( Rupees Thirteen Paise
Ten ) Only
25.2 Earthwork in excavation for removal of sediment from CuM Rs. 159.05
bed of irrigation canal / river by head load to a safe ( Rupees One Hundred
distance including bailing out water, dressing the bed as FiftyNine Paise Five ) Only
directed for normal lead of 30 M and lift of 1.5 M.
(Ordinary soil).

25.3 Carriage of excavated materials obtained out of CuM Rs. 199.80


earthwork in excavation of foundation trenches of canal ( Rupees One Hundred
structures by truck and depositing the same in the near NinetyNine Paise Eighty )
Only
by low lying areas within a distance of 4 KM from the
worksite including loading unloading at both ends
complete as directed.

25.4 Earthwork in excavation of deposited silt mixed with CuM Rs. 596.52
sand, pebbles, debrises, morums, slushy earth, gravel ( Rupees Five Hundred
from irrigation canal including resectioning, reshaping NinetySix Paise FiftyTwo )
Only
and grading the canal bed and removing the excavated
spoils by head load to the canal bank for lead upto 60 M
and all lift for further removal by truck carriage
including bamboo staircases complete as directed.

25.5 Earthwork in excavation in foudation of canal structures CuM Rs. 683.7


to proper depth and grade as designed in hard strata of ( Rupees Six Hundred
silt and clay deposits sandwiched therein gravals and all EightyThree Paise Seventy
) Only
sizes of boulders constituting very hard mass and
removing the excavated materials by head lead to a safe
distance from the working place and refilling the side
trenches of structure with ramming, compacting,
dressing with all lead and lift as directed.

25.6 Cost of dewatering involved during earthwork in CuM Rs. 178.98


excavation of foundation trenches of canal structures ( Rupees One Hundred
(by pump) in soil mixed with silt and sand etc. SeventyEight Paise
NinetyEight ) Only
Dewatering by using 1 no. 10 HP and 1 no. 5 HP water
pump.

25.7 Cost of dewatering involved during earthwork in CuM Rs. 201.54


excavation of foundation trenches of canal structures ( Rupees Two Hundred
(by pump) in soil mixed with silt and sand etc. One Paise FiftyFour ) Only
Dewatering by using 1 no. 10 HP and 2 nos. 5 HP water
pump.

25.8 Earthwork for removing the cofferdam including CuM Rs. 299.25
depositing the earth near the canal embankment and
depositing the earth near the canal embankment and ( Rupees Two Hundred
slopes where necessary including removing the pitched NinetyNine Paise
TwentyFive ) Only
boulders and stacking at safe distance in measurable
stacks including ramming, dressing the earth etc.
complete as directed.

25.9 Compaction of earthwork by hand roller in canal CuM Rs. 81.93


embankment, bed, approach road etc complete as ( Rupees EightyOne Paise
directed. NinetyThree ) Only

25.10 Earthwork in excavation of deposited silt mixed with CuM Rs. 266.36
slushy earth, sand, gravel etc. from the canal bed ( Rupees Two Hundred
including resectioning, grading the canal bed, bailing SixtySix Paise ThirtySix )
out water where necessary and carrying and depositing Only
the suitable earth on the top of both marginal
embankment / side slopes in layers of 15 cm thick and
breaking clods upto 15 mm cube by wooden rammer
properly as directed lead upto 30 M and lift 1.5 M.

25.11(A) Earthwork in excavation of deposited silt mixed with CuM Rs. 324.88
slushy earth, sand, gravel etc. from the canal bed ( Rupees Three Hundred
including resectioning, grading the canal bed, bailing TwentyFour Paise
EightyEight ) Only
out water where necessary and carrying and depositing
the suitable earth on the top of both marginal
embankment / side slopes in layers of 15 cm thick and
breaking clods upto 15 mm cube by wooden rammer
properly as directed inclusive of constructing bamboo
staircases with lead upto 60 M and lift of 1.5 M to 4 M.

(B) Extra lift upto 9.0 M beyond the initial lift of 4.0 M CuM Rs. 157.70
( Rupees One Hundred
FiftySeven Paise Seventy )
Only

25.12 Earthwork in excavation of deposited silt mixed with CuM Rs. 188.74
muddy earth, sand, etc. from the canal bed including
muddy earth, sand, etc. from the canal bed including ( Rupees One Hundred
resectioning, grading the canal bed, bailing out water EightyEight Paise
SeventyFour ) Only
where necessary and carrying and depositing the
suitable spoil on the top of both marginal embankment
/ side slopes in layers of 15 cm thick and breaking clods
upto 15 mm cube by wooden rammer properly as
directed lead upto 30 M and lift 1.5 M.

25.13 Earthwork in excavation of foundation trenches for CC CuM Rs. 147.72


beams as per design, drawing in bed and side of ( Rupees One Hundred
irrigation canal including ramming, dressing etc. FortySeven Paise
SeventyTwo ) Only
complete.

25.14 Earthwork in excavation in foundation trenches in all


soils including gravel and boulders of various size etc.
depressing the sub soil water table upto a depth of 4 M
including providing earth filled empty cement bags and
pallasiding as required to prevent sliding of slopes and
filling the sides of the structures after completion of
works with ramming, compacting, dressing complete as
directed and removing the surplus spoils to a safe place
as directed including all lead and lift.

(i) Without dewatering CuM Rs. 459.76


( Rupees Four Hundred
FiftyNine Paise SeventySix
) Only
(ii) With dewatering CuM Rs. 624.21
( Rupees Six Hundred
TwentyFour Paise
TwentyOne ) Only

25.15 Earthwork in excavation for diversion with CuM Rs. 607.80


channelisation in soil mixed with sand, gravel and ( Rupees Six Hundred
different sizes of boulders upto mansize by JCB / front Seven Paise Eighty ) Only
loader excavator and manual labour, removing the
same to a safe distance upto 1 KM by means of vehicle
and depositing the spoil in the form of spoils
embankment / bank as required at site including
dressing grading and cutting the sides slopes etc.
complete as directed by the department.

25.16 Supplying and laying of filter materials consisting of CuM Rs. 1431.73
sand and river shingles free from dust dirt and other
sand and river shingles free from dust dirt and other ( Rupees One Thousand
foreign materials and laying in three layers in position as Four Hundred ThirtyOne
Paise SeventyThree ) Only
per drawing and specification as directed by the
department.

25.17 Machine mixing charge of cement concrete / reinforced CuM Rs. 197.04
cement concrete with different types of concrete ( Rupees One Hundred
mixture machine of 10 / 7 CuFt capacity. NinetySeven Paise Four )
Only

25.18 Vibrating in CC / RCC work with vibrator including local CuM Rs. 142.25
carriage of vibrator etc. complete as directed. ( Rupees One Hundred
FortyTwo Paise
TwentyFive ) Only

25.19 RCC work in slab, abutment cap and above abutment,


pier cap, pedestal, dirt wall etc. in proportion 1:1:2
(M25) with hard broken stone aggregate of size 6 mm
to 20 mm with proper reinforcement as per design
including curing etc. complete as directed with
necessary timber shuttering, scaffolding etc. where
necessary complete as directed. (Reinforcement,
shuttering, scaffolding cost will be paid separately).

(i) Without shuttering CuM Rs. 9846.14


( Rupees Nine Thousand
Eight Hundred FortySix
Paise Fourteen ) Only

(ii) With shuttering CuM Rs. 11286.15


( Rupees Eleven Thousand
Two Hundred EightySix
Paise Fifteen ) Only

25.20 Collection of sand gravel (40% sand and 60% gravel of CuM Rs. 707.17
size 25 mm to 60 mm) free from dust and dirt including ( Rupees Seven Hundred
stacking in measurable stacks at quarry site and making Seven Paise Seventeen )
Only
payment of forest royalty etc. as directed complete.

25.21 Supplying, fitting and fixing GI manhole cover of size No. Rs. 1077.85
700 mm x 700 mm at centre of barrel of each span ( Rupees One Thousand
complete as directed. SeventySeven Paise
EightyFive ) Only
25.22 Providing rubber seal in the construction joints as per RM Rs. 4097.79
required size and shape and as per design and drawing, ( Rupees Four Thousand
16 mm minimum thickness including supplying, fitting NinetySeven Paise
SeventyNine ) Only
and fixing complete as directed.

25.23 Supplying and mixing rapidite in concrete works below Litre Rs. 156.15
ground water level where necessary etc. complete as ( Rupees One Hundred
directed. FiftySix Paise Fifteen )
Only

25.24 Supplying, fitting and fixing elastomeric bearing on the No. Rs. 18063.36
top of the pier caps and abutments and under side of ( Rupees Eighteen
girder with epoxy resin, mortar etc. as directed Thousand SixtyThree Paise
ThirtySix ) Only
complete.

25.25 Suuplying, fitting and fixing ISMB 450 (2 x 1350.70 cm) RM Rs. 5865.17
including carrying to worksite by crane / truck and ( Rupees Five Thousand
making plain grooving in RCC works as per design and Eight Hundred SixtyFive
Paise Seventeen ) Only
drawing as directed by the department complete.

25.26 Labour charges for spreading hard river shingles / sand CuM Rs. 257.49
gravels to required thickness over approach subway etc. ( Rupees Two Hundred
including ramming, dressing the seat before laying the FiftySeven Paise FortyNine
) Only
materials lead upto 30 M and lift 1.50 M, complete as
directed.
25.27 Providing bitumen of appropriate grade in the RM Rs. 82.38
construction joint of CC lining as per drawing complete ( Rupees EightyTwo Paise
as directed. ThirtyEight ) Only

25.28 Labour for dismantling of old CC work and stacking the CuM Rs 3219.37
spoils at suitable place including local carriage, ( Rupees Three Thousand
complete as directed. Two Hundred Nineteen
Paise ThirtySeven ) Only

********