You are on page 1of 2

www. NYLJ.

com ©2010 ALM

Volume 244—NO. 63 wednesday, september 29, 2010

Construction Law

Liability of Construction
Managers: Look to the Contract By
Kenneth M.
Block
And
John Patrick
Curran

I
n the last several years, construction managers acting “at risk” with respect to the cost, time or The construction manager as advisor may,
have taken on an increasingly larger share quality of performance by the trade contractors. of course, assume greater responsibility for
of construction projects. Unlike general Acting as a constructor, the construction manager the cost of the work, but will typically insist
contractors, which are generally at risk for all is generally responsible for the construction of on additional compensation to reflect that
aspects of the project—from cost to schedule to the project; however, the construction manager’s added risk and will insist upon adequate
the quality of the work—the risk and responsibility ultimate liability for the key elements of the contingencies in its estimates to account for
of a construction manager can vary greatly from project—cost, schedule and quality of the work— potential cost overruns and unforeseen costs.
project to project, depending on the nature of the can vary greatly based upon its agreement with The construction manager acting as constructor
contract. In this article, we will explore the key the owner. will be liable for the cost of the project if it agrees
aspects of construction management agreements Obligations of the Manager to perform the work for a guaranteed maximum
and present a sampling of relevant judicial price (GMP) or a lump sum. This is not the case
holdings. Perhaps the only universal statement that can where the agreement is structured on a “cost
The hallmark of construction management be made about the obligations and liabilities of a plus” basis. Under a cost plus arrangement, the
is the total participation of the manager in the construction manager is: “it depends upon what construction manager is reimbursed for all costs
construction process, often beginning with the it says in the contract.” As with almost any other of the work and is paid a fee, generally determined
conceptualization of the project. The construction legal relationship, the rights and obligations of as a percentage of the cost of the work. Under
manager will work with the owner and the design the construction manager (to the owner, to trade a GMP, the construction manager will guaranty
team to produce a coordinated and cost efficient contractors and to third-parties) are controlled the total cost of the project, which includes its
set of construction documents. The construction primarily by the language of the respective supervisory expenses and subcontract costs
manager will then assist the owner in selecting agreements. While there are certain statutory and (usually based on drawings which are 80-90 percent
subcontractors (or trade contractors) and, to common law rules regarding what can and cannot complete). A major component of a GMP is the
varying degrees, coordinate and administer the be included in construction contracts, very few establishment of a contingency, usually 3-5 percent
actual construction. generalities can be made. of the subcontract and general conditions (e.g.,
Generally speaking, construction managers act When the construction manager is acting only supervisory expenses) costs. The construction
either in an advisory capacity, as agent for the as the owner’s advisor—also known as pure manager can utilize the contingency to offset the
owner, or as a constructor, acting as an independent construction management—the construction cost of, for example, bid error, defective work,
contractor, much like a general contractor. When manger typically does not assume any responsibility subcontractor defaults, scheduling conflicts,
acting as advisor, the construction manager will for the cost, time or the quality of the work. The delays, etc.
enter into trade contracts as agent for the owner; construction manager may, as part of its contract Where the construction management agreement
as a constructor, the construction manager will with the owner, agree to prepare estimates of the provides for a GMP, there is often an arrangement
enter into contracts directly with subcontractors. cost of the work, but the estimates are typically not for the sharing of any savings between the owner
The construction manager’s contractual liability guaranteed. The American Institute of Architects and the construction manager if the final cost
varies drastically depending on the nature of its most current Standard Form of Agreement Between of the work is less than the GMP. Where there
employment. Owner and Construction Manager as Adviser (AIA is a sharing of savings, any unused contingency
As an advisor, the construction manager is, Document C132-2009) specifically provides that might likewise be shared. (The sharing of savings
essentially, liable only for its own acts of negligence “the Construction Manager does not warrant or both from the GMP and the contingency involves
or breach of contract. It is not considered to be represent that bids or negotiated prices will not detailed business negotiations which are project
vary from the budget proposed, established or specific.)
approved by the Owner, or from any cost estimate The construction management agreement will
Kenneth M. Block and John-Patrick Curran are partners or evaluation prepared by the Construction also determine the construction manager’s liability
of Tannenbaum Helpern Syracuse & Hirschtritt. Manager.” (AIA Document A132-2009 §6.2). for completion of the project in accordance with
wednesday, september 29, 2010

an agreed upon schedule. Generally speaking, In Blandford Land Clearing Corp. v. National contractors, the construction manager is typically
as a constructor, a construction manager is Union Fire Insurance Company of Pittsburgh, Pa., not liable to third parties for injuries resulting from
responsible for completing the project on time 260 A.D.2d 86, 698 N.Y.S.2d 237 (1st Dept. 1999), the work. A construction manager “may nonetheless
and may be responsible to the owner for damages a general contractor (claiming to be acting as the become responsible for the safety of the workers
incurred as a result of delay. The extent of the agent of the owner) attempted to insulate itself at a construction site if it has been delegated the
damages—whether they be liquidated, direct from an obligation to pay subcontractors on a authority and duties of a general contractor, or if it
or consequential—is a function of the terms of project by including language in its subcontract functions as an agent of the owner of the premises.”
the construction management agreement. Even agreements that read that “[f]or the purposes of Pino v. Irvington Union Free School District, 43 A.D.3d
in the absence of liquidated damages for delay, payment only, Contractor is acting as agent of 1130, 843 N.Y.S.2d 133 (3rd Dept. 2007). The issue
the construction manager may be obligated to Owner.” 260 A.D.2d at 88. The court found that, arises frequently in the context of claims of strict
maintain the progress of the work in accordance since the subcontractors owed an obligation to liability under New York Labor Law Section 240(1),
with the project schedule and be responsible the general contractor to perform the work, there also known as the Scaffolding Law.
for the cost of overtime and additional shifts in must be the corresponding obligation on the part In Walls, the Court of Appeals held that “[a]
order to maintain that schedule. Where there is a of the general contractor to pay the subcontractors lthough a construction manager of a work site is
contingency, the construction manager may utilize for the work. generally not responsible for injuries under Labor
funds in the contingency to cover such additional While Blandford involved a general contractor, Law § 240(1), one may be vicariously liable as an
costs. as opposed to a construction manager, there is no agent of the property owner for injuries sustained
As a constructor, the construction manager is reason to think that the decision would be different under the statute in an instance where the manager
also responsible for the quality of the work of its if a construction manager signed the contracts as had the ability to control the activity which brought
subcontractors. Where the construction manager the owner’s agent. The lesson to be learned is that about the injury.” 4 N.Y.3d 861 at 863-864, 798
cannot prevail upon the responsible subcontractor in order for the construction manager to insulate N.Y.S.2d 351 (2005).
to remedy the defective work, the construction itself from any contractual obligation to make The court found that the construction manager
manager will be required to remedy the defects payment to trade contractors, it must not enter had a duty, under its contract with the owner of the
at its expense; however, the contingency would project, to enforce compliance by the individual
be available for that purpose. trade contractors with applicable safety regulations
As an advisor, the construction manager only Perhaps the only universal statement and to direct trade contractors to correct unsafe
has an obligation to confirm generally that the that can be made about the obligations conditions. The court wrote that the defendant,
work of the trade contractors is being performed in and liabilities of a construction manager Turner Construction Co., was not the “typical
accordance with the respective trade contracts. The is: “it depends upon what it says in the construction manager,” but was instead the “eyes,
typical construction manger as advisor agreement ears and voice of the owner.” 4 N.Y.3d 861 at 864.
contract.”
will provide specifically that the construction Accordingly, the court confirmed that Turner was
manager is not responsible for and has no control into direct agreements with the trade contractors. vicariously liable as a statutory agent of the owner.
over the means, methods and procedures of the When the construction manager is acting 4 N.Y.3d 861 at 864.
construction and is not responsible for the failure as the constructor, it is typically assumed the While Walls and the cases that have followed it
of the trade contractors to perform the work in construction manager has the direct obligation appear as an odd deviation from the typical law
accordance with the terms of their respective to make payment to the trade contractors for the of agency—that a disclosed principal is liable for
contracts. performance of the work. This duty is ordinarily actions of its agent performed within the scope
Liability to Trade Contractors independent of the owner’s obligation to make of the agency, not the other way around—the
payments to the construction manager, and the decisions make it clear that, at least in the context
The common assumption is that the construction construction manager has a payment obligation of Labor Law §240(1) claims, the extent of the
manager as advisor is acting solely as the owner’s to the trade contractors irrespective of whether construction manager’s liability will be dictated by
agent and, under standard principals of agency, the construction manager has received payment the scope of its authority. Cf. Kindlon v. Schoharie
is not liable for the obligations of its disclosed from the owner. West-Fair Elec. Contractors v. Aetna Central School Dist., 66 A.D.3d 1200, 887 N.Y.S.2d
principal, the owner. Cas. & Sur. Co., 87 N.Y.2d 148, 638 N.Y.S.2d 394 310 (3rd Dept. 2009) (no direct control as to safety
However, as the Court of Appeals wrote in Walls (1995) (a provision in a subcontract that provides matters shielded the construction manager from
v. Turner Constr. Co., “the label of construction that the general contractor is only required to pay liability).
manager versus general contractor is not the subcontractor if the owner pays the general The obligations of a construction manager—
necessarily determinative.” 4 N.Y.3d 861, 864, 798 contractor—a so-called pay when paid provision— as an advisor or constructor, as an agent or
N.Y.S.2d 351 (2005). Simply calling itself an agent is unenforceable as against public policy). independent contractor—are a function of the
may not be sufficient to insulate the construction Liability to Third Parties terms of its contract with the owner. So, too, will the
manager from an obligation to make payment to liabilities of a construction manager to an owner,
the trade contractors. The construction manager With respect to tort liability, a construction subcontractor or third party vary depending on
has to be careful not to create a contractual manager’s liability to third parties depends both the agreement.
relationship between itself and the individual trade on the role that the construction manager assumes
contractors performing the work. If the contractors and the ability of the construction manager to
are bound to the construction manager for the control the activity that caused the injury.
proper performance of the work, it may not matter In the pure construction management scenario, Reprinted with permission from the September 29, 2010 edition of the NEW YORK LAW
that the construction manager has held itself out where the construction manager does not have JOURNAL © 2010. ALM Media Properties, LLC. All rights reserved. Further duplication
without permission is prohibited. For information, contact 877-257-3382 or reprints@alm.
solely as the owner’s agent. control over the performance of the work of the com. # 070-09-10-39

You might also like