You are on page 1of 2

*Any data highlighted in red below is data that has been added or updated in the last release of the

project
Capital PEC Report Project ID: 300155331

Project Name AL-KHARGA (ABU TARTUR) GRASSROOT PHOSPHORIC ACID PEC Activity Diagram
PLANT
Industry Code 07 Chemical Processing Project Type Grassroot
(CPI)
TIV (USD) 400,000,000
SIC Code 2874 Phosphatic Sector Ag Chemicals
Fertilizers
SIC Product 2874*0006 Phosphoric acid-mfg
Status Active Last Update 23-Apr-2018 Initial Release 27-Feb-2014
Environmental Air (A) Land (L) Water Construction Labor Preference Unconfirmed
(W)
Operations Labor Preference Unconfirmed
Project Capacity Planned 450,000 Metric T/yr of Phosphoric Acid

Plant Owner El Wady for Phosphate & Plant Parent Phosphate Misr Company
Fertilizers Industries
Plant Name Al-Kharga (Abu Tartur) Unit Name Phosphoric Acid
Fertilizer Complex
Plant ID 3116151
Location Abu TarturKharg Phone +20 225 171 058
City/State Al-kharga, Al Wadi al Zone/County EG*02, Al Wadi al Jadid
Jadid 0000 Egypt
Project Responsibility Project Company Project Contact
Project Manager El Wady for Phosphate & Fertilizers Industries Rasha Ahmed
9W/7, Lasilky Area - Autostrade, New Maadi Project Assistant Manager
Cairo, Al Qahirah 000 [Tel.] +20 225 167 532 [Alt.] +20 225 167 532 x1510 [Mob.]
+20 106 750 0852
Egypt rasha.ahmed@waphco.com
Inspection/Validation/Startup El Wady for Phosphate & Fertilizers Industries Ayman Ahmed Elkabany
9W/7, Lasilky Area - Autostrade, New Maadi Process Engineer
Cairo, Al Qahirah 000 [Tel.] +20 225 167 532 [Mob.] +20 100 141 2943
Egypt ayman.elkabany@waphco.com
Consultant Engineering Petroleum & Process Industries Imam el Said
P O Box 2521, Heliopolis General Manager for Chemical Project
Cairo, Al Qahirah 00000 [Tel.] +20 222 762 100
Egypt imamel_said@enppi.com
Design Engineering Fluor Daniel Arabia Limited Juansimon Arteaga Puente
P O Box 3381 Business Development Director
Al Khobar, Ash Sharqiyah 31952 [Tel.] +966 138 829 292 [Alt.] +966 138 829 292 x3804
Saudi Arabia juansimon.arteaga@fluor.com
PEC® Timing P1 PEC® Activity Detailed Design
Project Probability Medium (70-80%)
Scope El Wady for Phosphate & Fertilizers Industries (WAPHCO), Engineering Petroleum & Process Industries (ENPPI) (JV
Partner and Consultant) and Fluor Daniel Arabia Limited (FEED) performs Detailed Design for a Grassroot Phosphoric
Acid Plant. DETAILS: Construct a new plant and install process plus supporting equipment and utilities to produce
approximately 450,000 Metric T/yr Phosphoric Acid. REQUIRES: Building/Structural, Reactor Vessels, Hydrator,
Precipitator, Purifier, Dilution Tank, Compressor (Air), Evaporator, Calciner Mill, Heat Exchanger, Gypsum, Steam
Process Heating System, Condenser, Controls (DCS), Piping (Stainless Steel and Carbon Steel), Motors (VS),
Pumps, Pipe Racks, Level Indicators, Hopper, Filters, Feeder, Hydrolyzer, Absorber, Blowers, Temperature Sensors,
Tanks, Digital Transmitter/Controllers, Electrical Utilities. ENVIRONMENTAL: (A) Vents, Stacks, Scrubber, (L)
Containment, (W) Wastewater Treatment System.
Schedule WAPHCO, ENPPI and Fluor continues with Detailed Design and expects to receive final AFE by 4Q18 (Dec). Upon
Capital Approval, WAPHCO will select EPC by 2Q19 (Apr) and will release Equipment RFQs plus Subcontractor Bid
Documents 3Q19 (Jul). Expected Construction Kick-Off 3Q19 (Sep). Project Completion 4Q21 (Dec).
Eng 201904 AFE 201812 Sub Bid Doc 201907 Completion 30-Dec-2021 Precision QUARTER
Project
Construction
Milestones Long-Lead 201901 Equip RFQ 201907 Kick-Off 201909 Kickoff Slippage 41 Months 28 Months
Duration
Engineering Civil Electrical Environmental HVAC Instrumentation Mechanical Structural Process
Contracting Civil Electrical Environmental HVAC Instrumentation Mechanical Structural General [G/C]
Project Key Needs Civil/Site Structural Architectural Control Room Process Equip Heat Transfer
Instrumentation Electrical Mechanical HVAC Storage NDE
Piping/Fittings Insulation/Coatin Environmental Utilities Valves Pumps
gs
Communication Feedstock Continuous
s Process

Matter Phase Gas Liquid


Energy Boiler
Buy Electricity Fuel
Sell
Plant Standard Contacts
Functional/Actual Title Contact Name/E-mail Telephone/On-site QC Date
Plant Manager Ayman Ahmed Elkabany +20 225 167 532 Apr-2018
Process Engineer ayman.elkabany@waphco.com No

Historical Reports
Project Name Report Date TIV Phase
AL-KHARGA (ABU TARTUR) GRASSROOT
27-Feb-2014 400,000,000 USD Project Scope (P1 - 03)
PHOSPHORIC ACID PLANT
AL-KHARGA (ABU TARTUR) GRASSROOT
26-Feb-2015 400,000,000 USD Detailed Design (P1 - 09)
PHOSPHORIC ACID PLANT
AL-KHARGA (ABU TARTUR) GRASSROOT
04-Dec-2015 400,000,000 USD Detailed Design (P1 - 09)
PHOSPHORIC ACID PLANT
AL-KHARGA (ABU TARTUR) GRASSROOT
04-Aug-2016 400,000,000 USD Detailed Design (P1 - 09)
PHOSPHORIC ACID PLANT
AL-KHARGA (ABU TARTUR) GRASSROOT
19-Jun-2017 400,000,000 USD Detailed Design (P1 - 09)
PHOSPHORIC ACID PLANT
AL-KHARGA (ABU TARTUR) GRASSROOT
07-Feb-2018 400,000,000 USD Detailed Design (P1 - 09)
PHOSPHORIC ACID PLANT
AL-KHARGA (ABU TARTUR) GRASSROOT
23-Apr-2018 400,000,000 USD Detailed Design (P1 - 09)
PHOSPHORIC ACID PLANT